Skip to main content

Federal Real Property: GSA Could Better Identify Risks of Unforeseen Conditions in Repair and Alteration Projects

GAO-16-273 Published: Mar 17, 2016. Publicly Released: Mar 17, 2016.
Jump To:
Skip to Highlights

Highlights

What GAO Found

Both industry stakeholders and General Services Administration (GSA) officials told GAO that unforeseen conditions in repair and alteration projects are common. Such conditions, for example, included an unknown wood subflooring discovered during demolition work. Among the impacts identified by the stakeholders were increased project costs and schedule delays. In general, data are limited on unforeseen conditions since GSA does not analyze this type of information. Most of the repair and alteration projects GAO reviewed—11 of 18 projects--experienced an unforeseen condition. The overall impact of the unforeseen conditions on the 18 projects GAO reviewed was largely limited. On 9 of the 11 projects that experienced such conditions, the cost to remediate them accounted for 1 to 5 percent of the project's original construction contract award amount, and on one project the cost was approximately 6 percent. These amounts were below the typical 10 percent construction contingency GSA adds to project costs. Schedule impacts were also limited: 4 of the 11 projects experienced delays ranging from 23 to 105 days. GAO also found that three projects reviewed that did not experience unforeseen conditions were attached to larger projects that did experience these conditions. In two of these larger projects the cost increases from unforeseen conditions were about $2 million each. Incomplete building drawings and lack of building information were among the possible causes of the unforeseen conditions experienced in the projects GAO reviewed.

GSA has a variety of methods to identify and assess risks of unforeseen conditions. GSA's Project Planning Guide states that, among other things, facility condition assessments and site surveys should be conducted initially. GSA guidance also calls for preparation of a project management plan (PMP), which includes a risk assessment matrix. GAO found that, in general, GSA used at least one of its risk identification methods on the projects reviewed. For example, GAO found that GSA prepared PMPs for 13 of the 18 projects reviewed. Three of the remaining five projects were attached to larger projects that had PMPs and GSA was unable to provide a PMP for the other two projects. However, GSA's risk identification was sometimes inconsistent with unforeseen conditions that were actually experienced. For example, on 11 of the projects, GSA did not identify risks that later materialized during the project. The Standards for Internal Control in the Federal Government state that agencies should comprehensively identify risks using a variety of quantitative and qualitative methods. GSA officials told GAO that contract change orders are used to document unforeseen conditions that result in a change to the contract, but that these change orders are not analyzed to identify what role these conditions represent on projects or their causes or impacts. As shown in the projects GAO reviewed, unforeseen conditions can delay schedules and increase project costs—in some cases in the millions of dollars. Analyzing project information such as change orders would allow GSA to better know what role unforeseen conditions play in repair and alteration projects and the magnitude of this risk.

Why GAO Did This Study

GSA annually spends hundreds of millions of dollars making major and minor repairs and alterations to the more than 1,500 federally owned buildings that it holds. GAO's past work has indicated that GSA sometimes encounters “unforeseen site conditions”—conditions that are different from what was expected—in performing this work. Unforeseen conditions can add both time and cost to repair and alteration projects. GAO was asked to review issues related to tenant repair and alteration projects. This report addresses (1) information about the extent, impact, and cause of unforeseen site conditions on selected projects, and (2) how GSA identifies and assesses the risks of unforeseen conditions.

GAO reviewed 18 non-generalizable repair and alteration projects funded from fiscal year 2010 to 2013, valued at $2 million or more; interviewed GSA project managers and contracting officers about these projects; reviewed project documents; and interviewed a non-generalizable sample of organizations and individuals knowledgeable about the construction industry (industry stakeholders).

Recommendations

GAO recommends that GSA develop and implement a plan for analyzing information it collects to identify the role of unforeseen conditions in repair and alteration projects and the specific causes and impacts of these conditions. GSA agreed with the recommendation and the agency stated it will develop a plan to address it.

Recommendations for Executive Action

Agency Affected Recommendation Status
General Services Administration To improve risk assessments for repair and alteration projects, the Administrator of GSA should develop and implement a plan to periodically analyze information GSA already collects, for example, based on a representative sample of repair and alterations projects, in order to: (1) identify the specific impacts unforeseen conditions have had on project costs, schedules, and scope of work; (2) analyze the causes of these conditions for those projects that experienced unforeseen site conditions; and (3) identify actions that will be taken to address the potential causes of unforeseen site conditions.
Closed – Implemented
In 2016, GAO reported that unforeseen site conditions in repair and alteration projects are common. Among the impacts from these conditions is increased project costs and schedule delays. GAO's review of 18 repair and alteration projects conducted by the General Services Administration (GSA) found that 11 had unforeseen conditions. For nine of the projects there was an increase in project costs and for four of the projects there were schedule delays. Incomplete building drawings and lack of building information were among the possible causes of these unforeseen conditions. GAO also found that GSA has a variety of methods to identify and assess risks of unforeseen conditions. GSA's Project Planning Guide states that, among other things, facility condition assessments and site surveys should be conducted initially. GSA guidance also calls for preparation of a project management plan (PMP), which includes a risk assessment matrix. However, GSA's risk identification was sometimes inconsistent with unforeseen conditions that were actually experienced on a project. For example, on 11 of the projects GSA did not identify risks that later materialized during the project. The Standards for Internal Control in the Federal Government state that agencies should comprehensively identify risks using a variety of quantitative and qualitative methods. In general, data on unforeseen conditions are limited since GSA does not analyze this type of information. In addition, GSA uses contract change orders to document unforeseen conditions, but these change orders are not analyzed by GSA to identify the role unforeseen conditions represent on projects or their causes or impacts. Therefore, GAO recommended that GSA develop and implement a plan for analyzing information it collects to identify the role of unforeseen conditions in repair and alteration projects, the specific causes and impacts of these conditions, and identify actions to address these causes. In March 2016, GSA prepared an action plan to study potential unforeseen conditions on repair and alteration projects. This plan included conducting a study of contract change orders to identify the role of unforeseen conditions, analyzing possible categories of unforeseen conditions and assessing their budget and schedule impacts, and developing plans to address the potential causes and mitigate the risks. The study was issued in November 2016 and GSA issued a plan to implement the study's recommendations in March 2017. The implementation plan identifies improvements GSA plans to develop over the next several years to address the report's recommendations. This includes development of formal risk management procedures and development of environmental, survey, and testing guidance for project teams. GSA has begun implementing this plan. For example, in April 2017 GSA rolled out a standardized request for risk registers as a means to capture lessons learned during the course of repair and alteration projects. Also, in May 2017 GSA facilitated a workshop on Building Information Modeling (BIM) that, in part, explored how GSA's use of BIM compared with industry best practices. These actions should act to substantially improve GSA's ability to identify unforeseen conditions, assess their risk, and develop effective mitigation strategies so GSA's repair and alteration program can minimize cost and schedule impacts of these conditions.

Full Report

Office of Public Affairs

Topics

Facility constructionFacility maintenanceFacility repairsFederal propertyFederal property managementMaintenance (upkeep)Real propertyRisk assessmentRisk managementRepairs and alterations