Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of June 27, 2008

GAO-08-900T Published: Jul 08, 2008. Publicly Released: Jul 08, 2008.
Jump To:
Skip to Highlights

Highlights

This testimony is based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; our observations on the progress of work at the CVC construction site; and our discussions with the CVC team (AOC and its major CVC contractors) and AOC's Chief Fire Marshal. We also reviewed AOC's construction management contractor's periodic schedule assessments.