Brian X. Scott protests the cancellation of request for proposals (RFP) No. W91GDW-08-R-4006, issued by the Joint Contracting Command-Iraq/Afghanistan (JJC-I/A) for executive agent services for the Iraqi-Based Industrial Zone (I-BIZ) program. Mr. Scott complains that the cancellation of the RFP after receipt of proposals was unreasonable and was the result of bias against him.
B-310970; B-310970.2, Brian X. Scott, March 26, 2008
Decision
Brian X. Scott for the protester.
Capt. John J. Cho and Col. David P. Harney, Department of the Army, for the agency.
Guy R. Pietrovito, Esq., and James A. Spangenberg, Esq., Office of the General Counsel, GAO, participated in the preparation of the decision.
DIGEST
In a negotiated procurement, agency had a reasonable basis to cancel, after receipt of proposals, a solicitation for executive agent services, where the agency reasonably found that it would be more advantageous to satisfy its requirements through an existing contract.
DECISION
Brian X. Scott protests the cancellation of request for proposals (RFP) No. W91GDW-08-R-4006, issued by the Joint Contracting Command-Iraq/Afghanistan (JJC-I/A) for executive agent services for the Iraqi-Based Industrial Zone (I-BIZ) program. Mr. Scott complains that the cancellation of the RFP after receipt of proposals was unreasonable and was the result of bias against him.
The RFP provided for the award of a contract for an executive agent to oversee the I'BIZ program at the Victory Base Complex in
[t]his will consist of providing expert advice, assistance, and guidance on establishing I-BIZ Iniatives for [Multi-National Forces -], as well as identifying Iraqi candidate businesses and labor for I-BIZ initiatives. Iraq
In addition, the executive agent would submit advisory suggestions when necessary with policy recommendation to ensure theater wide requirements are integrated and synchronized with current and future theater level operations. RFP, SOW, para. 3.0. The executive agent was required to, at a minimum, be bilingual in English and Arabic, have a secret security clearance, and 2 years of experience working with business development projects in developing nations.
The agency received three proposals, including Mr. Scott's, by the November 23 closing date for receipt of proposals. Mr. Scott's and another offeror's proposal were transmitted for evaluation to the Resources and Sustainment, Sustainment and Fusion Directorate of the Multi-National Force-Iraq, the requiring activity for the RFP.[2] Prior to the requiring activity's receipt of the proposals for evaluation, the activity became aware of an existing JJC-I/A contract for Bilingual, Bicultural Advisor-Subject Matter Expert (BBA-SME) services, under which the I-BIZ executive agent might be obtained. The activity considered the use of the BBA-SME contract, but also evaluated Mr. Scott's and the other offeror's proposals. Agency Report (AR), Tab 15, Statement of Contracting Action Officer on the Deputy Chief of Staff, Resources and Sustainment, Sustainment Fusion Directorate of the Multi-National Force-Iraq.
The requiring activity found both proposals to be deficient in a number of respects. With respect to Mr. Scott's proposal, the requiring activity found that he
did not provide personnel experienced in accomplishing the requirement, did not have prior experience in accomplishing the requirement, did not have the desired Arabic language skills, had too much turnover of key personnel to establish the long term relationships anticipated in the requirement, and only had an interim secret security clearance.
Contracting Officer's Statement at 2.
The agency concluded that the services solicited by the RFP could be satisfied under the existing BBA-SME contract and that, in fact, the requiring activity was attempting to satisfy the I-BIZ requirement using both the I-BIZ solicitation and the BBA-SME contract. AR at 3. The agency decided, after its evaluation of Mr. Scott's and the other offeror's proposal, that satisfying this requirement under the BBA-SME contract would be more advantageous than continuing under the RFP. AR, Tab 6, Army E-Mails (
In a negotiated procurement, an agency has broad authority to decide whether to cancel a solicitation, and to do so need only establish a reasonable basis. The Borenstein Group, Inc., B-309751,
Mr. Scott contends that the I-BIZ executive agent services are outside the scope of the BBA-SME contract. Specifically, the protester contends that the BBA-SME contract provides for only expert and advisory services, with no responsibility for nothing, not for Executive Agents, who are responsible for program success. Protester's Supplemental Comments at 9.
We disagree with Mr. Scott that the executive agent services solicited by the RFP are not within the scope of the BBE-SME contract. As noted above, the RFP sought a bilingual individual with a secret security clearance and experience to provide expert advice, assistance and guidance with respect to establishing I-BIZ initiatives. In addition, the RFP described the executive agent's services as including recommend[ing] policy and at the direction of [Multi-National Forces -
We also find reasonable the agency's conclusion that it would be more advantageous to obtain the executive agent services under the existing BBA-SME contract rather than continuing with its procurement under this RFP. As noted above, the agency found that the protester's and the other offeror's proposals were deficient, and in particular that Mr. Scott's proposal did not demonstrate that he would satisfy the RFP's experience, Arabic language, and security clearance requirements. See Contracting Officer's Statement at 2. Although Mr. Scott disagrees with the agency's evaluation, he does not establish that the agency's concerns with his and the other offeror's proposals did not provide the agency with a reasonable basis to conclude it would be more advantageous to use its existing contract to satisfy these requirements. In addition, the agency concluded that obtaining these services from the BBA-SME contract, rather than under the RFP, could result in cost savings and would relieve the agency of having to administer two contracts.
Mr. Scott also complains that the agency's cancellation of the RFP was the result of bad faith and the agency's institutional bias against Mr. Scott. Specifically, the protester argues that it has protested other JCC-I/A procurements to GAO, which Mr. Scott described as essentially political protests to challenge the government's policy in
Government officials are presumed to act in good faith and a protester's claim that contracting officials were motivated by bias or bad faith must be supported by convincing proof. Our Office will not attribute unfair or prejudicial motives to procurement officials on the basis of inference or supposition. Shinwha Elecs., B'290603 et al.,
The protest is denied.
Gary L. Kepplinger
General Counsel
[1] The stated purpose for the Iraqi First program is to develop the Iraqi economy by increasing
[2] The agency states it has no information explaining why the proposal of the third offeror was not forwarded to the requiring activity for evaluation.