National Ignition Facility: Management and Oversight Failures Caused Major Cost Overruns and Schedule Delays
RCED-00-271
Published: Aug 08, 2000. Publicly Released: Aug 16, 2000.
Skip to Highlights
Highlights
Pursuant to a congressional request, GAO provided information on the Department of Energy's (DOE) National Ignition Facility (NIF), focusing on the: (1) magnitude of NIF's cost and schedule overruns; (2) reasons for these cost and schedule problems; (3) effects of NIF's cost and schedule on other weapons and science programs; and (4) DOE's and Lawrence Livermore's actions to correct these problems.
Full Report
Topics
Contract oversightCost overrunsFinancial managementFuture budget projectionsLaboratoriesNuclear weapons testingSchedule slippagesTest facilitiesCost and scheduleNuclear weapons