Skip to main content

Defense Infrastructure: Energy Conservation Investment Program Needs Improved Reporting, Measurement, and Guidance

GAO-16-162 Published: Jan 29, 2016. Publicly Released: Jan 29, 2016.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Department of Defense (DOD) collects information on how Energy Conservation Investment Program (ECIP) projects are expected to perform when operational, including anticipated returns on investment and energy or water savings. While DOD annually notifies congressional committees of proposed ECIP projects and includes some of this performance information with the notification, it does not do so consistently. In particular, for fiscal years 2009 through 2015, DOD reported anticipated returns on investment for 79 percent of projects. However, it did not consistently update these data as projects were added and revised or report any information on expected energy or water savings. While DOD is not required by law or its own guidance to report this information, federal internal control standards provide guidance for communicating with external stakeholders information that may have a significant effect on an agency achieving its goals. However, DOD has not developed guidance to require reporting the additional performance information and thus congressional committees may not be able to assess the extent to which DOD expects to achieve ECIP program objectives.

Since fiscal year 2011, DOD has required the services to measure and verify the extent to which ECIP projects have realized their projected savings and energy efficiencies. However, of the 35 domestic projects that the services have started and reported as completed since that requirement was adopted, only 8 projects have resulted in documented savings or reduced energy use. Managers of the remaining projects either did not complete projects according to their original scope, or did not measure or verify cost savings or reduced energy use. Managers, with few exceptions, did not specifically budget for postcompletion measurement and verification costs in their project proposals. If the military services do not include these costs in project proposals, managers will be less likely to set aside resources needed for the measurement and verification actions necessary to determine whether projects realized anticipated benefits.

DOD developed guidance in fiscal year 2011 describing a strategic vision for the program where projects meet at least one of six attributes, such as fundamental performance improvements, that it described as “game-changing” (i.e., significant) benefits. However, about 80 percent of the ECIP-funded projects that GAO reviewed only anticipate benefits that DOD considers traditional rather than significant. DOD has not clarified how the military services and defense agencies should choose ECIP projects to best achieve DOD's strategic vision. According to DOD officials, it is challenging to identify projects that align with DOD's strategic vision and deliver the return on investment that DOD expects of $2 for every $1 invested. This challenge exists because significant projects also tend to be more expensive and therefore have a lower return on investment. If DOD does not review its strategic goals for ECIP and update guidance to clarify how its components should balance their portfolios among traditional and other projects, the department will be unable to meet its strategic vision for the program.

Why GAO Did This Study

DOD established ECIP, which funds projects at military installations that are designed to conserve energy or water, generate electricity from renewable sources, promote energy security, or accomplish a combination of these goals. Senate Report 113-174 included a provision that GAO review energy savings from ECIP-funded projects. This report assesses the extent to which DOD has (1) reported anticipated returns on investment or reduced energy use from ECIP-funded projects; (2) found that completed ECIP projects have resulted in cost savings or lower energy use; and (3) developed and implemented a strategic vision for ECIP.

GAO obtained and analyzed the annual congressional notifications of the 441 proposed ECIP projects from fiscal years 2009 to 2015; analyzed applicable guidance, including DOD guidance from fiscal year 2011 for preparing ECIP proposals; developed, circulated, and analyzed a questionnaire to project managers; and analyzed project documentation to determine which contained attributes that formed part of DOD's strategic vision.

Recommendations

GAO recommends that DOD improve its reporting on anticipated ECIP savings; measure actual savings from ECIP projects; and review its goals and update guidance to best align projects with DOD's strategic vision. DOD concurred or partially concurred with all of the recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense To help improve DOD's ability to report on and measure anticipated and actual savings from ECIP projects, and to provide guidance to inform further project selection, the Secretary of Defense should direct the Under Secretary of Defense for Acquisition, Technology and Logistics (AT&L) to develop and implement guidance requiring that statutory notifications to congressional committees include (1) the anticipated return on investment for all projects, including new projects added to replace canceled projects and existing projects for which there is a significant change to the cost or scope of the project; and (2) information on the estimated energy or water savings, or renewable energy production, anticipated from proposed ECIP projects.
Closed – Implemented
DOD partially concurred with our recommendation. In the National Defense Authorization Act for Fiscal Year 2017 (December 2016), ECIP became the Energy Resilience and Conservation Investment Program (ERCIP). The primary focus of ERCIP is energy resilience, whereas ECIP's primary focus was energy conservation. ERCIP has maintained the reporting in this area that was in place under ECIP, and has expanded it in some areas. In September 2019, DOD provided its ERCIP Fiscal Year 2019 Congressional notification (December 2018), which includes project savings-to-investment ratio information as well as information on changes to prior year ECIP projects. DOD also provided its Fiscal Year 2018 ERCIP Annual Report to Congress (December 2018), which includes, among other things, original and current savings-to-investment ratio information as well as original and current measurement and verification (M&V) estimates, and M&V funding source and plan descriptions. As we reported in 2016, the annual ECIP guidance for fiscal year 2011 stated that all projects should include an M&V plan to determine cost and energy savings. In August 2020, DOD provided its ERCIP guidance for Fiscal Years 2022/2023. The requirements continue and deepen the progress on reporting M&V with rigor; moreover, they retain requirements to report on savings-to-investment ratio and payback. In addition, the guidance: (1) contains a requirement to identify applicable cybersecurity costs (which is consistent with program orientation toward mission assurance). (2) specifies that the Life Cycle Cost Analysis, while not part of Congressional notification materials, must include documentation for all energy and non-energy savings accounted for in the project, (3) contains a requirement for DOD components to be responsible for providing regular updates on the progress of their program's implementation. As such, each DOD component shall "maintain current, auditable documentation and report consistently on the execution of each approved ERCIP project. including M&V." Thus, we believe that DOD's current guidance to components meets the intent of our recommendation, particularly in the context of ERCIP's focus on energy resilience.
Department of Defense To help improve DOD's ability to report on and measure anticipated and actual savings from ECIP projects, and to provide guidance to inform further project selection the Secretary of Defense should also direct the Under Secretary of Defense for AT&L to direct the components to include projected measurement and verification (M&V) costs--in the military construction proposal or another appropriate document--as they develop projects; in so doing, the Under Secretary might build on existing Navy guidance, as appropriate.
Closed – Implemented
DOD partially concurred with our recommendation. In the National Defense Authorization Act for Fiscal Year 2017 (December 2016), ECIP became the Energy Resilience and Conservation Investment Program (ERCIP). The primary focus of ERCIP is energy resilience, whereas ECIP's primary focus was energy conservation. ERCIP has maintained the reporting in this area that was in place under ECIP, and has expanded it in some areas. In September 2019, DOD provided its Fiscal Year 2019/2020 ERCIP Guidance (September 2017). This guidance required that DOD components include an estimated monitoring and verification (M&V) cost and M&V plan in project proposal documents. Specifically, the guidance requires all project proposals submitted for consideration to include supporting documentation--DOD's form 1391, which is used for submitting requirements and justifications in support of funding requests to Congress, and a life-cycle cost analysis. DOD did, in its FY19 Notification to Congress, include projected M&V costs, which had been developed for every project. This action meets the intent of our recommendation.
Department of Defense To help improve DOD's ability to report on and measure anticipated and actual savings from ECIP projects, and to provide guidance to inform further project selection, the Secretary of Defense should provide the components with additional guidance on the range of options available when developing M&V plans that are appropriate for different project sizes and types; and how to scope ECIP projects to conform to available funding.
Closed – Implemented
DOD partially concurred with our recommendation. However, in May 2020, DOD provided us with minutes of ERCIP working group meetings that indicated that the Office of the Secretary of Defense was developing additional guidance and also ensuring that best practices for developing and refining M&V plans were shared among components (e.g., military services). In addition, DOD updated its annual guidance for FY19/20 project submissions. This action meets the intent of our recommendation.
Department of Defense To help improve DOD's ability to report on and measure anticipated and actual savings from ECIP projects, and to provide guidance to inform further project selection, the Secretary of Defense should review the strategic goals for the ECIP program and make any needed adjustments to reflect current DOD priorities.
Closed – Implemented
DOD concurred with our recommendation. And in the annual ERCIP guidance for FY19/FY20, the strategic vision for the program was updated to reflect current DoD priorities in a section entitled "Strategic Vision for the Program." This, together with DOD's proposed funding allocation for FY21-- which gives significant weight to the strategic priority to boost energy resilience -- meets the intent of our recommendation.
Department of Defense To help improve DOD's ability to report on and measure anticipated and actual savings from ECIP projects, and to provide guidance to inform further project selection, the Secretary of Defense should, after reviewing strategic goals and adjusting as needed, update installation energy management guidance and, as appropriate, annual ECIP guidance, to clarify (1) how the components-military services and defense agencies-should balance their ECIP portfolios among what DOD describes as traditional and game-changing projects to best achieve DOD's strategic vision for ECIP, (2) what constitutes a higher-return project that should be propose under alternative financing rather than ECIP, and (3) that managers proposing repair and minor construction projects should seek operation and maintenance rather than ECIP funds..
Closed – Implemented
DOD partially concurred with our recommendation. DOD stated that its guidance already provided language which directs the focus of the Services on proposed projects that would not necessarily be candidates for third-party financing or O&M funds, but added that it intended to review and revise guidance as necessary to make this portion more clear. The FY19/20 annual guidance addressed that portion of our recommendation. In September 2019, DOD provided us with information about the installation energy plans (IEP) that each individual installation was required to develop. IEPs require development of an energy project execution plan, which identifies energy projects needed installation-wide and discusses potential funding sources. Additionally, DoD holds regular ERCIP Working Group meetings, and officials stated that topics include the types of projects that should be considered for ERCIP funding versus third party financing and O&M. Given this information and the realignment of the program since our review to focus on installation energy resilience, we consider that DOD has met the intent of our recommendation.

Full Report

Office of Public Affairs

Topics

Congressional committeesCost analysisDefense capabilitiesDefense cost controlDefense procurementEnergy conservationEnergy consumptionEnergy costsEnergy securityMilitary facilitiesProgram evaluationRenewable energy sourcesReporting requirementsStrategic planning