Capitol Visitor Center:

Update on Status of Project's Schedule and Cost as of May 22, 2008

GAO-08-811T: Published: May 22, 2008. Publicly Released: May 22, 2008.

Additional Materials:

Contact:

Terrell G. Dorn
(202) 512-3000
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

This testimony is based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; our observations on the progress of work at the CVC construction site; and our discussions with the CVC team (AOC and its major CVC contractors) and AOC's Chief Fire Marshal. We also reviewed AOC's construction management contractor's periodic schedule assessments, proposed change order log, and weekly reports on construction progress.

Since the April 15, 2008, CVC hearing, the project's construction and fire alarm acceptance testing have moved forward, and despite continued delays in certain CVC and expansion space work, AOC still believes that the project will be ready to open in November 2008. According to AOC's construction management contractor, in dollar terms, the overall CVC project remains 99 percent complete. However, risks to the project's schedule remain in several time-critical activities, including the fire alarm acceptance testing. Many punch list items also remain to be completed, and a steady number of proposed change orders have to be resolved. At this time, however, AOC does not expect the punch list items or the proposed change orders to affect the project's completion date.

Jul 22, 2014

Jun 17, 2014

Jun 11, 2014

Jun 10, 2014

May 28, 2014

May 21, 2014

May 12, 2014

May 7, 2014

Apr 30, 2014

Looking for more? Browse all our products here