This is the accessible text file for GAO report number GAO-06-94 
entitled 'Department of Energy: Improved Guidance, Oversight, and 
Planning Are Needed to Better Identify Cost-Saving Alternatives for 
Managing Low-Level Radioactive Waste' which was released on October 31, 
2005. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Subcommittee on Energy and Water Development, Committee 
on Appropriations, House of Representatives: 

October 2005: 

Department of Energy: 

Improved Guidance, Oversight, and Planning Are Needed to Better 
Identify Cost-Saving Alternatives for Managing Low-Level Radioactive 
Waste: 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-94] 

GAO Highlights: 

Highlights of GAO-06-94, a report to the Subcommittee on Energy and 
Water Development, Committee on Appropriations, House of 
Representatives: 

Why GAO Did This Study: 

In 2004, the Department of Energy (DOE) disposed of more than 378,000 
cubic meters of low-level radioactive waste (LLRW)—contaminated 
building rubble, soil, and debris. In 2002, DOE directed its sites to 
use life-cycle cost analysis to manage LLRW. Life-cycle cost analysis 
examines the total cost of various options to manage LLRW over its 
life, including its packaging, treatment, transport, and disposal, to 
identify the lowest-cost alternative. GAO determined whether (1) DOE 
sites use life-cycle cost analysis to evaluate LLRW management 
alternatives and (2) DOE has a strategy for cost-effectively managing 
LLRW departmentwide, including state actions that may affect this 
strategy. 

What GAO Found: 

The six DOE sites we visited, representing more than 70 percent of the 
LLRW disposed of by DOE during 2003 and 2004, did not consistently use 
life-cycle cost analysis because of weak DOE guidance and a lack of 
oversight of contractors’ implementation of this guidance. As a result, 
DOE cannot ensure that lowest-cost LLRW management alternatives are 
identified, so that managers make decisions that fully weigh costs 
against noncost factors, such as safety and schedule. For example, DOE 
contractors at two sites did not consistently consider alternative 
transportation modes or postclosure maintenance and surveillance costs 
of disposal sites in their analyses for fiscal year 2004 disposal 
decisions. GAO also could not always determine how contractors used 
cost analyses in disposal decisions because of incomplete 
documentation. While DOE’s guidance requires each site to develop the 
mechanisms necessary to ensure use of life-cycle cost analysis, it does 
not specify, for example, (1) a systematic, consistent method of 
analyzing all cost elements to determine the lowest cost, or (2) when 
analyses should be performed. Also, no such guidance was incorporated 
into site contracts, and DOE site offices had not evaluated 
contractors’ use of life-cycle cost analysis. 

DOE has recognized that its current approach---having each site 
responsible for developing mechanisms necessary to control costs—may 
result in cost inefficiencies and may limit its ability to meet 
departmentwide strategic objectives. As a result, DOE plans to begin 
implementing a national LLRW disposition strategy by March 2006 to 
better coordinate disposal efforts—specific schedules have not yet been 
established for when the strategy will be fully in place. However, DOE 
faces challenges in developing and implementing this strategy. First, 
it needs to gather complete data on the amount of LLRW needing 
disposal. Second, the fact that DOE’s multiple program and site offices 
have differing missions and oversee many contractors presents 
coordination challenges. For example, one program office dismantled and 
disposed of a supercompactor used to reduce the volume of large LLRW 
items without a DOE-wide assessment of LLRW compacting needs and 
without considering other potential cost-effective uses for the 
supercompactor that might benefit other DOE sites. Third, DOE faces 
state actions that have restricted access to disposal facilities, 
making it more difficult to coordinate and integrate disposal 
departmentwide. 

Cost Elements of LLRW Management: 

[See PDF for image] 

[End of figure] 

What GAO Recommends: 

GAO is making recommendations to better ensure that DOE sites properly 
use life-cycle cost analysis to evaluate LLRW management options and 
that DOE successfully develop and implement a DOE-wide LLRW strategic 
plan. In commenting on the draft report, DOE generally agreed with our 
conclusions and thanked us for the recommendations, but disagreed with 
or wanted to clarify certain statements in the draft report and 
provided technical comments which we incorporated as appropriate. 

www.gao.gov/cgi-bin/getrpt?GAO-06-94. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Gene Aloise at (202) 512-
3841 or aloisee@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

DOE Sites Do Not Consistently Use Life-Cycle Cost Analysis in Managing 
LLRW: 

DOE Faces Challenges in Developing a National LLRW Disposition 
Strategy: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendixes: 

Appendix I: Disposed Waste Volume by Major DOE Generator Sites, Fiscal 
Year 2004 through Second Quarter, Fiscal Year 2005: 

Appendix II: Comments from the Department of Energy: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Table: 

Table 1: Cost Elements in Life-Cycle Cost Analysis and Associated 
Activities: 

DOE: Department of Energy: 

EM: Office of Environmental Management: 

LLRW: low-level radioactive waste: 

NNSA: National Nuclear Security Administration: 

Letter October 31, 2005: 

The Honorable David L. Hobson: 
Chairman: 
The Honorable Peter J. Visclosky: 
Ranking Minority Member: 
Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
House of Representatives: 

In fiscal year 2004, the Department of Energy (DOE) disposed of more 
than 378,000 cubic meters of low-level radioactive waste (LLRW)--enough 
to fill a football field to the depth of a 19-story building.[Footnote 
1] This waste included radioactively contaminated building rubble, 
soil, and debris, as well as a small volume of mixed waste, which is 
LLRW that is further contaminated with chemicals and other hazardous 
waste.[Footnote 2] DOE disposes of such waste at two federal 
facilities--the Hanford Site in Washington State and the Nevada Test 
Site--and one commercial facility in Utah. Disposal actions at these 
facilities are in some cases subject to regulation and licensing 
decisions by the states in which they are located. DOE's Office of 
Environmental Management (EM) manages the majority of LLRW at multiple 
sites where the department is cleaning up facilities that were 
contaminated with radioactivity as a result of, for example, nuclear 
weapons-related activities. Many factors must be taken into account in 
managing this waste, including health and safety and the target dates 
for cleaning up the sites. Cost is also an important factor. In 2000, 
we reported that DOE spent more than $700 million to manage LLRW from 
1997 through 1999.[Footnote 3] 

One tool for evaluating LLRW management costs is life-cycle cost 
analysis. Such analysis calculates the total cost to manage waste over 
its life, including cost elements like waste packaging, treatment, 
transportation, disposal, and monitoring of the disposal site after 
closure. The analysis is valuable for comparing the total costs of 
various waste management options leading up to and including disposal 
to identify the most cost-effective alternative. The results of such 
analyses can be used in making LLRW management decisions that weigh 
cost against noncost factors such as safety, health, and schedule. 
DOE's use of complete, current, and well-documented life-cycle cost 
analyses in making LLRW management decisions, if properly conducted, is 
consistent with the intent of DOE Order 430.1B on real property asset 
management. This order identifies requirements for life-cycle 
management of real property assets, including DOE land, improvements, 
facilities, and structures, from planning and acquisition through 
disposal. The order is relevant to LLRW management because many DOE 
facilities and structures that are considered real property assets 
eventually become LLRW through EM cleanup efforts. The proper use of 
life-cycle cost analysis is also consistent with Office of Management 
and Budget Circular A-94, which provides guidance on conducting cost- 
effective analyses of federal programs and projects. Among other 
things, the circular states that a program is cost-effective if, on the 
basis of life-cycle cost analysis of competing alternatives, it is 
determined to have the lowest costs for a given amount of benefits. 

Concerned that DOE may be relying too heavily on the Nevada Test Site 
and Hanford facilities instead of considering other alternatives, such 
as commercial disposal facilities, the House Committee on 
Appropriations directed DOE to prepare a cost study analyzing the life- 
cycle costs of LLRW management alternatives.[Footnote 4] DOE's life- 
cycle cost study, sent to Congress in July 2002, specified cost 
elements to include in life-cycle cost analysis, defined some LLRW 
management alternatives, and highlighted the potential for finding 
various cost differences among alternatives, among other 
things.[Footnote 5] The study stressed that a thorough evaluation of 
all life-cycle costs is crucial to identifying the lowest-cost 
alternative for LLRW management. Although the study recommended that 
DOE sites consider all life-cycle costs in evaluating alternatives for 
LLRW management, it cautioned that DOE's data collection and reporting 
processes needed to be improved to make any departmentwide cost 
analyses useful. 

In this context, you asked us to determine whether (1) DOE sites use 
life-cycle cost analysis to evaluate management alternatives for LLRW 
and (2) DOE has a strategy for cost-effectively managing LLRW disposal 
departmentwide, including state actions that may affect this strategy. 

To determine whether DOE sites use life-cycle cost analysis to evaluate 
management alternatives for LLRW, we obtained information from DOE and 
contractor officials using structured interview guides, reviewed agency 
documents on life-cycle cost analysis requirements and practices, and 
reviewed analyses prepared at a nonprobability sample of six DOE sites 
that generate LLRW.[Footnote 6] In selecting these waste generators for 
site visits, we used LLRW disposal volumes reported by two disposal 
facilities--DOE's Nevada Test Site and a commercial disposal facility 
in Utah--to select three waste generator sites under EM's control: two 
EM sites that disposed of the largest volume of LLRW in fiscal year 
2004--Fernald, Ohio, and Rocky Flats, Colorado--and one EM site with 
the largest projected volume for fiscal year 2005--Paducah, 
Kentucky.[Footnote 7] To provide a DOE-wide perspective, our 
nonprobability sample also included three waste generator sites under 
non-EM program offices. Because multiple DOE program activities can 
exist at a single non-EM site, and comprehensive, departmentwide data 
on LLRW volumes needing disposal do not exist, we selected our non-EM 
sites based on (1) the overall disposal volume of LLRW sent to the 
Nevada Test Site and Envirocare of Utah in fiscal year 2004 and (2) 
judgments made by DOE officials regarding the amount of newly generated 
LLRW volumes for which DOE's National Nuclear Security Administration 
(NNSA) is responsible. These three waste generator sites we visited 
were the Office of Science's Oak Ridge Reservation and East Tennessee 
Technology Park, and NNSA's Y-12 Plant--all in Oak Ridge, Tennessee. We 
assessed the general reliability of the information on LLRW disposal 
volumes by comparing data provided by waste generators with data from 
disposal facilities, and determined that this information was reliable 
enough for selecting sites. In total, the six sites we visited 
constituted about 70 percent of DOE's LLRW disposal volume for an 18- 
month period--October 1, 2003, through March 31, 2005. 

To examine whether DOE has a strategy for integrating DOE-wide disposal 
operations to ensure cost-effective disposal, we reviewed DOE's draft 
plan for a national LLRW disposition strategy and used structured 
interview guides to obtain information from DOE and contractor 
officials at DOE waste generator sites and disposal facilities. In 
addition, we spoke with DOE officials from DOE program offices in 
Washington, D.C, including EM, NNSA, the Office of Science, and the 
Office of Nuclear Energy, Science and Technology. We also spoke with 
appropriate DOE and state officials to identify state actions, such as 
regulatory and court actions, that have affected DOE LLRW disposal 
options and to determine DOE's response to these actions. We performed 
our work between June 2004 and August 2005, in accordance with 
generally accepted government auditing standards. 

Results in Brief: 

The six DOE sites we visited, representing more than 70 percent of the 
LLRW disposed of by DOE during 2003 and 2004, did not consistently use 
life-cycle cost analysis to ensure that the lowest-cost LLRW management 
alternatives are identified because of weaknesses in DOE's guidance for 
life-cycle cost analysis and a lack of oversight of contractors' 
implementation of this guidance. Specifically: 

* Cost analyses are not complete, current, or well documented. The six 
DOE sites prepared various types of cost analyses in making LLRW 
management decisions, but these analyses did not always include all 
life-cycle cost elements or examine alternative courses of action, and 
were not always current or formally documented. For example, DOE 
contractors at two sites--Rocky Flats, Colorado, and Paducah, Kentucky-
-did not consistently consider alternative transportation modes for 
shipping waste or postclosure maintenance and surveillance costs of 
disposal sites in their analyses supporting their fiscal year 2004 LLRW 
disposal decisions. In contrast, the contractor at Fernald, Ohio, 
prepared cost analyses that included all life-cycle cost elements and 
examined alternative options. However, Fernald's life-cycle cost 
analysis, used to justify its 2004 LLRW disposal decisions, was not 
current--it was over 10 years old and had not been updated to reflect 
any changes that might have occurred in the costs for packaging, 
treatment, transportation, or disposal. In other cases, such as at 
DOE's Rocky Flats site, we could not determine how contractors 
incorporated cost analyses into their disposal decisions because their 
documentation was incomplete. Rocky Flats officials told us that 
disposal decisions were at times based on noncost factors, such as 
schedule or safety, but agreed that decisions were not consistently 
documented to show the rationale for how cost was balanced against 
other factors. 

* DOE's guidance and contractor oversight are weak. The cost analysis 
inconsistencies have occurred, in part, because DOE's guidance on life- 
cycle cost analysis is incomplete. For example, EM headquarters' July 
2002 guidance to site offices on life-cycle cost analysis directed 
sites to develop mechanisms necessary to establish that its LLRW 
disposal decisions include the best estimate of full "cradle to grave" 
costs and analysis of alternatives, but it did not specify (1) a 
systematic, consistent method of analyzing all cost elements to 
determine the lowest cost; (2) when or under what circumstances the 
analysis should be performed; (3) relevant DOE orders, manuals, or 
other reference materials that could provide consistent direction on 
life-cycle cost analysis; or (4) how final LLRW management decisions 
should be documented. Furthermore, DOE site offices were ineffective in 
overseeing contractors' use of life-cycle cost analysis, which also 
contributed to ineffective implementation of the guidance. At the sites 
we visited, neither DOE nor contractors had taken identifiable steps to 
implement the guidance on life-cycle cost analysis. For example, DOE 
has not incorporated life-cycle cost analysis guidance into site 
contracts. When we brought these issues to DOE's attention, EM 
officials responded that they have relied on the use of incentive-based 
contracts to ensure contractors are making cost-effective decisions. 
Incentive-based contracts provide specific incentives for specified 
performance outcomes, often driven by site-specific goals and 
objectives in areas such as health, schedule, cost, or other areas, as 
negotiated between DOE and the contractor. For example, incentive-based 
contracts might help DOE meet goals such as accelerated cleanup, which 
may in some cases reduce overall site costs. However, the use of these 
contracts does not necessarily ensure that contractors identify the 
lowest-cost waste management alternatives, unless the contract provides 
this specific focus. 

DOE has recognized that its current approach---having each site 
responsible for developing mechanisms necessary to control costs--may 
result in cost inefficiencies and could limit its ability to meet 
departmentwide strategic objectives, such as accelerated waste cleanup 
and site closure. To overcome these problems, DOE has begun planning a 
national LLRW disposition strategy to minimize life-cycle costs, among 
other things. DOE plans to begin implementing this strategy in March 
2006, but specific schedules have not yet been established for when the 
strategy will be fully in place. The department faces the following 
challenges in achieving an integrated departmentwide strategy: 

* Collecting basic data on the amounts of LLRW needing disposal by 
program offices departmentwide. Although DOE continues to report 
progress in disposing of LLRW, the LLRW volumes it reports as needing 
disposal are not complete. DOE officials acknowledge that its databases 
are outdated and incomplete and do not include all LLRW expected to be 
generated in the future as part of ongoing environmental cleanup or 
produced by non-EM generators. Complete information is crucial for 
developing a national strategy and for holding organizations and 
individuals responsible and accountable for cost-effectively managing 
LLRW. EM plans to gather complete information as part of its national 
disposition strategy. 

* Overseeing LLRW management in a department with a complex 
organization and multiple missions. Specifically, DOE's multiple 
program offices and related site offices have differing missions and 
oversee a variety of site operating contractors, who manage wastes with 
many different characteristics. DOE's Oak Ridge site illustrates how 
this complexity can pose additional challenges for LLRW management. At 
the Oak Ridge site, DOE has three different program offices, each with 
its own contractor with differing levels of responsibility for managing 
or disposing of portions of LLRW. This condition has complicated 
efforts to dispose of LLRW cost-effectively. For example, in 2004, DOE 
allowed a contractor to dispose of a supercompactor used to reduce the 
volume of large pieces of LLRW debris from its gaseous diffusion plant. 
The decision to dismantle and dispose of this compactor was made 
without a departmentwide assessment of LLRW volume reduction needs and 
capabilities, and without fully considering the supercompactor's 
potential for reducing LLRW volumes and lowering costs for other 
program offices at Oak Ridge and other sites. Consequently, DOE may 
have missed a potential cost-saving opportunity because other waste 
generator sites might have benefited from the use of the 
supercompactor, such as Paducah, Kentucky, which has 37,000 tons of 
scrap metal that its current on-site compactor is incapable of 
crushing, according to the site's senior contractor official 
responsible for LLRW management. 

* Addressing the impacts of recent state actions. Over the past 2 
years, states' regulatory and legal actions have restricted DOE's 
access to disposal facilities, which compounds the challenges of 
coordinating and integrating disposal efforts departmentwide. For 
example, the state of Washington has sued to prevent LLRW from other 
DOE sites from being disposed of at the Hanford facility. Consequently, 
DOE is incurring increased costs for storage and treatment. 

To ensure the cost-effective management and disposal of LLRW, we are 
recommending that the Secretary of Energy take specific actions to 
ensure that DOE sites use complete, current, and well-documented life- 
cycle cost analyses in making LLRW management decisions, and develop 
and implement a strategy for managing LLRW disposal departmentwide. 
Overall, DOE generally agreed with our conclusions and thanked us for 
the recommendations. Specifically, DOE agreed that its sites are not 
consistently using life-cycle cost analysis in making LLRW management 
decisions. It also agreed that its current guidance and oversight in 
the area of life-cycle cost analysis for LLRW management decisions 
should be strengthened and expressed appreciation for our support of an 
effective National Disposition Strategy for LLRW management. DOE also 
provided technical comments on certain statements in the draft report 
with which it disagreed or wanted to clarify, which we incorporated as 
appropriate. 

Background: 

Under the LLRW Policy Act of 1980, as amended, the federal government 
is responsible for the disposal of LLRW owned or generated by 
DOE.[Footnote 8] DOE defines LLRW as all radioactive waste that does 
not fall within other classifications, such as spent (used) nuclear 
fuel and other high-level waste. Mixed waste is LLRW with hazardous 
components, such as lead and mercury. LLRW can include material of 
varying levels of radioactivity, from barely contaminated soil and 
debris to LLRW with enough radioactivity to require remote handling. 
LLRW can include items such as contaminated equipment, protective 
clothing, rags, and packing materials and is managed at multiple sites 
under a variety of contractors. (See app. I for a list of DOE sites 
that disposed of the majority of LLRW in fiscal years 2004 and 2005.) 

DOE sites typically dispose of LLRW at (1) on-site facilities, if 
suitable capacity is available,[Footnote 9] (2) DOE's regional disposal 
facilities at the Hanford Site or the Nevada Test Site, or (3) a 
commercial facility.[Footnote 10] The selection of the disposal 
facility is based partly on the facility's waste acceptance criteria. 
These criteria specify the allowable types and amounts of radioactive 
materials, and types of containers acceptable at the disposal facility. 

In 2000, we reported that DOE had not developed full life-cycle costs 
for its disposal facilities or established guidance to ensure that its 
contractors base their disposal decisions on departmentwide 
considerations of cost-effectiveness, among other things.[Footnote 11] 
We also reported in 2001 that cost analyses concerning the use of DOE's 
on-site disposal facilities should be periodically updated to take into 
account changing economic conditions.[Footnote 12] Subsequently, the 
House Committee on Appropriations directed DOE to prepare an objective 
analysis of the life-cycle costs of LLRW disposal for various federal 
and commercial disposal options.[Footnote 13] The committee was 
concerned that DOE needed to include in its life-cycle cost analysis 
certain cost elements, such as packaging, transportation, disposal, and 
postclosure maintenance and surveillance. 

In response, in its 2002 report to Congress on life-cycle cost analysis 
of LLRW disposal, DOE listed among its next steps for EM sites to 
consider the cradle-to-grave costs as they make LLRW management 
decisions. On July 18, 2002, EM issued guidance directing each site 
office to develop the mechanisms necessary to ensure that contractors' 
LLRW disposal decisions include the best estimate of full cradle-to- 
grave costs and analysis of alternatives. Several other documents on 
life-cycle cost analyses are also available. For example, DOE has a 
cost-estimating guide, developed in the mid-1990s, that provides a 
chapter dedicated to life-cycle cost analysis, including definitions, 
processes, limitations, common errors made in life-cycle cost analysis, 
methods, examples, and diagrams.[Footnote 14] In addition, although not 
directly applicable to LLRW management, guidance and manuals prepared 
by other federal agencies for other DOE programs may be useful to the 
sites in explaining life-cycle cost analysis methods. For example, the 
National Institute of Standards and Technology has published two 
documents on life-cycle cost analysis that are applicable to DOE's 
Federal Energy Management Program.[Footnote 15] 

DOE Sites Do Not Consistently Use Life-Cycle Cost Analysis in Managing 
LLRW: 

DOE sites prepare various types of cost analyses in making LLRW 
management decisions, but these analyses do not consistently use 
complete, current, or well-documented life-cycle cost analysis to 
ensure that the lowest-cost LLRW management alternatives are 
identified. As a result, the decisions the sites make may not take into 
account the most cost-effective alternative. These inconsistencies have 
occurred, in large part, because DOE's guidance lacks necessary detail 
and its oversight of contractor practices is weak. 

Site Cost Analyses Are Not Always Complete, Current, or Well 
Documented: 

Complete life-cycle cost analysis is cradle to grave and includes all 
costs associated with the management and disposal of LLRW. As DOE's 
2002 report to Congress explained, the costs preceding disposal vary 
greatly and can be significantly greater than the actual cost of 
disposal. As a result, DOE concluded it is essential to consider pre- 
disposal costs as well as disposal costs. Table 1 shows the cost 
elements of a complete life-cycle cost analysis, according to DOE's 
2002 report. 

Table 1: Cost Elements in Life-Cycle Cost Analysis and Associated 
Activities: 

Cost element: Preparation; 
Activities: The waste generator samples and analyzes the waste to 
ensure that it will be certified as acceptable to the disposal site--
actions also known as waste characterization. The generator is also 
responsible for treating the waste so that it is in a proper chemical 
and physical form to meet the disposal facility's acceptance criteria. 
Treatment can include drying or compaction. 

Cost element: Packaging; 
Activities: The generator is responsible for placing the waste--usually 
in the form of soil or debris--in containers or in bulk, such as in a 
railcar. The container type and cost vary with the characteristics of 
the waste. 

Cost element: Transportation; 
Activities: The generator sends LLRW off-site, usually by truck or 
rail. According to DOE, truck shipments can cost up to 1.9 times the 
cost of rail shipments, depending on the packaging method, waste 
density, and routing. 

Cost element: Disposal; 
Activities: The disposal facility operator receives and disposes of 
LLRW. Disposal facilities generally incur construction, operation, 
maintenance, and postclosure costs that they may pass on to waste 
generators through disposal fees. Postclosure activities are required 
to protect human health and the environment from hazards remaining 
after closure, and can include maintaining and repairing closure caps, 
monitoring environmental contamination, and erecting and maintaining 
barriers.[A]. 

Source: DOE. 

[A] Typically, DOE disposal facilities do not include past construction 
or future postclosure costs in their disposal fees because they operate 
on an annual appropriations basis. In contrast, Envirocare of Utah, a 
commercial operator, charges disposal fees that recoup such costs. 

[End of table] 

DOE LLRW generator sites we visited did not always include all life- 
cycle costs--including the postclosure costs of long-term maintenance 
and surveillance of the disposal site--and did not always consider 
alternative actions when deciding on how to manage and dispose of LLRW. 
For example, despite DOE's guidance to include all disposal costs in 
its life-cycle cost analyses, DOE contractors at two sites--Rocky 
Flats, Colorado, and Paducah, Kentucky--did not consistently consider 
postclosure costs in the analyses supporting their LLRW disposal 
decisions for fiscal year 2004. In contrast, the contractor at Fernald, 
Ohio, prepared a life-cycle cost analysis that included estimated 
postclosure costs for both the Nevada Test Site and for Envirocare of 
Utah, a commercial disposal facility. Nevada Test Site officials told 
us they do not include these future costs in their disposal fees 
because they operate on an annual appropriated funds basis. Nevada Test 
Site officials estimated that if they were to include postclosure costs 
in their fee, these costs would add an additional $2.38 per cubic foot 
of waste to the fee. Envirocare of Utah, on the other hand, includes 
the estimated postclosure costs in its disposal fees, as required by 
the state of Utah. 

Costs for certain LLRW activities vary widely among disposal sites and 
should be considered in preparing life-cycle cost analysis. For 
example, EM's 2002 report to Congress found that costs for one 
predisposal cost element--waste characterization--can be higher for 
wastes shipped to the Nevada Test Site and the Hanford Site for 
disposal than for wastes sent to Envirocare of Utah. Waste 
characterization costs for the two DOE sites ranged from $130 to $2,400 
per cubic meter, while these same costs ranged from $30 to $880 per 
cubic meter at Envirocare of Utah. The major factors contributing to 
this cost differential are (1) required procedures for accepting, 
handling, and disposing of LLRW with higher levels of radioactivity at 
the Nevada Test Site and Hanford and (2) the higher cost to the 
generator of characterizing wastes that are shipped in containers to 
the Nevada Test Site and Hanford Site for disposal. Although waste 
characterization is an important element in life-cycle cost analysis, 
the Rocky Flats contractor did not include the costs of these 
activities in its cost analysis. 

In addition, waste generators do not always include potential lower- 
cost alternatives when making LLRW decisions. For example, in fiscal 
year 2004, the Paducah contractor shipped 600 cubic meters of LLRW in 
trucks to Envirocare of Utah. Although in its preliminary analysis, the 
site contractor believed that using rail could save 25 percent in 
transportation costs, contractor officials indicated they did not 
validate these preliminary assumptions or complete a formal cost 
analysis of the rail option. 

DOE contractors' cost analyses are not always current. Despite DOE's 
2002 recommendation that cost estimates should be revisited 
periodically, one DOE waste generator disposed of large volumes of LLRW 
in fiscal year 2004 on the basis of cost studies completed several 
years earlier. Specifically, the contractor at Fernald acknowledged 
shipping over 100,000 cubic meters of LLRW to Envirocare of Utah in 
fiscal year 2004, using a cost analysis completed in 1994. This 
analysis, while considering all life-cycle cost elements, had not been 
updated during this 10-year period to account for any changes that 
might have occurred in cost elements, such as changes in disposal 
rates, costs for packaging, treatment, or transportation. For example, 
disposal rates charged by Envirocare of Utah can change from year to 
year, based on price discounts offered for larger LLRW disposal 
volumes. 

We also found that three of the five DOE sites that had expanded on-
site facilities since 2002 did not complete an analysis comparing the 
life-cycle costs of on-site and off-site disposal alternatives. A 2001 
congressional conference report requires DOE to perform such an 
analysis "before proceeding with any new on-site disposal 
cell."[Footnote 16] DOE asserts that the report language does not apply 
to ongoing facility development or expansion. Officials at two sites 
indicated they did not believe they needed to complete such a life- 
cycle cost analysis because the expansion of their on-site disposal 
facility was already accounted for in the initial facility design, 
completed before 2002. The third site completed a life-cycle cost 
analysis of LLRW waste streams for its on-site facility. However, site 
officials did not complete a life-cycle cost analysis of off-site 
disposal because they assumed that the costs of off-site transportation 
and disposal would be significant enough to preclude the off-site 
option. Although the remaining two sites completed life-cycle cost 
studies comparing on-site and off-site disposal costs, these studies 
were not submitted to the congressional appropriations committees. 

DOE contractors' cost analyses are not always well documented. In some 
cases, we could not determine how contractors incorporated cost 
analyses into their disposal decisions because documentation was 
incomplete. According to DOE and contractor site officials at Rocky 
Flats, disposal decisions were at times based on noncost factors, such 
as schedule or safety. For example, a 2003 cost study determined that 
using trucks to transport building debris to a nearby rail loading area 
less than 1 mile away would be more cost-effective than extending a 
rail line to the building. However, contractor officials told us they 
decided to build a rail extension to the building being demolished 
because the extra traffic at the site caused by trucks hauling the LLRW 
to the rail line could endanger the health and safety of the workers. 
This decision, however, was not documented. Contractor officials at 
Rocky Flats agreed that such LLRW management decisions were not 
consistently documented to show the rationale for how cost was balanced 
against other factors. 

At other sites, cost analyses were informal and not documented. For 
example, contractor officials responsible for LLRW disposal at Paducah 
told us that they made some disposal decisions informally because they 
believed their knowledge of the factors involved made it unnecessary to 
complete a formal analysis. In addition, Oak Ridge contractor officials 
coordinating the removal of LLRW from the site told us they did not 
complete a formal analysis of disposal options for each waste stream 
because their contract did not require such an analysis. 

DOE's 2002 Guidance Lacks Necessary Detail: 

DOE sites have not consistently used life-cycle cost analysis, in part 
because EM's 2002 guidance memo on life-cycle cost analysis lacks the 
necessary detail for how and when to use it. Consequently, each site 
was responsible for deciding how to incorporate cost into its LLRW 
management decisions. For example, although EM's guidance directed 
sites "to develop mechanisms necessary to establish that its LLRW 
disposal decisions include the best estimate of full 'cradle to grave' 
costs and analysis of alternatives," the guidance did not do the 
following things: 

* Lay out a systematic, consistent method for (1) analyzing all cost 
elements or (2) comparing key alternatives within these cost elements 
to determine the lowest cost. Consequently, as we found, analyses often 
did not include cost elements that might have altered a disposal 
decision. 

* Specify when or under what circumstances sites should prepare cost 
analyses. As we found, some sites did not update their analyses to show 
that their original LLRW management decisions were still supported by 
current economic conditions; 

* Refer sites to relevant DOE orders, manuals, or other reference 
materials that could provide consistent direction on life-cycle cost 
analysis. Such references could include, for example, the DOE order for 
real property asset management, the DOE manual on preparing life-cycle 
cost estimates, Office of Management and Budget guidance for completing 
a cost-effective analysis, and the National Institute of Standards and 
Technology guidance for completing life-cycle cost analysis, or 
portions of these documents. 

* Lay out how final LLRW management decisions should be documented. For 
example, the guidance does not explain how sites should weigh disposal 
costs against noncost factors such as safety and health. As we found, 
without adequate documentation at some of the sites we visited, it was 
difficult for site contractors to justify the decisions they had made. 

DOE Has Not Taken Steps to Oversee Contractors' Use of Life-Cycle Cost 
Analysis, Relying Instead on Incentive-Based Contracts to Ensure Cost- 
Effective LLRW Decisions: 

DOE site offices were ineffective in overseeing contractors' use of 
life-cycle cost analysis, which also contributed to ineffective 
implementation of the guidance. At the sites we visited, neither DOE 
nor the contractors had taken identifiable steps to implement the 
guidance on life-cycle cost analysis. 

First, DOE has not incorporated life-cycle cost guidance into 
contracts. Most of the incentive-based contracts at the sites we 
visited require contractors to comply with DOE Order 430.1A on life- 
cycle asset management, which requires the use of life-cycle cost 
analysis. However, neither that order, nor its successor, DOE Order 
430.1B, provide sufficient detail on life-cycle cost analysis 
definitions, methods, examples, or diagrams that would be useful in 
preparing such analyses. In contrast, DOE's cost-estimating guide 
provides a chapter dedicated to life-cycle cost analysis.[Footnote 17] 
This chapter includes definitions, processes, limitations, a list of 
common errors made in life-cycle cost analysis, methods, examples, and 
diagrams. However, the estimating guide is not explicitly cited in DOE 
Order 430.1A or 430.1B, or in the site contracts. As a result, the 
contractor official responsible for controlling LLRW costs at Rocky 
Flats, for example, could not tell us whether the contractor used DOE's 
cost-estimating guide, particularly the chapter on life-cycle cost 
analysis in LLRW management decisions, because he was not familiar with 
the guide. 

Second, DOE field offices have not taken steps to implement guidance or 
to evaluate contractors' use of life-cycle cost analysis. For example, 
contractor officials at Paducah were not aware of EM's July 18, 2002, 
guidance memo on life-cycle cost analysis until we showed a copy to 
them at the time of our visit. In addition, in October 2002, DOE's 
Rocky Flats Field Office sent a memo to its contractor, Kaiser-Hill 
Company, concerning this EM guidance. According to the memo, the 
department was already aware that the contractor used licensed 
commercial disposal facilities and that disposal decisions considered 
technical acceptability, schedule, and cost benefit; the field office 
therefore concluded that the mechanisms to establish cost-effective 
disposal decisions by Kaiser-Hill were already in place and thus 
satisfied the intent of the EM guidance. However, we found no 
indication at any of the sites we visited that DOE officials had 
specifically assessed the contractor's use of life-cycle cost analysis 
in making LLRW management decisions. 

When we brought our concerns to EM officials on the inconsistent use of 
life-cycle cost analysis at the sites, they responded that EM has 
relied on the use of incentive-based contracts to ensure contractors 
are making cost-effective LLRW management decisions, rather than 
encouraging the use of life-cycle cost analysis. Incentive-based 
contracts provide specific incentives for specified performance 
outcomes, often driven by site-specific goals and objectives in areas 
such as health, safety, schedule, cost, or other areas, as negotiated 
between DOE and the contractor. We recognize that incentive-based 
contracts might help DOE meet goals such as accelerated cleanup and 
that these contracts may, in some cases, reduce overall site costs. 
However, their use may not necessarily identify lowest-cost waste 
management alternatives, unless the contract provides this specific 
focus. Since the department relies on incentive-based contracts, it is 
critical that the contract's total estimated cost be based on, among 
other things, life-cycle cost analyses of LLRW management alternatives 
and that the contract specify the proper use of life-cycle cost 
analysis. 

Without the proper use of life-cycle cost analysis in establishing and 
overseeing incentive-based contracts, DOE cannot be assured that the 
contractor has identified the lowest life-cycle cost alternatives for 
LLRW management. For example, the Rocky Flats contractor, operating 
under an incentive-based contract, prepared various analyses of 
transportation alternatives from 2000 to 2003, but these analyses did 
not comprehensively address sitewide LLRW disposal needs because they 
were incomplete and not updated. Specifically, two DOE contractor draft 
studies in 1999 and 2000 indicated that adding rail as an alternative 
for shipping LLRW from Rocky Flats to off-site disposal facilities 
could save millions of dollars in transportation costs. Despite this 
cost-saving potential, the contractor decided in 2000 to rely 
exclusively on trucks for all Rocky Flats LLRW shipments. Subsequently, 
in 2002, the contractor analyzed transportation alternatives 
specifically for shipping certain contaminated LLRW soil off-site. 
Although the analysis concluded that using rail to transport this soil 
alone could save up to $216,000, the contractor continued using trucks 
exclusively in fiscal year 2003 and most of fiscal year 2004 to 
transport this waste to Envirocare of Utah. In 2003 the contractor 
determined that the total volume of this LLRW soil would be 
significantly higher than previously estimated, further increasing the 
cost-saving potential of using rail, but nevertheless did not update or 
formalize the analysis. Instead, the contractor decided to send the 
soil by rail only after determining that it would use rail for shipping 
debris from an altogether separate LLRW project at Rocky Flats. In 
September 2004, the site began to transport the LLRW soil by rail, 
after it had already sent over 4,200 truck shipments of soil to Utah in 
fiscal years 2003 and 2004. Use of rail instead of trucks to ship the 
LLRW soil might have saved the site over $4 million during fiscal year 
2004. Comprehensive, complete, and current analyses of transportation 
alternatives for sitewide LLRW disposal needs might have better 
identified the lowest-cost transportation alternative, therefore 
providing an opportunity for reducing LLRW management costs for the 
site. 

In April 2005, as part of our ongoing engagement, we briefed the 
Subcommittee on Energy and Water Development, House Committee on 
Appropriations, on the preliminary results of our work. We stated that 
DOE LLRW generators were not consistently using life-cycle cost 
analyses in their disposal decisions because of poor guidance and weak 
oversight. One month later, in its report to accompany the fiscal year 
2006 energy and water appropriations bill, the full Appropriations 
Committee emphasized its intention to have DOE use life-cycle cost 
analysis in LLRW management decisions. Using our preliminary findings, 
the committee noted its concern with the department's reliance on 
incentive-based contracts as a mechanism for ensuring cost-effective 
decision making rather than using life-cycle cost analyses, as 
directed.[Footnote 18] 

According to the committee, while contractors should pursue cost- 
effective cleanup activities at their sites, it is up to the federal 
management responsible for those contractors to provide guidance and 
make decisions that benefit the whole DOE complex. As such, the 
committee directed the Secretary of Energy to report to the committee 
within 30 days of enactment of the 2006 Energy and Water Development 
Appropriations Act, on the specific steps the department will take to 
ensure that contractors use life-cycle cost analysis in considering 
LLRW options, and that DOE maintains a viable oversight function to 
oversee the implementation of such guidance. The committee further 
recommended that a third of EM's budget for managing the cleanup 
program, or $82,924,000, be withheld until after the Secretary of 
Energy delivers a report to the committee.[Footnote 19] 

DOE Faces Challenges in Developing a National LLRW Disposition 
Strategy: 

To better coordinate disposal efforts among sites and program offices, 
increase efficiencies, and minimize life-cycle costs, DOE has begun 
developing a national LLRW disposition strategy. Although DOE expects 
to begin implementing this strategy by March 2006, specific schedules 
have not yet been established for when the strategy will be fully in 
place, and it faces several significant challenges. These include 
developing a database that can be used to manage LLRW complexwide and 
overcoming organizational obstacles created by the department's varied 
missions. 

DOE Expects to Begin Implementing a Departmentwide Strategic Plan for 
Disposing of LLRW in 2006: 

DOE has recognized that its current approach---having each site 
responsible for developing mechanisms necessary to control costs--may 
result in cost inefficiencies and could limit its ability to meet 
departmentwide strategic objectives, such as accelerated waste cleanup 
and site closure. To overcome these problems, EM has begun developing a 
National Disposition Strategy, which it plans to implement in 2006. EM 
plans to use the strategy to evaluate predisposal, storage, treatment, 
and disposal options across the department. The focus of the strategy 
will be on DOE LLRW that is shipped off-site for disposal and on waste 
for which DOE currently has no treatment or disposal options. EM hopes 
to make specific recommendations regarding waste without treatment or 
disposal options, develop a LLRW database, and reduce predisposal 
costs. To implement a successful strategy, EM expects to integrate 
sites' waste disposition plans by (1) identifying and quantifying LLRW 
by waste category and site, (2) developing potential treatment and 
disposal options, and (3) identifying federal and commercial site 
capabilities for disposal of LLRW. DOE has not yet established specific 
schedules for when the strategy will be fully in place. 

EM plans to develop this national disposition strategy in two phases. 
In Phase I, EM will examine those DOE sites that now have significant 
quantities of EM LLRW, including Oak Ridge, Savannah River, Idaho 
National Laboratory, Hanford (including the Office of River 
Protection),[Footnote 20] Fernald, Portsmouth (in Ohio), and Paducah 
(in Kentucky). DOE will also take into account LLRW requiring disposal 
from fiscal year 2005 to about fiscal year 2035. In Phase II, EM will 
examine the LLRW managed by other DOE program offices, such as NNSA and 
the Office of Science. Efforts in Phase II will require considerable 
coordination among different DOE program offices. 

DOE Lacks Departmentwide Data on Its LLRW Inventory: 

To develop and implement its national strategy for LLRW disposition, 
DOE needs basic data--both current and forecasted--from individual 
sites on their disposition plans. However, EM does not have complete 
data, either for its own sites or for non-EM sites with LLRW. Although 
DOE continues to report progress in disposing of LLRW, the LLRW volumes 
it reports as needing disposal are not complete. EM's databases do not 
include all LLRW expected to be generated in the future as part of 
ongoing environmental cleanup or waste produced by non-EM generators. 
This information may be time-consuming and costly to obtain from the 
different program offices. For example, when we sought information on 
current and forecasted LLRW volumes from the Office of Science, NNSA, 
and the Office of Nuclear Energy, Science, and Technology (Nuclear 
Energy), only the Office of Science provided the requested information. 
NNSA and Nuclear Energy did not provide this information because, 
according to officials from each of these program offices, the 
information was not readily available. 

Regarding cost information, EM's 2002 report to Congress recommended 
that DOE sites consider all life-cycle costs in evaluating alternatives 
for LLRW management, but it cautioned that DOE's data collection and 
reporting processes needed to be improved to make any departmentwide 
cost analyses useful. EM officials stated that they will consider LLRW 
costs in their National Disposition Strategy. Currently, according to 
EM, DOE does not have uniform requirements for defining, monitoring, 
and reporting waste disposal costs, and sites may differ significantly 
in their protocols for collecting cost information. However, EM agrees 
that if DOE is to use life-cycle cost analysis to improve the bases for 
sites' disposal decisions, standardized protocols for collecting and 
reporting the data would have to be established. 

DOE recognizes these problems and has begun to develop some information 
it needs to support the evolving disposition strategy. Specifically, 
DOE is determining (1) what data it needs; (2) whether it can use the 
data in existing databases or has to develop a new database; and (3) 
how these data should be organized in a database. 

DOE's Organization and Multiple Missions Pose Challenges to Developing 
a National Strategy: 

EM's ability to develop an integrated strategy for managing LLRW is 
further complicated by the fact that DOE has multiple program and site 
offices with different missions, and these offices oversee a variety of 
site contractors who manage waste with many different characteristics. 

DOE's experience with the use of a supercompactor at its Oak Ridge site 
illustrates the difficulty EM faces in developing a waste disposition 
strategy that covers multiple program offices. At this site, EM and 
NNSA program offices have their own contractors that are responsible 
for various activities, including managing or disposing of LLRW. In 
1997, DOE awarded BNFL a 6-year fixed-price contract to decontaminate 
and decommission three buildings once used to enrich uranium at the Oak 
Ridge gaseous diffusion plant.[Footnote 21] These buildings comprised 
more than 4.8 million square feet and housed more than 328 million 
pounds of material. To dispose of this waste, BNFL had constructed a 
supercompactor, the largest of its type in the nuclear industry. Using 
this supercompactor, the contractor was able to reduce the volume of 
several thousand tons of LLRW by 75 percent and save an estimated $100 
million in LLRW management and disposal costs. Despite the 
supercompactor's potential for reducing LLRW volumes and lowering costs 
for the other program offices at the Oak Ridge site, the contractor, 
with the approval of the DOE site office, decided in 2004 to dismantle 
the supercompactor and ship it as LLRW to Envirocare of Utah for 
disposal. 

According to NNSA officials at the Y-12 Plant, also located at the Oak 
Ridge site, they have contaminated buildings that need to be dismantled 
and disposed of, but neither DOE nor the contractor consulted with NNSA 
officials about the potential use of the supercompactor for NNSA's 
ongoing compacting needs. Similarly, contractor officials at EM's 
Paducah Site in Kentucky, which is about 300 miles away, stated that 
they might have benefited from the use of the supercompactor but were 
not given the opportunity to consider alternatives to its disposal. For 
example, Paducah had about 37,000 tons of remaining scrap metal, as of 
June 26, 2005, that its current on-site compactor is incapable of 
crushing, according to a contractor official at the Paducah site. 

A DOE official at the Oak Ridge site stated that it would probably not 
be cost-effective to ship debris to the supercompactor from other 
sites, and the supercompactor could not cost-effectively be relocated. 
However, neither DOE nor contractor officials provided any 
documentation of cost analysis to support this statement. Although the 
dismantling, shipping, and disposal of the supercompactor may have been 
the correct decision, DOE did not conduct a departmentwide assessment 
of volume reduction needs and capabilities, and the costs or potential 
obstacles associated with maintaining or moving the supercompactor 
under various LLRW management alternatives. Consequently, DOE may have 
missed a potential cost-saving opportunity. Oak Ridge officials told us 
that they are currently developing an integrated disposition plan to 
better coordinate LLRW management activities specifically for the Oak 
Ridge site. According to DOE, other integrated activities underway at 
Oak Ridge include, among other things, a pilot program between EM and 
the Office of Science to dispose of LLRW that needs no further storage 
or processing. 

Litigation and State Actions Can Affect DOE's Waste Management Options: 

As a result of lawsuits and state regulatory and legislative actions in 
two states--Washington and Nevada--DOE cannot currently rely on either 
of its federal disposal facilities--Hanford or the Nevada Test Site--to 
dispose of mixed LLRW. Consequently, DOE is incurring increased costs 
for storage and treatment. Texas may provide DOE with new disposal 
options, but not sooner than December 2007. Specifically: 

* In July 2004, Washington state asked a U.S. district court to 
prohibit DOE from sending LLRW from other DOE sites to Hanford for 
disposal.[Footnote 22] DOE voluntarily suspended LLRW shipments pending 
the court's decision. In May 2005, the court ruled in favor of the 
state, issuing a preliminary injunction prohibiting DOE from sending 
LLRW from other sites to Hanford for disposal.[Footnote 23] In 
addition, in November 2004, Washington state voters passed an 
initiative, now incorporated in Washington state law, that would 
prohibit DOE from accepting out-of-state waste until existing waste at 
Hanford is cleaned up.[Footnote 24] The scope and constitutionality of 
the initiative are currently being litigated in federal district 
court.[Footnote 25] DOE officials told us that its inability to ship 
mixed LLRW to Hanford from other states is increasing costs and may 
delay cleanup and closure plans at several sites. For example, at Rocky 
Flats, approximately 1,000 cubic meters of mixed LLRW, intended for 
disposal at Hanford, instead had to be shipped off-site for commercial 
treatment, temporary storage, and eventual disposal at Envirocare of 
Utah to avoid delaying site cleanup; the Rocky Flats contractor 
estimates incremental storage, handling, treatment, and disposal costs 
of this LLRW may exceed $8 million. 

* In Nevada, as of August 2005, DOE was still awaiting approval from 
state regulators for a permit to dispose of, at the Nevada Test Site, 
mixed LLRW from other sites.[Footnote 26] After DOE filed its permit 
application in December 2000, Nevada objected to DOE's planned method 
of disposal. DOE is working with the state regulators to achieve a 
mutually agreeable resolution, and state officials indicate this issue 
could be resolved by the end of 2005. Until DOE receives this permit, 
DOE cannot dispose of mixed LLRW generated at other sites at the Nevada 
Test Site. 

* In 2004, the Nevada Attorney General objected to DOE's plan to ship 
certain LLRW from DOE's Fernald, Ohio, site for disposal at the Nevada 
Test Site, asserting in a letter to DOE that the plan violated federal 
law and regulations. Pending a resolution of these issues, DOE signed a 
$7.5 million contract in April 2005 with a commercial facility in Texas 
to temporarily store 6,800 cubic meters of this LLRW for up to 2 years. 

* Texas may provide DOE with additional storage options. In February 
2005, the state approved a license amendment for Waste Control 
Specialists to enlarge its LLRW storage facility. In addition, the 
state has begun a technical review of WCS's application for a LLRW 
disposal facility license, which could be issued by December 2007. 

Conclusions: 

Given the large volumes of LLRW generated by DOE activities, it is 
imperative that DOE recognize the importance of life-cycle cost 
analysis in identifying the most cost-effective alternatives for 
managing LLRW and then weighing the cost of these alternatives against 
noncost factors, such as safety and schedule. However, EM's July 2002 
guidance on life-cycle cost analysis did not include information on how 
or when such an analysis should be completed. Moreover, the department 
has not performed oversight to ensure that contractors are completing 
life-cycle cost analyses. EM has elected not to encourage the use of 
life-cycle cost analysis in making LLRW management decisions, relying 
instead on incentive-based contracts to ensure contractors are making 
cost-effective decisions. However, we believe that this contract 
mechanism does not necessarily ensure that contractors identify the 
lowest-cost LLRW management options. Without complete, well-documented 
life-cycle cost analysis, EM may be overlooking cost-saving 
opportunities that could have resulted from pursuing alternative 
disposal options. Furthermore, this lack of transparency diminishes 
confidence in DOE's ability to ensure that contractors have considered 
life-cycle costs, regardless of whether the lowest-cost alternative is 
selected. 

Although DOE has been disposing of LLRW for decades, it still lacks an 
integrated national strategy for doing so. Such a departmentwide 
strategy is crucial for ensuring that LLRW management needs throughout 
DOE are identified and addressed in a cost-effective manner that also 
meets other departmental goals, such as timely site cleanup. 
Specifically, an integrated approach could help consolidate similar 
types of LLRW to obtain economies of scale and lower per-unit disposal 
costs across the complex. DOE will need to develop basic information on 
LLRW volumes departmentwide and by program office, and to overcome the 
challenges posed by DOE's complex organization and multiple missions, 
and recent state actions. 

Recommendations for Executive Action: 

To promote cost-effective LLRW management, we are recommending that the 
Secretary of Energy take the following four actions: 

* Prepare comprehensive guidance on life-cycle cost analysis that, at a 
minimum, specifies (1) a systematic, consistent method of analyzing all 
cost elements or of comparing key alternatives within these cost 
elements to determine the lowest cost; (2) when and under what 
circumstances sites should prepare cost analyses; (3) relevant DOE 
orders, manuals, or other reference materials that should be consulted 
to provide consistent direction on how and when to perform the 
analysis; and (4) how final LLRW management decisions should be 
documented to demonstrate that life-cycle cost factors were adequately 
weighed against noncost factors, such as safety, health, or schedule. 

* Incorporate the revised life-cycle cost guidance into new or existing 
site contracts or into the departmental orders cited in those 
contracts. 

* Direct DOE to oversee contractors to ensure that site contractor 
officials properly use life-cycle cost analyses in evaluating LLRW 
management alternatives. 

* Actively promote and monitor the development of a timely, national 
LLRW management strategy that is based on departmentwide data on LLRW 
needing disposal, and ensure that the implementation of the strategy is 
fully carried out. 

Agency Comments and Our Evaluation: 

We provided DOE with a draft of this report for review and comment. 
Overall, DOE generally agreed with our conclusions and thanked us for 
the recommendations, but disagreed with or wanted to clarify certain 
statements in the draft report and provided technical comments, which 
we incorporated as appropriate. Specifically, DOE agreed that its sites 
are not consistently using life-cycle cost analysis in making LLRW 
management decisions. It also agreed that its current guidance and 
oversight in the area of life-cycle cost analysis for LLRW management 
decisions should be strengthened and noted that it is currently 
reevaluating its guidance documents and their implementation. In 
addition, DOE expressed appreciation for our support of an effective 
National Disposition Strategy for LLRW management, and expects this 
strategy to be available by March 2006. 

DOE also provided comments on several specific statements in our 
report. First, DOE disagreed with our statement on the lack of an 
effective, integrated approach for LLRW management at Oak Ridge and 
offered examples of integration, which we have incorporated into our 
report. Nonetheless, we found that not all LLRW activities at Oak Ridge 
were integrated into a sitewide LLRW management strategy. For example, 
NNSA officials told us their future need to decontaminate and 
decommission numerous buildings on the site had not yet been included 
in any sitewide LLRW management strategy. 

Second, in its technical comments, DOE stated that our discussion of 
the supercompactor at Oak Ridge was misleading and did not agree that 
cost savings would have been realized if the supercompactor had been 
retained and redeployed to another site. We believe that our discussion 
of the supercompactor is accurate. It was intended to illustrate the 
difficulty EM faces in developing a waste disposition strategy that 
covers multiple program offices. In its technical comments, DOE told us 
that the contractor at Oak Ridge completed a cost analysis and decided 
that the supercompactor should not be reused. Nevertheless, neither DOE 
nor contractor officials provided us with any documentation of a cost 
analysis to support the dismantling and disposition of the 
supercompactor. DOE also told us that the contractor who owned the 
supercompactor and Oak Ridge management "openly solicited" other 
contractors in the complex about potentially reusing the supercompactor 
but did not find any interest. However, NNSA officials at Oak Ridge 
told us that neither DOE nor the contractor consulted with them about 
the potential use of the supercompactor, and the contractor at Paducah 
told us that it might have benefited from the supercompactor but was 
not given the opportunity to consider alternatives to its disposal. 

Finally, DOE also stated that the lack of consistency that we found in 
implementing cost guidance and preparing formal documentation should 
not be interpreted to mean that the department's waste disposal systems 
are necessarily inefficient or overly expensive, and asserted that 
flexibility is needed in the level of detailed cost analysis required. 
However, we did not conclude that the lack of consistent implementation 
and the lack of documentation was indicative of an inefficient or 
overly costly LLRW management system. Rather, we stated that we could 
not determine how contractors incorporated costs analyses into their 
disposal decisions because documentation did not exist or was 
incomplete. Conclusions cannot be drawn about the cost-effectiveness of 
LLRW management decisions if contractors do not adequately document 
their decisions for not using life-cycle cost analysis and DOE does not 
require them to do so. While we would agree that flexibility may be 
important in determining the level of cost analyses required, we 
believe this flexibility should be accompanied by proper documentation 
to support the level of analysis completed and the degree to which life-
cycle cost principles were followed. 

DOE's comments on our draft report are presented in appendix II. 

We are sending copies of the report to the Secretary of Energy, the 
Director of the Office of Management and Budget, and appropriate 
congressional committees. We will make copies available to others on 
request. In addition, the report will also be available at no charge on 
the GAO Web site at [Hyperlink, http://www.gao.gov]. 

If you or your staff have any questions about this report, please call 
me at (202) 512-3841. Contact points for our Office of Congressional 
Relations and Public Affairs may be found on the last page of this 
report. Other staff contributing to this report are listed in Appendix 
III. 

Signed by: 

Gene Aloise, 
Director, Natural Resources and Environment: 

[End of section] 

Appendixes: 

Appendix I: Disposed Waste Volume by Major DOE Generator Sites, Fiscal 
Year 2004 through Second Quarter, Fiscal Year 2005: 

Waste volume in cubic meters. 

Generator site/contractor: Rocky Flats/Kaiser Hill; 
Total waste disposed off-site, fiscal year 2004: 118,460; 
Total waste disposed off-site, October 2004-March 2005: 63,940; 
Total waste disposed for 18-month period: 182,400. 

Generator site/contractor: Fernald/Fluor Fernald; 
Total waste disposed off-site, fiscal year 2004: 102,343; 
Total waste disposed off-site, October 2004-March 2005: 68,495; 
Total waste disposed for 18-month period: 170,838. 

Generator site/contractor: Mound/CH2M Hill, Mound; 
Total waste disposed off-site, fiscal year 2004: 43,554; 
Total waste disposed off-site, October 2004-March 2005: 55,534; 
Total waste disposed for 18-month period: 99,088. 

Generator site/contractor: Oak Ridge ETTP/BNFL; 
Total waste disposed off-site, fiscal year 2004: 37,502; 
Total waste disposed off-site, October 2004-March 2005: 9,278; 
Total waste disposed for 18-month period: 46,780. 

Generator site/contractor: Knolls Atomic Power Laboratory/Nuclear Fuel 
Services; 
Total waste disposed off-site, fiscal year 2004: 21,208; 
Total waste disposed off-site, October 2004-March 2005: 3,432; 
Total waste disposed for 18-month period: 24,640. 

Generator site/contractor: Oak Ridge Reservation/Bechtel Jacobs; 
Total waste disposed off-site, fiscal year 2004: 9,658; 
Total waste disposed off-site, October 2004-March 2005: 7,686; 
Total waste disposed for 18-month period: 17,344. 

Generator site/contractor: Portsmouth/Bechtel Jacobs; 
Total waste disposed off-site, fiscal year 2004: 11,038; 
Total waste disposed off-site, October 2004-March 2005: 3,644; 
Total waste disposed for 18-month period: 14,682. 

Generator site/contractor: Brookhaven National Lab/Brookhaven Science 
Associates; 
Total waste disposed off-site, fiscal year 2004: 4,199; 
Total waste disposed off-site, October 2004-March 2005: 8,436; 
Total waste disposed for 18-month period: 12,635. 

Generator site/contractor: Paducah/Bechtel Jacobs; 
Total waste disposed off-site, fiscal year 2004: 9,690; 
Total waste disposed off-site, October 2004-March 2005: 268; 
Total waste disposed for 18-month period: 9,958. 

Generator site/contractor: Oak Ridge National Laboratory/University of 
Tennessee/Battelle; 
Total waste disposed off-site, fiscal year 2004: 440; 
Total waste disposed off-site, October 2004-March 2005: 4,984; 
Total waste disposed for 18-month period: 5,424. 

Generator site/contractor: Ashtabula/RMI Titanium; 
Total waste disposed off-site, fiscal year 2004: 4,056; 
Total waste disposed off-site, October 2004-March 2005: 0; 
Total waste disposed for 18-month period: 4,056. 

Generator site/contractor: West Valley/West Valley Nuclear Services; 
Total waste disposed off-site, fiscal year 2004: 1,124; 
Total waste disposed off-site, October 2004-March 2005: 2,042; 
Total waste disposed for 18-month period: 3,166. 

Generator site/contractor: Oak Ridge Y-12/BWXT; 
Total waste disposed off-site, fiscal year 2004: 2,485; 
Total waste disposed off-site, October 2004-March 2005: 400; 
Total waste disposed for 18-month period: 2,885. 

Generator site/contractor: Remaining generator sites (27); 
Total waste disposed off-site, fiscal year 2004: 12,508; 
Total waste disposed off-site, October 2004-March 2005: 5,461; 
Total waste disposed for 18-month period: 17,969. 

Total; 
Total waste disposed off-site, fiscal year 2004: 378,265; 
Total waste disposed off-site, October 2004-March 2005: 233,600; 
Total waste disposed for 18-month period: 611,865. 

Source: DOE waste generator sites and EM headquarters. 

Note: We identified 40 Department of Energy (DOE) waste generators for 
the period we examined. We list in this table the 13 generators with 
the highest volume of waste disposed off-site during this period. These 
13 generators accounted for over 97 percent of DOE's low-level 
radioactive waste (LLRW) volume disposed of off-site for the 18-month 
period. 

[End of table] 

[End of section] 

Appendix II: Comments from the Department of Energy: 

Department of Energy: 
Washington, DC 20585: 

October 14, 2005: 

Mr. Gene Aloise: 
Director: 
Natural Resources and Environment Team: 
U.S. Government Accountability Office: 
Washington, D.C. 20548: 

Dear Mr. Aloise: 

The purpose of this letter is to inform you that my office has reviewed 
the draft report entitled Department of Energy: Improved Guidance, 
Oversight, and Planning Are Needed to Better Identify Cost-Saving 
Alternatives for Managing Low-Level Radioactive Waste (GAO-06-94). This 
letter provides the Department's consolidated comments on the report; 
it has been coordinated with staff in the Office of Science; Office of 
Nuclear Energy, Science, and Technology; and the National Nuclear 
Security Administration. 

The information in the report validates our current efforts to improve 
the integration and management of low-level radioactive waste 
activities within the Department complex. Thank you for the 
recommendations provided in the report. 

We generally agree with your conclusions that our sites are not 
consistently using life-cycle cost analyses as they make waste disposal 
decisions. As you are well aware, cost is an important factor, but not 
the only factor considered in these decisions. We also acknowledge that 
our existing guidance and oversight in the area of life-cycle cost 
analysis for low-level radioactive waste disposal decisions should be 
strengthened, and we are currently re-evaluating the current guidance 
documents and their implementation. I especially appreciate your 
endorsement of our ongoing project to develop a National Disposition 
Strategy for low-level radioactive waste management. We plan to have 
the first phase of this Strategy available to the public by the end of 
March 2006. 

The enclosure provides our general and specific comments on the draft 
report. While we agree with the report's conclusions, we disagree with 
or wish to clarify many of the specific statements in the draft report. 
For example, we disagree with the draft report's statements regarding 
the lack of an effective, integrated approach for low-level radioactive 
waste management at Oak Ridge and the potential for reuse and 
disposition of a supercompactor brought to that site under a fixed- 
price contract. Furthermore, lack of consistency on implementation of 
cost guidance between sites and formal documentation should not be 
interpreted to mean the Department's waste disposal systems are 
necessarily inefficient or overly expensive. We feel strongly that the 
nature of the waste disposal options and details of a site's waste 
management challenge must be considered when determining the level of 
detailed cost analyses required and plan to revise our guidance to 
provide such flexibility. I hope our clarification provides you with an 
improved understanding of the factors we consider in developing and 
implementing waste management strategies and our overall efforts to 
address the environmental contamination resultant from the Department's 
national security legacy. 

If you have any questions, please contact Mr. Frank Marcinowski, Deputy 
Assistant Secretary for Logistics and Waste Disposition Enhancements, 
within the Office of Environmental Management. He can be reached at 
(202) 586-0370. 

Sincerely, 

Signed for: 

James A. Rispoli: 
Assistant Secretary for Environmental Management: 

Enclosure: 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Gene Aloise (202) 512-3841: 

Staff Acknowledgments: 

In addition to the individual named above, Daniel Feehan, Doreen 
Feldman, Thomas Kingham, Mehrzad Nadji, Omari Norman, Christopher 
Pacheco, Judy Pagano, Carol Herrnstadt Shulman, and Peter Zwanzig made 
key contributions to this report. 

(360488): 

FOOTNOTES 

[1] This volume is only for waste disposed of at off-site locations. 
Additional LLRW is disposed of at the DOE sites where it is generated. 

[2] Throughout this report, references to low-level radioactive waste 
also include mixed waste, unless otherwise specified. 

[3] GAO, Low-Level Radioactive Wastes: Department of Energy Has 
Opportunities to Reduce Disposal Costs, GAO/RCED-00-64 (Washington, 
D.C.: Apr. 12, 2000). 

[4] H.R. Rep. No. 107-112, at 135 (2001). A congressional conference 
committee later issued a similar directive. H.R. Rep. No. 107-258, at 
133 (2001). 

[5] Department of Energy, Report to Congress, The Cost of Waste 
Disposal: Life-Cycle Cost Analysis of Disposal of Department of Energy 
Low-Level Radioactive Waste at Federal and Commercial Facilities 
(Washington, D.C.: July 2002). 

[6] Results of nonprobability samples cannot be used to make inferences 
about a population because in a nonprobability sample some elements of 
the population being studied have no chance or an unknown chance of 
being selected as part of the sample. 

[7] We did not use information on LLRW volumes sent to DOE's Hanford 
disposal site to select waste generators for site visits. Hanford's 
disposal site accounted for less than 1 percent of DOE's off-site LLRW 
disposal volume in fiscal year 2004. 

[8] 42 U.S.C. § 2021c(b). 

[9] Sites with on-site disposal facilities include the Fernald 
Environmental Management Project (in Ohio), Hanford in Washington, 
Idaho National Laboratory, Los Alamos National Laboratory in New 
Mexico, Nevada Test Site, Savannah River Site in South Carolina, and 
the Oak Ridge site in Tennessee. 

[10] Currently, Envirocare of Utah is the primary commercial option 
available for disposal of DOE's LLRW. 

[11] GAO/RCED-00-64. 

[12] GAO, Nuclear Cleanup: DOE Should Reevaluate Waste Disposal Options 
Before Building New Facilities, GAO-01-441 (Washington, D.C.: May 
2001). 

[13] H.R. Rep. No. 107-112, at 135 (2001). A congressional conference 
committee later issued a similar directive. H.R. Rep. No. 107-258, at 
133 (2001). 

[14] Department of Energy, Cost Estimating Guide, DOE G 430.1-1 
(Washington, D.C.: Mar. 28, 1997). 

[15] A handbook, most recently updated in 1996, helps explain the 
methodologies used in conducting life-cycle cost analysis. (Department 
of Commerce, Life-Cycle Costing Manual for the Federal Energy 
Management Program, NIST Handbook 135, 1995 Edition, Washington, D.C.: 
February 1996). In addition, guidance prepared in April 2005 clarifies 
how DOE should determine life-cycle costs for energy programs, as 
required by section 401 of Executive Order 13123. (National Institute 
of Standards and Technology [Prepared for DOE], Guidance on Life-Cycle 
Cost Analysis Required by Executive Order 13123, Gaithersburg, 
Maryland: National Institute of Standards and Technology, April 2005). 

[16] H.R. Rep. No. 107-258, at 133 (2001). The five sites expanding 
their on-site disposal facilities since 2002 included the On-Site 
Disposal Facility at Fernald (Ohio), the Idaho CERCLA Disposal Facility 
at the Idaho National Laboratory, the TA-54 On-Site Disposal Facility 
at the Los Alamos National Laboratory, the Environmental Management 
Waste Management Facility at Oak Ridge, Tennessee, and the Engineered 
Trenches at the Savannah River Site in South Carolina. 

[17] DOE G 430.1-1. 

[18] H. R. Rep. No. 109-86, at 147-148 (2005). 

[19] H.R. Rep. No. 109-86, at 151 (2005). 

[20] In accordance with 50 U.S.C. § 2622, the Office of River 
Protection was established in 1998 to manage the Department of Energy's 
largest, most complex environmental cleanup project: Hanford tank waste 
retrieval, treatment, and disposal. 

[21] In 2005, BNFL changed its name to British Nuclear Group of 
America. 

[22] Washington asserted, among other things, that DOE did not comply 
with the National Environmental Policy Act of 1969 and implementing 
regulations. 

[23] Washington v. Bodman, 2005 WL 1130294 (E.D. Wash. May 13, 2005). 

[24] Initiative 297, the Cleanup Priority Act, is now codified in 
chapter 70.105E of the Revised Code of Washington. 

[25] United States v. Hoffman, No. CV-04-5128-AAM (E.D. Wash. filed 
Dec. 1, 2004). The U.S. district court certified questions of state law 
to the Washington Supreme Court, which issued its ruling on July 28, 
2005. United States v. Hoffman, 116 P.3d 999 (Wash. 2005). 

[26] At the Nevada Test Site, the hazardous components of mixed wastes 
are regulated by the State of Nevada under the Resource Conservation 
and Recovery Act of 1976, as amended. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: