This is the accessible text file for GAO report number GAO-09-852R 
entitled 'Defense Logistics: Observations on Army's Implementation of 
the Logistics Modernization Program' which was released on July 8, 
2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

GAO-09-852R: 

United States Government Accountability Office: 
Washington, DC 20548: 

July 8, 2009: 

The Honorable Carl Levin:
Chairman:
The Honorable John McCain:
Ranking Member:
Committee on Armed Services:
United States Senate: 

The Honorable Ike Skelton:
Chairman:
The Honorable Howard McKeon:
Ranking Member:
Committee on Armed Services:
House of Representatives: 

Subject: Defense Logistics: Observations on Army's Implementation of 
the Logistics Modernization Program: 

This letter formally transmits the enclosed briefing in response to 
House Report No. 110-652, which accompanied the Duncan Hunter National 
Defense Authorization Act for Fiscal Year 2009 (Pub. L. No. 110-417). 
The House report directed the Secretary of the Army to submit a report 
on Logistics Modernization Program (LMP) implementation at Army depots 
and the expected end-state capabilities of LMP to the Senate Committee 
on Armed Services, the House Committee on Armed Services, and GAO by 
January 31, 2009. The House report also directed us to review the 
report submitted by the Secretary of the Army for completeness and to 
provide a report to the Senate Committee on Armed Services and the 
House Committee on Armed Services by March 31, 2009. On March 31, 2009, 
we provided the enclosed briefing to staff of your committees to 
satisfy this mandate. 

We are sending copies of this report to the appropriate congressional 
committees. We are also sending copies to the Secretary of Defense; the 
Deputy Secretary of Defense; the Under Secretary of Defense for 
Acquisition, Technology and Logistics; and the Secretary of the Army. 
This report will also be available at no charge on our Web site at 
[hyperlink, http://www.gao.gov]. 

Please contact William M. Solis at (202) 512-8365 or solisw@gao.gov, 
Asif A. Khan at (202) 512-9859 or khana@gao.gov, or Nabajyoti Barkakati 
at (202) 512-4499 or barkakatin@gao.gov if you or your staff have 
questions on matters discussed in this report. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Key contributors to this report were J. 
Chris Martin, Senior Technologist; David Schmitt, Assistant Director; 
Evelyn Logue; Darby Smith; and Jim Melton. 

Signed by: 

William M. Solis:
Director, Defense Capabilities and Management: 

Signed by: 

Asif A. Khan:
Director, Financial Management and Assurance: 

Signed by: 

Nabajyoti Barkakati:
Chief Technologist:
Applied Research and Methods:
Center for Technology and Engineering: 

Enclosure: 

[End of section] 

Enclosure: 

Army’s Implementation of the Logistics Modernization Program: 

Congressional Briefing: 
March 31, 2009: 

Introduction: 

In February 1998, the Army Materiel Command began the Logistics
Modernization Program (LMP) to replace its existing material
management systems—the Commodity Command Standard System and the 
Standard Depot System. These systems have been in operation for more 
than 30 years. 

LMP is intended to transform logistics operations in six core 
processes: order fulfillment, demand and supply planning, procurement, 
asset management, material management, and financial management. 

When fully implemented, LMP is expected to manage goods and services 
valued at about $40 billion, including 6 million Army inventory items. 

GAO has previously reported on problems the Army has encountered in its
efforts to implement LMP.[Footnote 1] The specific problems related to: 

* data conversion errors that resulted in LMP containing inaccurate
unit prices or units of issue for certain materials; 

* billing and collection errors whereby some customers were not billed 
for costs that should have been included in their bills and other
customers were overbilled; 

* requirements management and testing process did not comply with
best practices, and; 

* a lack of an independent verification and validation process. 

House Report 110-652 directed the Secretary of the Army to report to 
the House and Senate Armed Services Committees and GAO by January 31, 
2009, on the Army’s efforts to implement LMP. The Army submitted its 
report to the House and Senate Armed Services Committees and GAO on 
October 21, 2008. In addition, the House report: 

* stipulated that the Army’s report on LMP address nine specific areas 
and; 

* directed GAO to review the Army’s report for completeness and to 
report to the House and Senate Armed Services Committees by March 31, 
2009. 

The nine specific areas that the Army was to report upon were: 

1) expected LMP capabilities at the levels of depot production, 
business operations and financial management, and Headquarters Army 
Materiel Command; 

2) specific LMP capabilities implemented at each depot; 

3) date of expected implementation at each depot; 

4) description of how LMP will forecast future maintenance capacity and 
drive budgetary decisions; 

5) percentage of workforce at each depot expected to be proficient on 
the system; 

6) strategy to educate and train depot employees on system capabilities 
and the new business approach to resource planning and supply chain 
management as a result of LMP implementation; 

7) detailed plan for ensuring that 100 percent of each depot’s 
operating files are loaded by the planned date of implementation at 
each depot; 

8) leveraging of lessons learned from previous implementations; and; 

9) detailed risk-mitigation strategy to support current production in 
the event that LMP implementation is not as successful as planned. 

Objectives: 

Our objectives were as follows: 

1. Determine the extent to which the Army’s report addressed the nine 
specific areas identified in the House committee report. 

2. Ascertain the specific actions the Army has taken, has under way, or 
has planned to address GAO’s prior recommendations pertaining to the 
Army’s implementation of LMP. 

3. Evaluate the management processes and controls that the Army 
established to assess the feasibility of future LMP deployments. 

Summary of Observations: 

Our review and analysis of the Army’s October 21, 2008, report to the 
House and Senate Armed Services Committees found that the report 
provided the required information to address each of the nine specified 
areas and thereby satisfied the reporting requirement. (See page 10.) 

The Army has begun to implement virtually all of GAO’s prior 
recommendations related to LMP to address issues related to data 
conversion, billing and collection, requirements management and 
testing, and independent verification and validation. The effective
implementation of these recommendations should help the Army to reduce 
its risk to acceptable levels. (See pages 11-15.) 

The Army has management processes and controls in place to assess the
feasibility of future LMP deployments, enabling it to understand the 
risks associated with making a deployment decision and evaluate whether 
those risks are acceptable. (See pages 16-28.) 

* The Army recognizes that deploying a system such as LMP can never be 
a risk-free proposition and that problems will arise after deployment
regardless of the actions taken prior to deployment. 
- Ability to go back to the legacy systems if needed. 

* The Army has a risk management approach in place to minimize the 
effects of those problems to provide reasonable assurance that depot 
operations in support of the warfighter are not significantly 
disrupted. 
- Enhanced help desk support to understand the “root cause” of problems 
identified by users and help those users immediately where possible. 

Background: 

The Army began efforts to implement LMP in 1999, with the intent of 
having the system fully deployed by June 2004. 

* LMP began operations in July 2003 at Tobyhanna Army Depot, the 
Communications-Electronics Command, the Army Materiel Command, and the 
Defense Finance and Accounting Service. No additional sites have been 
added since that time. 

* The Army will decide in April 2009 whether to have additional
deployments of LMP. 

As of September 2008, the Army has obligated approximately $880 million 
for the development and implementation of LMP. 

Objective 1 Observations: Mandated Army Report Provided Required 
Information: 

Our review and analysis of the Army’s October 21, 2008, report to the 
House and Senate Armed Services Committees found that the report 
provided the required information to address each of the nine specified 
areas and thereby satisfied the reporting requirement. 

The Army’s report provided details on (1) expected LMP capabilities, 
(2) LMP capabilities implemented at depots, (3) date of expected 
implementation, (4) how LMP will forecast maintenance capacity and 
drive budgetary decisions, (5) percentage of workforce expected to be 
proficient, (6) strategy to educate employees on LMP capabilities, (7) 
a plan to ensure the depot’s operating files are loaded into LMP, (8) 
leveraging of lessons learned, and (9) a detailed risk-mitigation 
strategy in the event that LMP implementation is not successful. 

Objective 2 Observations: Prior GAO Recommendations: 

The Army has acted to implement virtually all of GAO’s prior 
recommendations related to LMP. The effective implementation of these 
recommendations should help the Army reduce its risk to acceptable 
levels. 

GAO made recommendations regarding problems we identified in the 
following areas: 

* Data conversion; 
* Billing and collection; 
* Requirements management and testing; 
* Independent verification and validation. 

Data conversion: 

* We previously reported that during the first deployment, LMP contained
inaccurate unit price or unit of issue data for certain materials, 
resulting in excess material being ordered and incorrect prices being 
charged. Because of the inaccurate data, the Army received quantities 
of parts and supplies for use in repairing military assets that were 
far greater than intended. 

* When Tobyhanna converted from its legacy system to LMP in July 2003, 
the June 30, 2003, ending account balances in the legacy system did not 
reconcile to the beginning account balances in LMP. Accurate account 
balances are essential for financial reporting and preparation of 
future budgets. 

* The Army has since implemented a program to address the data 
conversion problems caused during the first deployment, and also has a 
process to evaluate whether its data conversion activities have reduced 
the risks associated with this critical factor to acceptable levels. 

Billing and collection: 

* We previously reported that shortly after LMP was implemented, 
Tobyhanna Army Depot began experiencing difficulty in accurately 
billing customers and recognizing revenue. 

* LMP’s billing problems resulted in (1) customers not being billed for 
costs incurred that should have been billed and (2) customers being 
billed too much. 

- As noted in a prior GAO report (GAO-07-860), 146 customer orders 
valued at approximately $5.4 million were not billed during the January 
31, 2007, billing cycle. 

- Similarly, during the January 31, 2007, billing cycle about 308 
customer orders amounting to about $5.8 million were shown as being 
over billed, and a credit should have been issued to the customer. 

- It is essential that revenue is properly recognized and customers are 
billed for work performed because these are the means by which the 
depots finance their day-to-day operations. Moreover, credits from the 
depots to the customers can be used by the customers to meet other 
funding demands. 

* In addition to improving its data conversion processes, the Army 
implemented technical and process improvements in December 2007. The 
Army reported that these improvements reduced the number of incorrect 
bills from 40 per cycle to zero. Because of time constraints, we did 
not independently verify these reported results. 

Requirements management and testing: 

* We previously reported that the Army did not have an adequate process 
for managing LMP requirements that complied with best practices. In 
2007, we reported (in GAO-07-860) that the Army revised and improved 
this process. 

* We previously reported that the Army did not have an adequate testing 
process for LMP because the tests conducted by the Army were not tied 
to specific requirements, were not “end-to-end,” and were not performed 
by users of the system and because test results were neither properly 
documented nor verified and validated by an independent reviewer in
accordance with best practices. 

* The Army has since revised its testing process, which we were unable 
to fully assess because of time constraints. However, we found that (1) 
users were conducting the test; (2) detailed test scripts were being 
used; (3) an automated system was capturing test results; and (4) test 
results were being evaluated daily by a group that consisted of users,
the LMP program office, and an independent contractor, which increased 
the assurance that identified problems were properly evaluated. 

Independent verification and validation: 

* The Army has implemented an independent verification and validation 
process, which should help to identify to management the issues or 
weaknesses that increase the risks associated with the project. 

Objective 3 Observations: Improved Management Processes: 

The Army has implemented critical project management processes and 
controls to identify and understand the risks associated with making a 
deployment decision and evaluate whether those risks are acceptable 
before deploying LMP at Corpus Christi, Letterkenny, and Redstone 
Arsenal. These key processes were absent during the first deployment at 
Tobyhanna. 

* Improved training to address human capital needs; 

* Data conversion processes developed to provide reasonable assurance 
that critical data are properly converted; 

* Quantitative metrics to evaluate the effectiveness of the revised 
project management process have been developed; 

* “Go Live” processes developed to rapidly evaluate and respond to 
potential issues that will invariably arise during the second 
deployment. 

Figure: Employee Training Hours as of March 26, 2009: 

[Refer to PDF for image: stacked vertical bar graph] 

Actual: 
Corpus Christ Army Depot: 24,280 hours; 
Letterkenny Arsenal: 14,832 hours; 
Redstone Arsenal: 37,120 hours; 
Total: 76,232 hours. 

Future: 
Corpus Christ Army Depot: 20,556 hours; 
Letterkenny Arsenal: 19,704 hours; 
Redstone Arsenal: 71,592 hours; 
Total: 111,852 hours. 

Total: 
Corpus Christ Army Depot: 44,836 hours; 
Letterkenny Arsenal: 34,536 hours; 
Redstone Arsenal: 108,712 hours; 
Total: 188,084 hours. 

Source: GAO analysis of Army data. 

Notes: On March 19, 2009, LMP estimated that its total training hours 
would be greater than the amount shown in the above chart. This 
difference was caused by LMP reevaluating its course offerings and 
employee training assignments, primarily at Corpus Christi Army Depot.
The LMP project office expects that the revised data will be loaded 
into the training system during the week ending April 3, 2009, and that 
the total number of employee training hours associated with the second 
deployment will be about 195,000 employee training hours. 

[End of figure] 

The majority of training (about 92 percent of the total employee hours) 
is expected to be delivered prior to deployment. 

Some training (e.g., budget stratification reporting) will occur at 
Redstone after deployment since the users will not be performing the 
functions designed to be addressed by the training until deployment has
occurred, and Army officials explained that it is more effective to 
train an individual when he or she is close to performing the expected 
function. 

Training process includes a means to evaluate the effectiveness of the
training program in delivering the expected skills. 

* Participants are tested and must achieve a 70 percent score to be
considered as passing the class. 

* If a person does not achieve a 70 percent score, he or she may take
other actions, such as taking the class again to achieve a passing
score. 

- One-on-one help is also offered if the participant continues to
experience problems. 

* Participants also provide feedback on whether they believe that the
course has helped them do their jobs. 

- According to the Army, overall the participants have rated the
training program as a 4.1 out of 5, with 5 being the highest score. 

LMP has conducted three data migration trial loads to identify issues 
associated with migrating data from the legacy systems to LMP. 

* At the end of February 2009, more than 95 percent, or about 12.5 
million of the 13.1 million records, could be loaded into LMP without 
issue. 

* As of March 27, 2009, about 96 percent of the records loaded into LMP 
successfully processed without issue. For the remaining records, Army 
officials stated that they will either resolve the issues before 
deployment or take actions to mitigate any adverse effects. 

The Army recognizes that not all legacy data will be successfully 
loaded into LMP prior to deployment. 

* Historical data are needed for planning or other purposes. 

- A data warehouse is being created that contains the data in the legacy
system that are not being converted--this is the same approach used at 
the initial deployment site and it has served the mission needs. 

- The legacy systems will remain available in an inactive state as long 
as the Army considers it necessary. 

* A review was made to determine which records were associated with 
work that is not expected to be performed at deployment locations 
during the next 3 years, and data conversion of these records will 
occur after deployment, if the need arises. 

* Data needed to support various LMP processes (commonly referred to
as master data) are being carefully reviewed. 

- Preventive measures have been implemented to ensure that all master 
data items being loaded into the system have correct base unit of 
measure (BUOM) values. 
-- In the initial deployment, items were loaded into LMP with incorrect 
BUOM values. For example, part numbers were loaded into the system with 
a BUOM with a qualitative measure such as “box” rather than a 
quantitative measure such as “each.” 

- The Army developed a manual work-around process to provide reasonable
assurance that items already contained in LMP with incorrect BUOM will 
not cause problems at the second deployment locations. 

-– LMP currently has about 329 items in its records that contain 
incorrect BUOM values. These errors caused reordering and billing 
problems at Tobyhanna: 
121 of these items are used by Corpus Christi and Letterkenny; 
72 are only used by Letterkenny; 
25 are only used by Corpus Christi. 

-– Manual work-around processes developed at Tobyhanna have addressed 
the problems and will be used at the second deployment locations until 
a long-term system fix can be implemented. 

Objective 3 Observations: Improved Management Processes–Quantitative 
Metrics: 

The Army has defined the critical business processes that must be 
completed prior to making a decision on whether the deployment should 
“Go Live,” and has developed quantitative metrics to evaluate whether 
this has occurred. 

Examples of quantitative measures that are used include the
following: 

* Validate that the critical business process testing has been 
completed and that any problems that have not been addressed have 
agreed-upon mitigation strategies. 

* Validate that the expert users can successfully execute the 
applicable processes--100 percent of the selected expert users are able 
to successfully execute their respective tasks. 

* Validate that end users have completed 90 percent of the required
training courses. 

* Validate that the overall data accuracy rate is 95 percent, with each
deployment location having accuracy of at least 90 percent. 

* Validate the interoperability, availability, and responsiveness of
LMP. 

– Failures associated with exchanging data with other systems are less 
than 2 percent, with an objective of 1 percent; 

– Availability is at least 99.5 percent; 

– Average response time is less than 2 seconds for 80 percent of the 
transactions, with an objective of 2 seconds or less for 95 percent of 
the transactions. 

Objective 3 Observations: Improved Management Processes –“Post-Go Live” 
Processes: 

The Army recognizes that deploying a system such as LMP can never be a 
risk-free proposition and that problems will arise after deployment 
regardless of the actions taken prior to deployment. The Army has 
implemented processes designed to reduce the adverse impacts associated 
with those problems to acceptable levels. 

* End users experiencing problems will contact expert users at their
location to help determine whether they are experiencing system 
problems or whether the users need help understanding how to perform a 
given task. 

- Help tickets are generated, regardless of the reason, to help the 
Army determine if additional training is needed or if the training 
needs to be modified. 

- When the training is modified, all users who have taken the course 
are notified of the changes. 

The Army has enhanced its help desk support to understand the “root 
cause” of problems identified by users and help those users immediately 
where possible. The Army is following best practices and will use a 
three-tier help desk system to address problems that cannot be 
addressed by the expert users at the deployment locations. 

* Tier 1: 

- Provides a single point of contact for end users; 

- Gathers the necessary data to assess the reported problem; 

- Determines if the problem can be resolved or escalates the problem to 
the next level; for example, the Tier 1 Help Desk (1) may be aware of a 
specific problem and can provide the user with the “work-around” that 
has been developed to address the problem or (2) can determine whether 
the system is operating as designed and provide the user with 
instructions on how to accomplish a specific transaction; 

- Verifies user satisfaction with the help desk process. 

* Tier 2 has more knowledgeable support personnel and determines if the 
problem can be resolved or escalates the problem to the next level. 

- May recommend changes to LMP based on the change management processes 
used by the program. 

* Tier 3 support is used for complex problems that cannot be addressed 
by the Tier 2 support or problems associated with vendor-supplied 
hardware and software. 

Agency Views: 

We provided a draft of these briefing slides to the Departments of 
Defense and the Army for their official review and comments. 

On March 30, 2009, we met with officials from the Defense Business 
Transformation Agency, the Office of the Secretary of Defense for 
Supply Policy, the LMP Program Office, and the Department of the Army to
discuss our observations and obtain their comments on the briefing 
slides. The participants agreed with our observations and the 
information in the briefing slides. 

Methodology: 

To determine if the Army’s report addressed the nine specific areas
identified in the House committee report, we reviewed the Army’s report
and supporting documentation and compared them against the 
requirements. 

To ascertain the specific actions that the Army has taken to address 
GAO’s prior recommendations on the implementation of LMP, we reviewed 
past GAO reports related to LMP implementation. We also met with Army
officials at the LMP Program Office to discuss the actions they either 
have implemented or have under way to address each recommendation, and 
we reviewed Army plans and policies that govern implementation. We also
traveled to an Army depot to determine if the actions were being taken. 

To evaluate the management processes and controls that the Army has in
place to ascertain if LMP should be deployed, we met with Army 
officials at the LMP Program Office and Corpus Christi Army Depot to 
determine the processes and controls they have in place. We also 
observed a training class being conducted for LMP users, and we 
analyzed Army data related to training. 

We conducted this performance audit from January 2009 to March 2009 in
accordance with generally accepted government auditing standards. Those
standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of enclosure] 

Footnotes: 

[1] GAO, DOD Business Systems Modernization: Billions Continue to Be 
Invested with Inadequate Management Oversight and Accountability,
[hyperlink, http://www.gao.gov/products/GAO-04-615] (Washington, D.C.: 
May 27, 2004); Army Depot Maintenance: Ineffective Oversight of Depot 
Maintenance Operations and System Implementation Efforts, [hyperlink, 
http://www.gao.gov/products/GAO-05-441] (Washington, D.C.: June 30, 
2005); and DOD Business Transformation: Lack of an Integrated
Strategy Puts the Army’s Asset Visibility System Investments at Risk, 
[hyperlink, http://www.gao.gov/products/GAO-07-860] (Washington, D.C.: 
July 27, 2007). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: