Highlights

Search and rescue--one of the Coast Guard's oldest missions--involves minimizing the loss of life, injury, and property damage by aiding people and boats in distress. The Coast Guard has previously reported that its 30-year-old search and rescue communication system, called the National Distress and Response System, has several deficiencies and is difficult to maintain. Thus, the Coast Guard contracted to replace and modernize it with a new system, called Rescue 21. GAO was asked to identify the status and plans of the Coast Guard's acquisition of Rescue 21 and the technical and program risks associated with Rescue 21.

Recommendations

Recommendations for Executive Action

Agency Affected Recommendation Status
United States Coast Guard To mitigate Rescue 21 risks and ensure that adequate testing occurs and all requirements are fulfilled so that the deployed system will work as specified, the Secretary of Homeland Security should direct the Commandant of the United States Coast Guard to establish a new schedule for critical testing phases and initial operating capability.
Closed – Implemented
The Coast Guard agreed with and implemented this recommendation. In July 2004, the Coast Guard Rescue 21 program office modified the Rescue 21 contract to establish new milestones for the critical testing phases and initial operating capability. Specifically, the contract modification included a schedule for the completion of formal qualification testing, system integration testing, operational test and evaluation, and for achieving initial operating capability.
United States Coast Guard To mitigate Rescue 21 risks and ensure that adequate testing occurs and all requirements are fulfilled so that the deployed system will work as specified, the Secretary of Homeland Security should direct the Commandant of the United States Coast Guard to ensure that milestones are established for completing test plans for formal qualification testing, system integration testing, and operational testing and evaluation and that test plans address all requirements of the system.
Closed – Implemented
The Coast Guard has fully implemented this recommendation. The Coast Guard developed test plans and completed formal qualification testing (FQT), system integration testing (SIT), and operational testing and evaluation (OT&E) for the Rescue 21 system. Coast Guard developed FQT test plans on October 17, 2003 and FQT testing was conducted between January 2004 and June 2004. At that time, 4 of the 235 allocated requirements were validated and performance issues in several areas, including fault management, archive/restore, and channel performance, were found that required additional development. FQT was repeated in June 2004, at which time the remaining 231 allocated requirements were validated. The Coast Guard conducted SIT testing between August 2004 and December 2004. During this time, additional software defects were found and Coast Guard decided to have the contractor concurrently fix the SIT problems while going into the OT&E phase. The Coast Guard developed the OT&E plan on October 4, 2004, and OT&E testing was conducted between January 2005 and March 2005. As a result, further software defects were found and Coast Guard requested additional changes to the human systems interface based on operator comments. The changes to the human systems interface were prioritized into three builds, the first of which was required by the Coast Guard before it would approve the initial operating capability. The remaining two builds are currently being negotiated with the contractor and represent additional development. Rescue 21 was deployed on December 20, 2005, with an initial operating capability and is currently being used at Atlantic City, New Jersey, and Chincoteague, Virginia. As a result of FQT, SIT, and OT&E testing, Coast Guard is taking steps to ensure that the system requirements are adequately fulfilled, so that the deployed Rescue 21 system will meet stakeholder and end-user needs.