Skip to main content

Military Bases: Opportunities Exist to Improve Future Base Realignment and Closure Rounds

GAO-13-149 Published: Mar 07, 2013. Publicly Released: Mar 07, 2013.
Jump To:
Skip to Highlights

Highlights

What GAO Found and Recommends

The Department of Defense (DOD) developed and used a quantitative model known as the Cost of Base Realignment Actions (COBRA), which GAO has found to be a reasonable estimator for comparing potential costs and savings among candidate alternatives, to estimate the costs and savings associated with Base Realignment and Closure (BRAC) 2005 recommendations. However, DOD’s process for providing the BRAC Commission with cost and savings estimates was hindered in many cases by underestimating recommendation specific requirements that were entered into the COBRA model. For example, military construction costs for BRAC 2005 increased from $13.2 billion estimated by the BRAC Commission in 2005 to $24.5 billion after implementation ended in 2011. Most of this 86 percent increase was caused by requirements that were added or identified after implementation began. While GAO recognizes that some military construction requirements were added after DOD submitted its initial cost estimates to the BRAC Commission, GAO found that other cost estimates increased because requirements were initially understated or not identified as inputs into COBRA. DOD also did not fully anticipate information technology requirements for many recommendations. For example, the initial information technology cost estimate for one recommendation was nearly $31 million, but implementation costs increased to over $190 million once those requirements were better defined. Also, DOD was unable to always document the methodology used to estimate savings from reducing military personnel positions. Therefore, to increase the fidelity of the initial cost estimates that DOD submits with its recommendations to the BRAC Commission for a future BRAC round, GAO is recommending that the Office of the Secretary of Defense (OSD) improve the process for identifying and estimating the cost of requirements for military construction and information technology and update the guidance on documenting how it identifies military personnel position-elimination savings.

The military services and other DOD components provided leadership and oversight over the 2005 BRAC round at the highest levels, and OSD established a governance structure that was led by higher-level leaders compared to previous rounds and included a larger role for specialized working groups. By implementing BRAC 2005, DOD closed 24 major bases, realigned 24 major bases, eliminated about 12,000 civilian positions, and achieved estimated net annual recurring savings of $3.8 billion; however, the department cannot provide documentation to show to what extent it reduced plant replacement value or vacated leased space as it reported in May 2005 that it intended to do. Also, DOD did not establish a target for reducing excess infrastructure, as it did in the 1995 BRAC round. In addition, DOD bundled multiple closures and realignments into single, highly complex recommendations in its report to the Commission without itemizing the costs and savings associated with each separate major action, thus limiting visibility into the estimated costs and savings for individual closures and realignments. Further, OSD did not establish a process to ensure a timely security review of its supporting data to prevent the disclosure of classified information, thus delaying the Commission’s work. To improve planning for measuring results of a future BRAC round, GAO is recommending that DOD identify appropriate measures of effectiveness, develop a plan to demonstrate the extent to which it achieved intended results, and establish a target for eliminating excess infrastructure in its initiating guidance, consistent with the selection criteria for a future BRAC round. Also, to improve the availability of cost and savings information to BRAC decision makers, GAO is recommending that, when planning a future BRAC round, DOD limit the practice of bundling potentially stand-alone realignments or closures into single recommendations; but if DOD determines that bundling multiple realignments or closures into one recommendation is appropriate, itemize the costs and savings associated with each major action in its report to the BRAC Commission. Furthermore, GAO is recommending that OSD develop a process to conduct a timely security review of all BRAC data during DOD’s recommendation development process to resolve any data-security issues and better ensure that the BRAC Commission receives timely information for its independent review.

Finally, GAO’s analysis of BRAC 2005 identified several opportunities where potential amendments to the BRAC statute could provide Congress with improved visibility over costs and savings expected from implementing BRAC recommendations and offer greater assurances about expected outcomes if future BRAC rounds are authorized. DOD’s goals for BRAC 2005 emphasized transformation and jointness. Although reductions in excess infrastructure to generate cost savings remained an important goal for DOD, the extent and timing of potential costs and savings, including the number of years it would take for the savings to exceed costs, was included as “other” or secondary criteria. As a result, many BRAC recommendations were not expected to produce 20-year net savings. Also, the BRAC Commission added contingency clauses to some recommendations, which allowed some outcomes to be defined by events or decisions that could occur after Congress could have prevented the BRAC recommendations from becoming binding, if it so chose. Hence, Congress had limited visibility into the potential cost of those recommendations. GAO is suggesting several matters for Congress to consider for amending the BRAC statute if it decides to authorize future BRAC rounds. First, if cost savings are to be a goal of any future BRAC round, Congress could elevate the priority DOD and the BRAC Commission give to potential costs and savings as a selection criterion for making BRAC recommendations. Second, Congress could consider requiring OSD to formally establish targets that the department expects to achieve from a future BRAC process and require OSD to propose selection criteria as necessary to help achieve those targets. Finally, Congress could consider whether to limit or prohibit the BRAC Commission from adding a contingent element to any BRAC recommendation and, if it is to be permitted, under what conditions.

How GAO Conducted Its Work

For this report, GAO analyzed DOD’s 2005 report to the BRAC Commission and the Commission’s report to the President and reviewed BRAC policy memorandums, guidance, and other relevant documentation. To assess how DOD estimated BRAC costs and savings and any ways its methodology could be improved, GAO analyzed DOD’s COBRA model and DOD’s BRAC budget submissions to Congress. To assess OSD leadership over BRAC 2005 and opportunities to improve planning for future BRAC rounds, GAO interviewed officials from the 2005 BRAC Commission, the Office of the Deputy Under Secretary of Defense (Installations and Environment), the military services’ BRAC offices, and officials working with the joint cross-service groups. Finally, to assess what legislative changes, if any, Congress may wish to make that could enhance oversight of any future round, GAO reviewed the goals of BRAC 2005 and the criteria used to develop and evaluate BRAC 2005 recommendations, in addition to interviewing officials from the 2005 BRAC Commission and the Office of the Deputy Under Secretary of Defense (Installations and Environment).

Agency Comments and GAO’s Evaluation

In commenting on a draft of this report, DOD did not concur with five out of ten recommendations, in part because it stated that the intent of GAO’s recommendations to establish targets and measures of effectiveness was to prioritize capacity reductions over military value. However, nothing in these recommendations precludes optimizing military value while still measuring effectiveness and setting capacity reduction targets. The military value analysis could identify which installations have greatest value while still permitting DOD to reduce excess capacity as appropriate. Thus, GAO continues to believe that implementing these recommendations would help improve the BRAC process.

A summary of BRAC 2005 lessons learned, for which GAO has made recommendations to OSD and matters for Congress to consider in authorizing any future BRAC rounds, is provided below.

GAO Findings and Recommendations

  • Some requirements were understated or not included in initial BRAC cost estimates, such as military construction and information technology requirements.

GAO is recommending that OSD improve the process for identifying these requirements as it develops initial cost estimates for a future BRAC.

  • The standard factor for estimating information technology costs was understated.

GAO is recommending that OSD update the standard factor for this expense item.

  • DOD did not consistently document its basis for military personnel savings estimates.

GAO is recommending that OSD update its guidance on how it will identify these savings for a future BRAC round.

  • Some intended BRAC results were not tracked.

GAO is recommending that OSD identify appropriate measures of effectiveness and develop a plan to demonstrate the extent it achieved intended results for a future BRAC round.

  • OSD did not establish a target for reducing excess infrastructure.

GAO is recommending that OSD establish a reduction target in its initiating guidance, consistent with the selection criteria for a future BRAC round.

  • Bundling of multiple closures or realignments into a single recommendation limited visibility of costs and savings in OSD’s report to the BRAC Commission.

GAO is recommending that OSD limit this practice, or itemize the costs and savings associated with each major action if OSD determines that bundling multiple realignments or closures into one recommendation is appropriate.

  • A timely review of BRAC supporting data for potential security risks did not take place.

GAO is recommending that OSD develop a process for a future BRAC round to resolve any data-security issues so the BRAC Commission receives the supporting data in a timelier manner for its independent review.

  • Cost savings was not a priority consideration in the BRAC statutory selection criteria nor was cost savings a priority when OSD established goals for the BRAC 2005 round.

If cost savings are to be a goal of any future BRAC round, GAO is suggesting that Congress consider amending a future BRAC statute by (1) elevating the priority DOD and the BRAC Commission give to potential costs and savings as a selection criterion for making BRAC recommendations, (2) requiring OSD to formally establish specific goals that the department expects to achieve from a future BRAC process, and (3) requiring OSD to propose selection criteria as necessary to help achieve those goals.

  • Contingency clauses for some BRAC recommendations limited Congress’s visibility of complete cost information and expected outcomes.

GAO is suggesting that Congress consider in a future BRAC statute whether to limit or prohibit the BRAC Commission from adding a contingent element to any BRAC recommendation and, if permitted, under what conditions.

Why GAO Did This Study

The 2005 BRAC round was the biggest, most complex, costliest BRAC round ever. Unlike the four previous rounds, which focused on reducing infrastructure, the Secretary of Defense saw BRAC 2005 as a unique opportunity to adjust DOD's base structure to meet new challenges, such as international terrorism and weapons of mass destruction, and to meet future challenges, such as designating where forces returning from overseas would be located. While DOD's stated goals for BRAC 2005 included eliminating unneeded infrastructure, they also included furthering the transformation of DOD's force structure and fostering joint capabilities among the military services, resulting in recommendations of unprecedented scope and complexity. As GAO found in June 2012, BRAC implementation costs grew to about $35 billion, exceeding the initial 2005 estimate of $21 billion by 67 percent. As part of its fiscal year 2013 budget request, DOD asked for two more rounds of BRAC in 2013 and 2015. Congress has not acted on this request.

As directed by the House Armed Services Committee, this report discusses lessons learned that could be applied if Congress chooses to authorize future BRAC rounds. GAO assessed (1) how DOD estimated BRAC costs and savings and any ways its methodology could be improved, (2) OSD leadership over BRAC 2005, and (3) any legislative changes Congress may wish to make that could enhance oversight of any future round.

For more information, contact Brian J. Lepore at (202) 512-4523 or leporeb@gao.gov.

Recommendations

Matter for Congressional Consideration

Matter Status Comments
If cost savings are to be a goal of any future BRAC round, Congress may wish to consider amending the BRAC statute by elevating the priority DOD and the BRAC Commission give to potential costs and savings as a selection criterion for making base closure and realignment recommendations.
Open
All the Matters for Congressional Consideration are contingent on the implementation of another round of BRAC. As of March 2024, Congress has not authorized another round of BRAC.
If Congress authorizes additional BRAC rounds, it may wish to consider amending BRAC legislation by requiring the Secretary of Defense to formally establish specific goals that the department expects to achieve from a future BRAC process.
Open
All the Matters for Congressional Consideration are contingent on the implementation of another round of BRAC. As of March 2024, Congress has not authorized another round of BRAC.
If Congress authorizes additional BRAC rounds, it may wish to consider amending BRAC legislation by requiring the Secretary of Defense to propose selection criteria as necessary to help achieve those goals, if necessary and appropriate.
Open
All the Matters for Congressional Consideration are contingent on the implementation of another round of BRAC. As of March 2024, Congress has not authorized another round of BRAC.
If Congress decides to authorize a future base closure round, it may want to consider whether to limit or prohibit the BRAC Commission from adding a contingent element to any recommendation and, if permitted, under what conditions.
Open
All the Matters for Congressional Consideration are contingent on the implementation of another round of BRAC. As of March 2024, Congress has not authorized another round of BRAC.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense
Priority Rec.
Contingent on the authorization of a future BRAC round, and to increase the fidelity of the initial cost estimates that DOD submits with its recommendations to the BRAC Commission for a future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to work with the military services, defense agencies, and other appropriate stakeholders to improve the process for fully identifying recommendation-specific military construction requirements and ensuring that those requirements are entered into the COBRA model and not understated in implementation costs estimates prior to submitting recommendations to the BRAC Commission.
Closed – Implemented
Although DOD did not initially concur with our recommendation, in January 2017 DOD officials agreed to take additional action to better forecast the initial costs inputted into COBRA that are related to military construction. In addition, in October 2019, DOD identified two specific actions taken to improve cost estimates: (1) incorporating lessons learned (such as improving military construction estimates) in the cost tool the Department used in its European Infrastructure Consolidation (EIC) initiative and (2) reviewing major cost drivers associated with the relocation of personnel, such as IT cost estimates, which will be improved to account for a variety of factors. According to DOD, these improvements are being incorporated into its efforts to update its cost tool. As of March 2020, Congress had not authorized another round of BRAC. Nevertheless, by incorporating lessons learned and reviewing major cost drivers for inclusion in its cost tool, DOD has met the intention of our recommendation.
Department of Defense
Priority Rec.
Contingent on the authorization of a future BRAC round, and to increase the fidelity of the initial cost estimates that DOD submits with its recommendations to the BRAC Commission for a future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to establish a process for ensuring that information technology requirements associated with candidate recommendations that are heavily reliant on such technology have been identified to the extent required to accomplish the associated mission, before recommendations and cost estimates are submitted to the BRAC Commission.
Closed – Implemented
DOD partially concurred with the original recommendation when the report was issued. However, in an October 2019 memorandum, DOD agreed to implement all recommendation with which it had concurred or partially concurred should Congress authorize a future BRAC and provided that implementation of this specific recommendation would be permissible under the authorization; be consistent with the objectives of the BRAC and the National Defense Strategy; and not subvert the selection criteria. In addition, DOD has taken action to review major cost drivers associated with the relocation of personnel, such as IT cost estimates, which will be improved to account for a variety of factors within its cost tool. As of March 2020, Congress had not authorized another round of BRAC. Nevertheless, together, these actions meet the intent of our recommendation.
Department of Defense
Priority Rec.
Contingent on the authorization of a future BRAC round, and to increase the fidelity of the initial cost estimates that DOD submits with its recommendations to the BRAC Commission for a future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to ensure that, during the development and comparison of BRAC scenarios, all anticipated BRAC implementation costs--such as relocating personnel and equipment--are considered and included in the COBRA model when comparing alternatives and generating cost estimates.
Closed – Implemented
Although DOD did not initially concur with our recommendation, in January 2017 DOD officials agreed to take additional action to better forecast the initial costs inputted into COBRA that are related to relocating military personnel positions and equipment. In October 2019, DOD officials identified specific actions taken to incorporate lessons learned and to review major cost drivers as part of its cost tool for estimating costs associated with BRAC recommendations. As of March 2020, Congress had not authorized another round of BRAC; nevertheless, these actions to improve the cost tool meet the intention of our recommendation.
Department of Defense Contingent on the authorization of a future BRAC round, and to increase confidence in the fidelity of the cost estimates that DOD submits to the BRAC Commission for a future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to take steps to ensure that COBRA's standard factor for information technology is updated and based on technological developments since the most recent COBRA update.
Closed – Implemented
DOD concurred with the original recommendation when the report was issued. Further, in an October 2019 memorandum, DOD agreed to implement all recommendation with which it had concurred or partially concurred should Congress authorize a future BRAC and provided that implementation of this specific recommendation would be permissible under the authorization; be consistent with the objectives of the BRAC and the National Defense Strategy; and would not subvert the selection criteria. In addition, DOD has taken action to review major cost drivers associated with the relocation of personnel, such as IT cost estimates, which will be improved to account for a variety of factors within its cost tool. As of March 2020, Congress had not authorized another round of BRAC; nevertheless, together, these actions meet the intent of our recommendation.
Department of Defense Contingent on the authorization of a future BRAC round, and to increase confidence in the fidelity of the cost estimates that DOD submits to the BRAC Commission for a future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to update COBRA guidance to require users to provide a narrative explaining the process, sources, and methods used to develop the data entered into COBRA to develop military personnel positionelimination savings.
Closed – Implemented
DOD concurred with the original recommendation when the report was issued. DOD noted it would update guidance to emphasize the need to identify source documentation for personnel changes. Further, in an October 2019 memorandum, DOD agreed to implement all recommendations with which it had concurred or partially concurred should Congress authorize a future BRAC and provided that implementation of this specific recommendation would be permissible under the authorization; be consistent with the objectives of the BRAC and the National Defense Strategy; and would not subvert the selection criteria. As of March 2020, Congress had not authorized another round of BRAC; nevertheless, the actions taken by DOD meet the intent of our recommendation.
Department of Defense Contingent on the authorization of a future BRAC round, and to improve planning for measuring the results of implementing the BRAC recommendations for a future BRAC round, the Secretary of Defense should direct the Deputy Under Secretary of Defense (Installations and Environment) to identify appropriate measures of effectiveness and develop a plan to demonstrate the extent to which the department achieved the results intended from the implementation of the BRAC round.
Closed – Implemented
Although DOD did not initially concur with this recommendation, in October 2019 DOD committed to reviewing variances between original cost and savings estimates and the actual costs and savings as part of the Business Plans process, should another BRAC round occur. As of March 2020, Congress had not authorized another round of BRAC, but the commitment to review variances meets the intent of our recommendation.
Department of Defense
Priority Rec.
Contingent on the authorization of a future BRAC round, and to improve planning for measuring the results of implementing the BRAC recommendations for a future BRAC round, the Secretary of Defense should direct the Deputy Under Secretary of Defense (Installations and Environment) to establish a target for eliminating excess capacity in its initiating guidance to high-level department-wide leadership, consistent with the BRAC selection criteria chosen for a future BRAC round.
Closed – Not Implemented
DOD did not concur with the original recommendation when the report was issued. As of October 2019, DOD stated that no further action by the department will be taken. As of March 2020, Congress has not authorized a new round of BRAC.
Department of Defense
Priority Rec.
Contingent on the authorization of a future BRAC round, and to provide more-complete information and increased visibility into the expected costs and savings for individual BRAC closures or realignments, when planning any potential future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to limit the practice of bundling many potentially stand-alone realignments or closures into single recommendations.
Closed – Implemented
DOD did not concur with the original recommendation when the report was issued. However, as of October 2019, DOD stated that it would implement our recommendation if this work is done as part of the Business Plan process right after BRAC actions become legal obligations. In addition, DOD committed to implement recommendation #9 to itemize the costs and savings associated with each major discrete action in bundled multiple realignments and closure recommendations. These combined actions would help address our finding that bundling limited visibility over the estimated costs and savings for individual closures or realignments that are elements of the bundle, and would improve visibility and oversight for future BRAC rounds . As of March 2020, Congress had not authorized a new round of BRAC; nevertheless, these actions meet the intent of our recommendation.
Department of Defense Contingent on the authorization of a future BRAC round, and to provide more-complete information and increased visibility into the expected costs and savings for individual BRAC closures or realignments, when planning any potential future BRAC round, the Secretary of Defense should direct the Under Secretary of Defense (Acquisition, Technology and Logistics) to if DOD determines that bundling multiple realignments or closures into one recommendation is appropriate, itemize the costs and savings associated with each major discrete action in its report to the BRAC Commission.
Closed – Implemented
DOD partially concurred with the original recommendation when the report was issued. DOD commented that, when appropriate, the cost savings associated with individual actions within the bundle could be identified. Further, in an October 2019 memorandum, DOD agreed to implement all recommendations with which it had concurred or partially concurred should Congress authorize a future BRAC and provided that implementation of this specific recommendation would be permissible under the authorization; be consistent with the objectives of the BRAC and the National Defense Strategy; and would not subvert the selection criteria. As of March 2020, Congress had not authorized another round of BRAC; nevertheless, these actions meet the intent of our recommendation.
Department of Defense Contingent on the authorization of a future BRAC round, and to ensure that the BRAC Commission receives timely access to information supporting BRAC recommendations for its review, the Secretary of Defense should develop a process to ensure that any data-security issues are resolved in time to provide all information to the BRAC Commission in a timely manner by conducting a security review of all BRAC data during DOD's recommendation development process, to include a review of the aggregation of unclassified data for potential security concerns and possible classification if necessary.
Closed – Implemented
DOD concurred with the original recommendation when the report was issued. Further, in an October 2019 memorandum, DOD agreed to implement all recommendation with which it had concurred or partially concurred should Congress authorize a future BRAC and provided that implementation of this specific recommendation would be permissible under the authorization; be consistent with the objectives of the BRAC and the National Defense Strategy; and would not subvert the selection criteria. As of March 2020, Congress had not authorized another round of BRAC; nevertheless, this commitment to implement meets the intent of our recommendation.

Full Report

GAO Contacts

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Congressional oversightMilitary base realignmentsMilitary basesRequirements definitionCost estimatesProgram implementationMilitary base closuresMilitary forcesInformation technologyDefense budgets