This is the accessible text file for GAO report number GAO-06-461R 
entitled 'Agency Management of Contractors Responding to Hurricanes 
Katrina and Rita' which was released on March 16, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
Washington, DC 20548: 

March 16, 2006: 

Congressional Committees: 

Subject: Agency Management of Contractors Responding to Hurricanes 
Katrina and Rita: 

In February 2006, we briefed the staffs of your committees on the 
results of our review of various contracting issues related to the Gulf 
Coast hurricanes. We conducted this work under the Comptroller 
General's statutory authority in order to assess how three agencies-the 
Federal Emergency Management Agency (FEMA), the U.S. Army Corps of 
Engineers (USAGE), and the General Services Administration (GSA)- 
planned for and conducted oversight of several key contracts in support 
of Katrina and Rita response and recovery efforts. The briefing 
document is attached. 

After we completed our work and briefed your staffs, the House Select 
Bipartisan Committee to Investigate the Preparation for and Response to 
Hurricane Katrina and later the White House issued reports based on 
their reviews of the various hurricane response issues. These reports 
contain findings and recommendations intended to address a number of 
the issues identified in our briefing. Additionally, we understand that 
the Senate Committee on Homeland Security and Governmental Affairs will 
be issuing its report later this month and that various inspectors 
general are proceeding with their reviews as well. In general, while 
the inspectors general are reviewing a broad range of contracting 
issues, such as competition and pricing, we focused our efforts on 
contract planning and oversight. During the course of our work, the 
agencies informed us that they are taking a number of steps to address 
the issues that have been identified, and we reflected those actions in 
the briefing where appropriate. Given these developments, we are not 
making any recommendations at this time; however, we continue to 
monitor agency actions in this area. 

We provided this briefing document to the Department of Homeland 
Security (DHS), the Department of Defense (DOD), and GSA for review and 
comment. While DOD did not have any comments, the Corps of Engineers 
provided some technical clarifications, which we incorporated in the 
briefing where appropriate. Officials at DHS said they had no further 
comments beyond those provided at the agency exit conference, which 
were incorporated where appropriate. GSA provided technical comments, 
which have also been incorporated in the briefing. 

We are sending copies of this briefing to interested congressional 
committees, the Administrator of General Services, and the Secretaries 
of Defense and Homeland Security. We will make copies available to 
others upon request. This briefing also will be available on the GAO 
Web site at http://www.gao.gov. Should you or your staff have any 
questions, please contact me at (202) 512-4841. Key contributors may be 
found on the last page of the briefing. 

Signed by: 

William T. Woods: 
Director, Acquisition and Sourcing Management: 

Enclosure: 

List of Committees: 

The Honorable Susan M. Collins: 
Chairman: 
The Honorable Joseph I. Lieberman: 
Ranking Minority Member: 
Committee on Homeland Security and Governmental Affairs: 
United States Senate: 

The Honorable Tom Davis: 
Chairman: 
Select Bipartisan Committee to Investigate the Preparation for and 
Response to Hurricane Katrina: 
Chairman: 
Committee on Government Reform: 
House of Representatives: 

The Honorable Henry A. Waxman: 
Ranking Minority Member: 
Committee on Government Reform: 
House of Representatives: 

The Honorable Peter T. King: 
Chairman: 
The Honorable Bennie G. Thompson: 
Ranking Minority Member: 
Committee on Homeland Security: 
House of Representatives: 

(120495): 

Briefing for Congressional Staff: 
March 2006: 

Briefing: 

Agency Management of Contractors Responding to Hurricanes Katrina and 
Rita: 

Why GAO Did This Study: 

The private sector is an important partner with the government in 
responding to and recovering from natural disasters such as Hurricanes 
Katrina and Rita. As we recently noted, [NOTE 1] such partnerships 
increasingly underlie critical government operations. 

With hundreds of billions of tax dollars spent each year on goods and 
services, it is essential that all federal agency acquisitions be 
handled in an efficient, effective, and accountable manner. The fact 
that disasters, such as hurricanes, are not entirely predictable must 
not be an excuse for poor contracting practices. Nevertheless, the 
circumstances created by the hurricanes created a difficult environment 
in which agencies had to balance the need to deliver goods and services 
quickly with the need for appropriate controls. 

Under the Comptroller General's statutory authority, GAO conducted work 
to assess how three agencies planned for and conducted oversight of 
several key contracts in support of Katrina and Rita response and 
recovery efforts: the General Services Administration (GSA), the 
Federal Emergency Management Agency (FEMA), and the U.S. Army Corps of 
Engineers (USAGE). A number of efforts are underway by these agencies 
to address the issues we and others have identified. This briefing does 
not contain any recommendations. 

All three agencies reviewed this briefing and either had no comments or 
provided technical clarifications, which we incorporated where 
appropriate. 

NOTE: 

[1] GAO, 21st Century Challenges: Reexamining the Base of the Federal 
Government, GAO-05-325SP (Washington, D.C.: February 2005). 

Overview: 

Background: 

Congress has appropriated over $62 billion as an initial commitment of 
federal support to the Gulf Coast states impacted by the recent 
hurricanes. The government's response to Hurricanes Katrina and Rita 
depended heavily on contractors to deliver ice, water, and food 
supplies; patch rooftops; and provide housing to displaced residents 
and temporary facilities to local government agencies. 

In any acquisition, agencies need to have in place sound acquisition 
plans, processes to make and communicate good business decisions, and a 
capable acquisition workforce to monitor contractor performance so that 
the government receives good value for the money spent. These 
components are critical to successfully managing contracts in any 
environment-even in a contingency situation such as that presented by 
Hurricanes Katrina and Rita. 

In reviewing contracts awarded for Iraq-another contingency situation- 
GAO found that without effective acquisition planning, management 
processes, and sufficient numbers of capable people, poor acquisition 
outcomes resulted. GAO made recommendations regarding the need for: 
ensuring that requirements for placing orders are within the scope of 
contracts; timely definition of contract terms and conditions; and 
sufficient numbers of trained staff who have clear responsibilities and 
guidance for overseeing contractor performance. Having these 
capabilities requires preparation, such as having pre-arranged 
contracts in place in advance of the disaster or other contingency. 

Summary of Findings: 

Given the environment in which they were operating, agency acquisition 
and contractor personnel worked hard to provide the goods and services 
required, often working long hours in order to be responsive. The 
response efforts nonetheless suffered from: 

* Inadequate planning and preparation to anticipate requirements for 
needed goods and services. 

* Lack of clearly communicated responsibilities across agencies and 
jurisdictions. 

* Insufficient numbers and inadequate deployment of personnel to 
provide for effective contractor oversight. 

Briefing Structure: 

Risk Areas: 

Inadequate planning and preparation; 
Lack of clearly communicated responsibilities; 
Insufficient numbers and deployment of oversight personnel. 

Appendix: 

Scope, methodology, and contributors. 

Related GAO Reports: 

Continuity of Operations: Agency Plans Have Improved, but Better 
Oversight Could Assist Agencies in Preparing for Emergencies, GAO-05-
619T (Washington, D.C.: Apr. 28, 2005). 

Results-Oriented Government: Improvements to DHS's Planning Process 
Would Enhance Usefulness and Accountability, GAO-05- 300 (Washington, 
D.C.: Mar 31, 2005). 

Homeland Security: Effective Regional Coordination Can Enhance 
Emergency Preparedness, GAO-04-1009 (Washington, D.C.: Sept. 15, 2004). 

Continuity of Operations: Improved Planning Needed to Ensure Delivery 
of Essential Government Services, GAO-04-160 (Washington, D.C.: Feb. 
27, 2004). 

Inadequate Planning and Preparation: 

Some key agencies involved in responding to the disaster did not have 
adequate acquisition plans for contingency situations. For example: 

While contracts for some items were in place prior to the storm, the 
Federal Emergency Management Agency (FEMA) did not adequately 
anticipate needs for such services as providing temporary housing and 
public buildings. 

The practice of the U.S. Army Corps of Engineers (USAGE) is to 
establish Planning and Response Teams for various missions assigned to 
it by FEMA prior to an event, with specific responsibilities assigned 
to team members. However, the Corps indicated it did not know prior to 
the hurricane that it would be tasked by FEMA with some of the mission 
assignments it received. In one case, FEMA tasked the Corps with 
acquiring temporary classrooms for Mississippi within a very short time 
frame. To meet the requirement, USAGE placed a non-competitive order on 
a pre-existing agreement for portable buildings. Information in the 
contract files suggests the negotiated prices were inflated and 
indicates USAGE did not have sufficient time or information to ensure a 
good acquisition outcome. [NOTE 2] 

Similarly, better management of requirements development could have 
avoided costs to house workers and victims. Based on information 
provided by local officials, FEMA spent $3 million for 4,000 base camp 
beds that were never used. 

Preparation was also lacking in implementation of the Stafford Act 
preference for contractors residing or doing business in the affected 
area. [NOTE 3] USAGE staff expressed uncertainty regarding how to apply 
preferences or determine if a company was in an affected area. Several 
General Services Administration (GSA) and FEMA officials indicated they 
were aware of the Stafford Act but stated it is difficult to 
immediately factor in local businesses in such a catastrophic event. 
GSA officials stated they plan to review the Federal Acquisition 
Regulation (FAR) to see if additional Stafford Act guidance is 
necessary.[NOTE 4] 

In discussing our findings and observations with FEMA officials, they 
indicated they were taking steps to improve in areas such as staffing 
and pre-mobilization capabilities in order to better respond to future 
disasters. However, they also stated that such pre-planning and 
preparedness has a cost. The USAGE commented that contracting staff 
need to have defined requirements in order to get the right type of 
contracts put in place and, unfortunately, the contracting staff did 
not always get defined requirements in a timely manner. Additionally, a 
USAGE official commented that until funding for a particular mission is 
secured, preparation for the mission cannot go forward and this also 
delayed contracting efforts. Finally, both GSA and the USAGE noted that 
they tried to reach out to local and small businesses through forums 
and other means to make them aware of opportunities to contract with 
the federal government. 

NOTES: 

[2] GAO, Hurricanes Katrina and Rita: Contracting for Response and 
Recovery Efforts, GAO-06-235T (Washington, D.C.: Nov. 2, 2005). 

[3] 42 U.S.C. § 5150. 

[4] See the FAR, Subpart 26.2-Disaster or Emergency Assistance 
Activities. 

Related GAO Reports: 

* Hurricanes Katrina and Rita: Contracting for Response and Recovery 
Efforts, GAO-06-235T (Washington, D.C.: Nov. 2, 2005). 

* Interagency Contracting: Problems with DOD's and Interior's Orders to 
Support Military Operations, GAO-05-201 (Washington, D.C.: Apr. 29, 
2005). 

* Homeland Security: Successes and Challenges in DHS's Efforts to 
Create an Effective Acquisition Organization, GAO-05-179 (Washington, 
D.C.: Mar. 29, 2005). 

* Homeland Security: Effective Intergovernmental Coordination Is Key to 
Success, GAO-02-1013T, (Washington, D.C.: Aug. 23, 2002). 

Lack of Clearly Communicated Responsibilities: 

We also found that processes for executing contracts were hindered by 
poor communication. As envisioned under the National Response Plan 
(NRP), federal agencies responding to a disaster carry out their 
acquisition functions through a network of federal, state, and local 
agencies. In some instances, the local or state officials determine the 
requirements and communicate them to FEMA; FEMA may write and award the 
contract or communicate the requirements to another agency that writes 
and awards the contract; and then FEMA or another agency oversees 
contract performance. This approach puts a premium on aligning roles 
and responsibilities clearly and maintaining good communications to 
ensure effective execution of the contract. 

Our fieldwork identified examples where unclear responsibilities and 
poor communications resulted in poor acquisition outcomes. For example: 

* FEMA officials stated that a contractor spent approximately $10 
million to renovate 160 rooms and furnish another 80 rooms in military 
barracks in Alabama that a FEMA survey team identified for use as 
temporary housing. To renovate the facility, FEMA headquarters awarded 
a contract without consulting local FEMA officials in Alabama. 
According to FEMA officials in Alabama, however, the facility was not 
needed and they tried to stop the renovation. These same FEMA officials 
stated that few evacuees agreed to live at the facility, and when 
officials decided to close the facility, it had only six occupants. 

* The process for ordering and delivering ice heavily depends on 
effective communications between FEMA and USAGE. However, according to 
Corps officials, FEMA did not fully understand the contracting approach 
used by the Corps and ordered at least double the amount of ice 
required, resulting in an oversupply of ice and a lack of distribution 
sites available to handle the volume ordered. Additionally, the local 
Corps personnel were not always aware of where ice might be delivered 
and did not have the authority to redirect ice as shipments arrived, 
resulting in inefficient distribution and receipt at the state level. 

* FEMA tasked GSA to write three contracts in Louisiana for base camps, 
hotel rooms, and ambulances, with a total value of over $120 million. 
GSA contracting officers awarded the contracts, but could not tell us 
which FEMA officials would be responsible for overseeing contractor 
performance. The FEMA official identified as the main point of contact 
by GSA did not have any knowledge of these contracts or who was 
responsible for oversight. Only after contacting multiple FEMA 
officials over a 3-week period were we able to determine the agency 
officials responsible for contract oversight. 

In commenting on this briefing, GSA officials stated that their role is 
to provide resource support in the response phase of a disaster, 
meaning they are responsible for executing contracts under the NRP, and 
FEMA is responsible for monitoring the contracts. FEMA officials 
commented that there needs to be more clarity regarding procurement 
roles and indicated one of their goals is to work with GSA to clarify 
procurement responsibilities for the future. GSA officials indicated 
that the current memorandum of understanding between GSA and FEMA is 
being updated to reflect the standards of the new NRP as well. 

Related GAO Reports: 

* Contract Management: Opportunities to Improve Surveillance on 
Department of Defense Service Contracts, GAO-05-274 (Washington, D.C.: 
Mar. 17, 2005). 

* Rebuilding Iraq: Fiscal Year 2003 Contract Award Procedures and 
Management Challenges, GAO-04-605 (Washington, D.C.: June 1, 2004). 

* Human Capital: Opportunities to Improve Federal Continuity Planning 
Guidance, GAO-04-384 (Washington, D.C.: Apr. 20, 2004). 

* Contract Management: Coast Guard's Deepwater Program Needs Increased 
Attention to Management and Contractor Oversight, GAO-04-380 
(Washington, D.C.: Mar. 9, 2004). 

Insufficient Numbers and Deployment of Oversight Personnel: 

Ensuring that contracted goods and services are delivered in accordance 
with the agreed upon schedule, cost, quality, and quantity provisions 
as stated in the contract is the purpose of agencies' monitoring 
processes. Without sufficient numbers of trained people properly 
deployed, however, effective monitoring is hampered and agencies are at 
risk of being unable to identify and correct poor contractor 
performance in a timely manner. Furthermore, agencies can be at risk of 
paying contractors more than the value of the services performed. 

Our work indicated that while monitoring was occurring on the contracts 
we reviewed, the number of monitoring staff available was not always 
sufficient or effectively deployed to provide effective oversight. For 
example: 

* FEMA's contracts for installing temporary housing in four states had 
only 17 of the 27 technical monitors that had been determined necessary 
to oversee contractor performance. [NOTE 5] 

* USACE officials told us that the "blue roof" program was slowed down 
due to the lack of sufficient monitors. [NOTE 6] 

Deployment practices did not always provide for appropriate 
notification of responsibilities or overlap of rotating contracting 
officers and oversight personnel, thus making knowledge transfer and 
continuity of contract management operations difficult. For example: 

* For four of the contracts we reviewed, officials were either unaware 
or not notified by FEMA of their oversight responsibilities. 

* The lack of overlap between oversight personnel for a large temporary 
housing contract left the most recent contract administrator with no 
knowledge or documentation of who had authorized the contractor to 
perform certain activities or why the activities were being performed. 

While discussing our findings and observations with FEMA officials, 
they emphasized that they lacked adequate staffing, but said they have 
made efforts to fill staffing gaps. Additionally, FEMA officials stated 
they recognize the need for continuity in contract oversight and 
indicated they are implementing a process to ensure workload and 
knowledge sharing among rotating personnel. However, they also believe 
that fewer transition difficulties exist now as a result of hiring more 
people and having more oversight officials staying in the affected 
areas. GSA officials indicated there may also be other alternatives for 
ensuring adequate contract oversight, such as designating GSA employees 
to conduct oversight on some contracts. USACE officials stated their 
policy is to rotate certain personnel every 29 days to keep personnel 
costs to a minimum due to regulations under the Fair Labor Standards 
Act. [NOTE 7] 

NOTES: 

[5] Data provided by FEMA official was dated November 18, 2005. 

[6] The USACE manages the Operation Blue Roof mission for FEMA. 
Operation Blue Roof provides assistance to storm victims in disaster 
areas through the installation of rolled plastic sheeting on damaged 
roofs, helping to protect property and allowing residents to remain in 
their homes. 

[7] 5 CFR § 551.208. 

Appendix: 

Contributors: 

If you have any questions concerning this briefing, please call Bill 
Woods, Director, Acquisition and Sourcing Management, at (202) 512- 
4841, or John K. Needham, Assistant Director, Acquisition and Sourcing 
Management, at (202) 512-5274. 

Other key contributors to this report were Penny Augustine, Elaine 
Boudreau, Myra Watts Butler, Dave Cooper, Lisa Henson, James Kim, 
Victoria Klepacz, Sandy Reigle, Ralph Roffo, Jeff Rose, Moshe Schwartz, 
and Shannon Simpson. 

Scope and Methodology: 

Due to the level of congressional interest in the federal response to 
Hurricanes Katrina and Rita, we initiated this review under the 
Comptroller General's statutory authority. We conducted our work from 
October 2005 through February 2006 in accordance with generally 
accepted government auditing standards. 

In order to determine which agencies to include in our review, we 
analyzed data collected from the Federal Procurement Data System-Next 
Generation (FPDS-NG) and agency websites on contract awards and dollar 
amounts for Hurricanes Katrina and Rita response and recovery work. 
This led us to review three agencies: GSA, USAGE, and FEMA. We 
discussed acquisition management issues with, and obtained 
documentation from, officials in these agencies, as well as with 
employees from other agencies that served in oversight positions on 
behalf of these agencies. We also traveled to sites in Louisiana and 
Mississippi to meet with agency officials at field locations and 
observe oversight practices at contractor locations. 

We selected 13 contracts from 12 contractors performing work for the 
agencies in our review to analyze in further detail how monitoring 
policies and processes were put into practice (see table below). Our 
criteria for selection included: 

* Minimum contract value of $5 million. 
* Variety of missions (type of activity to be conducted under the 
contracts). 
* Coordination with the Inspectors General and other audit offices to 
avoid duplication to the extent possible. 
* Contract award and administration locations (to facilitate data 
collection and interviews). 

Contractor Name: C. Henderson Consulting, Inc; 
Contracted Product or Service: Ambulance services. 

Contractor Name: Americold Logistics, LLC; 
Contracted Product or Service: Transportation, storage, and delivery of 
commodities. 

Contractor Name: Clearbrook, LLC; 
Contracted Product or Service: Base camp construction and operation. 

Contractor Name: CS&M Associates; 
Contracted Product or Service: Hotel rooms for displaced persons. 

Contractor Name: Gulf Stream Coach, Inc; 
Contracted Product or Service: Gulf Stream travel trailers. 

Contractor Name: Morgan Building & Spas, Inc; 
Contracted Product or Service: Travel trailers and shipping. 

Contractor Name: Bechtel National, Inc; 
Contracted Product or Service: Installing trailers/mobile homes for 
temporary housing. 

Contractor Name: Fluor Enterprises, Inc; 
Contracted Product or Service: Installing trailers/mobile homes for 
temporary housing. 

Contractor Name: CH2M Hill Constructors, Inc. (2 contracts); 
Contracted Product or Service: Installing trailers/mobile homes for 
temporary housing (FEMA); site preparation/installation of portable 
public buildings (USACE). 

Contractor Name: E.T.I., Inc; 
Contracted Product or Service: Quality assurance inspectors for 
temporary housing. 

Contractor Name: Ceres Environmental Services, Inc; 
Contracted Product or Service: Temporary roofing repairs ("blue roof 
program). 

Contractor Name: Thompson Engineering, Inc; 
Contracted Product or Service: Quality assurance inspectors. 

Source: GAO. 

[End of table] 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: