This is the accessible text file for GAO report number GAO-05-173 
entitled 'Federal-Aid Highways: FHWA Needs a Comprehensive Approach to 
Improving Project Oversight' which was released on February 1, 2005.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Chairman, Committee on Transportation and Infrastructure, 
House of Representatives: 

January 2005: 

Federal-Aid Highways: 

FHWA Needs a Comprehensive Approach to Improving Project Oversight: 

GAO-05-173: 

GAO Highlights: 

Highlights of GAO-05-173, a report to the Chairman, Committee on 
Transportation and Infrastructure, House of Representatives: 

Why GAO Did This Study: 

The federal-aid highway program provides over $25 billion a year to 
states for highway and bridge projects, often paying 80 percent of 
these projects’ costs. The federal government provides funding for and 
oversees this program, while states largely choose and manage the 
projects. Ensuring that states effectively control the cost and 
schedule performance of these projects is essential to ensuring that 
federal funds are used efficiently. 

We reviewed the Federal Highway Administration’s (FHWA) approach to 
improving its federal-aid highway project oversight efforts since we 
last reported on it in 2002, including (1) FHWA’s oversight-related 
goals and performance measures, (2) FHWA’s oversight improvement 
activities, (3) challenges FHWA faces in improving project oversight, 
and (4) best practices for project oversight.

What GAO Found: 

FHWA has made progress in improving its oversight efforts since 2002, 
but it lacks a comprehensive approach, including goals and measures 
that guide its activities; workforce plans that support these goals and 
measures; and data collection and analysis efforts that help identify 
problems and transfer lessons learned. FHWA’s 2004 performance plan 
established, for the first time, performance goals and outcome measures 
to limit cost growth and schedule slippage on projects, but these goals 
and measures have not been effectively implemented because FHWA has not 
linked its day-to-day activities or the expectations set for its staff 
to them, nor is FHWA fully using them to identify problems and target 
its oversight. 

FHWA undertook activities in response to concerns raised about the 
adequacy of its oversight efforts that have both promising elements and 
limitations. For example, while FHWA now assigns a project oversight 
manager to each major project (generally projects costing $1 billion or 
more) and identified skills these managers should possess, it has not 
yet defined the role of these managers or established agencywide 
performance expectations for them. While FHWA issued guidance to 
improve cost estimating and began collecting information on cost 
increases, it still does not have the capability to track and measure 
cost growth on projects. Finally, although FHWA received direction to 
develop a more multidisciplinary workforce to conduct oversight, it has 
not fully incorporated this direction into its recruiting and training 
efforts.

FHWA faces challenges to improving its oversight that are in large part 
rooted in the structure of the federal-aid highway program and in 
FHWA’s organization and culture. As such, they may be difficult to 
surmount. For example, because the program does not link funding to 
states with the accomplishment of performance goals and outcome 
measures, it may be difficult for FHWA to define the role and purpose 
of its oversight. Also, FHWA’s decentralized organization makes it 
difficult to achieve a consistent organizational vision. Human capital 
challenges affecting much of the federal government have affected FHWA, 
particularly in its need to transform its workforce to meet its 
evolving oversight mission. FHWA faces an increased oversight workload 
in the years ahead as the number of major projects grows and if 
provisions Congress is considering to increase FHWA’s responsibilities 
become law. Questions exist about FHWA’s ability to effectively absorb 
these new responsibilities, overcome underlying challenges, and improve 
its oversight.

We identified selected best practices that could help FHWA develop a 
framework for a comprehensive approach to project oversight. These 
include establishing measurable goals to objectively and quantifiably 
assess progress, making oversight managers accountable for the 
effective implementation of these goals, providing professional 
training, and collecting and transferring lessons learned.

What GAO Recommends: 

GAO recommends that FHWA link its activities and staff expectations to 
its oversight goals and measures, develop an overall plan for its 
oversight activities tied to goals and measures and supported in 
workforce plans, define the role of project managers, and develop the 
capability to track project costs to identify problems and transfer 
lessons learned. DOT generally agreed with this report’s facts and 
conclusions. 

www.gao.gov/cgi-bin/getrpt?GAO-05-173.

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Kate Siggerud at (202) 
512-6570 or siggerudk@gao.gov.

[End of section]

Contents: 

Letter: 

Results In Brief: 

Background: 

FHWA Established Some Oversight Goals and Measures but Has Not 
Effectively Implemented Them: 

FHWA's Oversight Activities Have Promising Elements and Limitations: 

FHWA Faces Challenges to Improving Oversight: 

Best Practices Can Help Improve Progress and Address Challenges to 
Improving Project Oversight: 

Conclusions: 

Recommendations: 

Agency Comments: 

Appendixes: 

Appendix I: Scope and Methodology: 

Appendix II: FHWA FY 2004 Major Project Team Work Plan Summary: 

Appendix III: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Staff Acknowledgements: 

Table: 

Table 1: Types of Projects Receiving FHWA Oversight versus State 
Oversight: 

Figures: 

Figure 1: Stages of a Highway or Bridge Project and State and FHWA 
Roles and Approval Actions: 

Figure 2: Goals and Associated Measures Articulated In FHWA's 2004 
Performance Plan: 

Abbreviations: 

AASHTO: American Association of State Highway and Transportation 
Officials: 

DOT: Department of Transportation: 

FHWA: Federal Highway Administration: 

FMIS: Financial Management Information System: 

FTA: Federal Transit Association: 

GPRA: Government Performance and Results Act of 1993: 

ISTEA: Intermodal Surface Transportation Efficiency Act of 1991: 

OIG: Office of Inspector General: 

OMB: Office of Management and Budget: 

PDP: professional development program: 

TEA-21: Transportation Equity Act for the 21st Century: 

Letter January 31, 2005: 

The Honorable Don Young: 
Chairman, 
Committee on Transportation and Infrastructure: 
House of Representatives: 

Dear Mr. Chairman: 

The federal-aid highway program provides over $25 billion a year to 
states for highway and bridge projects, often paying 80 percent of 
these projects' costs. The program is federally financed and state 
administered; that is, the federal government provides funding and 
oversees the program, while the states largely choose and manage the 
projects. These projects can take years of planning and environmental 
review, as well as the time spent in the design and construction 
phases. With highway congestion projected to worsen over the next 20 
years and freight traffic expected to double, widespread consensus 
exists on the need to maintain and improve the nation's surface 
transportation infrastructure. In the longer term, broader fiscal 
challenges face the nation, including federal and state budget deficits 
and a fiscal crisis looming as the baby boom generation retires, 
causing mandatory commitments to Social Security and Medicare to 
consume a greater share of the nation's resources, squeezing funding 
available for domestic discretionary programs. Thus, ensuring that 
states effectively manage and control the cost and schedule performance 
of federally-aided projects, and that federal funds are used 
efficiently and effectively, is critical in light of these challenges.

The Federal Highway Administration (FHWA), under the Department of 
Transportation (DOT), is responsible for overseeing the federal-aid 
highway program through its headquarters in Washington, D.C., and 
division offices located in every state, the District of Columbia, and 
Puerto Rico. To carry out this role, FHWA reviews and approves the 
transportation plans and environmental impact assessments that states 
periodically prepare, reviews and approves states' property acquisition 
activities; and enforces a variety of requirements, such as civil 
rights laws, that states accept as a condition of federal aid. FHWA 
also oversees the design and construction of federally-aided projects, 
but this oversight has evolved over the years and currently focuses on 
two broad areas: (1) for selected projects, direct review and approval 
of state design plans, contract awards, and construction progress; and 
(2) reviews of state management processes, also known as process 
reviews, to ensure that the states have adequate controls to 
effectively manage federally-assisted projects. FHWA also enforces 
requirements for "major projects"--generally those projects estimated 
to cost over $1 billion--such as reviewing and approving annual finance 
plans required by law for these projects.

We and others have raised concerns regarding FHWA's oversight of the 
federal-aid highway program. For example, from 1997 to 2002, we 
highlighted several problems, including the lack of a link between 
FHWA's oversight activities and its business goals; a lack of emphasis 
on FHWA's part to ensuring that containing costs is an integral part of 
states' project management; a lack of useful cost estimates, which 
typically have not been reliable predictors of the total costs or 
financing needs of projects; and a lack of information on the amount of 
and reasons for cost increases. In particular, we have highlighted the 
challenges that major, multibillion-dollar projects pose. These 
projects are very costly and complex--they require large commitments of 
public resources that may take several years to garner; can involve 
complicated financing arrangements; can be technically challenging to 
construct; and involve a wide range of social, environmental, land-use, 
and economic challenges before and during construction. To keep the 
projects on schedule and within budget, federal and state officials 
must carefully oversee their development, planning, and construction.

We also recognized actions Congress, DOT, and FHWA have taken to 
improve FHWA's oversight in response to concerns raised about its 
efforts. For example, in 1998, Congress required that states submit to 
the Secretary of Transportation an annual finance plan for major 
projects, which was intended to help provide an advance warning system 
for increased costs for large transportation projects receiving federal 
funds. In 2001, FHWA took steps to improve its oversight of these major 
projects by, among other things, establishing a major projects team to 
coordinate and implement oversight policies for major projects and 
designating project oversight managers to oversee these projects. In 
addition, for its reviews of state management processes, FHWA also 
began to conduct more risk assessments to identify and prioritize risk 
areas and allocate resources.

FHWA will face an increased oversight workload in the years ahead if 
provisions Congress is considering become law and as the number of 
federal-aid projects grows. In 2003, DOT proposed legislation for the 
reauthorization of the Transportation Equity Act for the 21st Century 
(TEA-21) that would increase FHWA's oversight responsibilities by 
requiring FHWA to annually review states' financial management 
processes and to periodically review how states plan and manage 
projects. The legislation would also extend certain oversight 
requirements that currently pertain only to major projects, to other 
large-dollar projects as well. This proposal was largely adopted in 
bills that were separately approved by the House and Senate in 2004, 
but which were not enacted before the adjournment of the 108TH 
Congress. In addition, during the course of our review, the number of 
major projects FHWA is responsible for overseeing increased from 15 to 
21, and that number is expected to nearly double to 40 in the next 
several years.

At your request, we reviewed FHWA's approach to improving its federal-
aid highway project oversight efforts since 2002, including (1) FHWA's 
oversight-related performance goals and measures, (2) FHWA's oversight 
improvement activities, (3) challenges FHWA faces in improving project 
oversight, and (4) best practices for project oversight.

To determine FHWA's approach to improving its oversight efforts since 
2002, the last time we reported on this issue, we evaluated the 
agency's strategic and performance plans, and supporting documents. 
Furthermore, we documented and analyzed the status of FHWA's various 
project oversight efforts. We interviewed officials at FHWA 
Headquarters and selected FHWA division offices, state departments of 
transportation, and others to document oversight implementation efforts 
and the challenges FHWA faces in improving its project oversight. We 
also reviewed FHWA's use of financial information from its Financial 
Management Information System (FMIS) to track and analyze trends in 
cost growth on projects. We did not independently assess the 
reliability of FMIS data as the Department's Inspector General has 
reported on weaknesses in FHWA's financial management and reporting 
processes, most recently in November 2004 as part of the annual audit 
of DOT's consolidated financial statements. In addition, our work 
focused primarily on FHWA's use of FMIS data for oversight purposes, 
rather than relying on FMIS data to support our findings and 
conclusions.

To provide information on project management best practices we 
conducted a literature search to identify best practices related to 
project oversight and evaluated their applicability to FHWA's oversight 
efforts. We conducted our work from August 2003 through December 2004 
in accordance with generally accepted government audit standards. 
Appendix I provides the details of our scope and methodology.

Results in Brief: 

FHWA has made progress in improving its oversight efforts since 2002, 
but it lacks a comprehensive approach to project oversight, including 
oversight-focused goals and outcome measures that guide its activities; 
an overall plan for its oversight activities that responds to past 
concerns and is linked to these goals and measures; workforce planning 
efforts that support these goals and measures; and data collection and 
analysis efforts that identify problems, help target resources, and 
transfer lessons learned. FHWA's 2004 performance plan established, for 
the first time, performance goals and outcome measures to limit the 
magnitude of cost growth and schedule slippage for major projects, but 
these goals and measures have not been effectively implemented because 
FHWA has not linked the day-to-day oversight activities of its division 
offices or the expectations set for its staff to them. For example, 
none of the three division offices we visited that are currently 
overseeing major projects had established any link in its unit 
performance plan between its activities and FHWA's goal and measure to 
limit cost increases and schedule slippage on major projects. FHWA also 
established performance goals and measures to contain costs on projects 
other than major projects, but it is not yet using these goals to 
identify problems on a state-by-state or project-by-project basis in 
order to target its oversight activities. FHWA also uses cost and 
schedule estimates developed relatively late in a project's 
development--at the point at which the project is ready to go to 
construction--as a baseline for measuring its progress in limiting cost 
growth. However, by the time a project goes to construction, a public 
investment decision has effectively been made, as substantial funds 
will have been spent on designing the project and acquiring property, 
and much of the increases in a project's costs may have already 
occurred.

In response to concerns raised about the adequacy of its oversight 
efforts, FHWA undertook a series of oversight-related activities that 
have both promising elements and limitations. For example, FHWA now 
routinely assigns a project oversight manager to each major project. It 
established core competencies identifying the skills that project 
oversight managers should possess, which are to serve as a guide for 
selecting these managers. However, FHWA has not yet defined the role of 
project oversight managers or established agency-wide performance 
expectations for them. Instead, expectations for this position were 
developed locally at division offices, and none of the three division 
offices' expectations for oversight managers that we reviewed 
specifically tasked the manager with achieving FHWA's goals and 
measures to limit cost increases and schedule slippage. Without this 
link between performance expectations and goals, it is unclear how the 
project oversight managers will improve oversight of major projects and 
what training and development are needed to achieve the desired 
performance. In another positive step, in June 2004, FHWA issued 
guidance to state transportation agencies to assist them in applying 
sound cost estimating practices, including guidance on developing more 
realistic early cost estimates. However, this guidance is voluntary and 
applies only to major projects, and it is too soon to tell whether it 
will be effective in improving the quality of estimates. DOT proposed 
legislation empowering FHWA to develop national standards for 
estimating project costs, which was included in the surface 
transportation reauthorization bills separately passed by the House and 
the Senate in 2004, but which were not enacted before the adjournment 
of the 108TH Congress. FHWA also started tracking information on the 
cost growth of major projects, and it recently started developing some 
cost information on all federal-aid highway projects over $10 million. 
However, FHWA still does not have the capability to track and measure 
cost growth on projects it oversees, which limits its ability to 
evaluate the reasons why cost growth occurs, identify problems and 
solutions, and transfer lessons learned. FHWA has also incorporated 
more risk assessments into its process reviews of state transportation 
agencies, but we found that some division offices are not using their 
risk assessments to guide their reviews. The DOT Inspector General 
recently reported that FHWA's risk assessments were voluntary and did 
not provide a systematic approach for assessing program risks 
throughout the agency. Finally, although FHWA received congressional-
committee direction to restructure its workforce to develop a 
multidisciplinary approach to oversight, it has made limited progress 
in doing so, as it has not fully incorporated such an approach into its 
human capital planning, recruiting, or training efforts.

FHWA faces several challenges to improving its oversight--challenges 
rooted in the structure of the federal-aid highway program as well as 
FHWA's organization and culture--that may be difficult to surmount. The 
federal-aid highway program provides states with broad flexibility in 
the use of federal funds. Although DOT has articulated goals for the 
program such as improving safety and reducing the growth of traffic 
congestion, the program does not have the mechanisms to link funding 
levels with the accomplishment of specific performance-related goals 
and outcomes. As a result, it may be difficult for FHWA to define its 
role and the purpose of its oversight. FHWA's long-standing culture of 
partnership with the states also poses challenges; FHWA and state 
officials believe this partnership has helped to build trust and 
respect between the state agencies and FHWA and has resulted in 
projects being planned and built more efficiently and effectively. 
However, there is a potential downside--when a project overseer becomes 
an active partner in a project, the arms-length, independent 
perspective that can be important to effective project oversight can be 
lost. Another challenge is FHWA's decentralized organization, which can 
make implementing a consistent oversight vision and strategies 
throughout FHWA difficult. Human capital challenges that affect much of 
the federal government have also affected FHWA's ability to improve its 
oversight, particularly in its need to transform its workforce and 
culture to support its evolving oversight mission. Finally, FHWA 
officials said that a challenge to improving oversight is that 
legislation passed in 1991 and 1998 has, in their view, sent mixed 
messages regarding FHWA's and states' roles, leading to confusion as to 
the extent of FHWA's authority and responsibilities over state-managed 
highway projects. Language in reauthorization legislation proposed by 
DOT and separately passed by the House and the Senate in 2004 but not 
enacted may help clarify FHWA's oversight role if it is reintroduced 
and enacted by the 109TH Congress.

We identified selected best practices that are relevant to FHWA's 
efforts to improve project oversight through analyzing our past work on 
effectively managing and overseeing projects, as well as reports by the 
National Research Council, the Office of Management and Budget (OMB), 
and others. While some of these best practices are beginning to be 
reflected in FHWA's activities, as a whole, they could provide a 
framework for moving to a comprehensive approach to project oversight. 
The best practices we identified include (1) establishing measurable 
project oversight goals and communicating these goals down through all 
levels of the agency; (2) establishing project oversight manager roles, 
responsibilities, and accountability measures based on oversight goals; 
(3) providing professional training and a career path in oversight 
management; and (4) identifying and transferring lessons learned. 
Establishing measurable project oversight goals and communicating these 
goals down through all levels of an agency illustrates how an agency 
will execute its oversight mission and establishes what its oversight 
is designed to accomplish. Establishing oversight manager roles, 
responsibilities, and accountability measures based on oversight goals 
links efforts to goals and makes managers accountable for proper 
project oversight. Providing professional training in oversight 
management could ensure that managers develop the skills necessary for 
conducting their oversight activities. Providing a career path would 
allow project managers to develop their abilities as they progress 
through increasingly challenging assignments. Identifying lessons 
learned from the successes and setbacks that occur on projects--and 
transferring those lessons to other projects--can prevent mistakes from 
being repeated and promote improved oversight.

FHWA will face an increased oversight workload in the years ahead if 
provisions Congress is considering become law and as the number of 
federal-aid projects grows. Given the limitations present in FHWA's 
oversight approach today, questions exist about its ability to 
effectively absorb new responsibilities and to improve its oversight 
efforts over federal-aid highway projects in the years ahead. Moreover, 
absent a comprehensive approach, FHWA is unlikely to overcome the 
structural, organizational, and cultural challenges it faces and to 
fully address the concerns raised about the adequacy of its oversight 
efforts. To address these limitations, we are recommending that FHWA 
link its day-to-day activities and the expectations set for its staff 
to its goals and outcome measures; develop an overall plan for its 
oversight initiatives that is tied to its oversight-related goals and 
measures; improve the use and performance of project oversight managers 
by centrally defining their role and responsibilities; and develop the 
capability to track and measure costs over the lives of projects to 
identify problems, help target resources, and transfer lessons learned.

We provided a draft of this report to DOT and met with FHWA officials, 
including the Deputy Administrator, to obtain their comments on the 
draft. FHWA generally agreed with the facts and conclusions in the 
report and our characterization of the challenges FHWA faces in 
improving its project oversight. FHWA officials emphasized that 
although we highlighted potential drawbacks associated with both its 
culture of partnership with the states and its decentralized 
organization, this partnership and organization are also major 
strengths of the federal-aid highway program that will allow the agency 
to absorb potential new responsibilities, help overcome challenges, and 
improve program oversight in the future through a more comprehensive 
approach. FHWA officials did not take a position on our 
recommendations, but they stated that they would be taking them under 
advisement. They also suggested some technical and clarifying comments 
that we incorporated into the report as appropriate.

Background: 

Federal funding for highways is provided to the states mostly through a 
series of formula grant programs collectively known as the federal-aid 
highway program. Periodically, Congress enacts multiyear legislation 
that authorizes the nation's surface transportation programs, including 
highways, transit, highway safety, research, and motor carrier 
programs. In 1998 Congress enacted TEA-21, which authorized $172.4 
billion for the federal-aid highway program from fiscal years 1998 
through 2003. The program expired on September 30, 2003, and it has 
been extended by six short-term extensions, the most recent extending 
the program until May 31, 2005. During the 108TH Congress, both the 
House and Senate approved separate legislation to reauthorize the 
federal-aid highway program; however, the reauthorization legislation 
was not been enacted before the adjournment of the 108THCongress. The 
bill approved by the House authorized $226.3 billion for the federal-
aid highway program for fiscal years 2004 through 2009, an increase of 
about 31 percent over TEA-21, while the bill approved by the Senate 
authorized $256.4 billion, an increase of about 49 percent.[Footnote 1] 
Because both bills contained funding increases, it is likely that the 
number of federal-aid highway projects will rise in the next several 
years.

FHWA administers the federal-aid highway program and distributes most 
highway funds to the states through annual apportionments established 
by statutory formulas contained in law. Once FHWA apportions these 
funds, they are available to be obligated for construction, 
reconstruction, and improvement of highways and bridges on eligible 
federal-aid highway routes and for other purposes authorized in law. 
About 1 million of the nation's 4 million miles of roads are eligible 
for federal aid; including the 161,000 mile National Highway System, of 
which the 47,000 mile Interstate Highway System is a part.[Footnote 2] 
While FHWA administers the program, the responsibility for choosing 
projects generally rests with state departments of transportation and 
local planning organizations. The states have considerable discretion 
in selecting specific highway projects and in determining how to 
allocate available federal funds among the various projects they have 
selected. For example, section 145 of title 23 of the United States 
Code describes the federal-aid highway program as a federally-assisted 
state program and provides that the federal authorization of funds, as 
well as the availability of federal funds for expenditure, shall not 
infringe on the states' sovereign right to determine the projects to be 
federally financed.

A highway or bridge construction or repair project usually has four 
stages: (1) planning, (2) environmental review, (3) design and property 
acquisition, and (4) construction. FHWA reviews and approves long-term 
and short-term state transportation plans and programs, environmental 
documents,

and the acquisition of property for all highway projects.[Footnote 3] 
However, its role in overseeing the design and construction of projects 
varies. On selected projects, FHWA exercises what is often considered 
"full" oversight, meaning that FHWA (1) prescribes design and 
construction standards, (2) approves design plans and estimates, (3) 
approves the selection of the contract award, (4) periodically inspects 
the progress of construction, and (5) renders final acceptance on 
projects when they are completed. However, relatively few projects are 
subject to this full FHWA oversight. The last two authorizations, the 
Intermodal Surface Transportation Efficiency Act of 1991 (ISTEA) and 
TEA-21, devolved an increasing amount of responsibility to the states. 
Under current law FHWA exercises full oversight of certain high-cost 
interstate system projects, while states oversee design and 
construction on other federal-aid projects.

The stages of a highway or bridge project and the corresponding state 
role and FHWA approval actions are shown in figure 1.

Figure 1: Stages of a Highway or Bridge Project and State and FHWA 
Roles and Approval Actions: 

[See PDF for image] 

[End of figure] 

The types of projects for which FHWA exercises full oversight as 
compared with state oversight are shown in table 1.

Table 1: Types of Projects Receiving FHWA Oversight versus State 
Oversight: 

Type of project: Interstate System; 
Mileage: 47,000; 
Percent of federal highway funds obligated in 2002: 12; 
Design and construction oversight: FHWA oversight; 
Exceptions: Certain types of projects, or projects below a dollar 
threshold, where FHWA and state determine state oversight is 
appropriate.

Type of project: National Highway System, non-Interstate routes; 
Mileage: 115,000; 
Percent of federal highway funds obligated in 2002: 45; 
Design and construction oversight: State may assume oversight; 
Exceptions: State or FHWA determines state oversight is not 
appropriate.

Type of project: Federal-aid highways off the National Highway System; 
Mileage: 798,000; 
Percent of federal highway funds obligated in 2002: 42; 
Design and construction oversight: State shall assume oversight; 
Exceptions: State determines state oversight is not appropriate. 

Source: GAO analysis.

[End of table]

According to FHWA, the agency retains the responsibility to oversee all 
federally-aided highway and bridge projects, including projects for 
which FHWA does not exercise oversight over the design and construction 
phases. FHWA conducts oversight of state transportation programs 
through a variety of means, including process reviews--reviews of state 
management processes to ensure that states have adequate controls to 
effectively manage federally-assisted projects. States and FHWA execute 
stewardship and oversight agreements to define their respective 
oversight responsibilities.

TEA-21 contains an additional oversight requirement for so-called 
"major projects"--generally those estimated to cost at least $1 
billion. Since TEA-21 was enacted in 1998, states must submit finance 
plans to DOT annually for such projects, based on detailed estimates of 
the costs to complete the project and on reasonable assumptions about 
future increases in such costs. FHWA developed guidance that requires 
states to include in these finance plans a total cost estimate for the 
project, adjusted for inflation and annually updated; estimates about 
future cost increases; a schedule for completing the project; a 
description of construction financing sources and revenues; a cash flow 
analysis; and a discussion of other factors, such as how the project 
will affect the rest of the state's highway program. FHWA approves 
these plans as a condition of federal aid. As of November 2004, 11 of 
the 21 current major projects had finance plans. Approved finance plans 
will be required for the other projects prior to FHWA authorizing 
federal funds for construction.[Footnote 4] FHWA forecasts that another 
19 major projects, estimated to cost from $34 billion to $60 billion, 
will be starting over the next several years and will also require 
finance plans.

Over the past several years, we and others have identified problems 
with FHWA's oversight of major projects and other large highway and 
bridge projects. For example, in 1997, we reported that the overall 
amount of and reasons for cost increases on highway and bridge projects 
could not be determined because data were not readily available from 
FHWA or the states.[Footnote 5] We found, however, on many of the 
projects for which we could obtain information, that costs had 
increased, sometimes significantly, and that several factors accounted 
for the increases. In addition, initial cost estimates were not 
reliable predictors of a project's total cost or financing needs 
because they were developed at the environmental review stage, and 
their purpose was to compare project alternatives, not to develop 
reliable cost estimates. We further reported that cost containment was 
not an explicit statutory or regulatory goal of FHWA's oversight; 
therefore, the agency had done little to ensure that cost containment 
was an integral part of the states' project management. In our May 2002 
testimony before the Highways, Transit, and Pipelines Subcommittee of 
your Committee, we reported that FHWA had begun to improve its 
oversight by implementing Congress' finance plan requirements for major 
projects and introducing risk-based decision making into its oversight 
of states' processes on other projects.[Footnote 6] However, we also 
reported that FHWA had not yet developed performance goals or 
measurable outcomes linking its oversight activities to its business 
goals, and that goals and strategies for containing costs could improve 
accountability and make cost containment an integral part of how states 
manage projects over time. Furthermore, we stated that opportunities 
existed for improving the quality of cost estimating and developing 
reliable and accurate information on the extent and nature of projects' 
cost performance to help direct federal oversight efforts. Our work 
identified several options for enhancing the oversight of major 
projects. Reports by DOT's Office of Inspector General, as well as 
reviews by state audit and evaluation agencies, have also shown that 
the escalating costs and management of major projects continue to be a 
problem. For example, the Inspector General has issued several reports 
on FHWA's oversight and stewardship of major projects, such as the 
Central Artery/Tunnel project in Massachusetts and the Woodrow Wilson 
Bridge in Virginia and Maryland. More recently, the Inspector General 
reported signs of improvement in FHWA's stewardship over major projects 
but identified improvements needed in eight areas, including developing 
more reliable cost estimates, managing project schedules better, 
strengthening efforts to prevent and detect fraud, and refocusing 
FHWA's efforts on project management and financial oversight.[Footnote 
7]

Partly in response to concerns that we and others have raised, in 
addition to the provisions Congress enacted in TEA-21, DOT also took 
further action. In 2000 the Secretary of Transportation established a 
task force to review oversight mechanisms and processes for major 
transportation projects across DOT. Among other things, the task force 
recommended that DOT improve the skills and qualifications of staff 
overseeing major projects and conduct more rigorous financial reviews 
of such projects. Although DOT did not formally implement the task 
force's recommendations, FHWA responded to the task force report by 
establishing a major projects team in Washington, D.C., to assist 
FHWA's division offices in reviewing financial plans and overseeing 
major projects and by assigning project oversight managers to each of 
the major projects. In addition, in 2003, DOT proposed new legislation 
as part of its TEA-21 reauthorization proposal requiring that (1) 
states submit a project management plan as well as an annual financial 
plan for any project with an estimated total cost of $1 billion or more 
or any other project at the discretion of the Secretary; (2) states 
develop financial plans for any project receiving over $100 million in 
federal funds; (3) FHWA perform annual reviews of state transportation 
programs' financial management and periodic reviews of state project 
delivery systems for planning and managing projects; and (4) DOT 
develop minimum standards for estimating project costs and perform 
periodic reviews of state practices for estimating costs and awarding 
contracts. This proposal was largely adopted in bills that were 
separately approved by the House and the Senate in 2004 but that were 
not enacted before the adjournment of the 108TH Congress.

To meet the requirements of the Government Performance and Results Act 
of 1993 (GPRA), DOT establishes goals and outcome measures for the 
programs under its jurisdiction, including the federal-aid highway 
program, through its strategic and performance plans. GPRA requires 
agencies to complete strategic plans in which they define their 
missions, establish outcome-oriented goals, and identify the strategies 
that will be needed to achieve those goals. GPRA also requires agencies 
to prepare annual performance plans to articulate goals for the 
upcoming fiscal year that are aligned with their long-term strategic 
goals. The establishment of goals and measures is a valuable tool for 
guiding an agency's strategies and resource allocations and for 
establishing accountability for the outcomes of its day-to-day 
activities. As our prior work has shown, measuring performance allows 
organizations to track the progress they are making toward their goals 
and gives managers crucial information on which to base their 
organizational and management decisions. When an agency's day-to-day 
activities are linked to outcome measures, these measures can create 
powerful incentives to influence organizational and individual 
behavior. In prior work, we found that leading agencies that 
successfully link their activities and resources also seek to establish 
clear hierarchies of performance goals and measures. Under these 
hierarchies, an agency links the goals and outcome measures for each 
organizational level to successive levels and ultimately to the 
agency's strategic goals. Without this link, managers and staff 
throughout the organization will lack straightforward roadmaps showing 
how their daily activities can contribute to attaining organization 
wide strategic goals.[Footnote 8]

FHWA Established Some Oversight Goals and Measures but Has Not 
Effectively Implemented Them: 

FHWA established measurable, outcome-oriented goals and measures 
related to cost and schedule performance for the first time in its 2004 
performance plan, but FHWA has not effectively implemented these goals 
and measures in order to improve oversight. Specifically, FHWA has not 
linked its day-to-day oversight activities to its goals for major 
projects, and it has not yet used its goals and measures for nonmajor 
projects to examine the performance of states or particular projects. 
FHWA also uses estimates developed relatively late in a project's 
development as its baseline for measuring its performance on achieving 
cost and schedule goals; thus, it does not task itself with controlling 
cost and schedule slippage during the early stages of a project's 
development.

FHWA Recently Established Goals and Measures: 

In December 2000, DOT issued a task force report concluding that a 
significant effort was needed to improve the oversight of major 
projects and recommending that DOT incorporate goals for its oversight 
efforts into its performance plans as well as into the plans of 
FHWA.[Footnote 9] In 2002, we reported that FHWA had not yet developed 
performance goals or measurable outcomes linking its oversight 
activities to its business goals and that goals and strategies for 
containing costs could improve accountability and make cost containment 
an integral part of how states manage projects over time.[Footnote 10]

FHWA has made some improvements over the past several years in 
developing goals and performance measures related to cost and schedule 
performance of federal-aid highway projects. In its fiscal year 2002 
performance plan, FHWA included a strategic goal of organizational 
excellence that had among its many strategic objectives the aim to 
improve organizational performance. Since that time, from fiscal year 
2003 to fiscal year 2005, FHWA's performance plans have specifically 
identified under the organizational excellence heading a general 
oversight goal to improve project oversight and stewardship so as to 
realize more cost efficient federal-aid funds administration and 
project management and more effective use of funds in terms of return 
on investment. In its fiscal year 2004 performance plan, DOT for the 
first time established goals and outcome measures specifically related 
to achieving cost and schedule targets for its transportation 
projects.[Footnote 11] FHWA incorporated these goals and measures into 
its performance plan for highway projects, establishing, for the first 
time, goals and measures for major projects that are outcome oriented 
and measurable and clearly define containing project costs and 
schedules as an integral part of FHWA's oversight mission. Figure 2 
shows the goals and associated measures articulated in FHWA's fiscal 
year 2004 performance plan.[Footnote 12]

Figure 2: Goals and Associated Measures Articulated In FHWA's 2004 
Performance Plan: 

[See PDF for image] 

[End of figure] 

FHWA Has Not Effectively Implemented its Goals and Measures: 

While linking day-to-day activities to goals and measures is an 
important element of implementing goals and measures by ensuring that 
they are being used as a framework to guide the activities, we found no 
evidence that FHWA has linked the day-to-day activities of its division 
offices to its goal and measure for major projects. In our visits to 
the three division offices that were overseeing a major project, we 
found a lack of documented goals, strategies, or measures showing how 
the division offices' activities supported and furthered the goals and 
measures articulated in FHWA's 2004 performance plan. While each 
division office had developed its own individual unit fiscal year 2004 
performance plan, there was no link in these plans between the division 
offices' activities and FHWA's goal and measure for major projects: 
that is, to meet 95 percent of schedule milestones and cost estimates 
for major projects or to miss them by less than 10 percent.[Footnote 
13] Furthermore, in these three division offices, the project oversight 
managers were not specifically tasked, as part of their duties and 
responsibilities, with implementing or furthering the articulated cost 
and schedule performance goals for major projects.

This absence of a link between activities and goals and measures was in 
noticeable contrast to the link that the division offices had 
established between their activities and the three areas of work that 
FHWA has designated as its "vital few" priorities. FHWA's vital few 
priorities, which consist of safety, congestion mitigation, and 
environmental stewardship and streamlining, are areas that FHWA has 
determined are key priorities and that it accordingly highlights in its 
performance plans as areas where the agency has identified performance 
gaps that must be addressed if FHWA is to be successful. Perhaps in 
line with this emphasis, FHWA has developed a better link between its 
division offices' activities related to these vital few priorities and 
its goals related to these vital few priorities. For example, all seven 
of the division offices we visited had unit plans that linked their 
activities to all three of FHWA's vital few priorities. This link was 
established through listing specific unit-level activities and measures 
that were designed to meet unit goals that mirrored the national 
performance plan's goals for its vital few priorities. For example, for 
the vital few priority of safety, FHWA's fiscal year 2004 performance 
plan set a performance goal of reducing highway fatalities to no more 
than 1.38 per 100 million vehicle miles traveled. The fiscal year 2004 
performance plan for one division office tasked itself with five 
performance objectives to address this national goal, including such 
objectives as improving accident rates involving roadway departures, 
increasing the capability of FHWA and state engineers in highway safety 
design, and reducing pedestrian fatalities.[Footnote 14] One or more 
division-level performance measures and several specific activities 
were identified for each of these five division objectives, and 
performance expectations set for key division staff identified which of 
these activities they were responsible for performing.

In addition to not linking its activities to its goal for major 
projects, FHWA has also not yet used its goals and outcome measures to 
help it identify and correct problems on the vast majority of projects 
that are not considered major projects. In 2004, FHWA did not develop 
numerical goals or outcome measures related to nonmajor projects, nor 
did it assess the cost and schedule performance of projects on a state-
by-state or project-by-project basis in order to gain a clear picture 
of whether certain states or projects have more cost or schedule 
overruns than others in order to target its oversight activities. 
Instead, FHWA officials told us that while FHWA's major projects team 
recently started developing this state-by-state information, FHWA 
relies on the division offices to monitor costs of individual contracts 
and take action as appropriate. However, these officials could not say 
with certainty whether their division offices were carrying out this 
monitoring function, or what kinds of corrective measures were being 
applied. FHWA officials also said that the agency relies on FHWA's 
division offices to execute formal oversight agreements with the states 
to ensure that they are working to control costs. However, none of the 
oversight agreements of the seven division offices we visited reflected 
an agreement between FHWA and the states to do this. As we concluded 
our review, FHWA officials stated that in response to issues we raised, 
FHWA would begin sharing information with its division offices and 
begin discussing appropriate solutions or actions the divisions can 
take to address incidences of cost growth.

For fiscal year 2005, FHWA made its cost-related goal for nonmajor 
projects more specific by adding the outcome measure that the total 
percentage of cost growth for all construction projects over $10 
million will be less than 10 percent above the estimated cost when the 
project went to construction. FHWA's preliminary information indicates 
that the agency is, in the aggregate, meeting its goal; however, 
sharing information with its division offices about variations in state 
contract costs could help FHWA target its oversight efforts. For 
example, FHWA's information also shows that about 1 in 5 of the 492 
contracts approved for construction in fiscal year 2003 exceeded the 10 
percent threshold in fiscal year 2004. One contract exceeded the 
threshold by 160 percent. Our analysis of FHWA's information also shows 
that some states may be more effectively controlling the costs of 
federal-aid highway contracts than others. For example, in one state, 6 
of 9 contacts over $10 million had exceeded the threshold, while in 
another state, all of the contracts were under the threshold. While 
opportunities exist for FHWA to use this information to better target 
its oversight efforts, it faces challenges in doing so in light of 
weaknesses recently reported by the DOT Inspector General's Office in 
its financial management and reporting processes.[Footnote 15]

FHWA Does Not Measure its Performance over the Full Life of Projects: 

FHWA uses cost and schedule estimates developed relatively late in a 
project's development--at the point at which the project is ready to go 
to construction--as a baseline for measuring its performance. We have 
discussed our concerns with FHWA's use of later estimates as its 
baseline measure in earlier work.[Footnote 16] We have recognized that 
developing early estimates is difficult; however, we have pointed out 
that using this late estimate as a baseline for measuring cost growth 
provides a misleading picture of actual cost growth. This is because 
cost estimates developed much earlier in the project--for example, at 
the environmental review stage--are used to make the public investment 
decision regarding the project. By the time the project goes to 
construction, a public investment decision effectively has been made, 
as substantial funds will have been spent on designing the project and 
acquiring property, commitments will have already been made to the 
public, and much of the increases in a project's costs may have already 
occurred.

Moreover, by measuring its performance only after construction begins, 
FHWA is not tasking itself with or establishing any accountability for 
controlling cost growth during the part of the process where it 
exercises direct oversight responsibility. Rather, it has focused its 
goals on the phases of the project where it exercises less oversight. 
This is because while FHWA is responsible for reviewing and approving 
certain state transportation plans, environmental impact assessments, 
and the acquisition of property for all projects, its role in approving 
the design and construction of projects varies.

FHWA's Oversight Activities Have Promising Elements and Limitations: 

FHWA and its major projects team undertook a number of activities to 
improve its oversight efforts, which the major projects team documented 
in its workplan summary (see app. II). Activities undertaken in 
response to prior concerns included increasing the use of project 
oversight managers, issuing guidance to states for improving cost 
estimates throughout the life of projects, developing some information 
on cost growth of major and other large projects, incorporating more 
risk assessments into its reviews of state management processes, and 
attempting to address congressional-committee direction to develop a 
multidisciplinary approach to its oversight. FHWA's activities in these 
areas have promising elements and limitations.

FHWA Established Competencies for Project Oversight Managers but Did 
Not Establish Roles or Consistent Performance Expectations: 

FHWA has taken some positive steps in its use of project oversight 
managers for major projects, but it has not yet defined the role of 
project oversight managers or established agency wide performance 
expectations for them. Currently, FHWA has assigned project oversight 
managers to 14 of the 21 active major projects, compared with 7 project 
oversight managers and 14 major projects in 2002. An FHWA official said 
that 6 project oversight manager positions would be advertised soon for 
the other projects and would be filled within 6 months.[Footnote 17] In 
August 2002, it issued a core competency framework to identify the 
technical, professional, and business skills that project oversight 
managers should possess and to serve as a guide for selecting and 
developing these managers. This core competency framework defines the 
skills and supporting behaviors of project oversight managers in areas 
such as project and financial management, contract administration, and 
program laws, and it specifies the desired proficiency level for each 
competency at each grade level.

FHWA has also taken steps to provide guidance and tools for project 
oversight managers, including an online resource manual and other 
guidance on reviewing project management plans and finance plans. It 
also made major projects team staff available to assist the project 
oversight managers in completing their reviews of such plans, and it 
sponsored annual meetings for project oversight managers to share 
experiences. Additionally, FHWA identified external training 
opportunities to help managers reach or improve their core competency 
skills. FHWA sent a listing of these opportunities to project oversight 
managers via email and invited these staff to enlist in courses that 
interested them. For the future, FHWA's 2004 major projects team work 
plan summary envisions a variety of additional activities to improve 
the effectiveness of project oversight managers, including working with 
universities and training vendors to establish a skill set development 
and certification program to ensure that all project oversight managers 
acquire the same critical skills and to establish a career path for 
them. According to FHWA, having a career path would make the position 
of project oversight manager a more attractive career option because it 
would provide opportunities to work with more challenging projects and 
provide promotion opportunities so that managers could advance within 
FHWA while staying in the project management track.

However, there are limitations with FHWA's efforts so far. While the 
core competencies define the skills that project oversight managers are 
expected to possess, they do not define what the managers should do to 
oversee a major project. FHWA has not yet articulated the role of 
project oversight managers or established agency wide performance 
expectations for them. In prior work, we established that setting 
performance expectations that are linked to goals is important, as a 
specific alignment between performance expectations and organizational 
goals helps individuals see the connection between their daily 
activities and organizational goals.[Footnote 18]

According to FHWA officials, project oversight managers are assigned to 
the division offices, and each division office defines what its project 
oversight manager does. At the three division offices we visited that 
had major projects and project oversight managers, none had set 
performance expectations for the project oversight manager that 
specifically tasked the project oversight manager with achieving the 
goals and outcome measures for the major projects. Project oversight 
managers and division officials stressed the project oversight 
managers' close, hands-on involvement with the state transportation 
agencies in the project, on an almost daily basis. For example, project 
oversight managers and other division office staff help state 
transportation agencies prepare finance and project management plans, 
get involved in design, participate in community outreach, and brief 
local political leaders on major projects. However, the extent to which 
the activity of the project oversight managers supported DOT's cost and 
schedule goals was not clear.

Finally, without clear roles, responsibilities, and performance 
expectations for project oversight managers that are clearly linked to 
FHWA's goals, it is unclear what training is most needed to enable 
project oversight managers to improve their performance and meet the 
agency's goals. Our guidance for assessing training efforts cites the 
need for training efforts to be an integral part of the strategic and 
performance planning process and to focus on reaching the agency's 
goals, rather than being implemented ad hoc.[Footnote 19]Currently, the 
training opportunities FHWA offers to project oversight managers are 
identified by the major projects team and are voluntary. There is no 
program of required courses--staff can choose which courses they would 
like to take, or take no courses at all. In March 2004, the head of 
FHWA's major projects team sent an e-mail to the oversight managers 
advising them of available training. To date, three project oversight 
managers and one other division office engineer have each volunteered 
to take one or two courses.

FHWA officials told us they eventually plan to establish a 
certification program for project oversight managers and to introduce a 
project oversight manager skills-set or career path to make project 
management a more attractive career option by setting out opportunities 
for more challenging projects, and providing promotion opportunities. 
However, as of December 2004, FHWA does not have a time frame for 
implementing its plans, and officials told us these activities would 
not be implemented without additional resources.

FHWA Provided Guidance to States on Developing Cost Estimates but this 
Guidance is Voluntary and Covers Only Major Projects: 

In another positive step since 2002, FHWA has provided guidance to 
state transportation agencies to assist them in applying sound cost 
estimating practices, including guidance in developing more realistic 
early cost estimates. However, this guidance is voluntary and covers 
only major projects, and we found evidence that there is some 
resistance by FHWA officials to focusing on developing earlier cost 
estimates. In past work, we have identified problems related to FHWA's 
lack of accurate cost estimates for projects. For example, in 1997, we 
found that cost increases occurred on projects, in part, because the 
initial cost estimates were not reliable predictors of the total costs 
or financing needs. Rather, these estimates were developed for the 
environmental review--the purpose of which is to compare project 
alternatives, not to develop reliable cost estimates. In addition, each 
state used its own methods and included different types of costs in 
developing its estimates, since FHWA had no standard requirements for 
preparing cost estimates. Since that time, in 2003, FHWA surveyed its 
division offices on cost estimating practices in their states and found 
a variety of approaches to developing cost estimates, including 
manually compiling estimates from historical data, using estimated 
quantity or cost per mile calculations, or utilizing various externally 
or internally developed software; one state reportedly lacked any 
formal process. Similarly, the American Association of State Highway 
and Transportation Officials (AASHTO) reported widely varying practices 
among the states in developing cost estimates.

In June 2004, FHWA issued guidance that articulated the importance of 
developing realistic early cost estimates that would be more stable as 
a project progresses. Specifically, FHWA's guidance stated that it is 
important that care be taken to present an achievable estimate even in 
the early stages of project development, because logical and reasonable 
cost estimates are necessary to maintain public confidence and trust 
throughout the life of a major project. Moreover, the guidance 
recognized that cost increases over and above the early planning and 
environmental estimates for major transportation projects have become 
of increasing concern to congressional and political leaders, federal 
and state top managers, and auditing agencies. In addition to 
recognizing the difficulty of developing more accurate cost estimates 
early in the project, this guidance includes such components as what 
should be included in an estimate, how it should be approved, factors 
to include in contingencies, and other information. This guidance may 
help states move towards more consistent and reliable cost estimates 
during the earlier planning phases when decisions are being made about 
whether or not to go forward with the project, as well as the project's 
potential design and construction.

FHWA also established help teams that travel to states that ask for 
assistance in creating better estimates. For example, in March 2003 
FHWA was asked by the Kentucky and Indiana transportation departments 
for help in reviewing the accuracy and reasonableness of the initial 
cost estimate to complete the Ohio River Bridges project. This project 
includes two new bridges over the Ohio River that would link eastern 
Louisville, Kentucky, and Clark County, Indiana, with additional 
interchange improvements. FHWA staff helped state officials identify 
the need for revised cost estimates and more realistic completion dates 
based on such factors as more realistic right-of-way costs, needed 
environmental mitigation, revised contingencies, and updated inflation 
rates. A team of federal and state staff working with consultants 
recommended that the total cost estimate of the project be revised from 
$1.6 billion to $2.5 billion and that its expected completion date be 
revised from 2017 to 2020. State officials accepted these 
recommendations.

While these cost estimating guidance and assistance efforts represent a 
positive step, it is too early to tell whether they will actually 
improve cost estimating efforts in most states. Furthermore, there are 
indications that there is some resistance among FHWA officials and 
states to emphasizing the importance of more accurate early estimates 
in practice. For example, some FHWA officials with whom we spoke said 
that costs cannot be accurately estimated early because issues such as 
public opposition to a project or unforeseen environmental mitigation 
procedures that are determined necessary are likely to drive up the 
cost of a project. They said early estimates should not be used as a 
basis for monitoring project costs. Other FHWA officials believed that 
the estimate developed at the conclusion of the design phase, as the 
project is ready for construction, is the only realistic estimate to be 
used as a baseline. Some FHWA officials told us that resolving concerns 
about cost estimates is more a matter of managing public expectations, 
so that the public understands that early estimates are not reliable 
and cannot be counted on, and that the actual cost will exceed early 
estimates. AASHTO also believes that accurately estimating costs at the 
early stages of a project can be a challenge. According to a May 2004 
AASHTO report, property acquisition needs and environmental and 
regulatory requirements may not be fully known early on, becoming clear 
only as the project progresses. Public input can contribute to 
additional features being added to projects, known as "scope creep," 
and litigation can delay a project, adding to costs because of 
inflation.

We recognize that many challenges exist to developing more realistic 
early estimates that more accurately reflect the expected cost of a 
project. However, as we have also reported, relying on estimates 
prepared as a project is ready to move to construction is too late in 
the process, as substantial funds may have already been spent on 
designing the project and acquiring property, and a public investment 
decision may, in effect, already have been made. FHWA's guidance 
recognizes that steps can be taken to take uncertainties into account 
when developing early cost estimates through such means as developing 
contingencies. Some states have begun taking action to improve the 
reliability of early cost estimates. For example, Washington State's 
Cost Estimate Validation Process uses project teams to identify risk 
factors, along with costs and mitigation strategies for each factor. 
These results are then entered into a computer-based modeling program 
that produces a range and a project cost estimate at the 90 percent 
confidence level, rather than a single dollar cost estimate.

DOT's proposed legislation for the reauthorization of TEA-21 in 2003 
included provisions empowering the Secretary to develop minimum 
standards for estimating project costs and to perform periodic reviews 
of state practices for estimating project costs. These provisions were 
adopted in bills that were separately approved by the House and the 
Senate in 2004 but that were not enacted before the adjournment of the 
108TH Congress. According to FHWA officials, if these provisions are 
adopted, the provisions may require them to move beyond voluntary 
guidance and issue regulations covering states' practices for 
estimating costs.

FHWA Has Started to Collect Some Cost Information, but it still Lacks 
the Capability to Determine the Extent of and Reasons for Cost Growth 
on Projects: 

FHWA has started to collect some cost information on some projects, but 
it still lacks the capability to determine the extent of and reasons 
for cost growth on projects so that it can better focus its oversight 
efforts. In 1997 we reported that cost growth occurred on projects, but 
the extent could not be determined because FHWA's information system 
for highway projects could not track total costs over the life of a 
project.[Footnote 20] In 2002, we testified that this information was 
still not available and noted that recent congressional attempts to 
gather complete and accurate information about the extent of and the 
reasons for cost growth had met with limited success.[Footnote 21] In 
response to these concerns and requests from Congress for data, FHWA 
has begun to collect project cost data, but it has not substantially 
improved its ability to monitor total costs on projects.

FHWA has undertaken two efforts to collect information on the cost 
performance of federally financed projects. First, it has started 
tracking information on cost growth of major projects. The small number 
of these projects allows the tracking to be done manually on a table 
containing cost and schedule information for key aspects of each major 
project. Second, FHWA has developed aggregated cost information on 
construction contracts over $10 million on a state-by-state basis. FHWA 
has done this by comparing the current estimated costs of all contracts 
over $10 million in each state with the engineering estimate developed 
before the contract was awarded. However, as mentioned earlier, the 
state-by-state information FHWA has developed has not yet been used to 
measure performance or target its oversight efforts.

In spite of this progress, FHWA still does not have the capability to 
measure the extent of and reasons for cost growth on projects. FHWA's 
principal vehicle for tracking project costs is its financial 
management system. This system is an accounting system, not a project 
information system, and it tracks federal reimbursements by contract 
rather than by project. Because one project can include many contracts 
over many years, and the system does not automatically link contracts 
to projects, FHWA has little easily accessible information to help it 
determine the total overall costs of each project, other than the major 
projects it tracks individually outside of its financial management 
system. In one case, FHWA division staff told us that because FHWA's 
financial management system does not track costs by project, the 
division developed its own spreadsheet to track project costs.

Our recent work confirmed FHWA's continued difficulty with tracking 
cost growth on projects. We randomly selected 14 contracts from 7 
division offices and asked FHWA's division offices to identify the 
project related to each contract. We then requested consolidated cost 
information on the 14 projects. FHWA took an average of more than 3 
months--and up to 6 months--to provide us this information for 12 of 
the 14 projects, and it was unable to provide us complete cost 
information on the other 2 projects. (See app. I for more details.) The 
primary reason for FHWA's difficulty in providing us with this 
information was that FHWA and state staff could not easily or 
electronically compile information on a project-by-project basis. For 
example, one division office said it had to develop and run special 
transaction reports and manually extract the information we wanted 
because the support files for the information were at different 
locations, including a state district office, state transportation 
agency offices, and comptroller offices. Another told us it had to take 
the extra step of either combining or separating contracts in order to 
compile information by project, which resulted in more "hand work." 
Another said that files on contracts for one project were kept in 
different locations depending on the stage of the project that the 
contract was related to. As a result, quite a bit of staff time was 
tied up as they attempted to get information from multiple departments 
of the state transportation agency. FHWA's continued difficulties in 
maintaining accurate and complete data to determine the extent of cost 
growth on projects limit its ability to evaluate why cost growth 
occurs, identify problems and solutions, target its oversight efforts, 
and transfer lessons learned.

FHWA Has Established Risk Assessments, but These Risk Assessments Are 
Not Always Used: 

FHWA expects its division offices to use some form of risk assessment 
to help guide its reviews of state management processes, also known as 
process reviews. However, risk assessments are not always being used 
consistently or effectively. As we reported in 2002, FHWA issued a 
policy in June 2001 encouraging its division offices to prioritize the 
risks in the transportation programs in their states and to direct 
their oversight efforts based on these results. The policy did not 
require a specific risk assessment approach but allowed division 
offices flexibility in developing an approach with their state 
agencies. FHWA considered its establishment of risk assessment 
practices at the division offices to be the first of a two-phased 
approach that would lead to an overall risk management program for 
FHWA, which was still under consideration within FHWA's leadership as 
of November 2004.

Each of the seven division offices we visited had developed a risk 
assessment approach, and five out of seven of the offices were using 
these risk assessments to guide their process reviews. However, at two 
division offices, the results had not been used to direct their process 
reviews. Staff at one division office we visited reported that although 
they had been doing risk assessments for a few years, they did not use 
the results to target state activities for review. Instead, they 
targeted state activities for review by meeting with state officials to 
draw up an intuitive list of state operations for process reviews. 
Similarly, another division office had drafted a risk assessment 
approach, but it had not yet tried to use it. Division office staff 
were skeptical that it would yield better results than their own more 
intuitive approach to identifying which state program operations 
warranted a process review.

In addition, in November 2004 the DOT Inspector General reported that 
FHWA's risk assessments were voluntary and did not provide a systematic 
approach for assessing program risks throughout the agency. The Office 
of Inspector General (OIG) reported that risks assessments varied 
significantly in the scope and methodology used and how the assessment 
results were rated and classified. As a result, some major programs 
were not reviewed, and risk assessment results were not reliable or 
comparable across states. To improve FHWA's process for managing risk, 
the OIG recommended that FHWA require all division offices to conduct 
risk assessments and that it issue guidance to division offices to 
ensure risk assessments are conducted more strategically and with a 
disciplined methodology. The OIG further recommended that FHWA analyze 
trends within individual risk assessments to identify agency wide 
issues and problems and establish a systematic follow-up process to 
ensure that oversight attention is given to high-risk areas.[Footnote 
22] FHWA was in the process of reviewing and responding to the OIG's 
recommendations when we concluded our review.

FHWA Has Begun to Take Steps to Develop a Multidisciplinary Approach to 
Oversight, but its Efforts so Far Have Been Limited: 

In February 2003, in the Conference Committee Report for the DOT fiscal 
year 2003 continuing appropriations, the conferees expressed continuing 
concern about FHWA's management of major projects, and in particular, a 
concern that FHWA's traditional engineering focus had inhibited 
oversight in such areas as financing, cost control, and schedule 
performance.[Footnote 23] Accordingly, FHWA was directed to evaluate 
the range of disciplines and skills within its staff and to develop a 
strategy for achieving a more multidisciplinary approach towards its 
oversight activities, including identifying staff with such skills as 
financing and cost estimation.

However, FHWA's human capital plan does not incorporate strategies for 
developing a workforce to support a more multidisciplinary oversight 
approach. In prior work, we noted that the process of strategic 
workforce planning addresses two critical needs: (1) aligning an 
organization's human capital program with its current mission and 
programmatic goals; and (2) developing long-term strategies for 
acquiring, developing, and retaining staff to achieve programmatic 
goals.[Footnote 24] To some extent, FHWA's human capital plan does this 
for the agency's current vital few priorities of safety, congestion 
mitigation, and environmental stewardship. But the agency's oversight 
mission is not truly incorporated into the plan. FHWA's human capital 
plan acknowledges the congressional-committee direction FHWA received 
to develop a more multidisciplinary approach to oversight. The plan 
states that this approach will require the development or acquisition 
of new skills, specifically in the areas of financing, funds 
accountability, project-level cost control, schedule performance, 
process management, and transportation planning. However, FHWA's human 
capital plan does not relate these needed skills to the skills 
possessed by its present workforce, nor does it address how these 
skills will be developed or acquired. Instead, FHWA's human capital 
plan is essentially a plan for replacing individuals in its current key 
occupations whom it expects to lose through attrition over a 5-year 
period.[Footnote 25]

Additionally, strategies for developing a multidisciplinary approach 
were not reflected in FHWA's guidance to its division offices for 
developing their workforce plans. This year, FHWA required its division 
offices and other units to prepare a workforce plan for the upcoming 3-
to-5 year period identifying anticipated skill gaps in their workforce. 
However, the guidance FHWA provided did not mention the 
multidisciplinary skills that FHWA had identified in its human capital 
plan. As we have pointed out in prior work, when planning for the 
future, leading organizations go beyond simply replacing individuals 
and engage in broad, integrated planning and management efforts that 
focus on strengthening both current and future organizational 
capacity.[Footnote 26] This is particularly important for FHWA, as its 
traditional engineering focus has drawn congressional committee concern 
that has led to direction to develop a multidisciplinary approach 
towards its oversight activities.

Similarly, FHWA's recruiting efforts do not incorporate strategies for 
developing a more multidisciplinary approach to project oversight. Like 
its human capital plan, FHWA's recruitment plan for 2003 through 2005 
is primarily a plan for hiring to fill the agency's traditional 
occupations. The recruitment plan does not set any specific goals or 
objectives for acquiring needed multidisciplinary skills that FHWA 
articulated in its human capital plan, such as project level cost 
control, schedule performance, process management, and transportation 
planning. Under the recruiting plan, the development of a 
multidisciplinary approach is addressed through FHWA's professional 
development program (PDP). FHWA's PDP, which historically focused on 
engineers, is a 2-year program that provides developmental assignments 
and on-the-job and classroom training for entry-level staff. Officials 
told us that PDP staff are now being given assignments allowing them to 
develop a broader range of skills at the start of their careers, 
including assignments to division offices with major projects. They 
also note that over recent years FHWA has been hiring fewer engineers 
for its PDP programs and more staff from other backgrounds.

The other principal component of FHWA's response to congressional 
committee direction to develop a multidisciplinary approach to project 
oversight is training, but the agency has made limited progress in 
developing new courses to bring new skills to its workforce. Only two 
new training courses were being developed specifically to address 
needed skills--a course on project cost estimation and a course on 
project management for managers in division offices. As of November 
2004, both courses were being pilot tested.[Footnote 27] As we noted 
earlier, it is important for training to be an integral part of an 
agency's performance planning process to ensure that it contributes to 
reaching agency goals. However, in its fiscal year 2005 performance 
plan, FHWA allows divisions the discretion to decide whether or not to 
participate in multidisciplinary training for its project oversight 
managers and professional development program staff. In addition, as 
noted earlier, FHWA has identified and offered external training 
courses to project oversight managers, but to date only a few managers 
and other key division staff have expressed an interest. Even so, FHWA 
human resources officials we spoke to told us they believed that the 
congressional committee's direction to develop a multidisciplinary 
approach to project oversight has been largely met through their 
already existing training efforts. These efforts include making courses 
available on risk assessment techniques, conducting process reviews, 
and implementing financial management improvements.

In addition to FHWA's limited progress in developing strategies for 
meeting this congressional-committee direction, FHWA has not fully 
embraced the need to develop a more multidisciplinary approach to 
oversight. FHWA human resources officials we spoke to believed the 
concern that FHWA's workforce is centered on engineering at the expense 
of other project oversight skills is based on a misperception--that is, 
not recognizing that FHWA engineers take on many other tasks not 
strictly related to engineering. Furthermore, two division office 
officials we spoke to in the course of our work questioned the need for 
FHWA to focus on multidisciplinary skills. One division administrator 
commented that "multidisciplinary" means that a person can do many 
things, and therefore that division's staff was already 
multidisciplinary. The deputy administrator in another division 
questioned what was meant by multidisciplinary skills, believing there 
was no guidance from headquarters on this.

FHWA Faces Challenges to Improving Oversight: 

FHWA's efforts to improve oversight face several challenges. These 
challenges stem from the structure of the federal-aid highway program 
and the culture of partnership that has resulted between FHWA and the 
states. These challenges also stem from FHWA's decentralized 
organization, human capital challenges that mirror those faced 
throughout government, and FHWA's perception that it has received 
conflicting signals on its oversight role over the years. Because these 
challenges are in large part rooted in FHWA's organization and culture, 
and in the structure of the program it administers, they may be 
difficult to surmount.

Structure of the Federal-Aid Highway Program: 

Because the federal-aid highway program is a state-administered, 
federally assisted program, it provides states broad flexibility in 
deciding how to use their funds, which projects to pick, and how to 
implement them. Furthermore, states are exempt from FHWA oversight on 
design and construction of many projects. Although DOT has articulated 
goals and outcome measures for the federal-aid highway program, such as 
improving safety and reducing the growth of traffic congestion, FHWA 
must implement and achieve these goals through a program over which it 
exercises limited control. Our past work across government programs has 
shown that in programs that have limited federal control, agencies face 
challenges to ensure that federal funds are efficiently and effectively 
used.[Footnote 28] We have also found that these challenges can be 
successfully overcome, in some cases, by ensuring that the program has 
clear goals and strong analytical data to measure program results. 
However, as stated earlier, FHWA's efforts both to implement its goals 
and to collect and analyze data on project costs have fallen short.

Exacerbating this challenge is the fact that, as our August 2004 report 
highlighted, the federal-aid highway program does not have the 
mechanisms to link funding levels with the accomplishment of goals and 
outcome measures that DOT has articulated.[Footnote 29] We have also 
reported that although a variety of tools are available to help measure 
the potential performance outcomes, such as those that measure the 
costs and benefits of transportation projects, such potential outcomes 
often do not drive investment decisions, as many political and other 
factors influence project selections.[Footnote 30] For example, the law 
in one state requires that most highway funds, including federal funds, 
be distributed equally across all of the state's congressional 
districts. Consequently, the structure of the federal-aid highway 
program provides no way to measure how funding provided to the states 
is being used to accomplish particular outcomes, such as reducing 
congestion or improving safety, and little assurance that projects most 
likely to accomplish goals and outcome measures articulated by DOT will 
be funded. The absence of such a link may make it more difficult for 
FHWA to define its role, the purpose of its oversight, and what its 
oversight is designed to accomplish.

In August 2004, we reported that policy makers may wish to consider 
realigning the federal-aid highway program's design, structure, and 
funding formulas to take into account the program's goals and to 
include greater performance and outcome oriented features. We also said 
that such consideration could include the appropriate roles of the 
federal and state governments, including what type of administrative 
structure for overseeing the federal-aid highway program would best 
ensure that the performance goals are measured and accomplished. Our 
report provided Congress with a matter for congressional consideration 
and said that the proposed National Commission to assess future revenue 
sources to support the Highway Trust Fund might be an appropriate 
vehicle through which to examine these options.[Footnote 31]

Culture of Partnership: 

Consistent with the structure of a state administered, federally 
assisted program, FHWA has developed a culture of partnership with the 
states. This culture of partnership dates back to the Federal-Aid Road 
Act of 1916, when the program was funded through a 50 percent federal 
and 50 percent state matching share. This partnership approach 
recognizes that states select, plan, and build projects, while FHWA 
ensures that federal laws and other requirements are followed by 
maintaining a close, hands-on involvement with state transportation 
agencies in delivering projects. FHWA and state officials believe that 
over the years this partnership has helped to build trust and respect 
between state transportation agencies and FHWA and ensure that 
priorities such as safety and the environment are addressed, and has 
resulted in projects being built more economically and efficiently.

However, there is a potential down side to this partnership approach. 
When a project overseer becomes an active partner in a project, an 
arms-length, independent perspective can be lost. In fact, FHWA's 
partnership approach to project oversight has failed in the past. FHWA 
had an oversight manager on the Central Artery/Tunnel Project in 
Boston, Massachusetts, a project that experienced widely-reported cost 
increases, growing from around $2.3 billion in the mid-1980s to almost 
$15 billion by 2004. In March 2000, an FHWA task force charged with 
reviewing FHWA's oversight of the project found that FHWA had been 
caught unaware earlier that year when the state revealed an estimated 
$1.4 billion cost increase. The task force attributed this to FHWA's 
over reliance on trust between itself and the state, reporting that 
FHWA's partnership approach failed to achieve independent and critical 
oversight of the project.

FHWA officials acknowledged that independence is critical to effective 
oversight and also acknowledged the need to closely monitor the 
performance and independence of their project oversight managers on an 
ongoing basis. However balancing the role of overseer and partner can 
be difficult. In one state we visited, the division's oversight manager 
for a major project had business cards that identified him as a member 
of the state's project team--with the project's logo, Website, and e-
mail address printed on the card--rather than as a federal employee. 
Only his position title on the card, "FHWA Project Administrator," 
identified him as an FHWA employee, rather than as a state employee. 
Ensuring that FHWA oversight personnel maintain an independent 
perspective is especially critical given the current lack of linkage 
between FHWA's performance goals and the roles and expectations of its 
project managers.

Another potential challenge presented by FHWA's culture of partnership 
with the states is that it may have prevented FHWA from considering 
other models for project oversight--including some models in use within 
DOT. For example, the Federal Transit Administration (FTA) uses 
competitively selected engineering firms as oversight contractors to 
monitor major mass transit projects costing over $100 million. During 
the project's design, the contractor reviews the grantee's plan for 
managing the project and determines whether the grantee has the 
technical capability to complete the project. Once FTA approves the 
plan, the contractor monitors the project to determine whether it is 
progressing on time, within budget, and according to plan. In prior 
work, we noted that FTA's project management oversight program 
benefited both the agency and the grantees carrying out the 
projects.[Footnote 32] As another example, DOT established a Joint 
Program Office to help carry out the Transportation Infrastructure 
Finance and Innovation Act Program, which provides credit assistance to 
states and other project sponsors for surface transportation projects. 
This office reviews and evaluates proposed projects for participation 
in the program, reviews financial plans and progress reports during 
project construction, monitors the project sponsor's credit, and 
coordinates site visits and other oversight activities with DOT field 
offices.

FHWA's Organization: 

FHWA administers the federal-aid highway program through a 
decentralized division office structure and delegates much of FHWA's 
decisionmaking and program implementation to those offices. Therefore, 
FHWA's division administrators enjoy wide latitude to implement their 
programs. FHWA has had a field office in every state since 1944, and, 
according to FHWA and state officials, this arrangement gives maximum 
flexibility to the people closest to the customer and to the issues to 
make decisions best suited to particular needs and situations. 
According to FHWA officials, this decentralization of decisionmaking 
and program implementation to the division offices increased after 1998 
and the passage of TEA-21, which eliminated FHWA's nine regional 
offices.

While this flexibility may have benefits, decentralization presents 
challenges for the implementation of a consistent national leadership 
vision and strategies. These long-standing organizational arrangements 
may have contributed to such conditions as the lack of uniform 
performance expectations for project oversight managers, widely varying 
methods used to develop cost estimates for projects, and different 
approaches to doing risk assessments. Some limitations are by design. 
For example, while FHWA's fiscal year 2005 performance plan discusses 
multidisciplinary skill training for its oversight managers and 
professional development program staff, it also specifically grants 
division administrators the discretion about whether to participate. 
FHWA officials acknowledged the challenges of consistently implementing 
national level goals and programs among the many division offices.

Human Capital: 

Our 2003 update to our High-Risk Series of reports recognizes that 
strategic management of human capital continues to be a high-risk area 
government wide.[Footnote 33] Although considerable progress has been 
made since we first designated human capital a government wide high-
risk area in 2001, federal human capital strategies are not yet 
appropriately constituted to drive the transformation that is needed 
across the federal government. Among the challenges agencies face are 
the need to improve their ability to acquire, develop, and retain 
talent, and the need to better and more fully integrate these and other 
human capital efforts with agencies' missions and program goals.

For FHWA, this government wide challenge manifests itself in a number 
of ways, including the need to transform its workforce and culture to 
meet its evolving mission. FHWA's workforce partnered with the states 
to build the Interstate Highway System from 1956 into the 1990s. FHWA 
needed engineering skills to perform tasks, such as detailed reviews of 
design plans and inspections of construction progress to ensure that 
national uniformity in terms of design and safety was established 
throughout the interstate system. These skills were especially 
important because, according to FHWA and state officials, state 
transportation agencies did not have the equivalent capability to do 
the job at that time. In recent years Congress has recognized the 
increased capacity of state transportation agencies and increasingly 
delegated approval authorities to the states, including the authority 
over design and construction decisions for most projects. As a 
consequence, FHWA's oversight role and mission have evolved to include, 
for example, greater reliance on broad reviews of state management 
processes.

As FHWA's oversight role and mission evolves, FHWA faces the challenge 
of transforming its workforce and culture to evolve with this role and 
mission. In our discussions with FHWA field staff, we noted reluctance 
among some FHWA staff to focus on these broader reviews that FHWA 
increasingly relies on because they see these as less important than 
the traditional tasks of reviewing design plans and inspecting the 
progress of construction. Division office officials in two states we 
visited told us that change has been an issue for its more tenured 
staff. For example, the Administrator at one office had begun to hire 
staff with a variety of skills, while officials at the other office saw 
a need for more specialists, including staff with financial expertise. 
Officials also said some staff have resisted doing process reviews 
because they see it as functioning as auditors rather than as partners 
with the state in delivering projects, which is how they prefer to be 
seen. Overcoming these challenges will become even more important in 
the years ahead should proposed legislation increasing FHWA's oversight 
responsibilities be enacted.

FHWA's Perception of Conflicting Legislative Direction on Oversight 
Role and Responsibilities: 

In 2001, a FHWA task force concluded that changes in the agency' s 
oversight role mandated by highway program authorizations enacted in 
1991 and 1998 had resulted in internal confusion and wide variation in 
interpretations by FHWA personnel covering the agency's roles and 
responsibilities in overseeing projects.[Footnote 34] In 2002, we 
reported that FHWA could not say whether it had resolved the internal 
confusion and variations in interpretations of the agency's oversight 
role identified by the task force.[Footnote 35]

During our review we found that some confusion continues, as some of 
the FHWA personnel we spoke to expressed the view that Congress has 
sent mixed messages about the extent to which it would like to see FHWA 
oversee projects. According to some division and headquarters FHWA 
officials, federal laws over the years have required FHWA to withdraw 
from direct oversight of most projects, while at the same time, 
legislation has increased the oversight requirements for major 
projects, resulting in mixed signals. Changes that were proposed by DOT 
and passed by the House and the Senate in 2004 but not enacted before 
the adjournment of the 108TH Congress could, if reintroduced and 
enacted by the 109TH Congress, help clarify FHWA staff's perception of 
their oversight role by, for example, mandating reviews of state 
financial system, developing cost estimating standards, and cascading 
requirements for major projects to other projects. Enactment of these 
provisions would also provide Congress the opportunity to provide a 
more detailed explanation of and purposes for these provisions 
regarding FHWA's role versus the states' role in overseeing cost and 
schedule performance of federal-aid highway projects in the legislative 
history accompanying the reauthorization bill. As we stated in our 2002 
testimony, such clarification would be helpful.

Best Practices Can Help Improve Progress and Address Challenges to 
Improving Project Oversight: 

Reports and analyses published by us, OMB, and the National Research 
Council suggest a set of best practices that agencies can benefit from 
in conducting effective oversight of large infrastructure projects such 
as those in the federal-aid highway program overseen by FHWA. While 
these reports and analyses tend to focus more on overall project 
management, there are elements in each of them that relate specifically 
to improving project oversight. From our review of these reports and 
analyses, we identified four best practices that are particularly 
applicable to FHWA's oversight efforts and that FHWA officials and 
decision makers can consider to help effectively oversee large 
infrastructure projects and states' financial and management processes. 
While some of these best practices are beginning to be reflected in 
FHWA's activities, as a whole, they could provide a framework for 
moving to a comprehensive approach to project oversight. These best 
practices are 1) establishing measurable project oversight goals and 
communicating these goals down through all levels of the agency, 2) 
establishing project oversight manager role and accountability based on 
oversight goals, 3) providing professional training and a career path, 
and 4) learning lessons and transferring them.

Establishing Measurable Project Oversight Goals and Communicating These 
Goals through All Agency Levels: 

As we discussed earlier, agencies seeking to make oversight a priority 
should establish measurable project oversight goals that help it carry 
out its mission and define what its oversight is designed to 
accomplish--and should communicate these goals down through all levels 
of the agency. Having measurable goals gives managers the means to 
objectively and quantifiably assess progress toward achieving certain 
outcomes. If an agency relies only on general goals to guide its 
efforts, the agency will not have any way of determining whether it 
achieves those goals since it has not first identified a way to 
quantify or measure the outcome. Once these goals are established, 
agencies should communicate these goals down to all levels of the 
agency. One way to ensure that the goals are communicated effectively 
is to link the agency's day-to-day activities to these goals. Our 1998 
report on leading practices in capital decision-making added that clear 
communication of an organization's vision and goals is a prerequisite 
for success. Top-level officials develop the organization's priorities 
and communicate them downward to subunits within the organization. 
Based on these goals, managers at all levels work to produce plans and 
activities that outline their individual strategies for achieving top-
level goals.[Footnote 36]

Establishing Project Oversight Manager Role and Accountability Based on 
Oversight Goals: 

Once an agency establishes its oversight goals, it should incorporate 
those goals into its strategies and activities by making oversight 
managers accountable for the effective implementation of the goals. We 
recently recommended that Amtrak adopt policies and procedures for 
managing infrastructure projects that, among other things, include 
mechanisms to ensure accountability for a project's success. We stated 
that such mechanisms should clearly indicate the individuals 
responsible for implementing the project, the expectations for their 
performance, the ways their performance will be measured, and the 
potential consequences for failing to meet expectations.[Footnote 37] 
In this report, we noted that some of the railroads we had contacted 
tied pay and personnel decisions to performance, holding project 
managers directly responsible for the project's success and failure. 
In other previous work, we have also noted that how such pay for 
performance efforts are done, when they are done, and the basis on 
which they are done can make all the difference in whether such efforts 
are successful.[Footnote 38] In addition, in other prior work, in 2000, 
we found a number of emerging benefits from the use of results-oriented 
performance agreements for executives, including, among other things, 
providing results-oriented performance information to serve as the 
basis for executive performance evaluations.[Footnote 39]

Providing Professional Training and a Career path: 

Professional training enables oversight staff to understand their 
expected roles in achieving the agency's oversight goals. Having a view 
of a future career is also desirable for the development of oversight 
staff. In 1999 the National Research Council reported that the 
Department of Energy could improve its project performance by 
developing skills, training opportunities, and a career path in project 
management. The report added that the agency needed to establish 
criteria and standards for selecting and assigning project managers, 
including documentation of training, and should require that all 
project managers be trained and certified.[Footnote 40] In prior work, 
we have found that an agency's training program should be linked to 
achieving the agency's strategic goals, while specific training for 
each individual should be based on his or her developmental 
needs.[Footnote 41]

Lessons Learned and Transferred: 

Effective oversight also requires a proactive approach to establishing 
evaluation mechanisms, collecting information, and transfering lessons 
learned on an ongoing basis. Learning from past successes and mistakes 
and sharing that information with decision makers, agency officials, 
and project managers is a critical element for effective oversight. Our 
1996 executive guide to help agencies implement GPRA reported that 
agencies analyzing the gap between where they are and where they need 
to be to achieve desired outcomes can target those processes that are 
in most need of improvement, set realistic improvement goals, and 
select an appropriate process improvement technique such as 
benchmarking. Benchmarking compares an internal agency process with 
those of private and public organizations that are thought to be the 
best in their fields.[Footnote 42] In addition, our 1998 report on 
leading practices in capital decision making also found that agencies 
could evaluate and compare results with goals by using financial and 
non-financial criteria that link its overall goals and objectives. In 
2000, we reported that agencies conducting program evaluations improved 
their measurement of program performance or understanding of 
performance and how it might be improved.[Footnote 43] In addition, our 
Executive Guide on Capital Decision-Making identified practices federal 
agencies can implement to enhance their evaluation processes.[Footnote 
44] In 1997, OMB stated in its Capital Programming Guide[Footnote 45] 
that agencies should be able to document and support the accomplishment 
of the respective agency goals. Agencies can also evaluate the planning 
and procurement process to determine whether a project accurately 
predicted the desired benefits 3 to 12 months after it has become 
operational. The Guide added that conducting a project post-
implementation review that evaluates the success or failure of projects 
serves as an assessment. The review compares actual results against 
planned cost, returns, and risk. The results are used to calculate a 
final return on investment, determine whether any additional project 
modifications may be necessary, and provide lessons learned for changes 
to the agency's capital programming processes and strategy. Finally, 
the National Research Council's 1999 report stated that agencies such 
as the Department of Energy should transfer knowledge gained about cost 
estimating techniques, project review processes, change control 
mechanisms, and performance metrics from one project to another.

Conclusions: 

FHWA has made progress since 2002 in improving its oversight efforts, 
including its direct oversight of major projects and its broader 
reviews of state management processes that are used to oversee states' 
management of most other projects. For example, FHWA's actions to 
enhance the capabilities of project oversight managers overseeing major 
projects and to incorporate risk assessments into its reviews of state 
management processes are both positive steps towards improving 
oversight. Most significantly, FHWA has established, for the first 
time, goals and measures that clearly make containing project costs and 
schedules an integral part of how FHWA conducts its oversight.

However, despite promising results, FHWA's efforts have also had 
limitations. FHWA still lacks a comprehensive approach to ensuring that 
its oversight of federal-aid highway projects supports the efficient 
and effective use of federal funds. A comprehensive approach would 
avail itself of best practices and would include (1) goals and outcome 
measures with activities and performance expectations set for its staff 
that are linked to these goals and measures; (2) an overall plan for 
FHWA's oversight initiatives and activities that responds to past 
concerns raised about its program and is tied to its goals and 
measures; (3) workforce planning efforts that support the goals, 
measures, and overall plan; (4) centrally defined roles and 
responsibilities for key staff, such as oversight managers for major 
projects; and (5) the capability to track and measure costs over the 
life of projects in order to identify problems, help target resources, 
and transfer lessons learned. Without such a comprehensive approach, 
FHWA cannot ensure that its varied activities are resulting in tangible 
improvements in the quality of its oversight and in the performance of 
federal-aid projects. Furthermore, without a comprehensive approach, 
FHWA is not able to articulate what it wants its oversight to 
accomplish, the composition of its workforce to accomplish it, and how 
it will measure whether its efforts have or have not been successful. 
Thus, it is limited in its ability to ensure that its oversight efforts 
are meeting its organizational goals, that these efforts address 
concerns that have been raised, and that they result in more effective 
and efficient use of federal funds.

Although broader questions exist about the structure of the federal-aid 
highway program and the role of FHWA, the agency will face considerable 
increases in its oversight responsibilities in the years ahead, 
particularly if the proposals made by DOT and considered by Congress 
become law. Given the limitations present today, questions exist about 
the ability of FHWA to effectively absorb these new responsibilities 
and to improve its oversight of the federal-aid highway program in the 
years ahead. Moreover, absent a comprehensive approach, FHWA is 
unlikely to be able to overcome the structural, organizational, and 
cultural challenges it faces in effectively overseeing the federal-aid 
highway program.

Recommendations: 

In order to establish a comprehensive approach to project oversight, we 
recommend that the Secretary of Transportation direct the 
Administrator, FHWA, to take the following four actions: 

* link FHWA's day-to-day activities and the performance expectations 
set for its staff to its goals and outcome measures;

* develop an overall plan for its oversight initiatives that is tied to 
its goals and measures, along with priorities and time frames, and that 
includes workforce planning efforts that support these goals and 
measures;

* improve the use and performance of project oversight managers by 
centrally defining their role and responsibilities; and: 

* develop the capability to track and measure costs over the life of 
projects to help identify the extent of and reasons for problems, 
target resources, and transfer lessons learned.

Agency Comments: 

We provided a draft of this report to DOT and met with FHWA officials, 
including the Deputy Administrator, to obtain their comments on the 
draft. FHWA officials generally agreed with the facts and conclusions 
in the report and our characterization of the challenges FHWA faces in 
improving its project oversight. FHWA officials emphasized that 
although we highlighted potential drawbacks associated with both its 
culture of partnership with the states and its decentralized 
organization, this partnership and organization are also major 
strengths of the federal-aid program that will allow the agency to 
absorb potential new responsibilities, help overcome challenges, and 
improve program oversight in the future through a more comprehensive 
approach. FHWA officials did not take a position on our 
recommendations, but they stated that they would be taking them under 
advisement. They also suggested some technical and clarifying comments 
that we incorporated into the report as appropriate.

We are sending copies of this report to the Honorable Norman Mineta, 
Secretary of Transportation. We will also make copies available to 
others upon request. In addition, the report will be available at no 
charge on the GAO Web site at [Hyperlink, http://www.gao.gov].

If you have any questions about this report, please contact me at 
[Hyperlink, siggerudk@gao.gov], or (202) 512-6570 or contact Steve 
Cohen at [Hyperlink, cohens@gao.gov] or (202) 512-4864. GAO contacts 
and acknowledgments are listed in appendix III.

Sincerely yours,

Signed by: 

Katherine Siggerud: 
Director, Physical Infrastructure: 

[End of section]

Appendixes: 

Appendix I: Scope and Methodology: 

We reviewed the Federal Highway Administration's (FHWA) approach to 
improving its federal-aid highway project oversight efforts since 2002, 
including (1) FHWA's oversight-related performance goals and measures, 
(2) FHWA's oversight improvement activities, (3) challenges FHWA faces 
in improving project oversight, and (4) best practices for project 
oversight.

We reviewed FHWA's oversight-related goals and measures by evaluating 
Department of Transportation (DOT) and FHWA strategic and performance 
plans, and supporting documents, from 2001 through 2004. We also 
reviewed FHWA's annual performance reports from 2002 and 2003 and 
current OMB President's Management agenda documents. We also reviewed 
FHWA and DOT fiscal year 2005 budgets. As criteria in reviewing this 
information we used GAO published guidelines and prior reports, 
including GAO's 2001 Performance Guide and GAO's 2003 Results Oriented 
Culture and GAO's 2003 Human Capital reports.

To review FHWA's oversight improvement activities we documented and 
analyzed the status of FHWA's various project oversight efforts since 
2002 using FHWA's FY 2004 Work Plan Summary from the major projects 
team (see app. II). We also reviewed FHWA's use of financial 
information from its Financial Management Information System (FMIS) to 
track and analyze trends in cost growth on projects. We did not 
independently assess the reliability of FMIS data as the Department's 
Inspector General has reported on weaknesses in FHWA's financial 
management and reporting processes, most recently in November 2004 as 
part of the annual audit of DOT's consolidated financial statements. In 
addition, our work focused primarily on FHWA's use of FMIS data for 
oversight purposes, rather than relying on FMIS data to support our 
findings and conclusions. In addition, to document continued difficulty 
in tracking cost growth on projects, we randomly selected 14 contracts 
from seven division offices, each of which had an estimated total cost 
of between $25 million and $50 million. We then asked FHWA's division 
offices to identify the project related to each contract (each contract 
was part of a different project, so there were 14 projects), and 
requested consolidated cost information on the 14 projects. FHWA took 
an average of more than 3 months--and up to 6 months--to provide us 
this information for 12 of the 14 projects, and it was unable to 
provide us complete cost information on the other 2 projects. Finally, 
we also interviewed officials at FHWA Headquarters, selected FHWA 
division offices, state departments of transportation, and other 
officials to document oversight implementation efforts.

We performed work at seven FHWA division offices and states located in 
Colorado, Georgia, Missouri, Nevada, Pennsylvania, Washington, and 
Wisconsin. We selected these 7 FHWA division offices and corresponding 
states by selecting states that had a current or planned major project 
and some that did not; states with large as well as relatively small 
federal-aid highway programs in terms of funding; large and small FHWA 
division offices as measured by the number of staff; and division 
offices and states that FHWA and the American Association of State 
Highway and Transportation Officials (AASHTO) officials had recommended 
because of ongoing initiatives related to project oversight and 
management.

To document and review the challenges FHWA faces in improving its 
project oversight we used our past work and interviewed FHWA 
headquarters, division office and state transportation program 
officials. We also interviewed AASHTO officials and state audit and 
evaluation organizations across the country.

To address the use of best practices as a framework for the oversight 
of large highway infrastructure projects, we conducted a literature 
search in 2004 to identify best practices related to oversight 
management. The literature included our previous reports and guidelines 
on best practices related to project management. It also included 
publications from the Office of Management and Budget (OMB) that 
provided detailed guidance to federal agencies on planning, budgeting, 
acquisition, and management of capital assets and from the National 
Research Council addressing methods the Department of Energy could 
implement to improve its project management, including oversight of 
environmental restoration, waste management, and construction 
projects. From this literature search, we compiled the list of best 
practices that can provide FHWA with a comprehensive approach and basic 
framework for effectively overseeing highway projects. For the first 
practice of establishing measurable project oversight goals we used 
information from two of our reports related to the Government 
Performance and Results Act and another report related to leading 
practices in capital decision-making. For the second practice of 
establishing project oversight manager role and accountability based on 
oversight goals, we used our report related to improving project 
management for Amtrak and another of our reports on performance 
agreements. For the third practice of providing professional training 
and a career path, we used a National Research Council report on 
improving project management at the Department of Energy. For the 
fourth practice of learning lessons and transferring them, we used 
information from the National Research Council report mentioned above, 
the GAO report on leading practices in capital decision-making, another 
GAO report on program evaluations, and OMB guidance in Circular A-11 
and its Capital Programming Guide.

[End of section]

Appendix II: FHWA FY 2004 Major Project Team Work Plan Summary: 

Activity: Issue final project management plan guidance; 
Status: Completed.

Activity: Develop cost estimating guidance; 
Status: Completed.

Activity: Issue major project delivery template; 
Status: Under Development.

Activity: Establish independent cost estimating review program; 
Status: Under Development.

Activity: Establish major project cost and schedule measures; 
Status: No Work Started.

Activity: Monitor project cost growth; 
Status: Ongoing.

Activity: Coordinate with other transportation programs; 
Status: Ongoing.

Activity: Reevaluate major project finance plan guidance; 
Status: Under Development.

Activity: Develop finance plan guidance for projects over $100m; 
Status: No Work Started.

Activity: Identify trends in finance plans; 
Status: Under Development.

Activity: Host new FHWA hires; 
Status: Ongoing.

Activity: Manage project oversight manager positions; 
Status: Ongoing.

Activity: Develop clear statement of team objectives; 
Status: Completed.

Activity: Implement major project team marketing plan; 
Status: Ongoing.

Activity: Develop working relationships with other DOT agencies; 
Status: Ongoing.

Activity: Develop executive level major projects training; 
Status: Under Development.

Activity: Develop risk-based conflict management model; 
Status: No Work Started.

Activity: Facilitate organizational career track for oversight 
managers; 
Status: No Work Started.

Activity: Monitor selected projects; 
Status: Ongoing.

Activity: Review project finance plans and annual updates; 
Status: Ongoing.

Activity: Conduct training and outreach; 
Status: Ongoing.

Activity: Establish risk management program; 
Status: Under Development.

Activity: Promote oversight best practices; 
Status: Ongoing.

Activity: Restructure oversight group website; 
Status: Under Development.

Activity: Establish and lead oversight working group; 
Status: Under Development.

Activity: Establish cross-functional oversight website; 
Status: Under Development.

Activity: Identify risk assessment training opportunities; 
Status: Under Development.

Activity: Identify national trends in process reviews; 
Status: No Work Started.

Activity: Establish oversight agreement repository; 
Status: Completed.

Activity: Develop new generation of oversight performance measures; 
Status: No Work Started.

Activity: Develop performance pilot measures; 
Status: No Work Started.

Activity: Facilitate the development of cost growth countermeasures; 
Status: No Work Started.

Activity: Prepare major project team report to Congress; 
Status: Ongoing.

Activity: Conduct monthly project tracking activities; 
Status: Ongoing.

Activity: Develop major project continuum model; 
Status: Under Development.

Activity: Establish skill sets development program for oversight 
managers; 
Status: Under Development.

Activity: Monitor large projects in preconstruction stage; 
Status: No Work Started.

Activity: Identify preconstruction project milestones; 
Status: No Work Started.

Activity: Establish major project speakers' bureau; 
Status: No Work Started.

Activity: Establish major project briefing repository; 
Status: No Work Started.

Activity: Establish training and development opportunities for new 
staff; 
Status: No Work Started.

Activity: Organize annual project oversight managers meeting; 
Status: Ongoing.

Activity: Participate in National Engineer's Week; 
Status: Ongoing.

Activity: Serve as structural liaison; 
Status: Ongoing.

Activity: Conduct security vulnerability assessments; 
Status: Ongoing.

Activity: Establish national best practice and lessons learned program; 
Status: Under Development.

Activity: Post best practices and lessons learned material on website; 
Status: Under Development.

Activity: Produce best practices and lessons learned bulletins; 
Status: No Work Started.

Source: GAO.

[End of table]

[End of section]

Appendix III: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Kate Siggerud (202) 512-2834: 
Steve Cohen (202) 512-4864: 

Staff Acknowledgements: 

In addition to those named above, Sam Abbas, Catherine Colwell, Pat 
Dalton, Don Kittler, Alex Lawrence, Sara Ann Moessbauer, John Rose, 
Stacey Thompson, and Alwynne Wilbur made key contributions to this 
report.

(544076): 

FOOTNOTES

[1] S. 1072, 108TH Cong.§1101 (2004); and H.R. 3550, 108TH Cong.,§1101 
(2004).

[2] The 1 million miles of roads eligible for federal aid accounted for 
about 85 percent of the vehicle miles traveled on the nation's roadways 
in 2002. The 3 million miles of roads that are generally ineligible are 
functionally classified as local roads or rural minor collectors.

[3] Specifically, FHWA approves state short-term transportation plans 
and reviews state and metropolitan planning processes.

[4] A finance plan has not been prepared for one major project that is 
nearing completion, because it predates the requirement for these 
plans.

[5] GAO, Transportation Infrastructure: Managing the Costs of Large-
Dollar Highway Projects, GAO/RCED-97-47 (Washington, D.C.: Feb. 27, 
1997).

[6] GAO, Transportation Infrastructure: Cost and Oversight Issues on 
Major Highway and Bridge Projects, GAO-02-702T (Washington, D.C.: May 
1, 2002).

[7] Management of Cost Drivers on Federal-aid Highway Projects, 
Statement of the Honorable Kenneth H. Mead, Inspector General, U.S. 
Department of Transportation, May 8, 2003. 

[8] GAO. Executive Guide: Effectively Implementing the Government 
Performance and Results Act, GAO/GGD-96-118 (Washington, D.C.: June 1, 
1996). 

[9] Report of the ONE DOT Task Force on Oversight of Large 
Transportation Infrastructure Projects; December 2000.

[10] GAO-02-702T.

[11] Between fiscal years 2001 and 2003 FHWA did have an outcome 
measure under the organizational excellence goal to reduce unexpended 
balances. However, this measure did not specifically relate to cost and 
schedule targets on transportation projects. Unexpended balances are 
the annual amount of federal-aid funds obligated but not expended on 
projects of $1 million or more and with no billing activity for more 
than a year. 

[12] For FY 2005, FHWA made its measure to prevent high growth in 
project costs more specific by adding that the total percentage of cost 
growth for construction projects will be less than 10 percent above the 
original estimate on construction projects over $10 million.

[13] Four of the division offices we visited were not at the time 
overseeing a major project; therefore, the major project goal and 
measure did not apply to their responsibilities at that time.

[14] The other two objectives were to increase the number of high-
accident intersection improvement projects and to support the state's 
safety plan.

[15] We did not independently assess the reliability of FMIS data as 
the Department's Inspector General has recently reported on weaknesses 
in FHWA's financial management and reporting processes as part of the 
annual audit of DOT's consolidated financial statements. In addition, 
our work focused primarily on FHWA's use of FMIS data for oversight 
purposes, rather than relying on FMIS data to support our findings and 
conclusions.

[16] GAO/RCED-97-47 and GAO-02-702T.

[17] One major project, which is nearing completion, predates the major 
project requirements, and a project oversight manager was not assigned 
to it.

[18] GAO, Results-Oriented Culture: Creating a Clear Linkage between 
Individual Performance and Organizational Success, GAO-03-488 
(Washington, D.C.: Mar. 14, 2003). 

[19] GAO, Human Capital: A Guide for Assessing Strategic Training and 
Development Efforts in the Federal Government, GAO-04-546G (Washington, 
D.C.: Mar. 24, 2004).

[20] GAO/RCED-97-47.

[21] GAO-02-702T.

[22] DOT Office of Inspector General, Managing Risk in the Federal-Aid 
Highway Program, MH-2005-012 (Washington, D.C.: Nov. 19, 2004).

[23] U.S. House of Representatives Conference Report 108-10, Making 
Further Continuing Appropriations for the Fiscal Year 2003, and Other 
Purposes (Feb. 12, 2003). p. 1263. 

[24] GAO, Human Capital: Key Principles for Effective Strategic 
Workforce Planning, GAO-04-39 (Washington, D.C.: Dec. 11, 2003).

[25] The plan focuses on what FHWA has identified as its mission 
critical occupations: civil engineers, planners, environmental 
specialists, financial management, engineering technicians, realty 
specialists, and transportation specialists.

[26] GAO, Human Capital: Succession Planning and Management is Critical 
Driver of Organizational Transformation, GAO-04-127T (Washington, 
D.C.: Nov. 1, 2003).

[27] FHWA officials told us the project management course is targeted 
to about 100 FHWA officials, and project cost estimating will be 
provided to about 450 staff, both over the next 2 years.

[28] GAO, Managing for Results: Measuring Program Results That Are 
Under Limited Federal Control, GAO/GGD-99-16 (Washington, D.C.: Dec. 
11, 1998).

[29] GAO-04-802.

[30] GAO, Surface Transportation: Many Factors Affect Investment 
Decisions, GAO-04-744 (Washington, D.C.: June 30, 2004).

[31] This commission, proposed by the administration and included in 
both the Senate and House reauthorization bills approved during 2004 
but not enacted before the adjournment of the 108TH Congress, is to 
consider how the program is financed and the role of other stakeholders 
in financing it. As we reported, the appropriate program structure and 
mechanisms for delivering that funding are important components of 
making these decisions.

[32] GAO, Mass Transit: Project Management Oversight Benefits and 
Future Funding Requirements, GAO/RCED-00-221 (Washington, D.C.: Sept. 
15, 2000).

[33] GAO, High-Risk Series: Strategic Human Capital Management, GAO-03-
120, (Washington, D.C.: Jan. 1, 2003).

[34] FHWA Stewardship/Oversight Task Force Final Report, March 20, 
2001.

[35] GAO-02-702T.

[36] GAO. Executive Guide: Leading Practices in Capital Decision-
Making, GAO-AIMD-99-32. (Washington D.C.: Dec. 14, 1999).

[37] GAO. Intercity Passenger Rail: Amtrak's Management of Northeast 
Corridor Improvements Demonstrates Need for Applying Best Practices, 
GAO-04-94 (Washington, D.C.: Feb. 27, 2004).

[38] GAO, Human Capital: Implementing Pay for Performance at Selected 
Personnel Demonstration Projects, GAO-04-83. (Washington, D.C.: Jan. 
23, 2004).

[39] GAO, Managing for Results: Emerging Benefits From Selected 
Agencies' Use of Performance Agreements, GAO-01-115 (Washington D.C.: 
Oct. 30, 2000).

[40] National Research Council, "Improving Project Management in the 
Department of Energy," National Academy Press, 1999.

[41] GAO-04-546G.

[42] GAO, Executive Guide: Effectively Implementing the Government 
Performance and Results Act, GAO/GGD-96-118. (Washington D.C.: June 
1996). 

[43] GAO, Program Evaluation: Studies Helped Agencies Measure or 
Explain Program Performance. GAO/GGD-00-204. (Washington D.C.: Sept. 
29, 2000).

[44] GAO, Executive Guide: Leading Practices in Capital Decision-
Making, GAO-AIMD-99-32. (Washington D.C.: Dec. 14, 1998).

[45] Capital Programming Guide, Office of Management and Budget. July 
1997. The Guide is a supplement to Circular A-11, which the Office of 
Management and Budget issued to help agencies integrate and implement 
GPRA requirements.

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548: 

To order by Phone: 



Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: