Highway Infrastructure:

Perceptions of Stakeholders on Approaches to Reduce Highway Project Completion Time

GAO-03-398: Published: Apr 9, 2003. Publicly Released: May 12, 2003.

Additional Materials:

Contact:

Katherine A. Siggerud
(202) 512-6570
contact@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

Constructing, improving, and repairing roads is fundamental to meeting the nation's mobility needs. The Federal Highway Administration (FHWA) supplies most of the money (about $20 billion in fiscal year 2003), and state departments of transportation are primarily responsible for completing projects. Many federal and state agencies (called resource agencies) help ensure that environmental and other concerns are considered. These and other organizations have recognized that the time it takes to complete complex federally funded highway projects is too long--in some cases nearly 20 years. GAO was asked to report the views of knowledgeable officials on the most promising approaches for reducing completion time for federally funded highway projects. GAO obtained the views of 33 officials from federal, state, and private organizations with interests in federally funded roads.

Respondents from 33 organizations identified 13 approaches as most promising for reducing the time it takes to plan, design, gain approval for, and build a federally funded highway project. These approaches fell into three areas. Improving project management: Most approaches (8 of 13) focused on state-level activities that could be conducted earlier than customary, with 90 percent of respondents indicating that establishing early partnerships and early coordination among all project stakeholders is highly important to reducing project completion time. Other approaches included added flexibility for states in determining impacts on historic properties and imposing time limits on environmental reviews. Delegating environmental review and permitting authority: Between half and two-thirds of the respondents indicated that utilizing programmatic agreements between transportation and resource agencies to address commonly occurring issues, unifying overall environmental assessments with reviews of project impacts on wetlands, and creating large banks of wetlands to replace those lost at highway project sites offered significant promise for reducing project completion time. Improving agency staffing and skills: Nearly 60 percent of the respondents indicated that using interagency funding agreements in which state departments of transportation can ensure timely attention to environmental reviews of their projects by funding staff at federal or state resource agencies offered significant promise to reduce project completion time. About half of the respondents told us that adequate training of transportation staff on the requirements of all steps in completing a highway project was also a promising approach. For the most part, the respondents were not able to estimate how much time adopting one or more of these approaches might save. Respondents' views varied both within similar types of organizations (such as state departments of transportation) and across lines of responsibility or interest. Generally, agencies and other organizations with primary responsibilities for or interests in building and funding highways ranked certain approaches higher than did agencies and associations with a primary focus on resource issues, and vice versa. Nonetheless, most of the 13 most promising approaches had widespread support across organizations. Although some of these approaches are in use across the country, respondents acknowledged that the usefulness of these approaches could vary by the type of project or community values. For example, projects that are not complex or contentious would not necessarily achieve the time savings that these approaches afford for projects with complex characteristics or disagreement among stakeholders.

Status Legend:

More Info
  • Review Pending-GAO has not yet assessed implementation status.
  • Open-Actions to satisfy the intent of the recommendation have not been taken or are being planned, or actions that partially satisfy the intent of the recommendation have been taken.
  • Closed-implemented-Actions that satisfy the intent of the recommendation have been taken.
  • Closed-not implemented-While the intent of the recommendation has not been satisfied, time or circumstances have rendered the recommendation invalid.
    • Review Pending
    • Open
    • Closed - implemented
    • Closed - not implemented

    Recommendation for Executive Action

    Recommendation: In order to reduce Highway project completion time, the Secretary of Transportation should direct the Administrator, Federal Highway Administration, to consider the benefits of at least each of the 13 most promising approaches discussed in this report relative to the costs and feasibility of implementing them and take the actions needed to foster more widespread adoption of those approaches that appear to be the most cost effective.

    Agency Affected: Department of Transportation

    Status: Closed - Implemented

    Comments: According to FHWA's June 2003 report to Congress on FHWA's efforts to streamline environmental activities, it appears that the agency has considered the benefits of 10 of the 13 most promising approaches in GAO's recommendation and that the agency is fostering a more widespread use of these approaches. The three outstanding approaches included (1) Preparing preliminary environmental assessment reports, (2) holding public information meetings early, and (3) employing wetlands banking. GAO contacted FHWA to determine to what extent these three recommendations had been/would be implemented. According to the agency, all three recommendations were currently in practice and/or being promoted. For example, FHWA said that with streamlining funds, it supports preliminary assessment work in Oregon, Texas, and Indiana. FHWA also encourages the efforts of resource agencies (i.e., the liaison requirement under TEA-21) to provide state DOTs with data early to scope and plan projects. Regarding holding public information meetings early, the agency said this is accomplished, in part, when FHWA's state division office administrators and their staff encourage state DOTs to use context sensitive design (CSD). One of the criteria needed to implement CSD is early public involvement. Regarding employing wetlands banking, FHWA said it has promoted this activity for a number of years. FHWA oversees state DOT efforts to implement these programs and provides funding to support states' efforts. Currently about 12 states employ wetland banking programs--including AL, FL, IN, MN, NC, TX, and VA. Also in 2003, FHWA issued guidance under the President's National Mitigation Action Plan--an interagency action plan for wetlands mitigation.

    Jul 31, 2014

    Jul 23, 2014

    Jun 25, 2014

    Jun 24, 2014

    Jun 18, 2014

    Jun 11, 2014

    May 30, 2014

    Looking for more? Browse all our products here