Capitol Visitor Center: Update on Status of Project's Schedule and Cost As of June 28, 2006

GAO-06-827T Published: Jun 28, 2006. Publicly Released: Jun 28, 2006.
Jump To:
Skip to Highlights

Highlights

We are pleased to be here today to assist Congressin monitoring progress on the Capitol Visitor Center (CVC) project. Our remarks will focus on the Architect of the Capitol's (AOC) progress in achieving selected project milestones and in managing the project schedule since Congress's May 24, 2006, hearing on the project. As part of this discussion, we will address a number of key challenges and risks that continue to face the project, as well as actions AOC has taken or plans to take to address these risks. In addition, we will discuss the status of the project's costs and funding. Our remarks today are based on our review of schedules and financial reports for the CVC project and related records maintained by AOC and its construction management contractor, Gilbane Building Company; our observations on the progress of work at the CVC construction site; and our discussions with the CVC team (AOC and its major CVC contractors), AOC's Chief Fire Marshal, and representatives from the U.S. Capitol Police. We also reviewed AOC's construction management contractor's periodic schedule assessments and daily reports on the progress of interior wall and floor stonework.

Full Report

Office of Public Affairs

Topics

Construction contractsContract administrationContract oversightContract performanceContractorsCost analysisCost overrunsFacility constructionFederal facilitiesFederal fundsFuture budget projectionsPublic visitor-centersSchedule slippagesCost estimates