This is the accessible text file for GAO report number GAO-06-321R 
entitled 'Architect of the Capitol: Addressing Staffing and Training 
Issues Is Important for Efficient and Safe West Refrigeration Plant 
Operations' which was released on March 13, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

February 10, 2006: 

The Honorable Wayne Allard: 
Chairman: 
Subcommittee on the Legislative Branch: 
Committee on Appropriations: 
United States Senate: 

The Honorable Jerry Lewis: 
Chairman: 
Committee on Appropriations: 
House of Representatives: 

Subject: Architect of the Capitol: Addressing Staffing and Training 
Issues Is Important for Efficient and Safe West Refrigeration Plant 
Operations: 

The West Refrigeration Plant Expansion (WRPE) project is the 
centerpiece of an effort to expand the capacity of the Capitol Power 
Plant (CPP) to meet the U.S. Capitol's growing heating and cooling 
needs and to update plant equipment, some of which dates to the 1950s. 
CPP generates steam and chilled water to provide heating and cooling 
for the Capitol and 23 surrounding facilities that, together, encompass 
about 16 million square feet of space. CPP will also serve the 580,000- 
square-foot Capitol Visitor Center (CVC), which is under construction. 
When completed, the WRPE project will increase CPP's chilled water 
production capacity by about 23 percent and enable central operation of 
CPP's chillers.[Footnote 1] The WRPE construction contract was awarded 
in March 2003, work is ongoing, and the project is now scheduled for 
completion in March 2006. Future contract changes may, however, extend 
this date to June 2006. The budget for the WRPE project and associated 
administrative expenses is $81.7 million. Several modifications have 
been made to the WRPE contract to incorporate other capital 
improvements at CPP. The budget for these modifications is $19.2 
million, bringing the total budget for the base WRPE project and 
related projects to $100.9 million. For clarity, we refer in this 
report to the base WRPE project and related projects collectively as 
the WRPE project. 

The Architect of the Capitol (AOC), who manages CPP, is responsible for 
commissioning the new West Refrigeration Plant equipment. According to 
the General Services Administration (GSA), which provides guidance to 
federal agencies on managing their facilities, commissioning is a 
systematic process to ensure, by verification and documentation, that 
all of a facility's systems perform interactively as designed and 
intended to meet the owner's operational needs. AOC and its contractors 
are carrying out the commissioning process, including a three-stage 
plan prepared by the construction contractor for testing the 
performance of the new WRPE equipment. AOC is also responsible for 
ensuring that CPP is staffed efficiently and that CPP personnel have 
the knowledge and skills to operate the plant safely. 

Over the years, we have reported on AOC's management of CPP several 
times and made recommendations for improvement. Our most recent report, 
issued in April 2005, included recommendations on CPP's 
staffing.[Footnote 2] As requested, this report updates our prior work 
and evaluates AOC's (1) commissioning activities to date and plans for 
commissioning the new equipment without disrupting current operations 
and (2) plans for staffing the modernized power plant efficiently and 
ensuring that CPP personnel are trained to operate it safely. In 
addition, the report estimates the costs to complete the WRPE project, 
taking into account the possible effects of anticipated contract 
changes, operational issues, and other challenges to a timely and 
successful startup. 

To evaluate AOC's commissioning activities to date and plans for 
commissioning the new equipment, we reviewed GSA's guidance on 
commissioning,[Footnote 3] visited CPP, and interviewed CPP managers 
and a construction management consultant retained by AOC. We also 
reviewed the equipment-testing plan prepared by the construction 
contractor. To support our evaluation of the commissioning activities 
and plans, we retained an engineering consultant who specializes in 
heating and cooling plant operations. To evaluate AOC's plans for 
staffing the modernized plant efficiently and ensuring that CPP 
personnel are trained to operate it safely, we reviewed our guidance on 
strategic training and development,[Footnote 4] interviewed CPP 
managers, and reviewed AOC's response to the staffing and training 
recommendations we made in our April 2005 report. Additionally, we 
randomly selected and interviewed five CPP operators to learn about the 
deployment and content of the training from their perspective. To 
estimate the costs to complete the WRPE project, we reviewed AOC's cost 
and schedule information related to the construction contract and 
identified contract changes, operational issues, and other challenges 
that could affect the project's costs and schedule. The same 
engineering consultant who helped us evaluate AOC's commissioning plan 
assisted us in developing our cost analysis, which includes, for each 
cost component, a range of costs to account for variations in 
circumstances, from best to worst case. We conducted our review from 
June 2005 through December 2005 in accordance with generally accepted 
government auditing standards. 

Results in Brief: 

The WRPE commissioning process has been effective thus far, although 
the bulk of the equipment testing remains to be done. According to our 
analysis, AOC's commissioning activities to date and commissioning 
plans are consistent with GSA's commissioning guidance and are designed 
to allow the new plant equipment to start up without disrupting CPP's 
current operations. GSA's guidance calls for document reviews, 
checklists, functional performance tests, and training in the use of 
the equipment. This process is intended to ensure that the equipment 
meets specifications and performs as intended. AOC and its contractors 
have been performing the activities GSA recommends. Since March 2003, 
when construction began, CPP project managers and AOC's construction 
management consultant have been reviewing documents and monitoring WRPE 
construction and equipment installation activities. In addition, 
starting in November 2005, a commissioning agent retained by AOC, as we 
recommended, has been overseeing the construction contractor's 
execution of the contractor's three-stage plan for testing the 
functional performance of the equipment--the heart of the commissioning 
process.[Footnote 5] Under this plan, which consists of a series of 
checklists, the contractor is testing the functioning of individual 
components, the manual operation of system components, and the 
automatic operation of system components. According to AOC, the 
functional testing has proceeded without incident, and overall plant 
operations have continued without disruption. However, most of the 
functional testing lies ahead, and the training for operators in the 
use of the equipment, which the equipment manufacturers will provide, 
has not started yet. Ultimately, the effectiveness of the commissioning 
process will be determined by how well the new systems function when 
CPP assumes full responsibility for their operation. 

By contrast, AOC has made less progress in planning to staff the 
modernized power plant efficiently and ensure that CPP personnel are 
trained to operate it safely. Specifically, AOC has just begun to 
address long-standing CPP staffing recommendations and has not 
developed a plan for evaluating the training provided to CPP operators. 
As far back as 1996, an AOC engineering consultant found that CPP was 
overstaffed and recommended staffing reductions. Most recently, in 
November 2004, a different AOC engineering consultant recommended a 
reduction in CPP staffing from 88 to 46 positions. In October 2005, AOC 
contracted with the same consultant it retained in 2004 for an updated 
workload-based staffing study, a draft of which was recently delivered 
to AOC for review. According to AOC, the new study includes a proposed 
organizational chart and an implementation plan for achieving the 
recommended organizational structure. While this draft study is a step 
toward staffing CPP more efficiently, it will not be completed in time 
to guide AOC's investments in training required for the new equipment's 
operation. As a result, AOC is providing training for all plant 
operators, even though fewer operators may be needed after a new 
staffing plan is in place. To help ensure that CPP personnel are 
trained to operate the modernized plant safely, AOC has planned, 
developed, and begun to implement training for CPP operators that 
addresses safe plant operations, but AOC has not developed a plan for 
evaluating the training and using the evaluation results to guide 
future training investments or to help implement a new staffing plan. 
Without an evaluation plan, AOC cannot ensure that CPP personnel have 
acquired the skills needed to operate the modernized plant safely or 
that the best prepared operators are included in CPP's restructured 
workforce. Feedback from AOC's construction management consultant and 
our interviews with CPP operators have raised concerns about how well 
the initial training has prepared CPP staff to operate the new 
equipment. To address these concerns, AOC plans to hire a startup 
contractor to provide technical assistance for up to 8 weeks after 
WRPE's completion. AOC believes this technical assistance will help CPP 
staff operate the new equipment safely, without damaging it, and will 
help AOC identify and address any gaps in operators' training. We are 
recommending that AOC develop and implement an updated workload-based 
staffing plan based on the results of its most recent consultant's 
study, evaluate the training provided to CPP operators, and use the 
evaluation results in implementing the updated staffing plan. 

We estimate that the cost to complete the WRPE project could differ 
from the $101 million budgeted for it, potentially ranging from about 
$98 million to nearly $106 million, depending on the outcomes of 
negotiations over future contract changes and the level of training and 
contractor technical support that CPP operators need. Currently, the 
WRPE construction contract is scheduled for completion in March 2006, 
but because of these contract changes, CPP project managers expect that 
it will be delayed until June 2006. Among the contract changes that are 
likely to have the greatest impact on WRPE's cost and schedule are 
those that affect the design and construction of the fire sprinkler 
system, the configuration of chilled water pipes, and the design and 
construction of the distributed controls system for the chillers. As 
commissioning progresses, funds are also likely to be needed for 
troubleshooting and repairs, as well as for startup support if 
operators require additional technical assistance. 

We provided a draft copy of this report to AOC for review and comment. 
AOC officials provided oral comments in which they generally concurred 
with our recommendations and offered technical clarifications and 
updated information concerning staffing and training efforts. 

Background: 

The director of CPP, who reports to the AOC Chief Operating Officer, is 
responsible for managing 95 full-time-equivalent staff and an operating 
budget that, in fiscal year 2005, totaled approximately $33 
million.[Footnote 6] The director's position has been vacant since May 
2005, but AOC is now working to fill the vacancy and expects to hire a 
new director in January 2006. 

Located at New Jersey and E Streets, Southeast, in Washington, D.C., 
CPP consists of four main facilities:[Footnote 7] a steam plant 
constructed in 1908; the East Refrigeration Plant, constructed in 1938; 
and the West Refrigeration Plant and administration building, 
constructed in 1978. WRPE, whose construction AOC is managing under an 
ongoing contract, will add approximately 25,000 square feet to the West 
Refrigeration Plant. This additional space will house new machines for 
generating chilled water (see fig. 1). The contract also provides for 
installing a centrally operated distributed controls system for CPP's 
chillers. AOC has budgeted $81.7 million for this contract and 
associated administrative expenses. AOC is also completing other 
projects related to CPP operations under the same contract, including 
installing a centrally operated distributed controls system for CPP's 
boilers, a fuel oil tank, and an emergency generator, and modernizing 
the plant's electrical system. AOC is using multiple funding sources-- 
primarily specific appropriations but also some CPP operating funds--to 
pay for these other projects, the combined budgeted cost of which is 
$19.2 million. In total, the budgeted cost of the WRPE project-- 
including both the base project and the related projects--is $100.9 
million. According to CPP project managers, the new WRPE chillers were 
manually tested before December 1, 2005, meeting a contract milestone. 
The WRPE project is now scheduled for completion by March 16, 2006; 
however, CPP project managers told us that pending contract changes are 
likely to delay its completion until June 2006.[Footnote 8] 

Figure 1: CPP West Refrigeration Plant Expansion Project Site and New 
Chiller (photo): 

[See PDF for image] 

[End of figure] 

The East and West Refrigeration Plants are used to generate chilled 
water for comfort cooling and equipment cooling. Together, these 
facilities currently have a nominal chilled water production capacity 
of 37,700 tons.[Footnote 9] The base WRPE project will provide three 
new 5,400-ton chillers, which will replace obsolete chillers in the 
East Refrigeration Plant. The obsolete chillers in the East 
Refrigeration Plant will be removed, and two new 3,000-ton 
chillers,[Footnote 10] temporarily located in the East Refrigeration 
Plant, are proposed to be moved to WRPE after it is completed. The 
expanded West Refrigeration Plant (WRP), including both the existing 
WRP and the WRP expansion, will then produce all of CPP's chilled water 
and will have a total production capacity of 46,200 tons, an increase 
of nearly 23 percent over CPP's current capacity. The East 
Refrigeration Plant will be available for alternative uses, such as 
housing a cogeneration system[Footnote 11] that AOC is currently 
considering. 

As part of our work for Congress, we have reported on AOC's management 
for several years. Recently, we have testified several times on AOC's 
management of the Capitol Visitor Center, which is under 
construction.[Footnote 12] In a September 2005 testimony, we identified 
incidents at CPP that we said could affect CPP's ability to provide 
chilled water and steam. For example, in July 2005, two chillers in 
CPP's East Refrigeration Plant were taken out of service because of a 
significant refrigerant gas leak that went undetected by CPP staff. AOC 
does not plan to repair the chillers because they are scheduled for 
demolition. In addition, in June 2005, one of CPP's two coal-burning 
boilers was damaged by a fire that, according to a CPP incident report, 
was caused by operator error. CPP has since repaired the damaged 
boiler. We further testified that management issues at CPP, including 
the absence of a staffing plan for WRPE, could affect WRPE's and CPP's 
operational readiness, and we stated that it was essential to fill the 
CPP director's position with an experienced manager who is also an 
expert in the production of chilled water and steam. 

Commissioning Activities to Date and Commissioning Plans Are Consistent 
with Federal Guidance on Achieving Intended Performance: 

AOC's commissioning activities to date and plans for commissioning the 
new WRPE equipment are consistent with GSA's guidance and are designed 
to allow the new plant equipment to start up without disrupting current 
operations. GSA's guidance calls for several activities during 
construction to help ensure that a facility's systems perform 
interactively as designed and intended. These activities include 
reviewing submittals for performance parameters, developing and using 
construction checklists, conducting functional performance tests, and 
providing training. See table 1 for details. 

Table 1: Facility Construction Commissioning Activities: 

Commissioning activity: Review submittals; 
GSA's description: 
* Evaluate product documentation provided by contractor for items 
intended to be used or installed during construction; 
* Documents include engineering drawings, product data sheets, and 
operating and training manuals. 

Commissioning activity: Develop and use construction checklists; 
GSA's description: 
* Checklists are tools for ensuring that product type and performance 
information specified in the contract documents is transferred to 
workers; 
* In completing checklists, all parties are assured that the contract 
requirements are satisfied; 
* Checklists cover activities from delivery and storage of products and 
materials to installation and startup steps; 
* Completion of checklists is reviewed during periodic site visits. 

Commissioning activity: Conduct functional performance tests; 
GSA's description: 
* Functional performance tests are the focal point of the commissioning 
process and are intended to evaluate the ability of the components of a 
system to work together to meet performance criteria; 
* Functional performance tests are performed after construction 
checklists are complete; 
* Outcomes of tests are recorded using photographs, forms, or other 
means; 
* Retesting is done as necessary. 

Commissioning activity: Provide training; 
GSA's description: 
* Training is conducted to teach operating personnel about required 
care, adjustment, maintenance, and operation of equipment and systems. 

Source: GAO analysis of GSA's The Building Commissioning Guide. 

[End of table] 

Since March 2003, when AOC awarded the WRPE construction contract, CPP 
project managers and AOC's construction management consultant have been 
working together to monitor building construction and equipment 
installation activities. The project managers have overall 
responsibility for administering the construction contract, and the 
construction management consultant provides administrative support. The 
consultant has coordinated the reviews and approvals of all submittals 
prepared by the construction contractor and has conducted field 
inspections to ensure that construction and equipment installation work 
meets contract specifications. Given the importance of the 
commissioning process to ensuring that WRPE meets its designed intent, 
we suggested to AOC in June 2005 that it provide strong oversight of 
the process. AOC subsequently retained an independent commissioning 
agent, who had previously been involved with the WRPE project as a 
subcontractor to AOC's construction management consultant, to provide 
dedicated oversight of the activities outlined in the construction 
contractor's testing plan. This commissioning agent will also be 
providing training to CPP operators to familiarize them with the new 
plant equipment, as discussed in the next section, and coordinating the 
equipment-specific training provided by the equipment manufacturers as 
part of the commissioning process. 

The operation of WRPE's chilled water generating system is being tested 
according to the construction contractor's three-stage plan. This plan 
includes functional testing of the individual components (stage one), 
manual operation of system components (stage two), and automatic 
operation of system components (stage three). Each stage of the plan is 
based on sequenced checklists that detail testing procedures.[Footnote 
13] According to CPP project managers, as of December 1, 2005, system 
components had been installed, and the three new chillers were manually 
operational, as planned. The CPP project managers reported that stage 
one testing, which began in October 2005, was largely complete and that 
stage two testing, which began in mid- November 2005, was ongoing. 
According to AOC officials, the testing has proceeded thus far without 
incident, and CPP has continued to operate without disruption. However, 
most of the testing lies ahead. Specifically, the stage three testing 
is to begin in February 2006 and continue for the duration of the 
construction contract. AOC's commissioning agent has started to provide 
familiarization training to CPP operators, but the manufacturer-
provided, equipment-specific training has not yet begun. 

AOC Lacks a Staffing Plan for CPP and Has Not Determined How It Will 
Evaluate Operator Training: 

To operate the modernized power plant efficiently and safely, AOC needs 
an appropriate number of staff with the knowledge and skills necessary 
to properly operate and maintain the new equipment and the new 
distributed controls systems. AOC has long recognized that CPP is 
overstaffed, but has not implemented staffing reductions and has only 
recently contracted for and received an updated draft study that it 
plans to use in establishing a new CPP staffing structure. AOC is 
providing training for all plant operators but has not yet determined 
how it will evaluate the training. 

Studies Have Long Identified Overstaffing, but AOC Has Just Begun to 
Address Staffing Recommendations: 

In 1996, in a technical and economic evaluation of CPP operations, an 
AOC engineering consultant reported that CPP was overstaffed compared 
with similar plants and estimated that a reduction in the number of 
staff from 86 to 61 would reduce CPP's staffing costs by about 29 
percent.[Footnote 14] In a March 2004 report on CPP, we noted that 
there had been little change in CPP's staffing since 1996 and 
recommended that AOC update the portion of its 1996 study related to 
staffing.[Footnote 15] AOC then contracted with a different engineering 
consultant to update the 1996 study. This updated study, which was 
issued in November 2004 and took the ongoing WRPE project into 
consideration, indicated that current staffing levels were high, and 
recommended a reduction in CPP staffing, from 88 to 46 
positions.[Footnote 16] In our April 2005 report, we recommended that, 
by the end of September 2005, AOC develop an implementation plan for 
adopting its consultant's November 2004 recommendations, including the 
CPP staffing reduction. In October 2005, AOC contracted with the same 
consultant it retained in 2004 to develop an updated staffing study. 
This new study, a draft of which was recently delivered to AOC, 
includes benchmarking and workload analyses that the consultant used to 
develop a proposed organizational chart and an implementation plan to 
achieve the recommended organizational structure. While this draft 
study is a step toward staffing CPP more efficiently, it was not 
completed in time to guide AOC's investments in training. As a result, 
AOC is providing training for all plant operators, even though fewer 
operators may be needed after a new staffing plan is in place. 

AOC Contractors Are Providing Training That Addresses Safe Plant 
Operations, but AOC Has Not Developed a Plan for Evaluating the 
Training: 

Training is critical to the WRPE project's success because operators 
will need updated knowledge and skills to efficiently and safely 
operate the advanced technologies that are being installed. When 
construction is complete, state-of-the-art equipment will replace aging 
system components that date as far back as the 1950s. Furthermore, the 
new plantwide distributed controls systems will fundamentally change 
CPP's operating methods: Operators will have a lesser need to directly 
control system components because certain functions will be 
automatically maintained by the distributed controls systems. 

AOC has planned and developed training for CPP operators and is 
implementing this training in stages. AOC's construction management 
consultant has already provided refresher training, lasting 
approximately 9 months, for all CPP operators on the fundamentals of 
chilled water and steam systems.[Footnote 17] AOC's commissioning agent 
has started to provide additional training for operators on chiller and 
boiler systems, as well as on the operation and maintenance of the 
distributed controls systems. This operator training includes two 8- 
hour sessions per week, to be offered from November 2005 through March 
2006 according to a schedule that will allow operators from all shifts 
to receive instruction. AOC's intent is to provide each operator with 8 
hours of training every other week. Finally, AOC's commissioning agent 
will coordinate with the WRPE construction contractor to schedule 
manufacturer-provided training on specific equipment. 

The operator training that AOC is implementing seems designed to help 
ensure that CPP personnel are trained to operate the modernized plant 
safely. For example, AOC's contract with the commissioning agent 
specifies that the training will address, among other topics, safe 
operating practices and procedures. In addition, under the contract, 
the commissioning agent will describe training objectives for major 
system components, identify what operators must be able to do upon 
completing the training, and test operators' knowledge of the subject 
matter twice each month. 

While AOC has planned, developed, and implemented training for CPP 
operators that addresses safe plant operations, it has not developed a 
plan for evaluating whether the training is achieving the desired 
outcome--preparing CPP staff to operate the modernized power plant 
safely. Our Guide for Assessing Strategic Training and Development 
Efforts in the Federal Government provides a model framework for 
training.[Footnote 18] This framework is designed to help organizations 
target their training and development investments strategically and 
avoid wasting resources on efforts that are irrelevant, duplicative, or 
ineffective. Figure 2 shows the four components of this framework-- 
planning, development, implementation, and evaluation--and the 
relationships between them. 

Figure 2: Strategic Training and Development Process: 

[See PDF for image] 

[End of figure] 

Without an evaluation component for its training program, AOC lacks a 
systematic means of obtaining feedback on the training's results. As 
our guide indicates, such feedback is important for determining whether 
training investments are being targeted strategically or being wasted. 
Additionally, without an evaluation component, AOC managers cannot 
determine how well the training has prepared CPP staff to operate the 
plant safely, and they cannot identify and address any specific 
training gaps or weaknesses. Having objective, consistent information 
on operators' performance in training will be important to AOC when it 
implements its updated staffing plan and makes staffing decisions. 

Although AOC has not developed a plan for evaluating its training for 
CPP operators or evaluated the initial 9-month refresher training, it 
has some evidence that the initial training was not as effective as 
intended. For example, some operators achieved low scores on tests 
administered by the construction management consultant during the 
initial training. The consultant gave these tests informally, but 
provided the results to us at our request.[Footnote 19] Additionally, 
CPP managers said, some operators were ambivalent about the training 
and skipped classes. The CPP operators we spoke with about the training 
varied in their assessments of it. Some acknowledged the training's 
value, while others were concerned that the training was not "hands on" 
or specific to the new equipment being installed as part of the 
expansion. As discussed, however, "hands-on," equipment-specific 
training will be provided by manufacturers during the commissioning 
process. 

To address concerns about the ability of CPP staff to operate the new 
equipment, AOC managers said they plan to hire a startup contractor to 
provide technical assistance to CPP operators for up to 8 weeks after 
the WRPE contract's completion. 

Cost to Complete WRPE Project Will Depend on Contract Changes and 
Operational Issues: 

We estimate that the cost to complete the WRPE project will range from 
about $98 million to nearly $106 million, depending on AOC's resolution 
of proposed contract changes and the level of training and contractor 
technical support that CPP operators will need. Although the WRPE 
construction contract is currently scheduled for completion in March 
2006, it may be delayed until June 2006 because of contract changes. 
Our analysis of the cost to complete the project appears in enclosure 
I. 

Through October 2005, nearly $100.9 million has been budgeted for the 
WRPE project, and over $95.1 million has been obligated for 
construction and administrative costs, leaving an unobligated balance 
of approximately $5.7 million.[Footnote 20], [Footnote 21] AOC's 
October 2005 progress report on WPRE's construction indicates that 
future costs may exceed the amount of funding that remains. According 
to the progress report, 65 contract changes are pending resolution 
between AOC and its construction contractor. As the project progresses, 
AOC anticipates additional changes to account for such activities as 
troubleshooting during commissioning tests and providing technical 
support to operators during the initial weeks of plant operations. Our 
analysis to estimate the project's cost at completion provides for a 
range of costs, from best to worst case, to account for the variability 
associated with forecasting these changes. Specifically, our analysis 
shows that the negotiated amount of these changes is likely to result 
in costs ranging between $2.9 million and $10.7 million. Given the 
project's unobligated $5.7 million balance, the settlement of these 
changes will yield approximate results ranging from a $2.8 million 
surplus to a $5 million shortfall (see fig. 3). Our analysis takes into 
account the likelihood that the project's completion date could be 
extended from March to June 2006. 

Figure 3: WRPE Budget Breakdown, Including Cost to Complete 
Projections: 

[See PDF for image] 

[End of figure] 

Pending or anticipated changes that may have a significant impact on 
the project's cost and schedule include the following: 

* Redesign of fire sprinkler system. After reviewing design 
documentation for the fire sprinkler system, AOC's Fire Marshall 
determined that changes were necessary to make the system compliant 
with the current fire code. Because of the Fire Marshall's decision, 
the construction contractor needed additional time to make design 
changes and prepare new submittals. As a result, sprinkler system 
components have not been ordered. The construction contractor does not 
expect the installation to be completed until August 2006, but AOC 
officials believe it can be completed by June 2006. Discussions between 
the two parties to resolve this issue are ongoing. Even if the fire 
sprinkler system is not operable when WRPE is turned over to AOC, AOC's 
Fire Marshall said steps could be taken that would enable him to issue 
a conditional occupancy permit so that CPP staff could operate the 
plant and its equipment. 

* Reconfiguration of chilled water pipes. AOC officials indicated that, 
because of the chiller failure in the East Refrigeration Plant in July 
2005, they wanted to gain greater operational flexibility and decided 
to configure WRPE and the West Refrigeration Plant as separate 
facilities rather than as one plant, as originally planned. This 
decision means that AOC needs to add components to the West 
Refrigeration Plant's piping system instead of demolishing that 
facility's chilled water distribution pipes. AOC officials anticipate 
making changes to the West Refrigeration Plant's piping system under a 
separate contract at an estimated cost of $600,000. AOC expects this 
work to be completed before the WPRE contract is completed in March 
2006. AOC officials also expect to receive a $150,000 credit from the 
construction contractor for the pipe demolition work that was part of 
the base WRPE project's scope but is no longer required. 

* Changes to the design of the WRP/WRPE distributed controls system. 
Because of an earlier decision to upgrade the distributed controls 
system for the chillers, AOC stopped installation work on June 24, 
2005, in order to resolve procurement issues and redesign the system. 
In November 2005, AOC issued a modification directing the construction 
contractor to proceed with the system's installation according to the 
revised design. The cost of the system upgrade and its impact on the 
contract's schedule are pending negotiation between AOC and the 
contractor. CPP project managers indicated that tying the existing WRP 
into the distributed controls system is contributing to the delay in 
completing the contract. 

* Commissioning troubleshooting. According to GSA's guidance, problems 
should be expected when equipment is tested as part of the 
commissioning process. In September 2005, AOC estimated, on the basis 
of its construction management consultant's experience, that $500,000 
may be needed for troubleshooting and repair work. Because 
commissioning is in its initial stages, it is still too early to assess 
the impact of troubleshooting on the project's cost and schedule. 

* Operational issues. As discussed, AOC plans to hire a startup 
contractor for up to 8 weeks after WRPE is finished to provide 
technical assistance to CPP operators. AOC managers said they were 
unsure whether this amount of startup support would be sufficient and 
recognized that additional support may be needed. To the extent that 
additional support is needed, AOC's costs are likely to increase. 

Conclusions: 

AOC's commissioning activities to date and plans for commissioning new 
CPP equipment, if fully implemented, should allow AOC to test the 
equipment thoroughly and bring it on line with minimal disruption to 
current operations. Nevertheless, the majority of the systems testing 
remains to be done and could prove more challenging than the completed 
testing. Additionally, the WRPE project still faces budgetary risks and 
schedule uncertainties, especially those stemming from the impact of 
contract changes that have not yet been negotiated. 

AOC's plans for staffing the modernized power plant efficiently and 
ensuring that CPP personnel are trained to operate it safely also face 
risks and uncertainties. AOC has delayed implementing recommendations 
to reduce CPP's staffing, and now has just a few months to develop an 
efficient staffing plan before WRPE is scheduled to be completed. AOC 
also lacks assurance that CPP staff will be prepared to operate the new 
equipment safely since it has not yet completed the training of CPP 
operators, and has not developed a plan to evaluate the training. 
Additionally, without some form of evaluation, AOC is missing an 
opportunity to measure its operators' preparedness, prior to 
implementing its consultant's updated staffing plan. 

Recommendations for Executive Action: 

To ensure that CPP is staffed efficiently and that CPP personnel are 
trained to operate the modernized power plant safely, we recommend that 
the Architect of the Capitol: 

* develop and implement a staffing plan for CPP that is based on the 
results of its most recent consultant's study and: 

* evaluate the training provided to CPP operators and use the 
evaluation results in implementing the staffing plan. 

Agency Comments and Our Evaluation: 

We provided a draft copy of this report to AOC for review and comment. 
AOC officials provided oral comments in which they generally concurred 
with our recommendations and offered technical clarifications and 
updated information concerning staffing and training efforts. 

Regarding CPP staffing, AOC indicated that it is continuing to review 
the draft staffing plan received from its consultant in December 2005 
and is working to develop new position descriptions based on this plan. 
AOC also noted that its 1996 consultant study attributes overstaffing 
to a lack of system automation and suggested that it will not be 
possible to begin implementation of revised staffing plans until 
completion of the ongoing WRPE project. We note, however, that AOC's 
2004 consultant report lists additional reasons for CPP overstaffing. 
Specifically, the 2004 report states that there are no cross 
responsibilities between different operation segments, and that over 
many years of operations, additional levels of management have been 
added. 

Concerning evaluation of operator training, AOC indicated that it has 
modified its training structure to include two weekly tests--one 
theoretical written test and one field test on actual equipment--that 
are used to assess operators' knowledge and highlight areas in which 
additional training may be needed. While this is a step in the right 
direction, given the imminent startup of the new equipment, AOC still 
faces challenges in establishing a systemic means of evaluating 
training and using the feedback to ensure that its staff is fully 
prepared to safely operate the modernized plant. This involves a look 
at not just operators' knowledge, but also an assessment of how 
training contributes to improving performance and achieving a greater 
capacity to meet new and emerging challenges. 

As agreed with your office, unless you publicly announce the contents 
of this report earlier, we plan no further distribution until 30 days 
from the report date. At that time, we will send copies of this report 
to the appropriate congressional committees and the Architect of the 
Capitol. Copies will also be made available to other interested parties 
on request. In addition, the report will be available at no charge on 
GAO's Web site at http://www.gao.gov. 

If you or your staff have any questions about this report, please 
contact me at (202) 512-2834 or goldsteinm@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. GAO staff who made major contributions 
to this report are listed in enclosure II. 

Signed by: 

Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 

Enclosures: 

Enclosure I: Estimated Cost to Complete the West Refrigeration Plant 
Expansion Project: 

Tables 1 through 3 provide our estimates of the costs to complete the 
Architect of the Capitol's (AOC) West Refrigeration Plant Expansion 
(WRPE) project. As shown in tables 1 and 2, the entire project consists 
of the expansion and several smaller capital projects. Table 1 shows 
the amounts provided, obligated, and remaining for each project through 
October 2005. Table 2 shows the additional amounts that we estimate 
will be required for each project in the best and worst cases. These 
amounts will depend on the outcomes of negotiations over potential 
change orders and other actions. Finally, table 3 shows our estimates 
of the costs to complete the entire project and the remaining funds in 
the best and worst cases. 

Table 1: Funds Provided to AOC, Obligated, and Remaining for the WRPE 
Project: 

Project: West Refrigeration Plant Expansion; 
Funds provided[A]: $81,670,076; 
Obligations[B]: $78,028,511; 
Unobligated balance[C]: $3,641,565. 

Project: Distributed controls system—boiler house; 
Funds provided[A]: $6,461,650; 
Obligations[B]: $5,188,793; 
Unobligated balance[C]: $1,272,857. 

Project: Fuel oil tank; 
Funds provided[A]: $4,175,220; 
Obligations[B]: $3,913,059; 
Unobligated balance[C]: $262,161. 

Project: Boiler deaerator tank and feedwater pumps; 
Funds provided[A]: $1,375,000; 
Obligations[B]: $1,375,000; 
Unobligated balance[C]: $0. 

Project: Electric modernization; 
Funds provided[A]: $4,400,000; 
Obligations[B]: $3,957,544; 
Unobligated balance[C]: $442,456. 

Project: Emergency generator; 
Funds provided[A]: $1,625,000; 
Obligations[B]: $1,580,071; 
Unobligated balance[C]: $45. 

Project: Condenser water filtration and basin heating; 
Funds provided[A]: $360,000; 
Obligations[B]: $331,090; 
Unobligated balance[C]: $28,910. 

Project: Miscellaneous projects[D]; 
Funds provided[A]: $802,945; 
Obligations[B]: $802,945; 
Unobligated balance[C]: $0. 

Project: Total; 
Funds provided[A]: $100,869,891; 
Obligations[B]: $95,177,013; 
Unobligated balance[C]: $5,692,878. 

Sources: Federal legislation and AOC. 

Notes: Our analysis is based on unaudited project financial information 
provided by AOC. 

[A] Includes appropriations for construction and related activities for 
fiscal years 2003 and 2004, authorized reprogramming, and Capitol Power 
Plant (CPP) operation funds. 

[B] Through contract modification 48. 

[C] Authorized reprogramming would be required to combine the funding 
for these separate projects. 

[D] These projects are being funded with CPP operating funds. 

[End of table] 

Table 2: Our Best-and Worst-Case Estimates of Potential Additional 
Funding Needed for WRPE: 

Project: West Refrigeration Plant Expansion; 
Best case[A]: $2,893,940; 
Worst case[B]: $9,146,287. 

Project: Distributed controls system--boiler house; 
Best case[A]: $0; 
Worst case[B]: $1,123,734. 

Project: Fuel oil tank; 
Best case[A]: $13,600; 
Worst case[B]: $127,539. 

Project: Boiler deaerator tank and feedwater pumps; 
Best case[A]: $7,000; 
Worst case[B]: $124,054. 

Project: Electric modernization; 
Best case[A]: $0; 
Worst case[B]: $165,000. 

Project: Emergency generator; 
Best case[A]: $28,000; 
Worst case[B]: $43,000. 

Project: Condenser water filtration and basin heating; 
Best case[A]: $0; 
Worst case[B]: $0. 

Total; 
Best case[A]: $2,942,540; 
Worst case[B]: $10,729,614. 

Sources: Federal legislation and AOC. 

Notes: Our analysis is based on unaudited project financial information 
provided by AOC. 

[A] Our analysis of best possible outcomes of potential change orders 
(PCO). This includes PCOs currently being negotiated, identified as 
estimates of future work, and previously denied. 

[B] Our analysis of worst possible outcomes of PCOs. This includes PCOs 
currently being negotiated, identified as estimates of future work, and 
previously denied. 

[End of table] 

Table 4: Our Best-and Worst-Case Estimates of the Cost to Complete the 
Entire WRPE Project and Remaining Funds: 

Amount/estimate: Funding provided through October 2005; 
Best case: $100,869,891; 
Worst case: $100,869,891. 

Amount/estimate: Obligations through October 2005; 
Best case: $95,177,013; 
Worst case: $95,177,013. 

Amount/estimate: Potential additional funding needed; 
Best case: $2,942,540; 
Worst case: $10,729,614. 

Amount/estimate: Estimated cost to complete; 
Best case: $98,119,553;  
Worst case: $105,906,627. 

Amount/estimate: Remaining funds; 
Best case: $2,750,338; 
Worst case: $(5,036,736). 

Sources: Federal legislation and AOC. 

Note: Our analysis is based on unaudited project financial information 
provided by AOC. 

[End of table] 

Enclosure II: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Mark L. Goldstein, (202) 512-2834 or goldsteinm@gao.gov: 

Staff Acknowledgments: 

In addition to the contact named above, Terrell Dorn (Assistant 
Director), Michael Armes, George Depaoli, Timothy DiNapoli, Elizabeth 
Eisenstadt, Kimberly Gianopoulos, Susan Michal-Smith, and Walter Vance 
made key contributions to this report. 

(543136): 

FOOTNOTES 

[1] The base WRPE contract provides for a distributed controls system 
that uses a computer program, rather than human operators, to monitor 
and control CPP's chillers. A contract modification is funding a 
similar system for CPP's boilers. 

[2] GAO, Capitol Power Plant: Actions Needed to Improve Operating 
Efficiency (Washington, D.C.: Apr. 8, 2005), issued as unnumbered 
correspondence. This work was mandated in the Consolidated 
Appropriations Act for Fiscal Year 2005 (Section 1101 of Division G, 
Title I of Pub. L. No. 108-447 118 Stat. 2809, at 3185 and 3186 
(2004)). 

[3] GSA, Public Buildings Service, Office of the Chief Architect, The 
Building Commissioning Guide (Washington, D.C., April 2005). 

[4] GAO, Human Capital: A Guide for Strategic Training and Development 
Efforts in the Federal Government, GAO-04-546G (Washington, D.C.: March 
2004). 

[5] The commissioning agent retained by AOC had been involved with the 
project as a subcontractor to AOC's construction management consultant. 
We recommended that, given the importance of the commissioning process, 
AOC have a direct relationship with an independent commissioning agent. 
In November 2005, AOC entered into a new contract for commissioning 
services with the same firm that was formerly a subcontractor to AOC's 
construction management consultant. 

[6] The $33 million operating budget primarily consists of payroll, 
maintenance, and utility costs. The utility costs largely consist of 
fuel and electricity to operate the boilers and chillers. 

[7] CPP does not currently produce electric power. According to AOC 
officials, CPP stopped producing power in 1952. 

[8] Other work under the contract, such as the installation of the 
distributed controls system in the boiler plant, is likely to continue 
beyond this date. 

[9] The rate at which a chiller produces cooling is generally expressed 
in tons per hour. One ton of cooling is equal to the amount of cooling 
provided by 1 ton (2,000 pounds) of ice melting in 1 day (12,000 
British thermal units per hour). The West Refrigeration Plant houses 
four 6,000-ton chillers, and the East Refrigeration Plant contains two 
new 3,000-ton chillers and four obsolete chillers (three 2,200-ton 
chillers--two of which were taken out of service in July 2005--and one 
1,100-ton chiller). 

[10] AOC purchased these chillers in September 2004 to supplement 
chilled water production in case of disruptions during construction. 

[11] A cogeneration system is a combustion turbine generator that 
produces electricity and uses the heat from the combustion to produce 
steam. 

[12] See GAO, Capitol Visitor Center: Schedule Delays Continue; 
Reassessment Underway, GAO-05-1037T (Washington, D.C.: Sept. 15, 2005); 
Capitol Visitor Center: Status of Schedule, Fire Protection, Cost and 
Related Issues, GAO-06-180T (Washington, D.C.: Oct. 18, 2005); and 
Capitol Visitor Center, Update on Schedule and Cost, GAO-05-251T 
(Washington, D.C.: Nov. 16, 2005). 

[13] The WRPE construction contractor has prepared the checklists for 
stages one and two of the testing plan but has yet to prepare 
checklists for stage three. AOC project managers expect to receive the 
third stage of the plan in February 2006. 

[14] See AOC, Capitol Power Plant Technical and Economic Evaluation of 
Plant Operations (Washington, D.C., April 1996). 

[15] GAO, Capitol Power Plant Utility Master Plan, GAO-04-456RNI 
(Washington, D.C.: Mar. 1, 2004). 

[16] See AOC, Utility Master Plan (Washington, D.C., 2004). 

[17] According to a CPP official, weekly 2-hour training sessions were 
scheduled for operators from February through December 2004. 

[18] GAO-04-546G. 

[19] Names of test takers were redacted from documents to maintain 
confidentiality. 

[20] Financial information is based on unaudited CPP project records 
used in preparing AOC's October 2005 WPRE monthly progress report. 

[21] Numbers may not add because of rounding.