Superfund:

EPA's Estimated Costs to Remediate Existing Sites Exceed Current Funding Levels, and More Sites Are Expected to Be Added to the National Priorities List

GAO-10-380: Published: May 6, 2010. Publicly Released: Jun 22, 2010.

Additional Materials:

Contact:

David C. Trimble
(202) 512-6225
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

At the end of fiscal year 2009, the Environmental Protection Agency's (EPA) National Priorities List (NPL) included 1,111 of the most seriously contaminated nonfederal hazardous waste sites. Of these sites, EPA had identified 75 with unacceptable human exposure, 164 with unknown exposure, and 872 with controlled exposure that may need additional cleanup work. EPA may fund remedial actions--long-term cleanup--from its trust fund, and compel responsible parties to perform or reimburse costs of the cleanup. GAO was asked to determine (1) the cleanup and funding status at currently listed nonfederal NPL sites with unacceptable or unknown human exposure; (2) what is known about EPA's future cleanup costs at nonfederal NPL sites; (3) EPA's process for allocating remedial program funding; and (4) how many NPL sites some state and EPA officials expect to be added in the next 5 years, and their expected cleanup costs. GAO analyzed Superfund program data, surveyed and interviewed EPA officials, and interviewed state officials.

At over 60 percent of the 239 nonfederal NPL sites with unacceptable or unknown human exposure, all or more than half of the work remains to complete the remedial construction phase of cleanup, according to EPA regional officials. By the end of fiscal year 2009, EPA had expended $3 billion on the 75 sites with unacceptable human exposure and $1.2 billion on the 164 sites with unknown exposure. Despite the relatively high level of expenditures at sites with unacceptable exposure, EPA officials told GAO that, in managing limited resources, some sites have not received sufficient funding for construction to be conducted in the most time and cost efficient manner. EPA's future costs to conduct remedial construction at nonfederal NPL sites will likely exceed recent funding levels. EPA officials estimate that EPA's costs will be from $335 to $681 million each year for fiscal years 2010 to 2014, which exceed the $220 to $267 million EPA allocated annually for remedial actions from fiscal years 2000 to 2009. In addition, these cost estimates are likely understated, since they do not include costs for sites that are early in the cleanup process or for sites where a responsible party is currently funding remedial construction but may be unable to do so in the future. Also, according to EPA officials, EPA's actual costs are often higher than its estimates because contamination is often greater than expected. EPA allocates funds separately for preconstruction activities--such as remedial investigation and remedial design--and remedial actions. EPA headquarters allocates funds for preconstruction activities to the regions for them to distribute among sites. For remedial actions, headquarters works in consultation with the regions to allocate funds to sites. EPA officials told GAO that EPA prioritized sites to receive the $582 million in American Recovery and Reinvestment Act funds in a manner similar to the way EPA prioritizes sites for remedial actions. Limited funding has delayed preconstruction activities and remedial actions at some sites, according to EPA officials. EPA regional officials estimated that from 101 to 125 sites--about 20 to 25 sites per year--will be added to the NPL over the next 5 years, which is higher than the average of about 16 sites per year listed for fiscal years 2005 to 2009. Most of the 10 states' officials GAO interviewed also expect an increase in the number of sites listed from their states. However, neither EPA regional officials nor state officials were able to provide cost estimates for cleaning up many of the sites. In addition, the number of sites eligible for listing could increase if EPA decides to assess the relative risk of vapor intrusion--contaminated air that seeps into buildings from underground sources--a pathway of concern among EPA regional officials and state officials interviewed. Although sites with vapor intrusion can pose considerable human health risks, EPA's Hazard Ranking System--the mechanism used to identify sites that qualify for NPL listing--does not recognize these risks; therefore, unless a site with vapor intrusion is listed on some other basis, EPA cannot clean up the site through its remedial program.

Status Legend:

More Info
  • Review Pending-GAO has not yet assessed implementation status.
  • Open-Actions to satisfy the intent of the recommendation have not been taken or are being planned, or actions that partially satisfy the intent of the recommendation have been taken.
  • Closed-implemented-Actions that satisfy the intent of the recommendation have been taken.
  • Closed-not implemented-While the intent of the recommendation has not been satisfied, time or circumstances have rendered the recommendation invalid.
    • Review Pending
    • Open
    • Closed - implemented
    • Closed - not implemented

    Recommendation for Executive Action

    Recommendation: To better identify sites that may be added to the NPL, the Administrator of EPA should determine the extent to which EPA will consider vapor intrusion as part of the NPL listing process and how this will affect the number of sites listed in the future.

    Agency Affected: Environmental Protection Agency

    Status: Open

    Comments: The Hazard Ranking System (HRS) is the principal mechanism EPA uses to evaluate sites for eligibility for NPL listing. Through discussions with EPA Regional management and staff, EPA evaluated whether vapor intrusion needs to be more specifically addressed within the HRS and made a decision in November 2010 to potentially proceed with a rulemaking to amend the HRS, adding an additional component to address vapor intrusion threats. A Notice of Opportunity for Public Input was published in the Federal Register on January 31, 2011 (76 FR 5370) in which EPA solicited stakeholder input on whether to add a vapor intrusion component in the HRS. Comments received from the FR Notice, as well as four public listening sessions held during February and March 2011, helped guide the decision to proceed with a Notice of Proposed Rulemaking. EPA has formally initiated the rulemaking process. The proposed rule was submitted to OMB on February 3, 2012 for inter-agency review under Executive Order 12866. The 90-day review has not yet begun. (EPA did not address the second part of the recommendation regarding determining the impact on the number of NPL sites).

    Jul 28, 2014

    Jul 16, 2014

    Jul 15, 2014

    Jul 9, 2014

    Jun 30, 2014

    Jun 16, 2014

    May 22, 2014

    May 21, 2014

    May 19, 2014

    May 12, 2014

    Looking for more? Browse all our products here