Contingency Contracting: Improved Planning and Management Oversight Needed to Address Challenges with Closing Contracts
Highlights
Since 2002, DOD obligated at least $166.6 billion on contracts supporting reconstruction and stabilization efforts in Iraq and Afghanistan. Many of these contingency contracts, in particular those awarded in Iraq, need to be closed. Contract closeout is a key step to ensure the government receives the goods and services it purchased at the agreed upon price and, if done timely, provides opportunities to use unspent funds for other needs and reduces exposure to other financial risks. To assess DOD's efforts to close its Iraq contracts, GAO examined the (1) number of contracts that are eligible for closeout and the extent to which they will be closed within required time frames, (2) factors contributing to contracts not being closed within required time frames, (3) steps DOD took to manage the financial risks associated with not closing contracts within required time frames, and (4) extent to which DOD captured and implemented lessons learned from closing its Iraq contracts. GAO reviewed contingency contracting guidance, analyzed contract and closeout data for contracts awarded between fiscal years 2003 and 2010, and interviewed DOD officials from six organizations responsible for awarding or closing out these contracts.
DOD does not have visibility into the number of its Iraq contracts eligible for closeout, but available data indicate that DOD must still review and potentially close at least 58,000 contracts awarded between fiscal years 2003 and 2010. GAO's analysis indicates that relatively few of its contracts will be closed within required time frames. For example, about 90 percent of the limited number of contracts for which DOD could provide closeout data are already over age for closeout. The U.S. Central Command's Contracting Command (C3) and its predecessors, which awarded many of DOD's Iraq contracts, did not have sufficient internal controls to ensure that contracting data were accurate and complete. C3's management visibility was further affected by limitations of its information systems, staff turnover, and poor contract administration. DOD's ability to close its contracts has been hindered by the lack of advance planning, workforce shortfalls, and contractor accounting challenges. For example, DOD's contingency contracting doctrine and guidance do not specifically require advanced planning for contract closeouts. DOD took steps in 2008 to address its backlog of contracts needing to be closed but such actions came too late to make significant difference in closing contracts within required time frames. DOD is now transitioning responsibility for closing out C3's contracts to the Army Contracting Command. Staffing challenges, however, during this transition have hindered efforts to close these contracts. Efforts to close large, cost-type contracts have been further hindered by Defense Contract Audit Agency staffing shortages and unresolved issues with contractors' accounting practices, which have delayed audits of the contractors' incurred costs. DOD's efforts to identify unspent contract funds and improper payments--two examples of financial risks that timely closeout of contracts may help identify--are hindered by limited visibility into its Iraq contracts. DOD identified at least $135 million in unspent funds that could potentially not be available to meet other DOD needs. If not used, these funds will be returned to the U.S. Treasury at the end of fiscal year 2011. Should DOD identify a need to pay for an unanticipated cost on these contracts, it will need to use other funds that are currently available. Additionally, instances of improper payments and potential fraud were sometimes found years after final contract deliveries were made, making it harder for DOD to recover funds owed to it and increasing the risk that it may need to pay contractors interest fees on late payments. DOD has identified and addressed some of the problems related to the closeout of Iraq contracts, but the growing backlog of over 42,000 Afghanistan contracts that need to be closed suggests the underlying causes have not been resolved. DOD officials noted that the lessons learned in Iraq highlight the need to improve contract data, increase the emphasis on contract administration and closeout, and improve contingency contracting doctrine and guidance. DOD officials reported that actions are underway to correct these deficiencies in future contingencies, but fully implementing these initiatives may take several years. GAO is making three recommendations to ensure DOD has sufficient resources to close its Iraq and Afghanistan contracts and to better plan for and improve visibility of closeout efforts in future contingencies. DOD concurred with each of the recommendations.
Recommendations
Recommendations for Executive Action
Agency Affected | Recommendation | Status |
---|---|---|
Department of Defense | To help address the current backlog of contracts supporting the efforts in Iraq and Afghanistan that need to be closed out, the Secretary of Defense should direct the Secretary of the Army to take steps to ensure the Army Contract Command-Rock Island's (ACC-RI) planned resources are adequate to meet forecasted closeout demands. |
The Department of the Army determined the total number of contracts that needed to be closed, determined the number of personnel required to close the contracts, and took steps to hire an adequate number of staff to close the contracts. The Army reported that as of June 2015, over 99 percent of the Iraq and Afghanistan contracts that needed to be closed out were closed.
|
Department of Defense | To help improve DOD's ability to manage the closeout of contracts awarded in support of future contingencies, the Secretary of Defense, in coordination with the Chairman of the Joint Chiefs of Staff, should revise DOD's contingency contracting doctrine and guidance to reflect the need for advanced planning for contract closeout. |
In May 2012, in response to our recommendation, DOD amended the Defense Federal Acquisition Regulation Supplement (DFARS) Procedures, Guidance, and Information (PGI) to require the written acquisition plans for contracts in support of contingency operations to include a plan for contract closeout support as necessary. Further, in July 2014, DOD revised its contingency contracting planning doctrine, Joint Publication 4-10, to emphasize that in-theater contracting planning should include ensuring that contracts are closed out in a timely manner and account for personnel turnover and contracting workload.
|
Department of Defense | To help improve DOD's ability to manage the closeout of contracts awarded in support of future contingencies, the Secretary of Defense, in coordination with the Chairman of the Joint Chiefs of Staff, should require senior contracting officials to monitor and assess the progress of contract closeout activities throughout the contingency operation so steps may be taken if a backlog emerges. |
In May 2012, DOD amended the Defense Federal Acquisition Regulation Supplement (DFARS) to require heads of contracting activities to monitor and assess on a regular basis the progress of contingency contract closeout activities and take appropriate steps if a backlog occurs.
|