Skip to main content

Checked Baggage Screening: TSA Has Deployed Optimal Systems at the Majority of TSA-Regulated Airports, but Could Strengthen Cost Estimates

GAO-12-266 Published: Apr 27, 2012. Publicly Released: Apr 27, 2012.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Transportation Security Administration’s (TSA) Electronic Baggage Screening Program (EBSP) reports that 76 percent of the airports (337 of 446) the agency regulates for security have a mix of in-line and stand-alone baggage screening configurations that best meet airport needs (i.e., optimal systems). However, only 36 percent (10 of 28) of the nation’s larger airports—based on factors such as the total number of takeoffs and landings annually—have complete optimal systems. This is because the larger airports generally need more complex in-line systems and often require a significant amount of airport infrastructure modification and construction. In August 2011, TSA shifted its focus from installing optimal baggage screening systems to replacing aging machines (recapitalization). However, TSA plans to continue to optimize systems during many of its recapitalization projects.

Using TSA cost estimates, GAO estimates that reducing the portion of costs that TSA pays for facility modifications associated with the installation of optimal baggage screening systems, from 90 percent to 75 percent, would lower the federal government’s cost for airport modification projects it supports by roughly $300 million from fiscal year 2012 through fiscal year 2030. Officials from all 10 airports with whom GAO spoke stated that airports benefit from the installation of integrated, in-line baggage screening systems. The primary benefit—cited by representatives from 9 of the airports GAO visited—is that passenger congestion is reduced by removing stand-alone machines from lobbies or ticketing areas. Other benefits cited by airports included a reduction in lost baggage and increased screening and passenger throughput. However, for a variety of reasons, representatives from 8 of 10 airports GAO visited opposed a reduction in the federal cost share for related airport modifications.

TSA established cost estimates for the EBSP to help identify total program cost, recapitalization cost, and potential savings resulting from installing optimal systems, but its processes for developing these estimates do not fully comply with best practices. These include, among other things, ensuring that the estimates comprise all costs and are well documented. For example, TSA’s estimates were properly adjusted for inflation and were developed using relevant data, such as existing contracts for equipment purchases and maintenance costs. However, the estimates did not include all costs, for example, the costs associated with detecting all security threats, and many assumptions and methodologies underlying the cost model were not clearly documented. As highlighted in GAO’s past work, a high-quality, reliable cost estimation process provides a sound basis for making accurate and well-informed decisions about resource investments and budgets and thus is critical to the success of a program. Developing accurate cost estimates would help ensure that the program does not experience unanticipated cost growth and program funding needs resulting from future recapitalization and facility modification activities. In addition, TSA is working with the Department of Homeland Security (DHS) to develop an approved acquisition program baseline, which according to DHS guidance is the contract between program and departmental oversight officials for what will be delivered, how it will perform, and what it will cost. TSA expects the baseline to be approved in May 2012.

Why GAO Did This Study

TSA’s EBSP, one of DHS’s largest acquisition programs, aims to improve security and lower program life cycle costs by optimizing checked baggage screening systems that best meet the needs of the nation’s airports. This includes, among other things, the integration of baggage screening equipment into baggage handling systems, referred to as in-line systems. Installing in-line systems typically requires airports to undertake costly facility modification projects, for which TSA will generally reimburse up to the applicable federal cost share. As requested, GAO examined (1) the status of TSA’s efforts to install optimal checked baggage screening systems in collaboration with airports, (2) how reducing the federal cost share for eligible airport modification projects from 90 percent to its previous level of 75 percent would affect the amount that TSA pays for modifications, and (3) whether TSA’s methods for estimating and validating costs for the EBSP are consistent with best practices. GAO reviewed EBSP planning and status documents, compared TSA’s cost estimation approach against GAO best practices, and visited 10 airports selected in part based on the status of the EBSP optimization at these airports. Although the results from these visits are not generalizable, they provided insights into the program.

Recommendations

GAO recommends that TSA ensure that its life cycle cost estimates conform to cost estimating best practices. DHS concurred with GAO’s recommendation.

Recommendations for Executive Action

Agency Affected Recommendation Status
Transportation Security Administration In order to strengthen the credibility, comprehensiveness, and reliability of TSA's cost estimates and related savings estimates for the EBSP, the Administrator of TSA should ensure that its life cycle cost estimates conform to cost estimating best practices.
Closed – Implemented
In their agency comments, DHS stated that it was implementing a management directive that applies DHS guidance and best practices from the GAO Cost Estimating and Assessment Guide. As part of this effort, TSA was (1) establishing a working group and executive board to review program cost estimates to validate whether the estimates are credible and affordable and meet GAO's best practices, (2) requiring all life cycle cost estimates to be approved by DHS to ensure consistency and quality across TSA programs, (3) purchasing and training its employees on specialized cost estimating software, and (4) initiating actions to hire additional cost estimating personnel. DHS anticipated that these actions would be completed by December 31, 2012. On August 17, 2012, DHS provided their 60-day response letter on actions taken and reported that:(1) TSA had approved a management directive establishing a working group and executive board to review program cost estimates. (2) This directive also required all LCCEs to be approved by the Component Acquisition Executive to ensure consistency and quality across TSA programs. (3) The TSA LCCE implementation Integrated Product Team completed the purchase of Automated Cost-Estimating Integrated Tools (ACEIT), a government-owned, cost estimating software suite that is recommended by DHS to all components. (4) Finally, TSA's Acquisition Management Functional Division continues to process hiring actions for additional federal cost-estimating personnel. On September 5, 2012, TSA reported that the EBSP has a number of initiatives that are being evaluated across the program to reduce overall operating costs to include completing an engineering analysis on the useful life of the EDS, exploring refurbishment options for the EDS to extend useful life of equipment (e.g. bearing replacements on equipment in the field), implementing just-in-time delivery of equipment where possible, and a number of other initiatives. Once completing these initiatives, TSA planned to update/rebaseline the LCCE to reflect the true life cycle cost of the program as well as transition the LCCE into a format that makes it more dynamic for the program. TSA estimated that it planned to complete these efforts by September 2013. During meetings in January 2014 and May 2014, TSA provided a demonstration of the ACEIT model and updated their cost estimating best practices to include four characteristics of a high quality and reliable cost estimate that are comprehensive, well-documented, accurate and credible. As a result, the recommendation is closed as implemented.

Full Report

GAO Contacts

Topics

AirportsBaggageExplosives detection systemsCost estimatesBaggage screeningExplosives trace detectionChecked baggage screeningAcquisitionBest practicesLife cycle costs