This is the accessible text file for GAO report number GAO-09-913 
entitled 'Nuclear Waste: Uncertainties and Questions about Costs and 
Risks Persist with DOE's Tank Waste Cleanup Strategy at Hanford' which 
was released on September 30, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Subcommittee on Energy and Water Development, Committee 
on Appropriations, House of Representatives: 

United States Government Accountability Office: 
GAO: 

September 2009: 

Nuclear Waste: 

Uncertainties and Questions about Costs and Risks Persist with DOE's 
Tank Waste Cleanup Strategy at Hanford: 

GAO-09-913: 

GAO Highlights: 

Highlights of GAO-09-913, a report to the Subcommittee on Energy and 
Water Development, Committee on Appropriations, House of 
Representatives. 

Why GAO Did This Study: 

At its Hanford Site in Washington State, the Department of Energy (DOE) 
is responsible for one of the world’s biggest cleanup projects: the 
treatment and disposal of about 56 million gallons of radioactive and 
hazardous waste, stored in 177 underground tanks. Two decades and 
several halted efforts later, none of this waste has yet been treated, 
cleanup costs have grown steadily, and prospective cleanup time frames 
have lengthened. 

GAO was asked to assess (1) DOE’s current tank waste cleanup strategy 
and key technical, legal, and other uncertainties; (2) the extent to 
which DOE has analyzed whether this strategy is commensurate with risks 
from the wastes; and (3) opportunities to reduce tank waste cleanup 
costs. GAO reviewed pertinent documents, visited the site, and 
interviewed officials and independent experts. 

What GAO Found: 

DOE’s tank waste cleanup strategy consists of five key phases—waste 
characterization, retrieval, pretreatment, treatment, and permanent 
disposal—but critical uncertainties call into question whether the 
strategy can succeed as planned. Technical uncertainties include 
whether DOE can retrieve waste from tanks at the rate needed to support 
continuous operation of the waste treatment complex now under 
construction and whether key treatment technologies will work. Legal 
uncertainties include whether DOE can treat and dispose of some tank 
waste as other than high-level (highly radioactive) waste and how much 
residual waste can be left in the tanks when they are eventually 
closed. Such uncertainties could lead to significant cost increases and 
further delays in completing Hanford’s tank waste cleanup activities. 

DOE has not systematically evaluated whether its tank waste cleanup 
strategy is commensurate with risks posed by the wastes. DOE lacks 
credible or complete estimates of how much the strategy will cost or 
how long it will take. The total project cost of constructing the waste 
treatment plant alone grew from $4.3 billion in 2000 to $12.3 billion 
in 2006. In addition, DOE did not include, or has been unable to 
quantify, a number of significant costs in its current estimate of the 
overall cost of its cleanup strategy. For example, DOE has not included 
some actual expenditures to date or storage costs for high-level waste 
canisters. Further, DOE’s schedule targets have slipped, with end of 
treatment extending from 2028 to 2047, which increases overall 
operations costs. Overall the total estimated cost could significantly 
exceed DOE’s current estimate of $77 billion, with estimates ranging 
from about $86 billion to over $100 billion, depending upon the date 
cleanup is completed. DOE has also fallen short in terms of risk-
informed decision making. While DOE has analyzed risks in environmental 
impact statements required for its tank waste treatment activities at 
Hanford, it has not followed a systematic risk assessment framework, 
like one outlined in a 1983 report, updated in 2008, by the National 
Academy of Sciences. As a result, DOE cannot be assured that its 
present strategy is proportional to the reduction in risk that cleanup 
is to achieve. 

Some opportunities may still exist to reduce the costs of DOE’s tank 
waste cleanup strategy, but the likelihood of success is unknown. For 
example, DOE is trying to increase the concentration of high-level 
waste in each disposal canister, thereby reducing the number of 
canisters and possibly shortening treatment time frames. DOE could also 
work with regulators to demonstrate, on a tank-farm basis, the 
feasibility of leaving varying amounts of residual waste in tanks at 
closing without threatening human or ecological health. In removing 
waste from tanks, DOE has found that the last portion can be 
disproportionately difficult and costly to remove. Specifically, the 
cost of removing the last 15 percent of waste can equal or exceed the 
cost of removing the first 85 percent. 

What GAO Recommends: 

GAO is recommending that, for Hanford, DOE (1) improve its life-cycle 
cost and schedule estimates, (2) adopt a risk assessment framework that 
considers available guidance, (3) consider seeking congressional 
clarification about reclassifying its high-level tank waste, and (4) 
work with regulators on tank closure options. DOE agreed with three of 
these; it disagreed with seeking further clarification about 
reclassifying high-level waste. GAO believes this recommendation 
remains valid, given the importance of waste reclassification to DOE’s 
strategy. 

View [hyperlink, http://www.gao.gov/products/GAO-09-913] or key 
components. For more information, contact Gene Aloise at (202) 512-3841 
or aloisee@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

Critical Uncertainties Persist in DOE's Hanford Tank Waste Cleanup 
Strategy: 

DOE Has Not Systematically Evaluated Whether Its Tank Waste Cleanup 
Strategy, Including Costs, Is Commensurate with Risks from the Waste: 

Some Opportunities May Exist to Reduce Costs of DOE's Hanford Tank 
Waste Cleanup Strategy: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Overview of DOE's Efforts to Select an Approach to 
Supplement Its Low-Activity Tank Waste Treatment Capacity: 

Appendix III: Comments from the Department of Energy: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Related GAO Products: 

Table: 

Table 1: Estimated Costs Associated with DOE's Tank Waste Cleanup 
Strategy: 

Figures: 

Figure 1: Changes in Hanford's Tank Waste Cleanup Strategy, 1989 to 
Present: 

Figure 2: Key Phases in DOE's Tank Waste Cleanup Strategy: 

Figure 3: Cost Estimates for Constructing Hanford's Waste Treatment 
Plant: 

Figure 4: Shifting Estimates of the Duration of Hanford Tank Waste 
Treatment: 

Abbreviations: 

CERCLA: Comprehensive Environmental Response, Compensation, and 
Liability Act: 

DOE: Department of Energy: 

EPA: Environmental Protection Agency: 

RCRA: Resource Conservation and Recovery Act: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

September 30, 2009: 

The Honorable Peter J. Visclosky: 
Chairman: 
The Honorable Rodney P. Frelinghuysen: 
Ranking Member: 
Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
House of Representatives: 

The Department of Energy (DOE) is responsible for one of the world's 
largest environmental cleanup programs: the treatment and disposal of 
nuclear waste created as a by-product of producing nuclear weapons. 
Decades of nuclear weapons production have left a legacy of radioactive 
and hazardous wastes to be cleaned up at DOE sites across the country. 
One of DOE's most contaminated locations is its Hanford Site, which 
lies along the Columbia River in southeastern Washington State. The 
site occupies 586 square miles upriver from the Tri-Cities area of 
Richland, Pasco, and Kennewick, with a combined regional population of 
over 200,000. DOE and its predecessor agencies[Footnote 1] produced 
nuclear materials at the Hanford Site from 1944 through 1988, 
generating millions of gallons of radioactive and hazardous waste 
during those years. Some of this waste was deposited directly into the 
soil; some was encased in drums or other containers and buried; and 
some was stored in 177 large, underground tanks. In total, these tanks, 
clustered together in 18 locations called tank farms, contain about 56 
million gallons of waste--enough to cover an entire football field to a 
depth of over 150 feet, or the height of a 15-story building. 

Since plutonium production ended at Hanford in the late 1980s, DOE has 
spent more than $12 billion[Footnote 2] to manage the tank waste and 
explore ways to treat and dispose of it. After beginning and 
discontinuing several different tank waste cleanup strategies, DOE has 
now embarked on a strategy that involves building a complex of 
treatment facilities, collectively called the Hanford Waste Treatment 
and Immobilization Plant. Currently under construction and estimated to 
cost $12.3 billion to design, build, and commission, this waste 
treatment plant consists of a laboratory for analyzing the waste's 
composition; a pretreatment plant to separate the waste into two 
streams (a highly radioactive fraction called high-level waste and a 
lower-radioactivity fraction called low-activity waste); two waste 
treatment facilities, one for high-level waste and one for low-activity 
waste; and more than 20 support facilities. DOE estimates that it will 
cost tens of billions of dollars and take until 2047 to complete tank 
waste cleanup and permanently close the underground storage tanks. To 
date, however, no tank waste at Hanford has been treated for final 
disposal, and none of the tanks has been permanently closed. 

DOE's cleanup, treatment, and disposal of radioactive and hazardous 
wastes are governed by a number of federal and state laws and 
implemented under the leadership of DOE's Assistant Secretary for 
Environmental Management. Key laws include the Comprehensive 
Environmental Response, Compensation, and Liability Act of 1980 
(CERCLA), as amended, and the Resource Conservation and Recovery Act of 
1976 (RCRA), as amended.[Footnote 3] In addition, most of the cleanup 
activities at Hanford, including emptying the underground tanks, are 
carried out under the Hanford Federal Facility Agreement and Consent 
Order among DOE, the Washington State Department of Ecology, and the 
federal Environmental Protection Agency (EPA).[Footnote 4] Commonly 
called the Tri-Party Agreement, this accord was signed in May 1989 and 
has been amended a number of times since then. The agreement lays out a 
series of legally enforceable milestones for completing major 
activities in Hanford's waste treatment and cleanup process. A variety 
of local and regional stakeholders, including county and local 
government agencies, citizen and advisory groups, and Native American 
tribes, also have long-standing interests in Hanford cleanup issues. 
Like nearly all of DOE's missions, the majority of the work at the 
Hanford Site is performed by private firms under contract to DOE. 
Cleanup activities employ thousands of people in the private and public 
sectors, thus contributing significantly to the economy of the Tri- 
Cities area. 

As requested, this report discusses (1) Hanford's current tank waste 
cleanup strategy and key associated technical, legal, and other 
uncertainties; (2) the extent to which DOE has determined whether its 
cleanup strategy at Hanford is commensurate with risks posed by the 
wastes; and (3) opportunities for DOE to reduce the costs of cleaning 
up Hanford's tank waste while still protecting human health and the 
environment. 

To address these objectives, we gathered and reviewed information on 
the Hanford waste cleanup strategy, including technical reports and 
internal and external reviews. We reviewed legal and regulatory 
requirements governing cleanup of hazardous and radioactive wastes, 
including requirements for determining whether some tank wastes can be 
classified as other than high-level waste. We also reviewed the Tri- 
Party Agreement to gain an understanding of its requirements and time 
frames. Several key documents were released by DOE just before, or were 
scheduled to be released shortly after, the date of this report. These 
included a tentative legal settlement with the state of Washington, an 
amended Tri-Party Agreement, a draft environmental impact statement for 
tank closure, and a new cost and schedule baseline for the Hanford tank 
waste cleanup effort. We reviewed an August 10, 2009, version of the 
tentative legal settlement and were provided access to a version of the 
draft environmental impact statement, but the remaining documents were 
not available at the time of our review. These documents are discussed 
in our report and factored into its conclusions and recommendations as 
available and appropriate. As agreed with DOE, we included only 
publicly available information about the draft environmental impact 
statement in our report. In addition, we interviewed officials at the 
Hanford Site's Office of River Protection and at DOE headquarters, 
including in the Office of Engineering and Construction Management and 
the Office of Environmental Management. We interviewed contractor 
officials at the Hanford Site responsible for building the waste 
treatment plant. We also visited the Hanford Site, including the waste 
treatment plant construction site. We interviewed officials with 
regulatory and other agencies, specifically, the Washington State 
Department of Ecology, EPA, the Nuclear Regulatory Commission, and the 
Defense Nuclear Facilities Safety Board. To assist in understanding 
concerns with various aspects of Hanford's tank waste cleanup strategy, 
we interviewed staff at the National Academy of Sciences. In addition, 
we identified and interviewed 18 independent experts for their input on 
various aspects of DOE's Hanford tank waste cleanup strategy. We 
provided an interim briefing in May 2009 to the subcommittee on the 
status of our work. Appendix I describes our scope and methodology in 
more detail. We conducted this performance audit from July 2008 to 
September 2009, in accordance with generally accepted government 
auditing standards. Those standards require that we plan and perform 
the audit to obtain sufficient, appropriate evidence to provide a 
reasonable basis for our findings and conclusions based on our audit 
objectives. We believe that the evidence obtained provides a reasonable 
basis for our findings and conclusions based on our audit objectives. 

Background: 

Established in 1943, the Hanford Site produced plutonium for the 
world's first nuclear device. At the time, little attention was given 
to the resulting by-products--massive amounts of radioactive and 
chemically hazardous waste. From 1944 through 1988, about 525 million 
gallons of radioactive tank waste was generated by Hanford's plutonium- 
processing plants. The federal government initially managed this waste 
by intentionally discharging it into the ground; reducing its volume 
through various waste concentration methods, such as evaporating off 
the liquids; and building underground tanks to store the waste until it 
could be treated and permanently disposed of. 

From the 1940s through the mid-1960s, 149 underground "single-shell" 
storage tanks were built at Hanford. Originally expected to last 10 to 
20 years until a permanent disposal solution could be found, each of 
these tanks consisted of an outer concrete wall lined with one layer of 
carbon steel. Grouped into 12 tank farms and buried some 6 to 11 feet 
beneath the surface, most of these single-shell tanks measure roughly 
75 feet in diameter, range from 30 to 49 feet high, and have a capacity 
ranging from 530,000 to 1 million gallons of waste.[Footnote 5] 
Together, the single-shell tanks contain almost 30 million gallons of 
waste; about 27 million gallons are in solid or semisolid form, and 
about 3 million gallons are liquid. By the mid-1990s, 67 of the single- 
shell tanks had leaked or were presumed to have leaked about 1 million 
gallons of waste into the surrounding soil. To address concerns with 
the design of the single-shell tanks, a new tank design with two carbon-
steel shells was adopted in the late 1960s. From 1968 through 1986, 28 
of these double-shell tanks, with storage capacities ranging from 1 
million to 1.2 million gallons, were built and sited in 6 more tank 
farms at Hanford. Together, these double-shell tanks contain about 26 
million gallons of waste.[Footnote 6] To help minimize further leaking, 
DOE had, by 2005, transferred most of the liquid in the single-shell 
tanks to the double-shell tanks, a process called interim 
stabilization. DOE is currently retrieving the remaining waste from 
single-shell tanks and moving it to the double-shell tanks in 
preparation for treatment.[Footnote 7] 

The contents of these tanks have settled and today exist in four main 
forms or layers: 

* Vapor: Gases produced from chemical reactions and radioactive decay 
occupy tank space above the waste. 

* Liquid: Fluids may float above a layer of settled solids or under a 
floating layer of crust; fluids may also seep into pore spaces or 
cavities of settled solids, crust, or sludge. 

* Saltcake: Water-soluble compounds, such as sodium salts, can 
crystallize or solidify out of wastes to form a moist salt-like 
hardened or crusty material. 

* Sludge: Denser, water-insoluble or solid components generally settle 
to the bottom of a tank to form a thick layer having the consistency of 
peanut butter. 

About 46 different radioactive elements--by-products of chemically 
separating plutonium from uranium for use in nuclear weapons--represent 
the majority of the radioactivity currently residing in the tanks. Some 
of these elements lose most of their radioactivity in a relatively 
short time, while others remain radioactive for millions of years. The 
rate of radioactive decay is measured in half-lives, that is, the time 
required for half the unstable atoms in a radioactive substance to 
disintegrate, or decay, and release their radiation. The half-lives of 
major radioactive tank constituents differ widely. The vast majority 
(98 percent) of the tank waste's radioactivity comes from two elements, 
strontium-90 and cesium-137, which have half-lives of about 29 and 30 
years, respectively. The remaining radioactive elements, which account 
for about 2 percent of the waste's total radioactivity, have much 
longer half-lives. For example, the half-life of technetium-99 is 
213,000 years, and that of iodine-129 is 15.7 million years. As we 
reported in 2003 on the basis of radioactivity levels measured as of 
August 2002, within 100 years, more than 90 percent of the 
radioactivity in the tanks will have dissipated, and within 300 years, 
99.8 percent will disappear.[Footnote 8] After the waste is separated, 
the high-level waste stream will contain over 95 percent of the 
radioactivity but total less than 10 percent of the volume to be 
treated. In comparison, the low-activity waste stream will contain less 
than 5 percent of the radioactivity but constitute over 90 percent of 
the volume. 

The tanks also contain large volumes of hazardous chemical waste, 
including various metal hydroxides, oxides, and carbonates. Like 
radioactive by-products of plutonium production, some of these 
chemicals--including acids, caustic sodas, solvents, and toxic heavy 
metals such as chromium--came from chemically reprocessing spent 
nuclear fuel to extract weapons-grade plutonium. Altogether, DOE added 
about 240,000 tons of chemicals to the tanks from the 1940s to the mid- 
1980s. A majority of the chemicals (caustics, such as sodium hydroxide) 
were added to neutralize acids in the waste. Other chemicals, such as 
solvents, ferrocyanide, and several organic compounds, were added 
during various waste extraction operations to help recover selected 
radioactive elements (uranium, cesium, and strontium) for reuse. These 
hazardous chemicals are dangerous to human health, and they can remain 
dangerous for thousands of years. 

Over the past 20 years, DOE has tried developing various approaches for 
treating and disposing of these wastes, at varying costs and with 
little success (see figure 1). In 1989, DOE's original strategy called 
for treating waste only from the double-shell tanks. Part of this 
effort involved renovating a World War II-era facility, called B Plant, 
[Footnote 9] in which it planned to start waste treatment. DOE spent 
about $23 million on this project but discontinued it because of 
technical and environmental issues and stakeholder concerns that not 
all the waste would be treated. In 1991, DOE decided to treat waste 
from all 177 tanks. Under this strategy, DOE would have completed the 
treatment facility before other aspects of the waste treatment program 
were fully developed, and the planned treatment facility would have had 
insufficient capacity to treat all the waste in a time frame acceptable 
to regulators. DOE spent about $418 million on this approach. Beginning 
in 1995, DOE attempted to "privatize" tank waste cleanup, shift risk to 
its contractor,[Footnote 10] build a demonstration facility to treat 10 
percent of the waste and 25 percent of the radioactivity by 2018, and 
end cleanup in 2028. But because of dramatically escalating costs and 
concerns about contractor performance, DOE terminated the contract 
after spending about $300 million, mostly on plant design. According to 
available information, since 1997 DOE has spent an average of more than 
$300 million each year on tank management and risk reduction 
activities, such as retrievals and facility upgrades. 

Figure 1: Changes in Hanford's Tank Waste Cleanup Strategy, 1989 to 
Present: 

[Refer to PDF for image: timeline] 

Renovate existing facility: treat double-shell tank waste: 
Estimated cost: $2.8 billion (constant 1988 dollars); 
Planned start of treatment: 1999. 

Build new facility: treat all tank waste: 
Estimated cost: $25 billion–$45 billion (current dollars); 
Planned start of treatment: 1999. 

Build demonstration facility: treat 10 percent of waste first: 
Estimated cost: more than $50 billion (current dollars); 
Planned start of treatment: 2002; 
Revised start of treatment: 2007. 

Current tank waste cleanup strategy: 
Estimated cost: about $80 billion (current dollars): 
Planned start of treatment: 2011; 
Revised start of treatment: 2019. 

Source: GAO analysis of DOE data. 

Note: When estimating costs for its cleanup strategies, DOE has not 
always included adequate contingency funding for unforeseen 
circumstances. The $80 billion estimate for DOE's current strategy 
includes such contingency funding of about $19 billion. 

[End of figure] 

Critical Uncertainties Persist in DOE's Hanford Tank Waste Cleanup 
Strategy: 

Critical uncertainties, such as technical and legal issues, call into 
question whether DOE's strategy to treat and dispose of millions of 
gallons of radioactive and hazardous tank wastes at its Hanford Site 
can succeed as planned. 

DOE's Waste Treatment Strategy Consists of Five Key Phases: 

DOE's current strategy generally consists of removing, or retrieving, 
waste from the underground tanks; separating the wastes into high-level 
and low-activity waste streams through a process called pretreatment; 
treating the waste on site; and ultimately disposing of the low- 
activity waste on site and sending the high-level waste to a geologic 
repository for permanent disposal (see figure 2). Specifically, the 
five key phases are: 

* Characterization: Sampling and analysis to determine the specific 
physical, radiological, and chemical components of the wastes in each 
tank. Waste is sampled and analyzed starting before it is retrieved 
from the tanks and continuing until it is ready for final treatment. 

* Retrieval: Removing waste from the tanks by pumping or other means 
and transferring it to the treatment facilities. DOE uses a variety of 
technologies, including high-pressure sprays to break up hardened waste 
on the tank bottom and vacuum systems to suck the waste out of the 
tanks. Because a large amount of liquid may be introduced during 
retrieval to break up hardened waste, waste removed from a tank is 
transferred to a facility to evaporate some of the liquid and reduce 
its volume before being sent to the waste treatment plant.[Footnote 11] 

* Pretreatment: Mixing and separating waste constituents into high-
level and low-activity waste streams by filtering, dissolving, and 
extracting radioactive from nonradioactive constituents such as 
aluminum, chromium, and salts. DOE uses a variety of technologies to 
extract specific radioactive and hazardous materials during this 
pretreatment phase. 

* Treatment: Immobilizing the radioactive and hazardous constituents in 
glass through a process called vitrification. The entire high-level 
waste stream, and about half the low-activity waste, is to be 
immobilized in the waste treatment plant by mixing it with a glass- 
forming material, melting the mixture into glass in two vitrification 
facilities--one for high-level waste and a second for low-activity 
waste--and pouring the vitrified waste into stainless-steel canisters 
(high-level waste) or containers (low-activity waste) to cool and 
harden. 

* Final disposal: Storing high-level waste canisters temporarily on 
site until a permanent geologic repository opens and then permanently 
disposing of it in a designated geologic repository and disposing of 
the low-activity waste on site in a designated disposal landfill. Tanks 
will be closed permanently after as much waste as technically possible 
has been removed. 

Figure 2: Key Phases in DOE's Tank Waste Cleanup Strategy: 

[Refer to PDF for image: illustration] 

Characterization: 
Sampling and analyzing the waste throughout preparation for treatment. 

Retrieval: 
Retrieving waste from tanks and preparing for treatment; 
Single-shell tanks; Double-shell tanks. 

Pretreatment: 
Mixing and separating waste constituents into high-level and low-
activity waste streams. 

Treatment: 
Vitrifying high-level waste and placing it into stainless-steel 
canisters; 
Vitrifying low-activity waste and placing it into stainless-steel 
containers. 

Final disposal: 
Storing high-level waste canisters temporarily on site until permanent 
repository opens; 
Storing low-activity waste containers permanently on site in landfill. 

Sources: GAO and DOE. 

[End of figure] 

Technical Uncertainties at Each Phase Could Threaten Cleanup Success: 

DOE faces critical technical uncertainties, including whether the pace 
of retrieving waste from the tanks will be sufficient to keep the waste 
treatment plant operating as planned and whether key treatment 
technologies will work. Unless DOE successfully resolves these 
uncertainties, it could face problems, such as facility shutdowns, 
facility modifications and retrofitting, or significant cost increases 
and delays in completing Hanford's tank waste cleanup activities. 

It Is Unclear Whether Systems Designed to Characterize the Waste Will 
Operate at the Rate Planned: 

DOE plans to rely on new systems to collect and analyze waste samples, 
but the performance of these new systems has not yet been fully 
demonstrated, although DOE continues to test them. It is unclear, for 
example, whether these systems will be able to complete the more than 
10,000 samples needed each year to ensure that the waste's composition 
is understood and meets the criteria for treatment and disposal. A 
sampling and analysis rate of 10,000 samples per year for the new 
analytical laboratory is several times the rate that samples have been 
taken and analyzed in existing Hanford laboratories. Given that waste 
sampling and analysis are to occur throughout preparation of the waste 
for treatment, a backlog in this system could substantially slow the 
overall waste treatment process. DOE officials told us that they 
recognize this uncertainty and that they are working to reduce the 
number of samples that will need to be analyzed. 

DOE May Have Difficulty Retrieving Waste from the Tanks at Planned 
Rates: 

DOE's strategy assumes that transferring waste from the single-shell 
tanks into the double-shell tanks (for mixing and blending before 
treatment) will progress faster than experience to date suggests. It is 
unclear, however, whether DOE can increase its retrieval rate to 
adequately supply waste to the waste treatment plant on a continuous, 
long-term basis when the plant begins operating in 2019, as currently 
planned. Since 2003, DOE has emptied 7 tanks--about 1 tank per year. 
[Footnote 12] According to an August 2009 tentative legal settlement, 
DOE has agreed to retrieve 10 tanks over the next 5 years--or an 
increase to 2 tanks per year. Even if DOE is successful in retrieving 
this number of tanks, it is uncertain whether sufficient space is 
available in the double-shell tanks to hold this waste. Further, 
according to DOE officials, to provide adequate waste feed to the 
pretreatment facility, waste retrieval will need to increase to an 
average of 5 to 7 tanks per year when operation of the waste treatment 
plant begins. Even if DOE is successful in retrieving waste at this 
rate from the single-shell tanks, the waste must again be retrieved 
from the double-shell tanks to feed into the pretreatment facility. 
Retrieving the waste in an uninterrupted manner over several decades 
requires enough trained personnel; equipment and infrastructure such as 
pumps, transfer lines, monitoring equipment, and scaffolding around the 
tanks; and a place to transfer and store waste removed from the tanks. 
A 2008 DOE report noted that tank waste retrieval rates could become 
the limiting process in maintaining the overall treatment schedule. 
[Footnote 13] Nevertheless, DOE officials told us they believe they 
will gain enough experience in retrieving waste over the next 10 years 
that increasing the retrieval rates will not be a problem. 

Failure of Pretreatment Technologies Could Shut Down the Entire Waste 
Treatment Operation: 

In 2006, an external team of experts reported that several problems and 
uncertainties with technologies designed to remove particular 
radioactive and hazardous constituents from the waste streams could 
make the pretreatment facility difficult to operate and maintain. 
Specifically, the experts noted the potential for plugging of piping 
that transports the waste through the facility; inadequate filtering to 
remove certain constituents, such as aluminum and chromium; and 
insufficient mixing of the waste before and during pretreatment. To 
address these problems, DOE built a test facility called the 
pretreatment engineering platform to test and demonstrate selected 
pretreatment technologies using simulated tank wastes.[Footnote 14] On 
the basis of preliminary results, DOE has adjusted the pretreatment 
technologies and believes that several potential problems have been 
mitigated. Although final test results have not been disclosed, DOE 
officials report that the first testing phase appears to be successful. 
Still, DOE has tested the systems in the pretreatment engineering 
platform using only simulated waste, and according to some independent 
experts we spoke with, using simulated waste to test a new system may 
not uncover all potential problems. Thus, until the pretreatment 
facility is operating with real waste, it will remain unclear how well 
the pretreatment technologies will perform. DOE's 2008 report noted 
that any single-point failure in pretreatment capabilities could halt 
operation of the entire waste treatment plant. 

Uncertainties over Waste Treatment Plant Capacity Complicate Treatment 
Time Frames: 

In addition to other rate-limiting uncertainties, questions persist 
over how to treat all the low-activity waste--about 90 percent of the 
total volume of waste that must be treated. At present, the low- 
activity waste vitrification facility is to process only about half the 
anticipated amount of low-activity waste by midcentury, when DOE hopes 
to complete treatment of high-level waste. Without supplemental 
capacity, DOE has estimated that tank waste cleanup could last as long 
as the 2090s. Over the years, DOE has taken steps to evaluate various 
supplemental options for treating low-activity waste, and the 
department has an environmental impact statement under way that 
includes further evaluation of supplemental treatment options (see 
appendix II). Nevertheless, the department has indicated that it is 
planning on a second vitrification facility specifically for low-
activity waste. The amount of low-activity waste that will ultimately 
need treatment depends in large part on the amount of sodium in this 
waste stream. Sodium hydroxide, which was added to the tanks to control 
corrosion, is also added during pretreatment to help dissolve and 
remove aluminum from the waste. Adding sodium helps reduce the volume 
of the high-level waste stream but increases the volume of the low-
activity waste stream. DOE is still studying how much sodium is likely 
to be needed, and if this amount is large, treatment time frames could 
be lengthened by several years. Building another vitrification 
facility--which, like the existing high-level and low-activity 
vitrification facilities, would depend on the same series of 
characterization, retrieval, and pretreatment processes--could worsen 
such potential bottlenecks. That is, because DOE has no alternative to 
the pretreatment facility, if this facility fails, the entire treatment 
operation, including all three vitrification facilities, could come to 
a halt. 

The Permanent Storage Location for High-Level Waste Has Become 
Uncertain: 

While DOE's plan to permanently dispose of Hanford's vitrified low- 
activity tank waste in an on-site landfill has been approved by state 
regulators, final disposition of the vitrified high-level wastes has 
become less certain. DOE had planned to store this waste temporarily at 
Hanford until it could be shipped to Yucca Mountain, Nevada, the 
designated repository for the nation's spent fuel and high-level waste. 
[Footnote 15] DOE has been developing a license application for 
constructing the repository and in June 2008 submitted this application 
to the Nuclear Regulatory Commission for review. In March 2009, 
however, the Secretary of Energy announced that Yucca Mountain would no 
longer be the final repository for the nation's nuclear waste and in 
its fiscal year 2010 budget justification, DOE proposed to eliminate 
all project funding, except $197 million, primarily for licensing 
activities. If no other high-level waste repository is established, DOE 
sites, including Hanford,[Footnote 16] could end up storing their high- 
level waste canisters on site indefinitely. Hanford's existing 
temporary storage facility can accommodate only 880 high-level waste 
canisters; at DOE's currently expected production rates of more than 
500 canisters of vitrified high-level waste per year, Hanford will run 
out of storage space less than 2 years after treatment operations 
begin, or as early as 2021. Consequently, Hanford officials told us 
they are exploring ways to provide additional temporary high-level 
waste storage space on site. DOE plans to look at a range of options, 
one of which could entail building additional modular storage 
facilities that could initially store about 2,000 to 4,000 high-level 
waste canisters, with future expansion for an additional 12,000 to 
14,000 canisters if necessary. Until a final decision is made about 
permanent disposal of high-level waste, neither the extent of 
additional storage capacity needed on site nor associated costs will be 
known. 

Legal and Regulatory Uncertainties May Limit DOE's Ability to Carry Out 
Certain Aspects of Its Tank Waste Cleanup Strategy as Planned: 

DOE's tank waste cleanup strategy faces two key legal and regulatory 
challenges. First, DOE's plans assume that the department will obtain 
regulatory approval to reclassify some tank waste as transuranic waste, 
thereby reducing the overall amount of high-level waste to be treated. 
[Footnote 17] Second, because the tank waste is managed as high-level 
waste and the technology to remove all of it from the tanks either does 
not exist or is extremely costly to use, DOE could face potential legal 
hurdles in leaving any radioactive waste in the bottom of the tanks at 
closing since the tanks are not considered permanent storage facilities 
for high-level waste. 

Regulatory Approval Uncertain for DOE to Treat Some Waste as 
Transuranic Waste: 

DOE believes that waste in 11 single-shell tanks, nearly 1.5 million 
gallons (of about 56 million gallons of waste at Hanford), can be 
treated and disposed of as transuranic, rather than high-level, waste. 
[Footnote 18] According to a DOE official, the waste in these tanks 
comes largely from chemical additives and other processes, not directly 
from the reprocessing of spent nuclear fuel that generates high-level 
waste. In addition, DOE believes that the tanks' contents are not 
radioactive enough to warrant the heavy shielding needed to protect 
workers when they handle high-level waste. DOE's present tank waste 
treatment strategy assumes that the department will be able to 
reclassify and treat this waste as transuranic waste, at a cost of $233 
million. Before DOE can go ahead with this plan, however, it will have 
to gain a series of regulatory approvals from EPA, the Washington State 
Department of Ecology, and the state of New Mexico, each of which has 
previously expressed reservations. In 2007, EPA raised doubts as to 
whether the waste qualified as transuranic waste and asked DOE for 
further substantiating documentation. Ecology must approve DOE's plans 
to retrieve and treat the transuranic tank waste and package it for 
final disposal, but Ecology officials told us they are reluctant to 
approve any treatment plans until DOE receives assurance that New 
Mexico will accept the waste in its geologic repository. And New 
Mexico, which has been reluctant to accept any waste once regarded as 
high-level waste, may decide not to allow disposal of Hanford's tank 
waste at its repository. If regulators do not approve DOE's plans for 
this waste, the schedule--and associated costs--of operating Hanford's 
waste treatment plant could increase by 1 year and about $1 billion. 

DOE Could Face Legal Challenges over Leaving Residual Waste in the 
Tanks at Closure: 

Under the Tri-Party Agreement, DOE must retrieve as much waste as 
technically possible from Hanford's single-shell tanks. Any waste left 
in the tanks, along with the tanks themselves, could be considered high-
level waste, which would not be permitted to stay in the ground but 
would have to be disposed of in a geologic repository. DOE has a 
process (spelled out in its order 435.1 and associated guidance manual) 
for determining whether high-level waste can be reclassified as another 
waste type, and it plans to use this process to allow residual waste to 
remain in Hanford's tanks when they are permanently closed. DOE's 
authority to apply this order to certain high-level waste, however, was 
challenged in a 2002 lawsuit, which eventually failed on procedural 
grounds.[Footnote 19] Meanwhile, in 2004 DOE sought legislation 
clarifying its authority to reclassify high-level waste, but although 
Congress enacted legislation allowing waste reclassification at two 
other sites, the relevant provision of the law specifically excluded 
Hanford.[Footnote 20] This conclusion could leave DOE open to further 
legal challenges if the department followed its reclassification 
process to close Hanford's tanks. And if DOE lost such a challenge, it 
could be forced to exhume Hanford's tanks, and any residual waste, and 
dispose of it all in a geologic repository (called clean closure). In 
2004, DOE estimated that this scenario could add delays and more than 
$19 billion to Hanford's cleanup costs. 

DOE Has Not Systematically Evaluated Whether Its Tank Waste Cleanup 
Strategy, Including Costs, Is Commensurate with Risks from the Waste: 

As the National Academy of Sciences and others have pointed out, a 
number of factors warrant consideration when undertaking a project of 
the magnitude of DOE's cleanup mission. Among these are costs, risks to 
human and ecological health, and cultural and societal impacts. Yet DOE 
lacks much of the information it would need to weigh these factors 
fully. 

DOE Lacks Credible Life-Cycle Cost Estimates for Cleaning Up Hanford's 
Tank Waste: 

DOE's estimates of how much it will cost to clean up Hanford's tank 
waste are not credible or complete. DOE has estimated the cost of a 
number of components that would go into a life-cycle cost estimate, 
including the cost to design and construct the waste treatment plant, 
the cost to manage and treat the tank waste, and contingency funds to 
cover unanticipated costs involved with this effort.[Footnote 21] But 
these estimates are not credible or complete, and each new estimate has 
increased over previous estimates.[Footnote 22] 

Specifically, in 2007 we reported that from 2000 to 2006, the estimated 
costs to construct the waste treatment plant almost tripled, increasing 
from $4.3 billion to about $12.3 billion (see figure 3),[Footnote 23] 
because of contractor and management performance problems, changes in 
contract scope, and technical issues.[Footnote 24] Likewise, DOE's 
estimates of costs for managing and treating the tank waste have 
increased significantly, raising doubts about the estimates' 
reliability. In 2006, for example, DOE estimated that cleanup 
activities would be finished by 2032, at an estimated cost of about $23 
billion.[Footnote 25] Two years later, the completion date was pushed 
out by 13 years, to 2045, with a corresponding rise in costs of about 
$23 billion, to $46 billion overall,[Footnote 26] and indications are 
that these costs could increase still further. DOE also normally 
develops an estimate for contingency costs when carrying out large 
projects like Hanford's tank waste cleanup--in this case, an estimate 
of the costs to cover unknown or unforeseen events during the design 
and construction of facilities and during tank waste management and 
treatment activities. While DOE has included a contingency-cost 
estimate of about $1 billion in the waste treatment plant's total 
project cost, DOE project officials estimate that an additional 
contingency of $700 million may be needed. DOE has also estimated that 
a contingency amount of about $18 billion may be needed for tank waste 
management and treatment.[Footnote 27] The magnitude of such 
contingency funding is still another indication of the overall 
uncertainty surrounding DOE's cost estimates for its tank waste cleanup 
strategy. In all, the estimated cost of these three key components-- 
waste treatment plant construction and initial operations, tank farm 
maintenance and treatment operations, and contingency costs--totals 
nearly $77 billion. 

Figure 3: Cost Estimates for Constructing Hanford's Waste Treatment 
Plant: 

[Refer to PDF for image: vertical bar graph] 

Original contract price as awarded in December 2000: $4.3 billion. 

Revised contract price as renegotiated in March 2003: $5.7 billion. 

Contractor’s revised cost estimate in March 2005: $8.3 billion. 

Contractor’s revised cost estimate in December 2005: $10.5 billion. 

Contractor’s latest cost estimate in December 2006: $12.3 billion. 

Source: GAO analysis of DOE data. 

Notes: Neither the $8.3 billion figure nor the $10.5 billion figure was 
approved by DOE. The $12.3 billion figure represents the current total 
project cost. The $10.5 billion figure does not include a contractor 
performance fee, which is a fee that a contractor can earn above a 
project's costs and that offers an added incentive to complete a 
project on time and on budget. 

[End of figure] 

DOE did not include, or was unable to quantify, a number of significant 
costs when estimating the overall cost of its cleanup strategy. DOE's 
own guidance states that life-cycle cost estimates should include 
actual expenditures and estimated costs from the time an activity 
begins until it is completed. For the cleanup strategy, however, DOE's 
estimates excluded: 

* Actual expenditures before 1997. DOE incurred more than $3 billion 
from 1989 through 1996 to manage Hanford's tank waste and explore ways 
to treat and permanently dispose of it, bringing life-cycle costs to 
about $80 billion. 

* Costs associated with any increase in waste volume. Uncertainties 
over the amount of sodium to be added during pretreatment could 
increase the volume of low-activity waste needing treatment and 
ultimately increase waste treatment costs by approximately $3 billion, 
according to a January 2009 DOE study.[Footnote 28] 

* Costs to build a second low-activity waste vitrification facility. 
DOE has yet to size or design this facility, but given costs for a 
supplemental technology that DOE already included in its estimate for 
managing and treating the tank waste, additional estimated costs for a 
second low-activity waste facility could increase total life-cycle 
costs by nearly $1 billion, according to DOE project officials. 

* Upgrading additional facilities. DOE is considering the need for as 
many as four interim holding facilities for temporarily storing waste 
retrieved from underground tanks before pretreatment. DOE will also 
need to upgrade Hanford's facility for processing secondary waste 
generated from the waste treatment operations. The costs of upgrading 
or building these facilities are not fully known but, according to DOE 
project officials, could be on the order of several hundred million 
dollars. 

* Adding temporary storage capacity for high-level waste canisters. DOE 
recently estimated that its present plans to expand existing space for 
storing high-level waste canisters would cost about $200 million. 
According to DOE project officials, uncertainties over the fate of 
Yucca Mountain could demand still more storage space on site--perhaps 
nearly 14 times as much as what DOE has planned--at a cost of hundreds 
of millions of additional dollars to build, maintain, and secure. 

* Transporting high-level waste canisters to, and permanently disposing 
of them in, a geologic repository. DOE expects to ship these canisters 
to a geologic repository eventually, but the transportation and long- 
term disposal costs are not included in a life-cycle cost estimate for 
Hanford. Although DOE project officials could not precisely estimate 
how much these activities would cost, they stated that the costs could 
amount to billions of dollars. 

Developing a credible, complete cost estimate including the foregoing 
components is especially important now that, under the terms of the 
August 2009 tentative legal settlement with Washington State, DOE is 
required to have a comprehensive life-cycle cost estimate and to update 
it annually. Since DOE has not included these cost components in its 
estimates to date, it is unclear whether the department will do so in 
future life-cycle cost estimates. 

Uncertainty surrounding DOE's overall tank waste cleanup schedule adds 
further doubt to the reliability of life-cycle cost estimates. Cleanup 
costs stem directly from cleanup duration, and any lengthening of 
cleanup time leads to cost increases of comparable magnitude. According 
to present Tri-Party Agreement milestones, DOE is required to complete 
treatment by 2028. In recent years, however, DOE's estimate of when it 
expects to complete tank waste treatment has shifted repeatedly. In its 
negotiations of new cleanup milestones with its regulators, it has 
agreed that tank waste treatment may not be completed until 2047. In 
addition, DOE's proposed fiscal year 2010 budget shows a range of 
treatment completion dates from 2042 to 2054. Other documents consider 
treatment time frames extending even further (see figure 4). 

Figure 4: Shifting Estimates of the Duration of Hanford Tank Waste 
Treatment: 

[Refer to PDF for image: illustration] 

Current Tri-Party Agreement milestones: 
Start of treatment: 2011; 
End of treatment: 2028. 

DOE’s approved project baseline schedule, fiscal year 2006: 
Start of treatment: 2016; 
Planned end of treatment: 2032; 
Revised end of treatment: 2042. 

DOE’s annual updated schedule, fiscal year 2008[A]: 
Start of treatment: 2019; 
End of treatment: 2045. 

DOE’s System Plan, 2008[B]: 
Start of treatment: 2018; 
Range of end of treatment: 2049-2060. 

DOE’s fiscal year 2010 budget submittal[C]: 
Start of treatment: 2019; 
Range of end of treatment: 2042-2054. 

Proposed change to Tri-Party Agreement milestones, 2009: 
Start of treatment: 2019; 
End of treatment: 2047. 

DOE’s System Plan, 2009[D]: 
Start of treatment: 2019; 
Range of end of treatment: 2047-2054. 

Source: GAO analysis of DOE data. 

[A] Department of Energy, Office of River Protection, Fiscal Year (FY) 
2008 Project Baseline Summary Sheets: GEN-02 Reports (Richland, Wash., 
September 2008). This document, submitted annually to Congress, 
represents DOE's best estimate of project costs and schedules. 

[B] CH2M Hill Hanford Group, River Protection Project System Plan, ORP- 
11242, rev. 3A, prepared for DOE (Richland, Wash., July 2008). This 
planning document explains how DOE believes it can carry out its tank 
waste cleanup strategy. 

[C] Department of Energy, FY 2010 Congressional Budget Request: 
Environmental Management, Defense Nuclear Waste Disposal, Nuclear Waste 
Disposal, DOE/CF-039, vol. 5 (Washington, D.C., May 2009). 

[D] Washington River Protection Solutions and AEM Consulting, River 
Protection Project System Plan, ORP-11242, rev. 4, prepared for DOE 
(Richland, Wash., September 2009). 

[End of figure] 

In the absence of a clear and reliable schedule, DOE cannot develop a 
reliable cost estimate for its tank waste cleanup strategy. Moreover, 
the former project manager for waste treatment plant construction 
suggested that a reliable completion schedule may not be known until 
2022--some years after treatment operations are to begin. Given that 
estimated average annual expenditures amount to about $1.2 
billion,[Footnote 29] if treatment activities actually last until 2054, 
as some DOE planning documents suggest, tank waste management and 
treatment could increase about $8.4 billion dollars more than 
anticipated (see table 1). 

Table 1: Estimated Costs Associated with DOE's Tank Waste Cleanup 
Strategy: 

Cost components: Waste treatment plant total project cost; 
Costs included in DOE's estimate: $12.3 billion. 

Cost components: Tank waste management and waste treatment operations, 
fiscal years 1997 to 2045[B]; 
Costs included in DOE's estimate: $46.0 billion. 

Cost components: Contingency: Waste treatment plant Tank waste 
management and waste treatment operations; 
Costs included in DOE's estimate: $0.7 billion and $18.0 billion. 

Cost components: Total of DOE's current estimate for cleanup; 
Costs included in DOE's estimate: $77.0 billion. 

Cost components: Actual costs, fiscal years 1989 to 1996; 
Costs not included in DOE's estimate[A]: $3.0 billion. 

Cost components: Increases in waste volume; 
Costs not included in DOE's estimate[A]: $3.0 billion. 

Cost components: Second low-activity vitrification facility; 
Costs not included in DOE's estimate[A]: $1.0 billion. 

Cost components: Cleanup schedule extension from 2045 to 2047[C]; 
Costs not included in DOE's estimate[A]: $2.4 billion. 

Cost components: Total potential costs if treatment extends to 2047; 
Costs not included in DOE's estimate[A]: $86.4 billion. 

Cost components: Cleanup schedule extension to 2054[D]; 
Costs not included in DOE's estimate[A]: $8.4 billion. 

Cost components: Total potential costs if treatment extends to 2054; 
Costs not included in DOE's estimate[A]: $94.8 billion. 

Cost components: Additional facilities; 
Costs not included in DOE's estimate[A]: Hundreds of millions of 
dollars. 

Cost components: Temporary storage capacity for high-level waste 
canisters; 
Costs not included in DOE's estimate[A]: Hundreds of millions of 
dollars. 

Cost components: Transporting and disposing for high-level waste 
canisters; 
Costs not included in DOE's estimate[A]: Billions of dollars. 

Cost components: Potential cost of DOE's cleanup strategy; 
Costs not included in DOE's estimate[A]: $86 billion to more than $100 
billion. 
Source: GAO analysis of DOE data. 

[A] Unless otherwise indicated, these estimates, provided by DOE, 
represent only rough orders of magnitude. 

[B] DOE's most recent estimate, dated September 2008, reflects a 
cleanup completion date of 2045. 

[C] DOE's most recent estimate, dated September 2008, reflects a 
cleanup completion date of 2045. In an August 2009 proposed legal 
settlement, however, DOE agreed to complete cleanup by 2047. The cost 
estimate is based on data provided by DOE. 

[D] DOE's latest internal planning document shows a range of cleanup 
completion dates from 2047 to 2054. The cost estimate is based on data 
provided by DOE. 

[End of table] 

Overall the total estimated cost could significantly exceed DOE's 
current estimate of $77 billion, with estimates ranging from about $86 
billion to over $100 billion, depending upon the date cleanup is 
completed. 

DOE Has Not Applied Risk-Informed Decision Making in Its Tank Waste 
Cleanup Strategy: 

Although the importance of risk assessment for decision making had been 
recognized for more than 2 decades before cleanup of DOE's weapons 
complex began, to date DOE has analyzed risks to human and ecological 
health mainly in the context of complying with environmental analysis 
requirements under the National Environmental Policy Act of 1969. 
[Footnote 30] Under this act, agencies evaluate the likely 
environmental effects of projects they are proposing by using an 
environmental assessment or, if the projects are likely to 
significantly affect the environment, a more detailed environmental 
impact statement. Under regulations implementing the act, an 
environmental impact statement must assess the environmental effects of 
the proposed agency action and all reasonable alternatives. A 1983 
National Academy of Sciences report, on the other hand, explicitly 
assessed the feasibility of, and offered guidelines for, federal 
agencies' use of risk assessment--separate from regulatory functions-- 
in their decision making.[Footnote 31] Since DOE's cleanup efforts 
started, some three dozen studies by academics, the National Academy, 
and DOE itself have examined aspects of risk assessment in relation to 
DOE's cleanup work. Many of these studies have identified shortcomings 
in the department's efforts to address risk in its decision making and 
urged it both to adopt a more disciplined process for analyzing risks 
and to use the results of such risk analyses when making key decisions. 

DOE's principal risk assessment to date with regard to tank waste is 
found in its 1996 environmental impact statement. This statement 
discussed the potential environmental effects related to several 
strategies for managing and treating Hanford's tank wastes.[Footnote 
32] Most of these alternatives involved vitrification technologies, to 
the near exclusion of other potential alternative treatment pathways. 
This environmental impact statement was not required to be--and was 
not--a systematic risk assessment of all options to treat Hanford's 
tank wastes. As we previously reported, for example, it did not purport 
to analyze the condition or long-term viability of Hanford's aging 
tanks or the risks of leaving waste in the tanks for several decades 
during cleanup operations.[Footnote 33] The environmental impact 
statement did examine 10 tank waste treatment strategies--including "no 
action" and a "preferred alternative"--and the potential effects of 
these strategies on different groups of people, such as site workers, 
recreational river shoreline users, farmers, and Native American users, 
under different long-term land-use scenarios. The "no action" 
alternative was predicted to result in 600 "latent cancer fatalities" 
among future farmers on the site over 10,000 years. DOE's preferred 
alternative--on which DOE's present strategy is based--was predicted to 
reduce to 10 the number of farmers' deaths over 10,000 years. This 
alternative would also result in disturbing the widest area of the 
region's native shrub-steppe ecosystem of all the alternatives 
presented. In comparison with no action, however, this alternative 
would add thousands of regional jobs during treatment plant 
construction. Significant costs were associated with all 10 treatment 
alternatives; in 1996 dollars, no action was estimated to cost $13 
billion to $16 billion, while the preferred alternative was projected 
at the time to reach $30 billion to $38 billion. 

Internal as well as external reports since that time have noted 
problems with DOE's risk assessment and decision making. One of the 
major findings of DOE's 2002 "top-to-bottom" review of its 
Environmental Management program, for example, states that 
"[Environmental Management's] complex-wide cleanup strategy is not 
based on a comprehensive, coherent, technically supported risk 
prioritization....This approach has resulted in costly waste management 
and disposition strategies that are not proportional to risks posed to 
human health and the environment."[Footnote 34] More recently, a 2005 
National Academy of Sciences report observed that "DOE risk assessments 
and decision processes...do not exhibit all of the characteristics of 
an effective and credible risk-informed decision-making process." 
[Footnote 35] 

DOE is planning to issue another environmental impact statement, 
[Footnote 36] expected in October 2009, but it is unclear to what 
extent its consideration of risks will follow available risk assessment 
guidelines. According to the National Academy's 2005 report, a risk 
assessment framework would weigh a number of factors--including costs, 
worker and public safety, effect on ecosystems, technical feasibility, 
cultural impact, and other trade-offs. A 2008 report by the academy 
goes further, outlining a three-phase framework for risk-based decision 
making that "maximizes the utility of risk assessment" in evaluating 
options to reduce hazards.[Footnote 37] DOE's forthcoming environmental 
impact statement will evaluate a number of alternative strategies for 
carrying out tank waste cleanup and other cleanup-related activities--
in particular, options for supplementing the capacity for treating low-
activity waste and options for closing the tanks.[Footnote 38] 
Regarding tank waste cleanup, for example, the document will discuss 
the short-and long-term effects of several options for treating both 
high-level and low-activity tank waste, coupled with various tank 
closure alternatives. These options include retrieving an amount of 
waste (90 percent) that is less than the goal set by the Tri-Party 
Agreement (99 percent) and retrieving nearly all the waste (99.9 
percent), an amount that would have to be achieved if the tanks are to 
be removed from the ground. In addition, the environmental impact 
statement will consider long-term cumulative effects from past 
practices (including waste already discharged into the soil), present 
activities, and future actions. The document's release has been delayed 
more than 2 years, and it is not yet clear when it will be 
issued.[Footnote 39] 

Given that environmental impact statements are DOE's primary risk 
assessment vehicle, the current effort provides an opportunity to use 
available risk assessment guidelines to consider scenarios the 
department has not considered to date--in particular, the possibility 
of removing varied quantities of waste from the tanks. The National 
Academy's 2005 report stated, for example, that removing every gram of 
high-level waste is technologically unfeasible without also removing 
the tanks themselves and that the effort is likely to be out of 
proportion with the concomitant risk reduction. Indeed, more than half 
the experts we spoke with said that the 99 percent figure has no 
scientific basis, and several recommended that DOE conduct a 
comprehensive risk assessment of residual tank waste. 

Some Opportunities May Exist to Reduce Costs of DOE's Hanford Tank 
Waste Cleanup Strategy: 

Given the current status of DOE's cleanup strategy and associated 
costs, three primary options appear available for reducing life-cycle 
costs of tank waste cleanup. The likelihood of their success--and 
potential effects on cleanup costs--has not yet been determined. 

Increasing the Amount of High-Level Waste Captured in Each Canister 
Could Reduce the Number of Canisters and Treatment Duration, Thereby 
Reducing Costs: 

DOE officials at Hanford are researching methods for increasing the 
amount of high-level waste ultimately immobilized in each canister in 
an attempt to reduce the total number of canisters produced and, 
perhaps, treatment duration. The total concentration of high-level 
waste per canister depends on, among other factors, the specific mix of 
radioactive and other constituents going into the canister. Certain 
chemical mixes lend themselves less well to vitrification than others. 
Chemicals such as aluminum can be added to glass only up to specific 
limits without altering glass quality. If aluminum concentration 
exceeds these limits, the resulting glass product may not be able to 
keep the radioactive constituents from leaching out over time. DOE is 
therefore studying techniques for fine-tuning the mix of constituents 
so as to maximize the concentration and retention of high-level waste 
in each canister. DOE estimates that its waste canisters may, on 
average, contain about 28-31 percent high-level waste.[Footnote 40] At 
this concentration, DOE would generate more than 500 high-level waste 
canisters per year, or a total of 9,000 to 15,000 high-level waste 
canisters. DOE is hoping to increase high-level waste concentrations in 
each canister, but it is too early to tell what levels can be 
consistently achieved during full-scale treatment. If successful, 
according to some DOE officials, such increases in waste concentrations 
could reduce the number of high-level waste canisters, potentially 
shaving years--and associated costs--off treatment operations. While it 
is unclear what savings could be achieved, DOE believes the savings 
could be substantial. 

Performing Additional Testing on Pretreatment Technologies Could Help 
Minimize Problems during Waste Treatment Operations: 

In 2008, DOE built a test facility, the pretreatment engineering 
platform, to help resolve uncertainties in selected pretreatment 
technologies, particularly the engineering designs for ultrafiltration, 
or filtering the waste to remove solids; efficiently dissolving 
components such as aluminum and chromium to facilitate separating high-
level from low-activity waste streams; and ensuring that piping 
throughout the facility will not clog with waste sludge moving through 
the system. A number of the experts we spoke with had concerns about 
the reliability of these and other pretreatment technologies.[Footnote 
41] In May 2009, DOE officials stated that the department has completed 
most of the testing on these technologies (with a report to be released 
later this year), and project officials stated that they had improved 
the facility's design as a result of the testing. It appears, however, 
that the pretreatment platform provides DOE with an opportunity to use 
the platform to test additional pretreatment technologies and also to 
refine or enhance the efficiency and effectiveness of future 
pretreatment operations. Given the delays--and costs--that could arise 
if the pretreatment facility becomes a significant bottleneck for waste 
treatment plant operations overall, some of the experts we spoke with 
commented that using the pretreatment engineering platform for testing 
before full operations begin could help reduce uncertainties. As we 
reported in 2003, if pretreatment processes at Hanford do not work as 
planned, facilities would likely have to be retrofitted, resulting in 
potential cost increases and schedule delays much greater than those 
associated with process testing in a pilot facility.[Footnote 42] DOE 
has recognized this opportunity and is considering options for further 
testing and for obtaining needed funding. 

Allowing More Residual Waste to Remain in Selected Tanks at Closing 
Could Help Reduce Costs without Adding Risks to Human or Ecological 
Health: 

With regard to amounts of residual waste permitted in the tanks at 
closure, DOE's present strategy is driven in large measure by 
milestones agreed to in the Tri-Party Agreement. This agreement calls 
for retrieving as much waste as technically possible, with tank waste 
residues not to exceed specified volumes.[Footnote 43] Federal 
regulations under RCRA define a waste container as "empty" if, among 
other criteria, it contains no more than 1 inch of waste residues, 
which is the equivalent of the volume limits stipulated in the Tri- 
Party Agreement.[Footnote 44] According to one DOE official, the volume 
limits in the agreement were set to ensure that at least 99 percent of 
the waste would be removed from the single-shell tanks. Several of the 
experts we interviewed, however, suggested that DOE could leave more 
waste in selected tanks at closing and still protect human health and 
the environment. 

As DOE has emptied the single-shell tanks, it has found that estimates 
for retrieving the waste have significantly understated actual costs. 
For example, in 2003, DOE estimated that retrieving waste from all the 
single-shell tanks would cost approximately $1.1 billion, or an average 
of about $7.6 million per tank. Actual costs of removing waste from the 
first seven tanks, however, have amounted to $236 million, or about $34 
million per tank.[Footnote 45] Because four of the emptied tanks were 
Hanford's smallest, actual costs for the more-numerous larger tanks 
could be much higher. 

In retrieving waste from Hanford's single-shell tanks, DOE has also 
found that retrieving the last portion of waste from a tank can be 
disproportionately costly. In at least five out of the seven tanks 
emptied to date, DOE has found it technically challenging to retrieve 
99 percent of the waste and meet the Tri-Party Agreement goal. For some 
of these tanks, DOE has estimated that the cost of retrieving the last 
15 percent of the waste can equal or exceed the cost of removing the 
first 85 percent (the cost per gallon can be as much as three times 
higher). For example, as we previously reported, DOE found that in 
retrieving the waste from one large tank (C-106), the cost of removing 
each additional cubic foot, or about 8 gallons, of waste ranged from 
$35,000 to $84,000--in other words, from 7 to 16 times the average cost 
per cubic foot to retrieve the first nearly 99 percent of the 
waste.[Footnote 46] Moreover, in its analysis, DOE concluded that the 
risk to workers from removing this waste, combined with the high cost, 
outweighed a relatively minimal reduction in risk to the public and 
future users of the site. Similarly, a DOE official told us that for 
another tank (C-103), the cost to date of retrieving about 85 percent 
of its residual waste was about $4 million and for retrieving an 
additional 12 percent of the residual waste, $2 million.[Footnote 47] 

Currently, DOE has not analyzed how to close the tanks in a manner that 
would balance risk with cost. The Washington State Department of 
Ecology and DOE developed a plan for a tank closure demonstration 
project to be carried out in collaboration with DOE, its contractors, 
EPA, and the state itself. The project's purpose was to bring the 
agencies together to, among other objectives, gather engineering and 
cost data on technologies that might be used to close single-shell tank 
systems; identify and begin to gather information needed for specific 
regulatory decisions associated with tank closure; and develop a common 
understanding of the relevant regulatory processes in order to 
facilitate permitting. In the August 2009 tentative legal settlement, 
DOE agreed to complete certain activities in this tank closure 
demonstration project by 2011. These activities include determining the 
process DOE will follow to reclassify residual tank waste, studying 
technical aspects of exhuming tanks, and evaluating alternatives for 
removing residual waste from a selected tank. Such a demonstration 
project could be expanded to include analyzing varying amounts of waste 
that could be left in a group of tanks at closing, with the goal of 
reducing costs while adequately protecting human and ecological health. 
This demonstration could allow DOE and the state to determine how to 
close the tanks in a cost-effective manner, as well as to streamline 
the tank closure process by determining closure goals and methodologies 
on a group of tanks, instead of one tank at a time. 

Conclusions: 

In 1989, when DOE began its cleanup mission at the Hanford Site, the 
total estimated cost was $2.8 billion, with treatment to begin in 1999. 
Despite the passage of two decades, investment of $12 billion, attempts 
at several ultimately discontinued strategies, and numerous 
recommendations from us and others, no waste has yet been treated for 
final disposal. DOE has, however, learned lessons along the way. It has 
improved its strategy, developed and refined its retrieval and 
treatment technologies, and made progress constructing the treatment 
facilities. DOE has also learned that cleaning up the legacy of 
radioactive and hazardous waste is more complex, more time-consuming, 
and significantly more expensive than envisioned. Yet DOE still faces 
many critical unknowns, including whether the treatment plant will 
actually work as planned, whether DOE can reclassify waste as planned 
without explicit statutory authority, and where treated high-level 
waste will be permanently disposed of. And although it is clear that 
the total costs--now estimated at $77 billion--will be much higher than 
originally anticipated, ranging from $86 billion to more than $100 
billion, it is unclear at this point what the final costs will be. 
Moreover, as we have previously reported, certain risks--such as 
radioactivity--are declining with time, even as costs continue to climb 
and cleanup completion dates recede into the future. Given that the 
intersection is constantly shifting between actual cleanup costs and 
changing risks posed by the wastes, it is imperative that Congress have 
access to reliable life-cycle cost and risk information as it decides 
how to best allocate limited financial resources among many competing 
needs. And given escalating expenditures, it is also imperative that 
DOE diligently seek ways to reduce the costs of this massive 
undertaking without unduly compromising ecological, worker, or public 
health. Otherwise, the effort, worker exposure, and expense associated 
with retrieval, immobilization, and final disposal of tank waste in a 
geologic repository might be out of proportion with the risk reduction 
achieved. 

Recommendations for Executive Action: 

In light of growing costs and lengthening schedules as DOE proceeds 
with its strategy to treat and permanently dispose of Hanford's tank 
waste, we recommend that the Secretary of Energy direct the Assistant 
Secretary for Environmental Management to take the following four 
actions: 

* Develop credible and complete life-cycle cost and schedule estimates, 
which include actual costs expended to date and projected future 
expenditures for all key elements; obtain independent expert evaluation 
of these estimates; and report these estimated costs to Congress. 

* Adopt a risk assessment framework for Hanford cleanup that considers 
available guidance, such as that provided by the National Academy of 
Sciences. 

* Consider seeking clarification from Congress about the department's 
authority at Hanford to determine whether some waste now managed by DOE 
as high-level waste can be treated and disposed of as a waste type 
other than high-level waste. 

* Work with state and federal regulators to develop a risk-based 
approach for closing waste storage tanks in an efficient and effective 
manner--such as through a tank closure demonstration project--and to 
analyze varying amounts of waste that could be safely left in the tanks 
or a group of tanks at closing, with the goal of reducing costs while 
adequately protecting human and ecological health. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to the Department of Energy for its 
review and comment. On behalf of the department, DOE's Assistant 
Secretary for Environmental Management wrote that DOE generally agreed 
with three of the four recommendations we made. DOE did not agree with 
our recommendation to consider seeking clarification from Congress 
about the department's authority at Hanford to determine whether some 
waste now managed as high-level waste can be treated and disposed of as 
other than high-level waste. In addition, DOE expressed concerns about 
how we characterized the Office of Environmental Management's progress 
at cleaning up Hanford tank waste with respect to three primary issues: 
addressing technical and other challenges, developing credible and 
complete life-cycle cost and schedule estimates, and assessing risks. 
On September 18, 2009, we met with the Assistant Secretary for 
Environmental Management to discuss selected DOE comments on our draft 
report, as well as the Assistant Secretary's concerns that readers may 
be confused about the scope of our report and assume that we also 
reviewed and based our conclusions on an assessment of legal and 
technical documents that are scheduled to be released shortly after our 
report is issued. We added a clarification in the scope and methodology 
section of this report to note that our conclusions and recommendations 
are based only on information available to us during our review. DOE's 
written comments on our draft report are reproduced in appendix III. 
DOE also provided general and specific technical comments, which we 
discuss below or incorporated in the body of the report as appropriate. 

The first major issue for DOE regards progress in addressing technical 
and other challenges. DOE stated that we did not adequately describe 
the department's substantial experience in and processes in place for 
addressing technical and other challenges of treating and disposing of 
Hanford's tank waste. In its letter, DOE cited a number of examples of 
cleanup activities across the DOE complex of sites that it said are 
applicable to the challenges at Hanford and inform its technical and 
project management approach. Without doubt, DOE has gained knowledge 
about treating tank waste and closing tanks through its work at the 
Savannah River Site, South Carolina; the Idaho National Laboratory; and 
other locations. At none of these sites, however, does the waste 
approach the amount and complexity of Hanford tank waste. About 56 
million gallons of tank waste must be treated at Hanford, more than at 
any other DOE site. In addition, this tank waste is uniquely complex 
because of the specific radioactive and chemical elements that have 
been mixed in it over the years, so that work done at other sites, 
though helpful, may not always be directly relevant to treating 
Hanford's tank waste. The examples of success DOE cited in its written 
comments are informative but, relative to the final output expected at 
the Hanford Site, of much smaller scope. For example, DOE cited West 
Valley, New York, where about 275 high-level waste canisters were 
produced. Some estimates for Hanford, in contrast, put the number of 
high-level waste canisters alone between 9,000 and 15,000. Moreover, 
the scope of our study, as requested by Congress, was to look at 
Hanford's tank waste cleanup project, not cleanup across the rest of 
the DOE complex. 

DOE also commented that we did not cite all the initiatives it has 
under way to help address technical uncertainties specifically at the 
Hanford Site. We did discuss several initiatives, including the 
pretreatment engineering platform and external review teams, which have 
been very useful in identifying and helping address technical 
challenges that DOE faces at Hanford. Even with these and other efforts 
mentioned by DOE in its letter, however, DOE's own assessments of the 
waste treatment plant point out that a number of uncertainties still 
exist and that solving these may be critical to operating the plant as 
planned. Also, some experts we spoke with said that it is to be 
expected that some technical issues may remain unresolved until the 
plant is operating and actual waste is being treated. As discussed in 
our report, many of the technical uncertainties at Hanford surround 
whether treatment operations will be able to achieve the throughput 
assumed in DOE's planning documents. The former project manager at the 
Hanford Site told us that it may take a few years of plant operation 
before DOE will be able to accurately determine how many years it will 
take to treat all of the site's tank waste. Finally, technical concerns 
discussed in this report have been documented in DOE's own assessments 
and studies, as well as echoed by the experts we spoke with. 

Further, DOE stated that our report should provide better context for 
our analysis of the challenges at Hanford and, as evidence, cited a 
2001 report we issued on the Rocky Flats closure project.[Footnote 48] 
In that report, we stated that DOE could have difficulty meeting the 
target closure date because of significant challenges that DOE and its 
Rocky Flats contractor faced. Nevertheless, despite these challenges, 
DOE and its contractor did meet their target closure date of 2006. Our 
conclusions in that report were based on the contractor's own 
assessment that it had only about a 15 percent probability of 
completing the project by 2006. In our view, by highlighting the 
challenges DOE and its contractor faced, our report helped focus 
attention needed to successfully complete the project in a timely 
manner. 

The second issue DOE raised in its written comments relates to whether 
DOE is developing credible and complete life-cycle cost and schedule 
estimates. In agreeing with our recommendation on this topic, DOE 
stated that it has a process for developing credible and complete life- 
cycle cost estimates for Hanford. We maintain, however, that past cost 
estimates for Hanford tank waste cleanup were neither credible nor 
complete. As discussed in this report, costs for constructing the waste 
treatment plant and managing the tank waste, for example, have grown 
significantly over the life of the project. Although DOE stated that we 
used a point estimate of our own construct, we in fact discussed with 
DOE officials at the Office of River Protection the cost estimates 
making up the $77 billion figure in table 1. These officials provided 
updated figures to reflect a 2045 completion date, rather than a 2042 
date for the figures quoted by DOE in its written comments. DOE's 
current estimate for cleanup could range from $58.3 billion if no 
contingency is included to $77.0 billion if the full $18.7 billion 
contingency is included, in contrast to the range of $56 billion to $74 
billion that DOE provided in its letter. 

Further, many potentially significant costs were not included in any 
estimates DOE provided us. If these are added in, the total cost for 
this undertaking could range from $86 billion to more than $100 
billion. We recognize that DOE has been taking steps to try to improve 
its cost-estimating process, including using GAO's cost-estimating 
guide,[Footnote 49] when developing cost and schedule estimates. DOE is 
also developing a new cost and schedule baseline for the Hanford tank 
waste cleanup effort, but since this baseline has not yet been 
validated or approved by DOE, it was not available for our review. 
Further, as noted in its comments, under the August 2009 tentative 
legal settlement for Hanford (which is still subject to public review 
and comment), DOE has agreed to prepare a life-cycle analysis of all 
Hanford cleanup costs to meet the legally mandated cleanup timelines. 
We look forward to development of this analysis because we believe that 
until DOE develops a complete life-cycle cost analysis at Hanford--one 
that takes into account all potentially significant costs stemming from 
the effort to clean up tank wastes, including those for interim and 
permanent storage of waste canisters--information presented to Congress 
could understate the true costs of this challenging cleanup effort. 

DOE's third issue relates to consideration of risk. DOE agreed with our 
related recommendation to adopt a risk assessment framework that 
considers available guidance, such as that provided by the National 
Academy of Sciences, but added that it believes it already has a risk 
assessment framework for Hanford and that our report does not recognize 
existing DOE risk management efforts (our emphasis). We acknowledge 
that DOE has taken steps to assess risks, such as in its forthcoming 
draft environmental impact statement, which is expected to be released 
for public comment in October 2009. DOE also has a process for managing 
risks, and its letter says the Tri-Party Agreement contains provisions 
for mitigation of programmatic risk. Risk assessment, however, is not 
the same as risk management. Specifically, in the view of the National 
Academy of Sciences, the assessment of risks and related scientific 
findings and policy judgments should be distinguished from risk 
management alternatives. In essence, the science of risk analysis and 
assessment to inform policy are related to but distinct from actions 
taken to manage identified risks. In its technical comments on our 
report, DOE addressed risk management activities at some length. For 
example, it stated that we failed to mention DOE guidance on risk 
management, the River Protection Project Federal Risk Management Plan, 
and other key documents that include risk mitigation actions. DOE 
described these documents, for example noting that the river protection 
plan lays out the critical technical, programmatic, and operational 
risks facing Hanford's cleanup projects. But in our view, DOE's 
description focuses on mitigation steps for addressing risks to meeting 
the project's cost and schedule estimates. Therefore, although we 
considered these documents, we did not include them in our analysis 
because they focused on project risks rather than addressing risks to 
human and ecological health. 

Moreover, we are not the first to suggest that DOE's risk assessment 
framework falls short. As stated in our report, some three dozen 
studies by academics, the National Academy of Sciences--including 
studies done at the behest of DOE--and DOE itself have examined aspects 
of risk assessment in relation to DOE's cleanup efforts and found 
shortcomings. As early as 1983, a National Academy of Sciences report 
offered guidelines for federal agencies' use of risk assessment, 
distinct from regulatory functions, in their decision making. Yet we 
found, and DOE's comments also stated, that the draft environmental 
impact statement on tank waste treatment and closure, required under 
the National Environmental Policy Act, is a primary risk assessment 
vehicle. In light of DOE's comments on this topic, confusion seems to 
persist about the differences between risk assessment and risk 
management. 

With regard to the issue of the risks of leaving more waste in tanks, 
DOE stated that it is important to recognize that the department has 
limited discretion when it comes to decisions on how to proceed with 
cleanup. It noted that the Tri-Party Agreement generally requires 
removal of 99 percent of waste from the tanks using available 
technologies. We recognize that DOE must operate within the legal 
constraints placed on it. That said, the Tri-Party Agreement does allow 
DOE to seek an exemption from the 99 percent target on a tank-by-tank 
basis, and DOE is currently using this exemption process for one tank 
it has been emptying. Our point is that, given the enormous task DOE 
faces and the enormous associated costs, if and when situations arise 
where the efforts and costs to meet the 99 percent waste removal 
standard are significantly out of proportion with the actual risk 
reduction achieved, DOE and its regulators should perhaps reconsider 
the reasonable and appropriate path forward. We, like DOE, believe the 
tank closure demonstration project DOE plans to carry out in 
collaboration with Washington State and EPA will be useful in informing 
this discussion. 

DOE disagreed with our recommendation suggesting that the department 
consider seeking clarification from Congress about its authority to 
reclassify high-level waste, stating that it does not believe it needs 
clarification about the department's authority at this time. DOE stated 
that its attention for the next 10 years will be on removing waste from 
tanks, finishing construction of the waste treatment plant, and 
starting waste treatment operations. The department was silent, 
however, on the merits of the recommendation itself. We recognize that 
DOE requested this clarification once before and that in 2004 
legislation (section 3116 of Public Law No. 108-375), Congress provided 
this authority to DOE sites in Idaho and South Carolina while 
specifically excluding DOE sites in Washington State. Given the 
importance of waste classification to the overall Hanford cleanup 
strategy, however, we believe that it may be prudent to consider 
revisiting the topic with Congress. By indefinitely postponing 
potential resolution of this question, DOE may be leaving itself 
vulnerable to future litigation on a topic that could pose more severe 
problems later. By pursuing the question now, DOE could have time on 
its side and can work with regulators and stakeholders to tailor its 
strategy appropriately. 

Finally, in its technical comments, DOE stated that many comparisons 
made in the report do not have consistent or equitable bases. DOE 
commented that while the costs and schedules for its Hanford tank waste 
cleanup strategy have varied over time, the associated scope has 
greatly changed, and earlier cost estimates did not include over $2 
billion in funded contingency. In describing the previous and current 
treatment strategies, our report does note that the scope, as well as 
associated costs, has changed over time. This information is given as 
background for readers, not an exhaustive discussion of previous 
strategies that did not reach fruition. DOE also commented that we 
compared information, such as treatment completion dates, from 
documents having different purposes, such as a baseline schedule and a 
strategic planning document. We recognize that the documents were 
developed for varied reasons. Nevertheless, we believe that the wide 
range of completion dates from these different documents, in 
particular, contributes to a better understanding of the potential 
uncertainties surrounding an effort of this magnitude and complexity. 

We are sending copies of this report to other interested congressional 
committees and to the Secretary of Energy. The report also is available 
at no charge on the GAO Web site at [hyperlink, http://www.gao.gov]. 

If you or your staff have any questions regarding this report, please 
contact me at (202) 512-3841 or aloisee@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Key contributors are listed in appendix 
IV. 

Signed by: 

Gene Aloise: 
Director, Natural Resources and Environment: 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the Department of Energy's (DOE) current Hanford Site 
cleanup strategy and the key technical, legal, and other uncertainties 
it faces, we gathered and reviewed numerous reports and studies 
addressing DOE's overall plan to retrieve, treat, and dispose of 
Hanford's tank waste. We reviewed historical documents to understand 
how DOE's tank waste cleanup strategy has evolved. We reviewed reports 
by DOE and its contractors, which discussed technical problems with the 
waste treatment plant and other phases of DOE's strategy. We also 
reviewed documents analyzing DOE's need for supplemental capacity, and 
the department's analysis of potential options, for treating low- 
activity waste. To identify legal, regulatory, and other uncertainties, 
we reviewed applicable laws, regulations, policy, and guidance 
documents, as well as information on past and pending lawsuits. In 
addition, we interviewed DOE Hanford Site officials in the Office of 
River Protection and visited the Hanford Site. We also interviewed 
officials at DOE headquarters in the Office of Engineering and 
Construction Management and in the Office of Environmental Management's 
Office of Project Recovery and Office of Engineering and Technology. We 
interviewed contractor officials at the Hanford Site responsible for 
building the waste treatment plant. We interviewed officials with 
regulatory and other agencies--specifically, the Washington State 
Department of Ecology, the Environmental Protection Agency (EPA), the 
Nuclear Regulatory Commission, and the Defense Nuclear Facilities 
Safety Board--as well as the National Academy of Sciences. 

To determine the extent to which DOE has assessed whether Hanford's 
tank waste cleanup strategy, including costs, is commensurate with the 
risks from its tank wastes, we examined budget and financial documents, 
environmental impact studies, and other relevant DOE documents. Budget 
information we reviewed included DOE's proposed budget for 2010, DOE's 
estimated costs for tank waste cleanup, and project cost and schedule 
baselines. We spoke with DOE officials and took other steps to ensure 
that all cost data were sufficiently useful for purposes of this 
report. We reported all cost data as provided by DOE--rather than 
normalize them for comparison by using constant dollars, for example-- 
because not all cost information was available annually. We also 
reviewed GAO's recent cost-estimating guide for further information on 
life-cycle costs and risks in developing credible cost estimates. 
[Footnote 50] Further, we reviewed milestones DOE agreed to under the 
Tri-Party Agreement, as well as alternative schedules, such as DOE's 
suggested milestone changes proposed during negotiations with the state 
of Washington and EPA, and other documents showing schedule plans. We 
reviewed DOE's guidance on risk assessments, as well as National 
Academy of Sciences reports and published articles by risk assessment 
professionals. We also reviewed DOE's past environmental impact 
statement and information on DOE's most recent environmental impact 
statement, as well as performance assessments; both assessment types 
discuss risks. 

To evaluate options that DOE could follow to reduce costs of its tank 
waste cleanup strategy, we reviewed DOE documents discussing various 
options. To gain additional insights, we interviewed 18 experts, all of 
whom are independent of DOE and its contractors and have extensive 
knowledge of DOE's tank waste cleanup strategy. We identified these 
experts in consultation with various sources, including the National 
Academy of Sciences and Defense Nuclear Facilities Safety Board; prior 
independent reviews of DOE's Hanford tank waste cleanup strategy; and 
our technical consultant, George W. Hinman, Professor Emeritus of 
Applied Energy Studies at Washington State University, who has 
extensive nuclear energy experience in industry, government, and 
academia. We developed a structured interview guide, containing open- 
ended questions about various aspects of Hanford's waste cleanup 
strategy. These questions addressed uncertainties with DOE's current 
waste treatment strategy, treatment technologies for low-activity 
waste, and developing risk assessment information for DOE's tank waste 
cleanup strategy. We pretested our interview guide to ensure the 
questions were clear and relevant. Using the guide, we interviewed each 
expert either by telephone or in person. Because the questions were 
open-ended, and experts were knowledgeable about varied but not all 
aspects of the issues covered, we did not attempt to quantify their 
responses for reporting purposes. 

Several key documents were just released or were scheduled to be 
released by DOE shortly after our report was to be issued. These 
included a tentative legal settlement with the state of Washington, an 
amended Tri-Party Agreement, a draft environmental impact statement for 
tank closure, and a new cost and schedule baseline for the Hanford tank 
waste cleanup effort. We reviewed an August 10, 2009, version of the 
tentative legal settlement and were provided access to a version of the 
draft environmental impact statement, but the remaining documents were 
not available at the time of our review. These documents are discussed 
in our report and factored into its conclusions and recommendations as 
available and appropriate. As agreed with DOE, we included only 
publicly available information about the draft environmental impact 
statement in our report. 

We conducted this performance audit from July 2008 to September 2009, 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Appendix II: Overview of DOE's Efforts to Select an Approach to 
Supplement Its Low-Activity Tank Waste Treatment Capacity: 

As DOE's strategy for cleaning up tank waste at the Hanford Site has 
evolved over the past 20 years, the department has evaluated a number 
of technologies to supplement its capacity to treat the low-activity 
fraction of the waste.[Footnote 51] As of July 2009, however, DOE 
officials told us they had postponed further testing of one potential 
supplemental technology at Hanford and were proceeding with planning 
for another low-activity waste vitrification facility to provide more 
treatment capacity. 

Over the years, DOE's approach to treating low-activity waste at 
Hanford has moved away from grout, a method used at other DOE sites, to 
vitrification. DOE's original plan in 1989 called for mixing low- 
activity waste with materials to form the hardened, cementlike 
substance called grout, which would be permanently disposed of on site 
in more than 200 large, underground vaults with elaborate environmental 
controls. This disposal method is similar to those widely used in the 
commercial nuclear industry and by DOE at sites besides Hanford, such 
as Savannah River and West Valley, for immobilizing and disposing of 
low-activity and hazardous wastes. In the early 1990s, however, state 
regulators and other stakeholders raised concerns about using grout at 
Hanford. These concerns included doubts about grout's ability to 
prevent long-lived radionuclides, such as technetium-99, from migrating 
into groundwater over a long period; reliance on engineered barriers to 
further limit water infiltration into the vaults; the irretrievability 
of grout from the vaults once disposed of; and the large land area 
(over 200 acres) that would be needed for the underground vaults. Given 
these concerns, DOE suspended efforts to develop a grout-based disposal 
form while it studied the feasibility of other options, including 
various vitrification alternatives. 

In 1994, DOE officially decided against grout and chose to pursue 
vitrifying Hanford's low-activity tank waste. DOE studies concluded 
that a vitrified disposal form offered superior performance over grout. 
These studies showed that glass was capable of retaining long-lived 
radionuclides over a much longer period, required a much smaller 
permanent disposal facility, and had life-cycle costs generally 
comparable to those for grout. In 1994, the Tri-Party Agreement was 
amended to include immobilization of low-activity waste by 
vitrification.[Footnote 52] DOE's 1996 tank waste remediation system 
environmental impact statement--which evaluated treatment options and 
short-and long-term effects for Hanford's tank waste cleanup--largely 
considered vitrification as the technological option for treating low- 
activity waste. DOE ultimately decided on a phased approach to treating 
the waste, that is, building demonstration-sized facilities to test 
treatment technologies on a small portion of the waste--eventually 
determined to be 10 percent of the waste volume--with construction of a 
full-scale facility after testing was complete.[Footnote 53] After the 
contract was awarded in 2000 to build the waste treatment plant, 
however, DOE opted to have its contractor build a full-scale treatment 
plant, which included a low-activity vitrification facility that was 
not large enough to treat all of Hanford's low-activity tank waste by 
the time high-level waste treatment was completed. 

In 2002, DOE shifted its treatment strategy to an accelerated approach 
to meet regulatory and other commitments calling for completing 
treatment of Hanford's tank waste by 2028. DOE recognized, however, 
that the low-activity vitrification facility planned for Hanford would 
not be able to treat more than 50 percent of the low-activity waste by 
this deadline. DOE, along with the Washington State Department of 
Ecology; EPA; and experts from national laboratories, industry, and 
academia, then met to evaluate a number of technologies that could be 
used to supplement Hanford's treatment capacity to meet the accelerated 
schedule.[Footnote 54] 

Together, the agencies identified three technologies--bulk 
vitrification, fluidized bed steam reforming, and cast stone--along 
with a second low-activity vitrification facility, as the most viable 
options for supplementing DOE's treatment capability. Bulk 
vitrification is a vitrification process similar to the technology 
planned for the first low-activity waste vitrification facility-- 
whereby waste is mixed with other materials, heated in a melter to form 
a glass substance, then poured into stainless-steel containers for 
disposal--except that in bulk vitrification, the melter also serves as 
the final disposal container. Steam reforming is a thermal process that 
uses steam and chemical additives mixed with the waste to form a 
granular, mineral-like waste form. Cast stone is a nonthermal, cement- 
based approach that mixes the waste with Portland cement to create a 
monolithic disposal form. While the Washington State Department of 
Ecology participated in selecting technologies for further testing, the 
state has maintained that any supplemental treatment technology must be 
shown to be "as good as glass," which means that it must meet or exceed 
all the same performance standards and disposal criteria to protect 
human and ecological health that apply to the approved glass form. 
Further evaluations concluded that steam reforming and bulk 
vitrification showed the most promise for performing comparably to 
glass in immobilizing Hanford's low-activity tank waste. 

Then, in 2003, DOE decided to proceed with development of bulk 
vitrification at the Hanford Site because it believed the technology 
would be less costly, able to be more rapidly demonstrated and 
deployed, and more acceptable to state regulators than the other 
options. After spending more than $100 million on the bulk 
vitrification demonstration project, however, DOE officials have 
suspended construction activities and elected not to pursue additional 
funding for the project in fiscal year 2009. Throughout testing, bulk 
vitrification had proved to be more costly and technically difficult to 
develop than initially envisioned. Because DOE opted to proceed only 
with testing and developing bulk vitrification for Hanford wastes, 
other technologies--such as steam reforming or cast stone--have not 
been extensively tested using actual Hanford waste. With the suspension 
of bulk vitrification, DOE officials told us they currently have no 
other supplemental technology development under way or planned for 
treating a majority of Hanford's low-activity waste. 

Since suspending bulk vitrification, DOE officials have said that the 
department is planning for a second low-activity vitrification facility 
to provide the additional capacity needed to complete treatment of 
Hanford's low-activity waste within a realistic time frame.[Footnote 
55] While DOE maintains the decision is not final, a second 
vitrification facility will be the path forward for planning purposes. 
For example, in 2008, DOE released an external review of its systems 
planning for low-activity waste treatment at Hanford, which concluded 
that a second low-activity waste vitrification facility was the most 
viable option from a cost perspective for supplementing DOE's low- 
activity waste treatment capability.[Footnote 56] In addition, the 
report suggested that further demonstration of bulk vitrification 
should be given a low priority while the department focuses its 
attention on resolving other uncertainties with its strategy, such as 
the total amount of waste to be processed. 

On the basis of its 2008 report, DOE project officials told us in March 
2009 that they are moving forward in their planning as if a second 
vitrification facility were the selected technology and that the new 
project baseline, due out by the end of the year, will include a second 
low-activity vitrification plant as the supplemental treatment 
approach. Despite these planning decisions, DOE maintains that a final 
determination on its supplemental treatment approach will be made in 
accordance with its project management orders and after issuance of the 
environmental impact statement. In a December 2008 letter to Congress, 
DOE indicated that a final decision on its supplemental treatment 
approach will not likely be made until 2015 at the earliest. 

[End of section] 

Appendix III: Comments from the Department of Energy: 

Department of Energy: 
Washington, DC 20585: 

September 18, 2009: 

Mr. Gene Aloise: 
Director of Natural Resources and Environment: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Dear Mr. Aloise: 

Thank you for the opportunity to review the draft report "Nuclear 
Waste: Uncertainties and Questions about Costs and Risks Persist with 
DOE's Tank Waste Cleanup Strategy at Hanford." Although we generally 
agree with three of the four recommendations, we would like to provide 
clarifications regarding key technical and legal uncertainties facing 
the Tank Waste project at Hanford. In addition, we are concerned with 
how the U.S. Government Accountability Office (GAO) has characterized 
the Office of Environmental Management's (EM) progress at Hanford. 
Specifically, we believe the report's findings should provide a better 
supported, balanced and more accurate portrayal of EM's Tank Waste 
Strategy at Hanford, in part by including descriptions of ongoing 
initiatives and actions, a number of which EM launched in recognition 
of the need for improvement. We are providing our concerns on the draft 
report below and through technical comments, which include factual 
corrections to certain information in GAO's draft report. We are 
looking forward to reporting in the future on the progress being made 
as we continue to focus on removing waste from tanks, finishing 
construction of the Waste Treatment Plant (WTP), and initiating waste 
treatment operations. 

We believe that we have gained substantial experience over the past 
decade in the cleanup of tank waste within the EM complex with the 
vitrification of waste at Savannah River Site's (SRS) Defense Waste 
Processing Facility, with the cleanup in New York State's West Valley 
Demonstration Project and Oak Ridge, and from waste processing and tank 
closures completed at Idaho National Laboratory (INL). This experience 
is applicable to our challenges at Hanford and informs our technical 
and project management approach. In 2009, one of our key initiatives is 
an Integrated Project Team specifically to evaluate current and 
emerging tank waste strategies for Hanford and SRS, to take advantage 
of best practices and lessons learned, and to provide recommendations 
on which strategies to pursue to reduce technical risks and 
uncertainties. This is one example of information we believe is 
critically important to the concerns raised and the characterization of 
this program by the GAO, but absent from the draft report. 

We agree that some technical uncertainties remain; however, we believe 
that we have developed a systematic approach to evaluate alternative 
strategies and transformational solutions that will continue to improve 
and optimize the tank waste operations and help us realize life-cycle 
cost reductions. We believe that the processes we have put in place
Printed with soy ink on recycled paper to reduce technical 
uncertainties will result in the resolution of the issues in a timely 
manner. We have gained a great deal of experience in tank waste 
characterization, retrieval, treatment, and immobilization from the 
cleanup efforts at other sites and believe that this experience will 
also help to reduce uncertainties at Hanford. Tank closure and waste 
processing successes have been realized at Department of Energy (DOE) 
facilities at West Valley, SRS, Oak Ridge, and INL. At West Valley, for 
instance, 628 tons of glass in 275 canisters were produced, 
immobilizing 8,640 cubic feet of high-level waste. Since 1996, SRS has 
vitrified over 2.6 million gallons of sludge waste, and since 2008 has 
vitrified about 2.9 million gallons of high-level waste producing over 
2,700 canisters of high-level waste that arc in two onsite storage 
facilities. At Oak Ridge 8 tanks with a capacity of 90,000 gallons were 
cleaned and grouted, and at INL 11 high-level waste tanks with a 
capacity of 2.2 million gallons were grouted and closed. The River 
Protection Project (RPP) takes advantage of that experience in many 
ways; e.g., through lessons learned, technical exchanges, contracting 
and through interaction of contractor and Federal staff that have been 
involved in operations at these sites. Highlights of these exchanges 
included updated approaches to high-level waste tank integrity, new 
approaches to tank chemistry, and aluminum and chromium mitigation. 

The report should be revised to reflect that the Secretary of Energy is 
planning on convening a Blue Ribbon Panel to evaluate the options for 
high-level waste disposal, and the Panel will provide DOE 
recommendations to resolve this issue. In the meantime, EM has already 
built two interim storage facilities at SRS and one at Hanford 
(Canister Storage Building). Therefore, we are confident that we are 
fully able to build interim storage facilities at Hanford if necessary 
and will be able to calculate life-cycle costs for this operation at 
Hanford, if it is needed. We believe it is premature to anticipate 
these costs until after the Blue Ribbon Panel completes its work. 

DOE agrees that it is important to assess the impacts on human health 
and the environment for the range of possible cleanup strategies with 
regard to the Hanford tanks. To that end, the Department is nearing 
completion of a draft Environmental Impact Statement (EIS) which 
rigorously evaluates 11 alternatives for accomplishing cleanup of the 
tanks ranging from no action to complete removal of the tanks. The 
Office of River Protection provided the GAO access to review the draft 
EIS. 

While DOE has assessed the costs and risks of its actions at Hanford, 
it is important to recognize that the Department has limited discretion 
when it comes to decisions on how to proceed with cleanup. Pursuant to 
Federal law, DOE must comply with state requirements for control of 
hazardous waste (such as the chemical constituents of the tanks at 
Hanford) "in the same manner and to the same extent as any person is 
subject to such requirements" (42. U.S.C. section 6961). The pertinent 
Washington State regulatory framework requires the use of best 
available technology. Hanford's Tri-Party Agreement thus requires 
removal of 99 percent of waste from the tanks using available 
technologies. 

Likewise, the regulatory framework established by Congress in Section 
31 16 of Public Law 108-375 (if it were applicable to Hanford) would 
require a technology-based approach where highly radioactive 
radionuclides are removed from the tanks to the maximum extent 
practical. 

DOE agrees that it is important to develop credible and complete life-
cycle cost and schedule estimates, and we have done this. We believe 
that our estimates represent our most current and best understanding of 
the actions necessary to meet regulatory commitments and to complete 
tank waste cleanup at Hanford. The Tank Farms Project (TFP) life-cycle 
cost estimate range is between $44 and $62 Billion (B). The Office of 
Engineering and Construction Management (OECM) verified the 
reasonableness of that range. An External Independent Review of the TFP 
was performed as required in DOE Order 413.3A prior to validation of 
the near-term baseline. The WTP total estimated contract price is 
$11.07B, including incentives and award fee; $12.26B when DOE 
contingency and other DOE project costs are included. This cost was 
reviewed by the U.S. Army Corps of Engineers, validated by OECM, and 
approved by the Deputy Secretary of Energy in late 2006. The RPP, which 
includes TFP and WTP, total cost range is $56B to $74B as provided 
during the factual accuracy review with your staff. GAO, instead, chose 
to use a point estimate of their own construct. 

EM utilizes strategic planning in developing its overall approach to 
high-level waste treatment at Hanford, and other sites where such waste 
was created, to reduce life-cycle costs. This effort includes ongoing 
evaluations to identify opportunities for cost and schedule improvement 
and risk reduction, and the use of External Technical Reviews and 
Technology Readiness Assessments to focus attention on resolving 
technical uncertainties and ensuring that technology risks are properly 
managed. EM focuses its Technology Development and Demonstration (TDD) 
efforts to identify and develop promising technologies for use in 
further reducing baseline costs and schedule durations, and has 
requested more than a three-fold increase in TDD funding in fiscal year 
(FY) 2010. 

The draft GAO report should provide a better context for its analysis 
of the challenges at Hanford. The GAO's conclusion in 2001 (GAO-01-284, 
Nuclear Cleanup: Progress Made at Rocky Flats, but Closure by 2006 Is 
Unlikely, and Costs May Increase) stated that "Kaiser-Hill and DOE are 
unlikely to meet the December 2006 target closure date" for Rocky 
Flats, and yet this closure date was indeed met by DOE and the Rocky 
Flats cleanup contractor Kaiser-Hill. The Rocky Flats cleanup was 
completed nearly 50 years earlier and for $20.513 less than original 
estimates. As recommended by the GAO in 2006 (GAO-06-352, Nuclear 
Cleanup of Rocky Flats: DOE Can Use Lessons Learned to Improve 
Oversight of Other Sites' Cleanup Activities), EM used the lessons 
learned from Rocky Flats for other cleanup efforts across the complex 
to accomplish extremely successful cleanups. We won the Project 
Management Institute award for our prowess in project management in 
2006 and 2007 for the Rocky Flats and Fernald cleanup projects, 
respectively. 

The draft GAO report does not recognize existing DOE risk management 
efforts. The report states that DOE has not applied risk-informed 
decision making to its tank waste cleanup strategy. While there is a 
limited discussion of the Tri-Party Agreement and draft ETS, there are 
gaps in addressing the overall RPP risk management. Uncertainties noted 
in the report are in the RPP risk management plan and risk mitigation 
actions, and contingencies are included in the life-cycle baseline, yet 
GAO fails to mention this. 

In addition, the Tri-Party Agreement does include provisions for 
mitigation of programmatic risk; Appendix H is in place to provide a 
means to set, evaluate, and revise criteria for determining the 
allowable residual waste following waste retrieval operations on the 
Hanford single shell tanks (SST). The process allows reassessment of 
the retrieval goals based upon the tank farm retrieval experience. A 
Performance Assessment for each SST waste management area will be 
performed. This process includes a risk-based analysis. Finally, the 
draft EIS provides a cumulative risk analysis of the overall process. 

As new technological improvements are developed, we are committed to 
continuously assess the strategies and operations of the WTP to ensure 
that it is protective of human and ecological health and that it is 
operated cost effectively and efficiently. 

Although we agree with the finding that "Some Opportunities May Exist 
to Reduce Costs of DOE's Hanford Tank Waste Cleanup Strategy," it may 
be premature to state that "Allowing More Residual Waste to Remain in 
Selected Tanks at Closing Could Help Reduce Costs without Adding Risks 
to Human and Ecological Health." We need to complete the analysis for 
the tank closure demonstration project in collaboration with Washington 
State and the U.S. Environmental Protection Agency and to work with the 
regulators to determine what will be acceptable. 

With the August 11, 2009, announcement by Secretary of Energy Chu, 
Washington State Governor Gregoire, Oregon State Governor Kulongoski, 
U.S. Senators Murray and Cantwell, and Acting Assistant Attorney 
General Cruden, we have a proposed legal settlement for Hanford (still 
subject to a public comment period). Under the agreement, DOE will 
prepare a life-cycle analysis of all Hanford cleanup costs to meet the 
legally mandated timelines for cleanup. We are also committed to an 
"End Date Review Process" that will ensure that the Hanford tank waste 
cleanup remains as aggressive as possible. In addition, DOE is 
committed to publishing an upcoming draft EIS that fully examines the 
costs and consequences of a wide range of cleanup options. 

The draft GAO report does not acknowledge the work that DOE has been 
doing on the RPP. It does not reflect the successful tank waste 
treatments that DOE has completed nationwide, which have advanced the 
RPP tank waste cleanup efforts. Furthermore, the report does not 
adequately acknowledge the environmental risk reduction activities that 
DOE has performed. Removal of the pumpable liquids from SSTs to achieve 
Interim Stabilization was conducted from late 1970 until 2005. In 
addition, DOE has removed 140 million curies from Hanford's tanks in 
the form of cesium and strontium capsules. 

We generally agree with GAO's recommendation one, two and four. We 
believe that we have a process for developing credible and complete 
life-cycle cost and will continue to update the costs on an annual 
basis. We already have a risk assessment framework for Hanford and will 
be publishing the draft EIS in FY 2010. We continue to work closely 
with the States of Washington and Oregon, the Tribal nations, the 
Environmental Protection Agency, the Defense Nuclear Facility Safety 
Board, the Hanford Advisory Board, and other stakeholders to complete 
Hanford's cleanup. 

DOE does not agree with GAO's third recommendation. At this time, we do 
not believe that we need to seek clarification from Congress about the 
Department's authority at Hanford to determine whether some waste now 
managed by DOE as high-level waste can be treated and disposed of as a 
waste type other than high-level waste. Our focus for the next ten 
years is to remove waste from tanks, finish construction of the WTP, 
and initiate waste treatment operations. 

Again, thank you for your assistance as we seek to strengthen our tank 
waste cleanup strategy at Hanford. We welcome direct dialogue with you 
on these issues prior to finalizing your report. We would also 
appreciate you including the enclosed comments in the final report. if 
you have any questions with regard to these comments, please contact me 
at (202) 586-7709 or Mr. Mark Gilbertson at (202) 586-0755. 

Sincerely, 

Ines R. Triay: 
Assistant Secretary for Environmental Management: 

Enclosure: 

cc: 
D. Chung, EM-2: 
J. Owendoff, EM-3: 
F. Marcinowski, EM-l0: 
M. Sykes, EM-30: 
S. Olinger, ORP: 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Gene Aloise, (202) 512-3841 or aloisee@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, Janet E. Frisch, Assistant 
Director; Ellen W. Chu; Doreen Eng; George W. Hinman; Richard P. 
Johnson; Karen Keegan; Nancy Kintner-Meyer; Mike Meleady; Mehrzad 
Nadji; Joshua Ormond; Thomas C. Perry; Timothy M. Persons; Jena 
Sinkfield; and John Smale made key contributions to this report. 

[End of section] 

Related GAO Products: 

Nuclear Waste: DOE Lacks Critical Information Needed to Assess Its Tank 
Management Strategy at Hanford. [hyperlink, 
http://www.gao.gov/products/GAO-08-793]. Washington, D.C.: June 30, 
2008. 

Hanford Waste Treatment Plant: Department of Energy Needs to Strengthen 
Controls over Contractor Payments and Project Assets. [hyperlink, 
http://www.gao.gov/products/GAO-07-888]. Washington, D.C.: July 20, 
2007. 

Nuclear Waste: DOE Should Reassess Whether the Bulk Vitrification 
Demonstration Project at Its Hanford Site Is Still Needed to Treat 
Radioactive Waste. [hyperlink, http://www.gao.gov/products/GAO-07-762]. 
Washington, D.C.: June 12, 2007. 

Hanford Waste Treatment Plant: Contractor and DOE Management Problems 
Have Led to Higher Costs, Construction Delays, and Safety Concerns. 
[hyperlink, http://www.gao.gov/products/GAO-06-602T]. Washington, D.C.: 
April 6, 2006. 

Nuclear Waste: Absence of Key Management Reforms on Hanford's Cleanup 
Project Adds to Challenges of Achieving Cost and Schedule Goals. 
[hyperlink, http://www.gao.gov/products/GAO-04-611]. Washington, D.C.: 
June 9, 2004. 

Nuclear Waste: Challenges to Achieving Potential Savings in DOE's High- 
Level Waste Cleanup Program. [hyperlink, 
http://www.gao.gov/products/GAO-03-593]. Washington, D.C.: June 17, 
2003. 

Nuclear Waste: Department of Energy's Hanford Tank Waste Project-- 
Schedule, Cost, and Management Issues. [hyperlink, 
http://www.gao.gov/products/GAO-RCED-99-13]. Washington, D.C.: October 
8, 1998. 

Nuclear Waste: Management and Technical Problems Continue to Delay 
Characterizing Hanford's Tank Waste. [hyperlink, 
http://www.gao.gov/products/GAO-RCED-96-56]. Washington, D.C.: January 
26, 1996. 

Nuclear Waste: Further Improvement Needed in the Hanford Tank Farm 
Maintenance Program. [hyperlink, 
http://www.gao.gov/products/GAO/RCED-95-29]. Washington, D.C.: November 
8, 1994. 

Nuclear Waste: Hanford Tank Waste Program Needs Cost, Schedule, and 
Management Changes. vGAO/RCED-93-99. Washington, D.C.: March 8, 1993. 

Nuclear Waste: Hanford Single-Shell Tank Leaks Greater Than Estimated. 
[hyperlink, http://www.gao.gov/products/GAO/RCED-91-177]. Washington, 
D.C.: August 5, 1991. 

Nuclear Waste: Problems and Delays with Characterizing Hanford's Single-
Shell Tank Waste. [hyperlink, 
http://www.gao.gov/products/GAO/RCED-91-118]. Washington, D.C.: April 
23, 1991. 

Nuclear Energy: Consequences of Explosion of Hanford's Single-Shell 
Tanks Are Understated. [hyperlink, 
http://www.gao.gov/products/GAO/RCED-91-34]. Washington, D.C.: October 
10, 1990. 

Nuclear Waste: Program to Prepare High-Level Radioactive Waste for 
Final Disposal. [hyperlink, 
http://www.gao.gov/products/GAO/RCED-90-46FS]. Washington, D.C.: 
November 9, 1989. 

Nuclear Waste: DOE's Management of Single-Shell Tanks at Hanford, 
Washington. [hyperlink, http://www.gao.gov/products/GAO/RCED-89-157]. 
Washington, D.C.: July 18, 1989. 

[End of section] 

Footnotes: 

[1] DOE has managed the Hanford Site since 1977. Before then, the site 
was managed by the U.S. Army Corps of Engineers (1943-47), the Atomic 
Energy Commission (1947-75), and the Energy Research and Development 
Administration (1975-77). 

[2] Unless otherwise specified, all cost numbers come from DOE and are 
reported in current dollars. 

[3] 42 U.S.C. 9601 et seq. (CERCLA); 42 U.S.C. 6901 et seq. (RCRA). 

[4] Since 2007, DOE has been renegotiating Tri-Party Agreement 
milestones that it has missed or believes it will miss, such as the 
starting date of waste treatment operations. In 2008, the state of 
Washington filed suit against DOE, claiming DOE violated the Tri-Party 
Agreement by missing enforceable milestones, including tank retrieval 
and treatment milestones. On August 10, 2009, DOE and the state 
announced they had reached a tentative settlement, including agreement 
on new cleanup milestones. A 2047 completion date was agreed to by DOE 
and its regulators in the tentative settlement. 

[5] Sixteen of Hanford's 149 single-shell tanks are much smaller, with 
a storage capacity of 55,000 gallons. 

[6] The total volume of waste in all of Hanford's underground tanks 
fluctuates over time as DOE carries out its tank waste cleanup process. 

[7] Hanford's underground storage tanks were not designed with specific 
waste retrieval features. Waste must be retrieved through openings, 
called risers, in the top of the tanks. Technicians must therefore 
insert specially designed pumps into the tanks to pump the waste up 
about 45 to 60 feet to ground level. Removing waste from the tanks that 
have already leaked without releasing still more material into the soil 
also poses a challenge, which DOE is trying to address with new 
retrieval technologies. 

[8] GAO, Nuclear Waste: Challenges to Achieving Potential Savings in 
DOE's High-Level Waste Cleanup Program, [hyperlink, 
http://www.gao.gov/products/GAO-03-593] (Washington, D.C.: June 17, 
2003). 

[9] B Plant was originally used to recover plutonium for nuclear 
weapons. In the early 1960s, it was refurbished and used to remove 
certain high-level radioactive materials from the tank wastes. 

[10] Under its privatization approach, DOE planned to set a fixed price 
and pay the contractor for canisters and containers of immobilized tank 
waste that complied with contract specifications. If costs grew as a 
result of contractor performance problems, the contractor, not DOE, was 
to bear these cost increases. Any cost growth occurring as a result of 
changes directed by DOE was to result in an adjustment to the contract 
price and was to be borne by DOE. 

[11] DOE estimates that additional liquid introduced into the tanks may 
amount to three or four times the volume of waste in the tanks, or 176 
million gallons for single-shell tanks. DOE does not have an estimate 
of the additional liquid that will be added to the double-shell tanks 
during retrieval. 

[12] DOE is limited in the amount of waste it can retrieve from single- 
shell tanks, in part because of limited storage capacity in the double- 
shell tanks. Although the double-shell tanks have an estimated capacity 
of slightly over 32 million gallons, as of June 2009 (the latest data 
available), they already contained nearly 26 million gallons of waste. 

[13] Department of Energy, External Technical Review of System Planning 
for Low-Activity Waste Treatment at Hanford (Washington, D.C., November 
2008). 

[14] The pretreatment engineering platform also partially addresses a 
recommendation we made in 2003 to pilot-test pretreatment technologies 
before full-scale operation. See [hyperlink, 
http://www.gao.gov/products/GAO-03-593]. 

[15] Congress approved the Yucca Mountain site in 2002. Pub. L. No. 107-
200, 116 Stat. 735 (2002). 

[16] DOE's budget justification noted that the administration intends 
to convene a panel of experts to evaluate alternative approaches for 
meeting the federal responsibility to manage and ultimately dispose of 
spent nuclear fuel and high-level radioactive waste from both 
commercial and defense activities. The panel is to provide 
recommendations that will form the basis for working with Congress to 
revise the statutory framework for managing and disposing of spent 
nuclear fuel and high-level radioactive waste. 

[17] The term transuranic generally applies to wastes containing 
radionuclides (radioactive elements) with atomic numbers higher than 92 
(uranium's atomic number) and half-lives longer than 20 years in 
concentrations exceeding 100 nanocuries (a measure of radioactivity) 
per gram. 

[18] DOE's transuranic wastes are destined for transfer to and final 
disposal at the Waste Isolation Pilot Plant, a geologic repository in 
Carlsbad, New Mexico. 

[19] Natural Resources Defense Council v. Abraham, 271 F.Supp.2d 1260 
(D.Idaho 2003), vacated as unripe 388 F.3d 701 (9th Cir. 2004). 

[20] Pub. L. No. 108-375, Div. C, Title XXXI, § 3116, 118 Stat. 2162 
(2004). 

[21] Unless otherwise specified, all cost numbers come from DOE and are 
reported in current dollars. 

[22] Our report on best practices for estimating project costs 
highlights the need for credible cost estimates as a critical function 
in managing agency projects. See GAO, GAO Cost Estimating and 
Assessment Guide: Best Practices for Developing and Managing Capital 
Program Costs, [hyperlink, http://www.gao.gov/products/GAO-09-3SP] 
(Washington, D.C.: March 2009). 

[23] The original $4.3 billion was to construct and operate a 
demonstration waste treatment plant with initial capacity to vitrify 10 
percent by mass of the waste and 25 percent of the radioactivity by 
2018. The $12.3 billion is to construct a plant with increased capacity 
to vitrify all the high-level waste and about half the low-activity 
waste. 

[24] GAO, Department of Energy: Major Construction Projects Need a 
Consistent Approach for Assessing Technology Readiness to Help Avoid 
Cost Increases and Delays, [hyperlink, 
http://www.gao.gov/products/GAO-07-336] (Washington, D.C.: Mar. 27, 
2007). 

[25] This figure reflects estimated costs from fiscal year 2007 to 
2032. If DOE had included available actual costs from fiscal year 1997 
through fiscal year 2006, this estimate would come to about $26 
billion. 

[26] These dollar amounts reflect actual costs from 1997 through 2007 
and future costs from 2008 through 2045. Complete cost information 
before 1997 was not available from DOE. 

[27] Both the $700 million and $18 billion figures are "unfunded 
contingency" estimates, which represent additional funds that may be 
needed for potential future problems. 

[28] Department of Energy, Technical Studies Plan for Assessing 
Alternative Sodium Management Strategies for the River Protection 
Project, DOE/ORP-2009-01 (Richland, Wash., January 2009). 

[29] This $1.2 billion estimate includes costs of both tank farm and 
waste treatment plant activities beginning in 2019. 

[30] 42 U.S.C. § 4332(2)(C). 

[31] National Research Council, Risk Assessment in the Federal 
Government: Managing the Process (Washington, D.C.: National Academy 
Press, 1983). 

[32] Department of Energy and Washington State Department of Ecology, 
Final Environmental Impact Statement for the Tank Waste Remediation 
System, Hanford Site, Richland, Washington, DOE/EIS-0189 (Richland, 
Wash., August 1996). 

[33] GAO, Nuclear Waste: DOE Lacks Critical Information Needed to 
Assess Its Tank Management Strategy at Hanford, [hyperlink, 
http://www.gao.gov/products/GAO-08-793] (Washington, D.C.: June 30, 
2008). 

[34] Department of Energy, A Review of the Environmental Management 
Program (Washington, D.C., Feb. 4, 2002). 

[35] National Research Council, Risk and Decisions about Disposition of 
Transuranic and High-Level Radioactive Wastes (Washington, D.C.: 
National Academies Press, 2005), and list of references therein. 

[36] Department of Energy, Tank Closure and Waste Management 
Environmental Impact Statement for the Hanford Site, Richland, 
Washington, forthcoming. 

[37] National Research Council, Science and Decisions: Advancing Risk 
Assessment (Washington, D.C.: National Academies Press, 2008). 

[38] This document considers tank waste cleanup and closure in 
combination with two other major cleanup-related activities: 
decommissioning of the Fast Flux Test Facility (a nuclear research 
reactor that operated at Hanford from 1982 to 1992) and waste 
management and disposal on the Hanford Site. 

[39] DOE had originally intended to issue a public draft of the 
environmental impact statement in spring 2007. After delays, DOE 
officials told us in May 2009 that the document would be issued by the 
end of June 2009. As of July 2009, DOE had again delayed the 
statement's release until revisions could be made analyzing the effects 
of the uncertainty regarding the ultimate repository site for DOE's 
high-level waste. DOE officials said they plan to issue the statement 
for public review before the end of October 2009. 

[40] The remaining canister contents consist of glass-forming material. 

[41] Some of the experts we interviewed also had concerns about the 
reliability of the ion exchange system that extracts the waste from the 
highly radioactive element cesium-137. The ion exchange process was not 
tested as part of the pretreatment engineering platform. 

[42] [hyperlink, http://www.gao.gov/products/GAO-03-593]. 

[43] Under the Tri-Party Agreement, DOE is required to retrieve as much 
tank waste as technically possible, with tank waste residues not to 
exceed 360 cubic feet in the so-called "100" series of tanks, 30 cubic 
feet in the "200" series tanks, or the limit of waste retrieval 
technology capability, whichever is less. (Tri-Party Agreement Action 
Plan, appendix D, milestone M-045-00.) These quantities represent 99 
percent waste retrieval for each single-shell tank. If DOE believes 
that waste retrieval to these levels is not possible for individual 
tanks, DOE may request an exception. 

[44] 40 C.F.R. 261.7(b)(1)(ii). A container is also considered empty if 
no more than 0.3 percent by weight of the total capacity of the 
container remains in the container or inner liner, if the container is 
greater than 119 gallons in size. 40 C.F.R. 261.7(b)(1)(iii)(B). 

[45] Retrieval costs per tank for each of the seven tanks retrieved 
thus far have varied significantly, ranging from $143 million for a 
large tank (530,000 to 1 million gallons) to less than $10 million per 
tank for four of the smallest tanks (55,000 gallons). 

[46] [hyperlink, http://www.gao.gov/products/GAO-08-793]. 

[47] These costs do not include costs to design and construct tank 
waste retrieval structures and equipment. 

[48] GAO, Nuclear Cleanup: Progress Made at Rocky Flats, but Closure by 
2006 Is Unlikely, and Costs May Increase, GAO-01-284 (Washington, D.C.: 
Feb. 28, 2001). 

[49] [hyperlink, http://www.gao.gov/products/GAO-09-3SP]. 

[50] [hyperlink, http://www.gao.gov/products/GAO-09-3SP]. 

[51] Under Tri-Party Agreement milestone M-62-08, DOE was to submit by 
June 30, 2006, a report comparing the performance of potential 
supplemental technologies with that of a second low-activity waste 
vitrification facility. In an August 2009 proposed legal settlement 
with its regulators, DOE agreed to submit a report on potential 
supplemental treatment technologies by 2014 only if the department 
proposed to pursue a technology other than a second vitrification plant 
for low-activity waste. 

[52] Tri-Party Agreement, appendix D, milestones M-61 and M-62. 

[53] "Record of Decision for the Tank Waste Remediation System, Hanford 
Site, Richland, Washington," 62 Fed. Reg. 8693 (February 1997). 

[54] In all, DOE compared about 10 available technical options for 
treating Hanford's low-activity waste. Criteria used to rank them were 
(a) waste treatment acceleration, (b) technology maturity, (c) 
implementation flexibility, (d) ease of regulatory compliance, (e) 
human health and safety risk reduction, (f) operational safety (worker 
protection), (g) compatibility with the Tri-Party Agreement (milestone 
schedules), and (h) waste retrieval acceleration. 

[55] While the Tri-Party Agreement still includes a milestone for 
completing treatment by 2028, both DOE and Washington State acknowledge 
that DOE will not be able to achieve this goal, and the August 2009 
tentative legal settlement sets a revised cleanup date of 2047. Even 
with this extended treatment schedule, DOE believes that the low- 
activity waste vitrification facility currently under construction will 
lack the capacity to treat all the low-activity waste within this time 
frame. 

[56] Although the report acknowledged cast stone and steam reforming as 
other potentially viable options, and noted that these options were 
being evaluated within the environmental impact statement process, it 
did not assess these options, focusing only on alternatives to increase 
Hanford's vitrification capacity. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: