What GAO Found

Over the past year and a half, the Department of Defense (DOD) has taken steps to implement its plan to collect contractor manpower data directly from contractors and to develop and implement a department-wide system, based on the Army's existing system, to collect and store these and other inventory data. DOD officials estimate that the data system will be available in fiscal year 2014, with DOD components reporting on most of their service contracts by fiscal year 2016. DOD, however, is still working on key decisions related to security, funding, and other technological issues and has not developed a plan of action with anticipated time frames and necessary resources to help ensure DOD remains on track to meet its goals. Making timely decisions and developing a plan of action with anticipated timeframes and necessary resources, as GAO has previously recommended, would facilitate DOD's stated intent of implementing a DOD-wide system to collect required inventory information. For the fiscal year 2011 inventory, DOD components generally used the same compilation processes used in the previous year. As such, with the exception of the Army, which already has an inventory data collection system, the remaining components relied primarily on the Federal Procurement Data System-Next Generation (FPDS-NG). GAO previously reported that FPDS-NG has several limitations, including the inability to identify more than one type of service in a contract or the number of contractor full-time equivalents (FTE), which limit its utility for purposes of compiling a complete and accurate inventory.

Consistent with DOD's December 2011 guidance, 29 of the 31 components submitted letters certifying that they had conducted an inventory review as of April 2013. DOD officials stated that the requirement to submit certification letters represented a significant improvement over prior years' reviews, when DOD could not determine whether the required reviews were conducted. These officials also stated that the letters provided useful insights into the components' efforts. GAO's analysis, however, indicates that none of the components' certification letters discussed all six elements required by DOD's guidance. For example, GAO's analysis found that the letters generally provided only limited information on their review methodologies or the results of their review efforts. In addition, it is unclear based on the information provided in the certification letters the extent to which the differences in the methodologies components used to conduct the reviews contributed to the variation in the identification of contractors performing inherently governmental functions, unauthorized personal services, or closely associated with inherently governmental functions. For example, the Army, using its review process, identified over 44,000 contractor FTEs performing closely associated with inherently governmental functions, while the Air Force identified about 1,400 contractor FTEs and 13 components reported they had no contractors performing these functions. Further, the Army and the Air Force did not provide complete information on actions taken to resolve instances where they had identified contractors performing inherently governmental functions as part of their reviews, such as by transferring performance of these functions to DOD personnel or modifying the contract's statement of work. The ability to identify contractors performing these functions is valuable as it allows actions to be taken, but that value is significantly reduced if decision-makers have no assurance as to whether corrective actions were taken.

Why GAO Did This Study

DOD is the government's largest purchaser of contractor-provided services. In fiscal year 2011, DOD reported $199 billion in obligations for service contracts, which include services as varied as medical services and intelligence support. In 2008, Congress required DOD to compile and review an annual inventory of its contracted services to include the number of contractors providing services to DOD and the functions these contractors were performing. The 2010 National Defense Authorization Act directed GAO to report for 3 years on these inventories.

For this third report, GAO assessed (1) the progress DOD has made in compiling the fiscal year 2011 inventory of contracted services and efforts to collect contractor manpower data, and (2) the extent to which defense components complied with DOD's guidance for reporting on their inventory reviews. GAO reviewed relevant laws and guidance, analyzed inventory submissions from 31 components, reviewed component certification letters, and interviewed DOD acquisition and manpower officials.

What GAO Recommends

GAO recommends that the Secretary of Defense direct component heads to discuss in their certification letters all required inventory review elements, as well as how instances where contractors are performing inherently governmental functions were resolved. DOD generally concurred with our recommendations, but indicated that the Secretary’s involvement was not necessary. GAO believes it is, as discussed in the report.

For more information, contact Timothy J. DiNapoli at (202) 512-4841 or dinapolit@gao.gov.

Recommendations for Executive Action

  1. Status: Open

    Comments: DOD concurred with our recommendation, however, DOD did not believe that it was necessary for the Secretary of Defense to provide additional guidance, but rather indicated that the Under Secretaries for Acquisition Technology and Logistics, and Personnel and Readiness, which have lead responsibility for the inventory, will disseminate our report to the components with a reminder that each component must specifically address each item listed in the fiscal year 2012 inventory of contracted services guidance. This recommendation will remain open and we will continue to monitor through our ongoing audit work evaluating the 2012 inventory of contracted services and review process.

    Recommendation: To ensure that the inventory of contracted services reviews provide greater context and value to DOD leadership, the Secretary of Defense should direct component heads to comply with DOD's February 2013 guidance, by ensuring that all required inventory review data elements, including a comprehensive description of their inventory review methodology, are addressed in their certification letters.

    Agency Affected: Department of Defense

  2. Status: Open

    Comments: DOD partially concurred with our recommendation. DOD stated that while it agreed with the intent to ensure complete information is provided in certification letters regarding how component heads resolved instances of contractors performing inherently governmental or unauthorized personal services, DOD believes that the focus should be on the current and future reviews of the inventory of contracted services, rather than a correction of prior inventory reviews. DOD stated that the Under Secretaries for Acquisition, Technology and Logistics, and Personnel and Readiness will ask each component to include in the fiscal year 2012 certification letters any updated information on how they resolved the instances of contractors performing inherently governmental functions or unauthorized personal services in prior inventory reviews. DOD added that the fiscal year 2013 inventory of contracted services guidance will be updated to include this requirement when it is published in February 2014. Subsequently, DOD stated that any instances of contractors performing inherently governmental functions or unauthorized personal services recorded in prior inventory reviews that persist will be included and documented in the fiscal year 2012 and future review processes. DOD said it will verify that the certification letters contain a complete and accurate description of all required data elements, including actions taken to resolve outstanding issues related to contractors performing inherently governmental functions and unauthorized personal services prior to closing the respective review process. This recommendation will remain open, and we will continue to monitor through our ongoing audit work.

    Recommendation: To ensure that the inventory of contracted services reviews provide greater context and value to DOD leadership, the Secretary of Defense should direct component heads to provide updated information in certification letters on how they resolved the instances of contractors performing inherently governmental functions or unauthorized personal services in prior inventory reviews.

    Agency Affected: Department of Defense

 

Explore the full database of GAO's Open Recommendations »

Nov 20, 2014

Nov 19, 2014

Nov 18, 2014

Oct 30, 2014

Oct 16, 2014

Oct 10, 2014

Oct 8, 2014

Sep 30, 2014

Looking for more? Browse all our products here