Skip to main content

Patriot Modernization: Oversight Mechanism Needed to Track Progress and Provide Accountability

GAO-16-488 Published: Aug 25, 2016. Publicly Released: Aug 25, 2016.
Jump To:
Skip to Highlights

Highlights

What GAO Found

While the currently fielded version of the Army's Patriot surface-to-air missile system is an improvement over prior versions, the Army currently plans to spend about $2.9 billion between fiscal years 2013 and 2021 on an upgrade strategy to address a variety of capability needs. These efforts are intended to improve the system's performance, reliability, and communications as well as address obsolescence and sustainment issues. The figure below shows planned costs for ongoing efforts, near-term upgrades which begin fielding prior to fiscal year 2017, mid-term upgrades which begin fielding between fiscal years 2017 and 2021, and long-term upgrades—including a long-term radar solution. Key among the mid-term efforts are major software upgrades called Post Deployment Build-8 (PDB-8) and PDB-8.1, which are intended to improve communications and system capabilities against threats. The Army plans to begin operational testing for PDB-8 and PDB-8.1 in fiscal years 2016 and 2019, respectively. These testing results will reveal the extent to which the near and mid-term upgrades work as intended.

Breakdown of $2.9 Billion between Fiscal Years 2013 and 2021 for Army Strategy to Address Patriot Capability Needs

Breakdown of .9 Billion between Fiscal Years 2013 and 2021 for Army Strategy to Address Patriot Capability Needs

Note: Long-term upgrade costs include $364 million for the long-term radar solution which will be a separate major defense acquisition program.

Although the Army estimated in 2013 that costs for Patriot upgrades would meet the threshold to be considered a major defense acquisition program (MDAP), the Army chose to incorporate the Patriot upgrade efforts into the existing Patriot program which made certain oversight mechanisms inapplicable. Further, it decided not to put a mechanism in place to track or report the upgrades' progress against initial cost, schedule, or performance estimates, similar to those generally required of MDAPs, which GAO considers essential for program oversight. Operational testing for PDB-8 and PDB-8.1 provides the Army with an opportunity to increase oversight. If performance shortfalls indicate a need for further development, the Army will have an opportunity to track progress on these upgrades to provide the oversight tools decisionmakers need to make important investment decisions.

Why GAO Did This Study

Patriot is a mobile Army surface-to-air missile system deployed worldwide to defend critical assets and forces. To respond to emerging threats and address a diverse set of capability needs, the Army has spent nearly $1.1 billion and requested $1.8 billion over the next 5 years to upgrade Patriot, begin developing a long-term radar solution, and integrate Patriot components into a central network and command and control system—the Integrated Air and Missile Defense.

A House report included a provision for GAO to assess, among other things, the status of the Patriot system and the Army's strategy for completing the upgrades. Among other things, this report examines (1) the extent to which the latest upgrades will address Patriot capability needs and (2) the level of oversight and accountability provided for the upgrade efforts. To conduct this review, GAO examined Army and program documents including test plans and schedules. GAO also interviewed Department of Defense (DOD) and other relevant officials.

Recommendations

GAO recommends that the Secretary of Defense direct the Army to establish oversight mechanisms, similar to those for major defense acquisition programs, if additional development is required for upgrades operationally tested with PDB-8 and PDB-8.1. DOD partially concurred, focusing its response on plans to track other MDAPs, but did not clarify how or if it would track current PDB-8 and PDB-8.1 progress. GAO maintains DOD should provide oversight for any additional PDB-8 and PDB-8.1 development.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense In the event that operational test results for PDB-8 and PDB-8.1 reveal performance shortfalls that require additional development of the near and mid-term upgrades tested, the Secretary of Defense should direct the Secretary of the Army to establish mechanisms for overseeing those upgrades commensurate with other major defense acquisition programs, to include an initial report--similar to a Selected Acquisition Report--as soon as practical following operational testing for both PDB-8 and PDB-8.1, on the near and mid-term upgrades evaluated during these tests, including: (1) cost, schedule, and performance estimates for any additional development that is needed; and (2) an estimate of the amount of development costs it has incurred since 2013 for near- and mid-term Patriot upgrades operationally tested along with PDB-8 and PDB-8.1.
Open
DOD partially concurred with this recommendation. In 2017, operational testing for PDB-8 was completed and results show some performance shortfalls although DOD asserts that there is no additional development required. DOD plans to reassess the need for any additional action after operational testing for PDB-8.1 is completed as planned in September 2023. Final results are planned to be available in a report published January 2024.
Department of Defense In the event that operational test results for PDB-8 and PDB-8.1 reveal performance shortfalls that require additional development of the near and mid-term upgrades tested, the Secretary of Defense should direct the Secretary of the Army to establish mechanisms for overseeing those upgrades commensurate with other major defense acquisition programs, to include annual updates to Congress comparing the latest cost and schedule estimates against the initial estimates and providing explanations for any major deviations until development is complete.
Open
DOD partially concurred with this recommendation. In 2017, operational testing for PDB-8 was completed and results show some performance shortfalls although DOD asserts that there is no additional development required. DOD plans to reassess the need for any additional action after operational testing for PDB-8.1 is completed as planned in September 2023. Final results are planned to be available in a report published January 2024.

Full Report

GAO Contacts

Cristina T. Chaplain
Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Ballistic missile defenseAir defense systemsCost analysisSoftwareDefense acquisition programsBallistic missilesMissilesMissile defense systemsOperational testingAnalysis of alternativesDefense capabilitiesPerformance shortfalls