This is the accessible text file for GAO report number GAO-02-785 
entitled 'Pipeline Safety and Security: Improved Workforce Planning and 
Communication Needed' which was released on September 26, 2002.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Report to the Ranking Minority Member, Committee on Energy and 

Commerce, House of Representatives:



United States General Accounting Office:



GAO:



August 2002:



Pipeline Safety and Security:



Improved Workforce Planning and Communication Needed:



GAO-02-785:



Contents:



Letter:



Results in Brief:



Background:



OPS Has Set an Ambitious Schedule for Implementing Integrity 

Management:



OPS Faces Additional Challenges in Implementing the Integrity 

Management Approach:



OPS’s Plan for Obtaining Resources and Expertise Is Not Complete or 

Adequately Communicated to State Partners:



OPS Is Taking Action to Improve Data Quality:



Conclusions:



Recommendations for Executive Action:



Agency Comments and Our Evaluation:



Scope and Methodology:



Appendix I: Comments from the U.S. Department of 

Transportation:



Tables:



Table 1: Hazardous Liquid and Natural Gas Pipeline Mileage in the 

United States:



Table 2: OPS’s Data Quality Initiatives:



Figure:



Figure 1: Time Line for OPS’s Implementation of the Integrity 

Management Approach:



Abbreviations:



DOT: Department of Transportation



OPS: Office of Pipeline Safety



RSPA: Research and Special Programs Administration:



August 26, 2002:



The Honorable John D. Dingell

Ranking Minority Member

Committee on Energy and Commerce

House of Representatives:



Dear Mr. Dingell:



The Office of Pipeline Safety (OPS), within the Department of 

Transportation’s (DOT) Research and Special Programs Administration 

(RSPA), is implementing a new approach to overseeing the safety of a 

2.2-million-mile network of pipelines in the United States that 

transports potentially dangerous materials, including hazardous 

liquids, such as oil, and natural gas. Traditionally, OPS has carried 

out its oversight responsibility by issuing minimum safety standards 

and enforcing them uniformly across all pipelines. To better focus on 

safety risks that are unique to individual pipelines, OPS has been 

exploring a risk-based approach to overseeing pipeline safety since the 

mid-1990s and is now implementing this approach. This initiative--

termed “integrity management”--requires pipeline operators, in 

addition to meeting minimum safety standards, to develop programs to 

assess, evaluate, and mitigate any risks to pipeline segments where a 

leak or rupture could have significant consequences, such as near 

highly populated areas. To address security concerns after September 

11, 2001, OPS advised pipeline operators to consider potential 

terrorist threats to their pipelines in their assessments of pipeline 

risks. In addition to the integrity management initiative, OPS is 

implementing several actions to collect better data on pipeline 

incidents in order to improve its oversight of the pipeline industry 

and help evaluate the performance of the integrity management approach.



You asked us to examine what OPS has done and plans to do to implement 

this new approach, which differs significantly from OPS’s traditional 

oversight activities. Accordingly, we examined OPS’s (1) steps to 

implement the integrity management approach, (2) challenges in 

implementing this approach, (3) plans for obtaining the resources and 

expertise needed to oversee pipeline safety under integrity management, 

and (4) major initiatives to improve the quality of its data on 

pipeline incidents.



Results in Brief:



OPS has to complete several important steps to implement its integrity 

management approach within an ambitious, self-imposed schedule. The 

agency began applying this new regulatory approach to hazardous liquid 

pipelines in 2000 by issuing final rules requiring operators of these 

pipelines to develop integrity management programs. OPS now plans to 

finalize integrity management requirements for natural gas transmission 

pipelines and to inspect the programs of more than 1,000 hazardous 

liquid and natural gas transmission pipeline operators. Although OPS 

may take until 2006 or later to complete these steps, the agency’s 

schedule for the next 2 years is particularly challenging. For example, 

OPS plans to:



* issue proposed and final rules to establish requirements for 

integrity management programs for natural gas transmission pipeline 

operators by spring 2003,



* conduct comprehensive inspections--each of which takes about 2 weeks-

-of the programs for over 200 hazardous liquid pipeline operators from 

summer 2002 through fall 2004, and:



* prepare to conduct comprehensive inspections of the programs for 

about 830 natural gas transmission pipeline operators from summer 2004 

to summer 2006.



While implementing its integrity management approach, OPS must also 

perform ongoing oversight duties, such as inspecting the construction 

of new pipelines and investigating pipeline incidents. Although OPS 

officials believe that the agency can achieve this ambitious schedule 

with the assistance of state pipeline safety inspectors, the schedule 

leaves little margin for error if OPS is to meet its time frame. For 

example, agency officials acknowledge that they have prepared protocols 

for comprehensive inspections of hazardous liquid operators under a 

tight schedule in order to start these inspections in summer 2002, as 

planned.



In addition to meeting its ambitious schedule, OPS faces a number of 

other challenges in implementing this new regulatory approach. These 

challenges include (1) enforcing the integrity management requirements 

consistently and effectively, (2) ensuring that natural gas 

transmission pipeline operators use assessment methods appropriately, 

(3) establishing an inspection interval for natural gas transmission 

pipelines, (4) measuring and reporting on the effectiveness of the 

approach, and (5) developing and implementing an approach for 

overseeing pipeline security. OPS is pursuing a variety of actions to 

address these challenges. For example, the agency has developed 

detailed guidance for inspectors to use in reviewing operators’ 

integrity management programs to help ensure that enforcement decisions 

will be consistent, is preparing a proposed integrity management rule 

for natural gas transmission pipelines that will include proposed 

requirements on assessment methods and inspection intervals for these 

pipelines, and is developing protocols for reviewing operators’ 

security programs. However, although some hazardous liquid pipeline 

operators have begun to implement their integrity management programs, 

OPS has not yet established uniform performance measures for these 

programs. OPS officials told us that they intend to establish such 

measures, which would allow the agency to track the progress of these 

programs in improving pipeline safety, by the end of 2002. OPS also 

needs to resolve several issues related to its approach for overseeing 

pipeline security. For example, OPS needs to determine how best to use 

its own and its state partners’ resources for carrying out this 

oversight because the agency does not anticipate obtaining additional 

resources for this purpose.



OPS’s efforts to identify the resources and expertise needed to 

implement its integrity management approach are hampered by the lack of 

an up-to-date assessment of current and future staffing and training 

needs and an examination of the workforce’s deployment across the 

organization--essential elements of a “workforce plan.”[Footnote 1] 

Although OPS has estimated the number of inspectors it needs to hire to 

implement its integrity management approach and has developed a 

curriculum to train federal and state inspectors, its resource 

estimates are outdated and cover only the initial phases of 

implementation. In addition, OPS has not communicated its intentions 

for involving its state partners in implementing the integrity 

management approach. Although the agency believes it will need to 

augment its own resources with those of states to effectively implement 

integrity management, OPS officials have acknowledged that the agency’s 

efforts to communicate with state partners have been limited. This 

limited communication has left some states unsure of the roles they 

will play. OPS is acting to resolve some of these issues, but a 

workforce plan--including updated multiyear resource estimates--would 

help the agency better plan for future resource needs. Furthermore, a 

strategy for communicating with states would help OPS to effectively 

involve its state partners in the implementation of the integrity 

management approach.



In the past, OPS has experienced a number of problems with the 

completeness and accuracy of its data on pipeline incidents, which the 

agency uses in overseeing pipeline safety. For example, OPS’s incident 

report forms used a limited number of cause categories--”other” 

accounted for about one-fourth of all pipeline incidents--and OPS did 

not have a procedure for following up with operators to ensure that 

their incident reports included any necessary revisions. OPS is 

implementing several initiatives to improve the completeness and 

accuracy of its data, which, if effectively implemented, should help 

the agency improve its oversight of pipeline safety. For example, OPS 

has revised its incident report forms to include more than 3 times as 

many cause categories, has assigned inspectors to review forms and 

follow up with operators, and has proposed to require an annual report 

from hazardous liquid operators. The agency plans to have most of the 

initiatives implemented for 2002 data. OPS plans to use the improved 

data to, among other things, help develop performance measures for the 

integrity management approach, focus its oversight efforts on the 

greatest risks to pipeline safety, and prioritize research and 

development projects. According to some state and federal government 

and industry officials, these initiatives address OPS’s underlying data 

problems and will enable the agency to better understand the causes of 

incidents and improve its oversight of pipeline safety.



Although OPS has efforts under way to address several challenges it 

faces in implementing its new regulatory approach, the lack of a 

workforce plan and strategy for communicating with its state partners 

puts it at risk of not being able to overcome these challenges and 

effectively implement this approach on schedule. Therefore, we are 

recommending that OPS prepare a workforce plan that includes updated 

current and future resource estimates and develop a strategy for 

clearly communicating with its state partners about the role that they 

will play in implementing the integrity management approach. In 

commenting on a draft of this report, DOT officials noted that OPS 

recognizes the need for workforce planning and improved communication 

with the states, as we recommended. They also provided information on 

the agency’s current and planned efforts in these areas. DOT’s comments 

are reprinted in appendix I.



Background:



Pipelines transport about 65 percent of the crude oil and refined oil 

products and nearly all of the natural gas in the United States. Table 

1 shows the three primary types of pipelines that form a 2.2-million-

mile network across the nation.



Table 1: Hazardous Liquid and Natural Gas Pipeline Mileage in the 

United States:



Type of pipeline: Hazardous liquid; Description: Transports crude oil 

to refineries and refined oil products, such as gasoline, to product 

terminals; Approximate miles in the: 159.



Type of pipeline: Natural gas transmission; Description: Transports 

natural gas over long distances from sources to communities; 

Approximate miles in the: 325[A].



Type of pipeline: Natural gas distribution; Description: Transports 

natural gas throughout the communities to consumers; Approximate miles 

in the: 1,850.



[A] This mileage figure includes onshore and offshore transmission 

pipelines as well as some gathering lines, which collect natural gas 

from producing wells and carry the product to a natural gas 

transmission pipeline.



Source: OPS data.



[End of table]



Pipelines are inherently safer than other modes of freight 

transportation for hazardous liquids and natural gas. Although an 

average of about 24 fatalities resulted from pipeline incidents each 

year from 1989 through 2000, this number is relatively low compared 

with the number of fatalities from other forms of freight 

transportation. On average, about 66 people die each year in barge 

incidents, about 590 in railroad incidents, and about 5,100 in truck 

incidents. Despite the relative safety of pipelines, pipeline incidents 

can have tragic consequences, as evidenced by the pipeline ruptures in 

Bellingham, Wash. (1999), and Carlsbad, N. Mex. (2000). These 

incidents, which caused 15 fatalities, highlight the importance of 

pipeline safety.



OPS develops, issues, and enforces regulations to ensure the safe 

transportation of hazardous liquids and natural gas by pipeline. In 

fiscal year 2002, OPS employed about 135 people, over half of whom were 

pipeline inspectors. In addition, state agencies have roles in pipeline 

safety. In general, OPS retains full responsibility for inspecting and 

enforcing regulations on interstate pipelines but certifies states to 

perform these functions for intrastate pipelines.[Footnote 2] Certified 

states are allowed to impose safety requirements for intrastate 

pipelines that are stricter than the federal regulations. In 2002, 48 

state agencies, the District of Columbia, and Puerto Rico were 

certified for intrastate natural gas pipeline inspections, and 13 state 

agencies were certified for intrastate hazardous liquid pipeline 

inspections. OPS also uses some states to help inspect interstate 

pipelines. These states, or “interstate agents,” inspect segments of 

interstate pipelines within their boundaries. However, OPS handles any 

enforcement actions identified through inspections conducted by these 

interstate agents. In 2002, 11 states were acting as interstate agents-

-2 states for hazardous liquid pipelines, 5 states for natural gas 

pipelines, and 4 states for both types of pipelines. In total, there 

are about 400 state pipeline safety inspectors trained to assist OPS in 

overseeing pipeline safety within their states.



OPS has traditionally carried out its oversight responsibility by 

establishing minimum standards in its regulations and enforcing them 

uniformly across pipelines.[Footnote 3] However, this uniform 

regulatory approach does not account for differences in the risks faced 

by individual pipelines. For example, pipelines located in the Pacific 

Northwest states are susceptible to damage from geologic hazards, such 

as landslides, but OPS’s uniform, minimum regulations do not address 

this risk.



Recognizing that pipeline operators face different risks depending on 

such factors as location and the products they carry, OPS began 

exploring the concept of a risk-based approach to pipeline safety in 

the mid-1990s. In 1996, the Accountable Pipeline Safety and Partnership 

Act included provisions for DOT to establish a demonstration program to 

test a risk-based approach.[Footnote 4] As a result, OPS established 

the Risk Management Demonstration Program, which went beyond the 

agency’s traditional regulatory approach by allowing individual 

companies to identify and focus on the unique risks to their pipelines. 

Partly on the basis of OPS’s experience with the demonstration program, 

the agency moved forward with a new regulatory approach--termed 

integrity management--to supplement uniform, minimum regulations. In a 

May 2000 report, we recognized the potential benefits of a risk-based 

approach to pipeline safety; however, we expressed concern that OPS did 

not have performance measures in place to demonstrate the effectiveness 

of the Risk Management Demonstration Program or the resulting integrity 

management approach.[Footnote 5]



The integrity management approach requires individual pipeline 

operators to develop programs to systematically identify and address 

risks to the segments of their pipelines that could affect “high 

consequence areas” where a leak or rupture would have the greatest 

impact, including highly populated or environmentally sensitive 

areas.[Footnote 6] OPS designed the integrity management approach to 

achieve greater safety by allowing individual operators flexibility in 

tailoring their programs to the characteristics of their pipelines. 

This flexibility is reflected in performance-based requirements, which 

allow operators to determine the most appropriate processes and 

technologies to use in their integrity management programs, subject to 

OPS’s review. For example, operators may use a variety of techniques 

for assessing pipeline integrity and analyzing these results and other 

available information about the conditions of their pipelines. In 

addition, OPS’s integrity management program requirements include 

prescribed elements that provide some consistency among integrity 

management programs. For example, OPS requires all hazardous liquid 

pipeline operators to conduct a baseline assessment of the integrity of 

all pipeline segments that could affect high consequence areas, 

periodically reassess the integrity of these pipeline segments, take 

prompt action to address any anomalies found during the assessments 

that threaten the integrity of the pipeline, and develop measures of 

the program’s effectiveness. After September 11, 2001, OPS advised 

pipeline operators also to consider potential terrorist threats to 

their pipelines in their assessments of pipeline integrity.[Footnote 7]



OPS Has Set an Ambitious Schedule for Implementing Integrity 

Management:



OPS has to complete several important steps to implement its integrity 

management approach under an ambitious self-imposed schedule, including 

finalizing requirements for integrity management programs and 

inspecting the programs of more than 1,000 hazardous liquid and natural 

gas transmission pipeline operators. Although it may take OPS until 

2006 or later to complete these steps, the agency’s schedule for the 

next 2 years is particularly challenging.



To finalize the requirements for integrity management programs, OPS 

plans to issue proposed and final rules establishing these requirements 

for natural gas transmission pipeline operators by spring 

2003.[Footnote 8] The agency has already issued separate rules 

establishing requirements for hazardous liquid pipelines.[Footnote 9] 

OPS is issuing separate rules for the different types of pipeline 

operators because of differences in the products carried by their 

pipelines, the types of risks faced, and the configuration of the 

pipelines. For example, hazardous liquid pipelines are more subject to 

metal fatigue, which can increase the risk of pipeline failure, than 

gas pipelines because they experience a greater number of pressure 

cycles. However, hazardous liquid pipelines also tend to be more 

uniform in size than natural gas pipelines, which makes it easier for 

them to accommodate internal inspection devices to detect corrosion. 

These differences have implications for the requirements for integrity 

management programs, such as the types of assessment methods that 

operators can use to identify risks to their pipelines and the 

appropriate intervals between required safety assessments.



OPS chose to issue the rule for operators of large hazardous liquid 

pipelines (those with 500 or more miles of pipeline) first because it 

needed more information on how integrity management principles should 

be applied to smaller hazardous liquid pipelines and natural gas 

transmission pipelines. Consequently, OPS issued requirements for 

operators of large hazardous liquid pipelines in December 2000 and 

similar requirements for operators of small hazardous liquid pipelines 

(those with less than 500 miles of pipeline) in January 2002. OPS 

anticipates issuing a proposed rule for operators of gas transmission 

pipelines by the end of summer 2002 and a final rule in spring 2003.



In addition to completing the requirements, OPS needs to inspect the 

integrity management programs developed by more than 1,000 individual 

operators of hazardous liquid pipelines and natural gas transmission 

pipelines. OPS has developed and begun to implement the following four-

phased approach for reviewing and monitoring the programs for 65 

operators of large hazardous liquid pipelines.



* Phase 1: From January through April, 2002, OPS conducted “quick hit” 

inspections of each operator’s identification of pipeline segments that 

could affect high consequence areas to determine if the operator had 

correctly identified these segments. OPS also reviewed documents 

describing how each operator intends to implement all elements of an 

integrity management program to determine whether the operator was 

making satisfactory progress in developing a program.



* Phase 2: From August 2002 through November 2004, OPS plans to conduct 

“comprehensive” inspections of each operator’s more fully developed 

integrity management program, including each operator’s plans for 

conducting an initial assessment of the safety of its pipelines. OPS 

estimates that each inspection will require about 2 weeks.



* Phase 3: After completing phase 2, OPS plans to monitor operators’ 

progress on their programs through periodic inspections. OPS 

anticipates that each operator will be inspected at least once every 2 

years.



* Phase 4: Concurrently with the other phases, OPS plans to review and 

respond to notifications from operators of changes in their 

programs.[Footnote 10] For example, an operator is required to notify 

OPS if it cannot repair any anomaly that affects the integrity of the 

pipeline within the time frame specified in the rule.[Footnote 11]



OPS is conducting and planning a variety of activities aimed at 

carrying out these four phases, including developing inspection 

protocols and providing training to federal and state inspectors on 

conducting the inspections. OPS anticipates using a similar phased 

approach to review and monitor the programs for operators of small 

hazardous liquid and natural gas transmission pipelines. [Footnote 12]



According to OPS officials, OPS’s schedule for implementing the 

integrity management approach is ambitious and presents a significant 

challenge. For the 65 operators of large hazardous liquid pipelines, 

OPS plans to conduct all of the comprehensive inspections within 4 

years of issuing the final rule requiring integrity management programs 

for these operators. If OPS issues the final rule for integrity 

management programs for natural gas transmission pipelines in spring 

2003, as it anticipates, and follows a similar schedule for conducting 

comprehensive inspections, then the agency will not complete 

inspections of these pipelines before spring 2006. However, because 

there are about 60 more interstate natural gas transmission pipeline 

operators than hazardous liquid operators that OPS will need to 

inspect, it may take the agency longer to complete these inspections. 

During this time frame, OPS also has to perform ongoing oversight 

activities, such as conducting standard inspections, investigating 

incidents, and inspecting pipeline construction.[Footnote 13] Figure 1 

shows a time line for the steps that OPS must complete to implement 

integrity management for large and small hazardous liquid pipelines and 

gas transmission pipelines.



Figure 1: Time Line for OPS’s Implementation of the Integrity 

Management Approach:



[See PDF for image]



[A] This time frame assumes that OPS will issue the final rule for 

integrity management programs for natural gas transmission pipelines in 

spring 2003 and will follow a schedule for conducting inspections of 

small hazardous liquid and gas transmission operators similar to the 

inspections for large hazardous liquid operators.



Source: GAO analysis of information provided by OPS.



[End of figure]



According to OPS officials, the agency is implementing integrity 

management under an ambitious time frame because it wants to emphasize 

to operators the importance of evaluating and improving the safety of 

their pipelines. In addition, OPS’s integrity management approach 

fulfills some long-standing congressional mandates and recommendations 

of the National Transportation Safety Board (the Safety Board), and the 

agency wants to address concerns about the amount of time it has taken 

to fulfill these mandates and recommendations.[Footnote 14] Although 

the schedule is ambitious, OPS officials believe the agency can meet 

its time frame by hiring additional federal inspectors, using 

contractor support, and relying on state pipeline safety inspectors to 

conduct integrity management inspections for intrastate pipelines. 

However, as shown in figure 1, the next 2 years leave little margin for 

error if OPS is to follow its schedule. For example, agency officials 

acknowledge that they have prepared protocols and guidance for 

comprehensive inspections under a tight time frame in order to meet 

their target date for starting these inspections.



OPS Faces Additional Challenges in Implementing the Integrity 

Management Approach:



In addition to meeting its ambitious schedule, OPS faces a number of 

other challenges in implementing its integrity management approach. 

Some challenges--such as enforcing the requirements for integrity 

management programs consistently and effectively, and measuring and 

reporting on the effectiveness of the integrity management approach--

are more urgent for hazardous liquid pipeline operators because they 

have begun implementing their programs. Other challenges--such as 

ensuring that operators use pipeline safety assessment methods 

appropriately and establishing an inspection interval--have been 

addressed in OPS’s requirements for integrity management programs for 

hazardous liquid pipelines and must now be resolved for natural gas 

transmission pipelines before OPS can issue a final rule for these 

pipelines. In addition, since September 11, 2001, OPS faces the 

challenge of developing an approach to overseeing pipeline security, 

including how to incorporate security into its integrity management and 

standard inspections of pipeline operators.



OPS is taking a variety of actions to address these challenges as 

hazardous liquid pipeline operators are implementing their individual 

programs. However, in attempting to meet its ambitious schedule for 

implementing the integrity management approach for hazardous liquid 

pipeline operators, OPS has not yet required these operators to adopt 

standardized measures for monitoring the performance of their programs 

or to provide the agency with the results of such measures. Agency 

officials told us that they intend to establish such requirements by 

the end of 2002 and are considering ways to report performance 

measurement data to local officials. OPS also needs to resolve several 

issues related to its approach for overseeing pipeline security. For 

example, OPS will need to determine how best to use its existing 

resources, as well as those of its state partners, for carrying out 

security oversight because the agency does not anticipate obtaining 

additional resources for this purpose.



Enforcing the Integrity Management Requirements Consistently and 

Effectively:



In implementing its integrity management approach, OPS faces the 

challenge of enforcing compliance with the program’s flexible 

requirements consistently and effectively--a much more difficult task 

than enforcing compliance with uniform minimum safety standards, as OPS 

has traditionally done. According to representatives of the pipeline 

industry, environmental organizations, and states, inspectors will face 

difficulties in judging the adequacy of complex integrity management 

processes that will vary from company to company. For example, under 

the integrity management rules, operators must analyze risks for each 

pipeline segment that could affect high consequence areas in order to 

identify actions needed to enhance public safety or environmental 

protection. Operators may choose from a range of actions, such as 

improving leak detection systems or installing shut-off valves to limit 

the amount of product released during a leak or rupture, but they must 

implement those actions they have identified as necessary. It will be 

challenging for inspectors to determine the adequacy of operators’ risk 

analyses because, although the rule specifies some risk factors that 

operators should consider, it allows them to choose from a wide variety 

of methods for conducting risk analyses. Furthermore, because 

inspections will be conducted by five regional offices and 48 state 

partners, it will be challenging for OPS to ensure that inspectors make 

consistent judgments nationwide.



OPS officials have told us that their main goal in implementing the 

integrity management rules is to develop a nationally consistent 

approach for inspecting operators’ integrity management programs. The 

agency is taking a number of steps aimed at ensuring consistency, 

including:



* completing a set of detailed inspection protocols and guidance 

designed to provide clear criteria to inspectors for evaluating the 

adequacy of operators’ actions and making enforcement decisions;



* putting together inspection teams of staff from multiple regions, 

including its most experienced inspectors, as well as external experts 

and state representatives; and:



* requiring all OPS and state inspectors who will conduct integrity 

management inspections to complete a set of relevant training courses.



According to OPS officials, the development and use of detailed 

protocols and guidance for conducting integrity management inspections 

are their most important means for ensuring the consistency of 

inspectors’ decisions during these inspections. OPS has developed an 

initial set of protocols and guidance for the comprehensive inspections 

of operators of large hazardous liquid pipelines. The agency plans to 

pilot test the use of these protocols in its first five comprehensive 

inspections, which are scheduled for August through October, 2002. The 

agency intends to make necessary adjustments to the protocols and 

guidance on the basis of this pilot testing and to revise them 

periodically afterward on the basis of further experience with its 

inspections.



OPS, according to some environmental organization representatives, may 

face particular difficulties in enforcing its integrity management 

rules because operators may disagree with enforcement actions 

pertaining to flexible requirements in the rules.[Footnote 15] OPS 

officials told us that they intend to vigorously enforce the integrity 

management rules, levying fines for serious violations, to ensure that 

operators comply with the requirements. After conducting 40 quick hit 

inspections of hazardous liquid pipeline operators, the agency has 

decided to take enforcement actions in 36 cases. OPS anticipates that 

about half of these actions will be notices of amendment and the other 

half will be notices of probable violation. Notices of amendment cite 

inadequate operator procedures and require operators to make needed 

improvements. Notices of probable violation generally contain a 

proposed compliance order requiring companies to take action to correct 

the violations found and may propose fines.



According to OPS officials, the agency anticipates that many operators 

will question integrity management enforcement actions, but it has 

prepared for this challenge by increasing its enforcement staff. It 

also plans to establish a new Enforcement Office, which will formulate 

enforcement policies and review enforcement actions to ensure 

consistency, and it plans to provide more training on enforcement 

issues for inspector and enforcement staff. OPS officials have stressed 

that they have been under tight time frames in developing an inspection 

and enforcement approach for large hazardous liquid pipelines and that 

this approach will evolve over time, as the agency implements the 

approach for small liquid and gas transmission pipelines.



Ensuring That Natural Gas Pipeline Operators Use Assessment Methods 

Appropriately:



Because the methods typically used for assessing the integrity of 

hazardous liquid pipelines are either not currently suitable for a 

large portion of natural gas pipelines or would interrupt the supply of 

gas to customers, OPS faces the challenge of ensuring that natural gas 

transmission pipeline operators use alternative assessment methods 

appropriately. Integrity management programs for hazardous liquid 

pipeline companies allow the use of two primary assessment methods: (1) 

internal inspection devices, or “smart pigs,” that run inside the 

pipeline to detect anomalies, such as corrosion, metal loss, or damage 

to the pipeline, and (2) hydrostatic testing, a process of draining the 

pipeline, filling it with water, and increasing the pressure of the 

water to test the strength of the pipeline. Both methods have limited 

applications for testing natural gas transmission pipelines. 

Specifically, one industry association estimates that smart pigs cannot 

move through about half of gas transmission pipeline mileage because of 

such pipeline features as variations in diameter, sharp bends, and 

valves that do not fully open. Hydrostatic testing, which interrupts 

the supply of natural gas to consumers for up to 3 weeks per test, may 

leave communities without an energy source because natural gas 

transmission pipelines have minimal storage facilities.[Footnote 16] 

Although integrity management programs for hazardous liquid pipeline 

operators allow the use of alternative safety assessment methods, they 

also specify that any other method must provide an equivalent level of 

protection and that operators must notify OPS before conducting the 

assessment.[Footnote 17]



As an alternative to smart pigs and hydrostatic testing, OPS is 

considering allowing gas transmission pipeline operators to use a 

method called “direct assessment” to assess the integrity of their 

pipelines. Direct assessment consists of four steps:



* Preassessment. The pipeline operator analyzes information about the 

physical characteristics of the pipeline--such as the coating material, 

soil moisture, and past leaks--to determine whether direct assessment 

is appropriate, what threats are likely to be present and significant, 

where these threats are likely to occur, and what tools should be used 

to inspect the areas of the ground above the pipeline where the threats 

are likely to occur.



* Indirect inspections. The operator uses one or more inspection tools 

to examine the pipeline through the soil in areas identified during the 

preassessment. For example, to identify corrosion on the exterior 

surface of a pipeline, an operator walks over the areas of the pipeline 

holding a tool that takes readings through the soil to assess the 

condition of the pipeline’s surface. Separate passes over the pipeline 

with two or more different types of tools are generally required to get 

an accurate assessment.



* Direct examinations. Using the results of the aboveground 

examination, the operator digs holes at intervals along the pipeline to 

examine suspected problem areas. After the holes have been dug, the 

pipeline can be examined visually and with diagnostic equipment, such 

as tools that measure the thickness of the pipe, to determine whether 

the operator needs to repair the pipeline or take other corrective 

action. For safety reasons, the pressure of the natural gas within the 

pipeline is generally reduced by about 25 percent during this step.



* Postassessment. The operator integrates and analyzes the information 

gathered during the three previous steps to determine whether 

additional excavations are necessary and how often pipeline segments 

should be reassessed.



Like other assessment methods, direct assessment has some limitations. 

For example, direct assessment has been proven reliable in detecting 

only one threat to the integrity of pipelines--external corrosion--

while smart pigs can identify a wide range of threats to the integrity 

of pipelines, such as external corrosion, internal corrosion, and metal 

loss from external damage.[Footnote 18] State pipeline safety officials 

and some natural gas pipeline company representatives we spoke with are 

concerned about the limitations of direct assessment and believe that 

its use should be closely monitored. For example, the Texas Railroad 

Commission’s pipeline safety section requires intrastate pipeline 

operators to obtain approval from the office if they plan to use direct 

assessment to assess the safety of their pipelines.[Footnote 19] To 

obtain approval, the operators must present evidence at a hearing that 

this method is a valid choice for the circumstances of the pipeline and 

receive approval from the commission.



OPS officials explained that the agency has ongoing research activities 

focused on advancing the state of the art of direct assessment 

technology. Agency officials expect to issue a proposed rule by the end 

of this summer for integrity management requirements for natural gas 

transmission pipeline operators, which will address how direct 

assessment should be treated as an assessment method.



Establishing an Inspection Interval for Gas Pipelines:



Establishing an appropriate interval between the safety inspections 

that operators are required to make of gas pipelines is likely to be a 

complex and controversial challenge for OPS because the agency must 

strike a balance between the existing industry standards, which allow 

intervals of up to 20 years, and shorter intervals. Although the 

appropriate interval for individual pipelines could vary with their 

circumstances, OPS is including a maximum interval in the requirements 

for integrity management programs to ensure that all operators conduct 

their inspections within a reasonable time frame. For hazardous liquid 

pipelines, OPS requires inspections at least once every 5 

years.[Footnote 20] For natural gas transmission pipelines, longer 

intervals could be justified for several reasons:



* Pressure fluctuations, which can weaken a pipeline, are less 

frequent.



* Thicker pipeline walls or operation at lower pressure is already 

required in high consequence areas[Footnote 21] under the existing 

uniform requirements.



* Internal corrosion is less likely because natural gas contains a 

minimal amount of moisture.



* Fewer storage facilities exist, therefore, interrupting the flow of 

gas to conduct inspections of the pipeline would have a greater impact 

on customers.



Because of these differences, the industry standards for natural gas 

pipeline integrity management programs (published by the American 

Society of Mechanical Engineers) allow maximum inspection intervals 

from 5 years to 20 years, depending on the type of assessment method 

and test procedures used and the operating pressure of the 

pipeline.[Footnote 22] For higher pressures, the maximum interval is 5 

years for less stringent methods and procedures (e.g., using direct 

assessment and excavating a sample of potential problem areas) or 10 

years for more stringent methods and procedures (e.g., using direct 

assessment and excavating all problem areas). For lower pressures, the 

maximum interval is 20 years using any type of assessment method and 

the most stringent test procedures.



According to some pipeline industry and environmental group 

representatives, the maximum inspection interval for natural gas 

transmission pipelines should be limited to between 5 and 10 years to 

allow for a “worst-case” scenario. However, industry representatives 

noted that longer inspection intervals could be justified more for 

natural gas pipelines than for hazardous liquid pipelines, given the 

differences in their characteristics. For example, they cited the 

greater possibility of damage to liquid pipelines from pressure 

fluctuations and internal corrosion and noted that external corrosion 

can threaten both types of pipelines. One natural gas transmission 

pipeline operator told us that it would take 12 years for a worst 

possible case of external corrosion to damage a pipeline enough to 

cause a failure. According to this operator, a 10-year inspection 

interval would allow time for pipeline operators to detect and repair 

such a worst case before it resulted in an incident.



OPS is trying to achieve a balance between these arguments as it 

prepares the proposed rule on integrity management for gas transmission 

pipelines. For the proposed rule, OPS is considering a maximum 

inspection interval of 5 or more years for pipelines assessed by direct 

assessment and 10 years for pipelines inspected by smart pigs or 

hydrostatically tested. For pipelines that operate at lower pressure, 

OPS is considering allowing inspection intervals that are longer than 

10 years.



Measuring and Reporting on the Effectiveness of the Integrity 

Management Approach:



OPS faces the challenge of establishing performance measures to 

determine the overall effectiveness of the integrity management 

approach and monitor the progress of individual operators’ programs. 

Such performance measures would assist in determining the impact of the 

integrity management approach on pipeline safety and identifying needed 

improvements. OPS officials told us that the agency has identified some 

performance measures for integrity management, intends to require 

operators to report the results of these measures to the agency, and is 

considering ways to report performance measurement information to local 

officials and the public.



According to OPS officials, the agency has developed measures of the 

overall effectiveness of the integrity management approach on the basis 

of its data on pipeline leak and rupture incidents and will start 

publicly reporting these measures by early 2003.[Footnote 23] Some 

recent improvements in OPS’s incident data, such as new requirements 

for operators to report on whether incidents occurred in high 

consequence areas, should allow OPS to use these data to measure the 

overall performance of the integrity management approach in reducing 

incidents in these areas.[Footnote 24] (OPS’s efforts to improve these 

data are discussed later in this report.) For example, the agency 

intends to measure the effectiveness of integrity management by 

tracking reductions in the number of significant pipeline incidents and 

in the volume of oil spilled in high consequence areas. However, 

because operators of large hazardous liquid pipelines did not begin 

implementing their integrity management programs until 2002 and other 

types of pipeline operators will not begin implementing their programs 

until subsequent years, it will be some time before OPS can analyze 

trends and determine the impact of the integrity management approach on 

safety.



OPS also intends to develop new requirements for operators to report 

uniform performance measures for their individual integrity management 

programs. OPS’s current integrity management rules for hazardous liquid 

pipelines require operators to develop performance measures for their 

programs, but the rules do not specify what measures they should use. 

As a result, these measures will not be consistent, and therefore OPS 

will not be able to use these data to develop industrywide measures or 

to compare the performance of operators. OPS and industry officials 

have told us that the development of consistent performance measures 

for operator integrity management programs has been difficult because 

of a lack of agreement on which measures can be standardized. OPS 

officials have recently worked with both the hazardous liquid and gas 

transmission pipeline industries to identify performance measures for 

integrity management programs that can be standardized, such as the 

numbers of integrity assessments conducted and repairs completed. OPS 

intends to modify its integrity management requirements for liquid 

pipeline operators by the end of 2002 to include a requirement that 

operators adopt these standardized measures and make the results of 

these measures available to OPS.[Footnote 25] Until these operators 

start providing such standardized data to OPS, the agency’s ability to 

monitor and compare the performance of operators’ integrity management 

programs, some of which began in spring 2002, will be limited. The 

agency also intends to include similar requirements for gas 

transmission pipeline operators in the proposed and final integrity 

management rules for these pipelines, anticipated by spring 2003. OPS 

intends to require that hazardous liquid as well as natural gas 

transmission operators start making these standardized performance 

measurement data available to the agency in 2004.[Footnote 26]



Although OPS intends to make industrywide measures on the effectiveness 

of the integrity management approach available on its Web site and in 

public reports, the agency has not yet determined what measures of 

individual operators’ performance will be made publicly available or 

how this information will be communicated. The Safety Board and some 

public interest organizations have recommended that pipeline operators 

provide more information to the public about their safety operations. 

In response, the hazardous liquid and gas transmission pipeline 

industries, with the encouragement of OPS, are developing joint 

guidelines for operators on communicating safety information about 

their pipelines to the public and expect to finalize these guidelines 

by the end of 2002. At that time, OPS plans to consider whether to 

adopt all or part of these guidelines as regulations. However, the 

guidelines will not address what information operators should provide 

to state and local officials and the public about their integrity 

management programs. The liquid and gas pipeline industries intend to 

develop additional guidelines on this issue after finalizing their 

initial guidelines, and OPS plans to consider incorporating these 

additional guidelines as requirements after they are finalized. In 

addition to this industry initiative, OPS is currently considering 

alternatives for reporting information on the performance of individual 

operators’ integrity management programs. Because operators want to 

protect information that may pose a security risk if publicly 

distributed, OPS officials have told us that they are considering 

developing a system that would make information on individual 

operators’ performance available to local officials who need it, but 

not to the general public.



Developing and Implementing an Approach for Overseeing Pipeline 

Security:



Since September 11, 2001, OPS has faced the challenge of ensuring that 

operators are taking appropriate actions to protect their pipeline 

systems from acts of terrorism.[Footnote 27] To address this challenge, 

OPS has been developing an approach for overseeing pipeline security 

that does not involve the development of new regulatory requirements. 

Under this approach, OPS and state inspectors will review operators’ 

pipeline security programs to determine whether they follow guidelines 

developed by the pipeline industry with OPS’s participation and review. 

The agency intends to conduct these reviews as part of its 

comprehensive inspections of integrity management programs as well as 

its ongoing standard inspections of pipelines.[Footnote 28] These 

reviews will focus on how operators are managing security risks at 

critical facilities, because the agency will expect operators to have 

more rigorous security practices in place at these facilities.[Footnote 

29] OPS is developing protocols for conducting these security reviews, 

but it still needs to resolve several issues to fully develop and 

implement its security oversight approach.[Footnote 30]



Currently, OPS’s regulations have few specific requirements pertaining 

to security. The agency has decided not to develop new security 

regulations because it believes that progress can be achieved more 

quickly by encouraging companies to voluntarily improve their security 

practices following industry guidelines. In addition, OPS officials are 

concerned that the inherent openness of the rulemaking process would 

require the agency to publish sensitive information, such as 

definitions of critical facilities and specific protective measures. 

Furthermore, RSPA’s Office of the Chief Counsel has determined that OPS 

currently has enough statutory and regulatory authority to take 

enforcement actions if it finds that security at a critical pipeline 

facility is inadequate. Industry representatives told us that they 

prefer a nonregulatory approach, citing concerns about the need for 

flexibility in designing security programs suitable for each facility. 

However, some state pipeline safety officials, as well as some Members 

of Congress, have suggested that new security regulations may be needed 

to ensure that operators improve their security programs and practices. 

Legislation has been proposed that would require DOT to prescribe 

standards for pipeline security programs and approve or disapprove each 

operator’s program on the basis of their adherence to these 

standards.[Footnote 31]



Before fully implementing its security oversight approach, OPS must 

reach agreement with pipeline operators on certain aspects of its 

security reviews, including the identification of critical pipeline 

facilities.[Footnote 32] A representative of the hazardous liquid 

pipeline industry told us that pipeline companies are concerned about 

this issue because of the cost of increased security at critical 

facilities, particularly if higher threat levels are declared. OPS has 

worked with the pipeline industry to develop guidance on how to 

determine which pipeline facilities are critical and what protective 

measures need to be taken at these facilities for various threat 

levels.[Footnote 33] According to OPS officials, during security 

reviews of individual operators, OPS and state inspectors will review 

whether each operator has appropriately applied this guidance to its 

facilities. OPS must also reach agreement with the pipeline industry on 

what sensitive company security information inspectors will need to 

examine when reviewing pipeline security programs. Industry 

representatives have told us that operators are reluctant to share such 

information with OPS because the agency may not be able to prevent its 

public disclosure under the Freedom of Information Act.[Footnote 34] 

OPS officials have told us that they will try to address such concerns 

by having inspectors review sensitive documents on-site and take with 

them only those documents they need.



OPS will also need to determine how best to deploy its existing 

resources as well as those of its state partners for carrying out 

pipeline security oversight, because it does not anticipate obtaining 

additional resources for this purpose. This effort will involve 

determining the role of state inspectors in conducting security reviews 

and identifying the training that OPS and state inspectors will need to 

conduct these reviews. OPS officials have told us that states will play 

a key role in conducting these reviews, but some state pipeline safety 

officials have told us that they have not received clear guidance from 

OPS on their role in security oversight. One official noted that states 

have very limited resources and would need additional staff to conduct 

security reviews of pipeline operators. Furthermore, several state 

officials emphasized to us that their inspectors would need security-

related training to be able to conduct security reviews of pipeline 

operators. However, according to an official of the Transportation 

Safety Institute, which trains OPS and state inspectors, the institute 

has not yet developed such training for these inspectors.



OPS officials have told us that the agency’s next step in developing 

its security oversight approach is to communicate with its state 

partners regarding their role in implementing this approach. The agency 

intends to work with states in refining its protocols for security 

reviews and in developing security-related training for OPS and state 

inspectors. However, the lack of a workforce plan and a strategy for 

communicating with its state partners, as discussed in the next section 

of this report, may hamper OPS’s ability to ensure that it has the 

resources and expertise it needs to oversee pipeline security and that 

it is effectively involving states in this effort.



OPS’s Plan for Obtaining Resources and Expertise Is Not Complete or 

Adequately Communicated to State Partners:



OPS’s efforts to ensure it has the resources and expertise needed to 

implement its integrity management approach are hampered by the lack of 

an up-to-date assessment of current and future staffing and training 

needs and an examination of the workforce’s deployment across the 

organization--essential elements of a workforce plan.[Footnote 35] 

Although OPS has estimated the number of inspectors it needs to hire to 

implement its integrity management approach and has developed a 

curriculum to train federal and state inspectors, the agency has not 

prepared a workforce plan--an important component of successful human 

capital management. Furthermore, the resource estimates are outdated 

and cover only the initial phases of implementation. Also, although OPS 

says it will need to augment its own resources with those of states to 

implement integrity management, the agency has acknowledged that its 

efforts to communicate with states about their role in integrity 

management have been limited. This limited communication has left some 

states uncertain of their role and uncertain about whether they will be 

prepared to carry out their expected responsibilities under OPS’s 

integrity management approach. OPS has several initiatives that may 

address some of these issues, such as using teams of inspectors and 

developing inspection protocols and guidance, but no initiative to 

estimate its long-term resource needs. Finally, while the agency 

intends to hold some discussions with states about their role in 

integrity management, it lacks a strategy for communicating how it will 

involve states in implementing this new regulatory approach.



OPS Lacks a Workforce Plan:



OPS is hampered in its efforts to ensure that it has the resources and 

expertise to successfully implement its integrity management approach 

by the lack of a workforce plan. By workforce planning, we mean the 

short-and long-term strategies to identify OPS’s current and future 

staffing needs; the appropriate workforce deployment across the agency; 

the knowledge, skills, and abilities needed for staff to implement 

integrity management; and the training to fulfill these needs. OPS has 

estimated that it needs to hire 28 inspectors by fiscal year 2003, an 

increase of 50 percent from fiscal year 2001, to inspect approximately 

1,000 individual integrity management programs for hazardous liquid and 

gas transmission operators. This estimate is in addition to the 

approximately 100 of about 400 state inspectors that OPS plans to train 

and use to assist with inspecting integrity management programs, 

although some states may need to hire additional inspectors. OPS based 

these estimates on the proposed integrity management rule for operators 

of large liquid pipelines. However, OPS made several significant 

changes between the proposed and final rules but did not adjust its 

estimates to account for these changes.[Footnote 36] The following are 

examples of the outdated and incomplete components of OPS’s resource 

estimates:[Footnote 37]



* OPS added inspections to its implementation process. The agency based 

its resource estimates on the assumption that inspectors would perform 

one inspection but has since revised its procedures to include two 

different inspections. This change should have increased the original 

resource estimates.



* Resource estimates cover only the first two phases of a four-phase 

implementation process. According to OPS officials, their ultimate goal 

is to hire enough inspectors to carry out the third and fourth phases-

-conducting inspections every 2 years and responding to notifications 

from operators of changes in integrity management programs. However, 

OPS has not determined its resource needs for the third and fourth 

phases.



According to OPS officials, they informally updated their resource 

estimates for integrity management for each fiscal year budget request 

but did not document the changes.



Furthermore, OPS does not have an agencywide estimate of the resources 

it needs to maintain its entire range of pipeline safety oversight 

activities. In addition to the new integrity management inspection 

responsibilities, OPS must still conduct its standard inspections. 

However, OPS could not tell us how the coordination of time and 

resources for all types of inspections will take place. Because OPS has 

not created a workforce plan, it is unclear how the implementation of 

its integrity management approach will affect the resources it needs to 

fulfill other obligations.



Another important element of a workforce plan is training. OPS has 

developed a training curriculum designed to prepare state and federal 

inspectors for successfully implementing the integrity management 

approach. The agency is working with the Transportation Safety 

Institute to design and teach several new training courses specifically 

on OPS’s hazardous liquid integrity management approach. OPS 

anticipates that about 180 inspectors (80 federal and 100 state) will 

complete the training by spring of 2003. The training involves 

classroom courses and on-the-job training. The classroom training 

involves eight core classes, which have already been taken by most 

state and federal inspectors, and an additional seven classes 

specifically designed for integrity management. The additional classes 

cover such issues as the requirements and basic concepts of using smart 

pigs to assess the integrity of pipelines and integrity management 

program inspection and compliance requirements. For on-the-job 

training, OPS is using a “team approach” to conduct integrity 

management inspections, in which trainees will attend inspections led 

by OPS’s senior inspectors who have been involved in all phases of 

implementing the integrity management approach. Each team will consist 

of staff from multiple regions, including its most experienced 

inspectors and inspectors-in-training, as well as external experts. 

Starting in August 2002, when OPS will begin its comprehensive 

inspections of hazardous liquid operators, state representatives will 

also be included in these teams. This approach will allow senior 

inspectors to serve as mentors to the trainees, provide on-the-job 

training, and help inspectors make the transition to this new approach. 

When OPS finalizes the rule on the gas transmission integrity 

management requirements, inspectors will require additional training.



OPS’s training may help ensure that inspectors have the technical 

expertise to conduct integrity management inspections, but making the 

transition to this new approach may present a challenge for some 

inspectors. Pipeline operators, industry associations, environmental 

organizations, and OPS officials acknowledge that the integrity 

management approach represents a fundamental shift in how OPS oversees 

the pipeline industry. Federal and state inspectors that are accustomed 

to following an approach for inspecting pipelines for compliance with 

uniform standards will now have to evaluate programs that are unique to 

individual operators. One OPS regional office official stated that this 

new approach “will require a different thought process,” and that not 

making the transition adequately could result in inconsistent 

inspections between OPS regions and states. However, according to OPS 

headquarters officials, the agency’s detailed inspection protocols and 

guidance as well as inspector training will help ensure that integrity 

management inspections are conducted consistently.



OPS Has Not Adequately Communicated Its Plans to State Partners:



OPS officials told us that they will use the assistance of state 

pipeline safety inspectors to achieve their ambitious schedule for 

inspecting the integrity management programs of pipeline operators, but 

OPS has had only limited communications with its state partners about 

their role in implementing integrity management. This limited 

communication could result in states not being adequately prepared to 

meet the demands of the integrity management approach. State pipeline 

safety inspectors are an invaluable resource for OPS because they are 

familiar with pipeline safety issues unique to their states and can 

improve safety by increasing the frequency and thoroughness of 

inspections of pipeline operators. OPS plans to leverage federal and 

states’ resources to inspect the integrity management programs of more 

than 1,000 hazardous liquid and gas transmission operators. For 

example, states will be primarily responsible for inspecting the 

programs of an estimated 156 intrastate hazardous liquid and 520 

intrastate gas transmission operators.



Despite the important role of the states, state pipeline officials we 

spoke with said that they have had little to no communication with OPS 

about how states will be involved in integrity management inspections. 

For example, one state’s officials assumed OPS would contact them to 

participate in the quick hit inspection, but these officials did not 

know that states were being excluded from these inspections. OPS did 

not allow state inspectors to participate in the quick hit inspections 

because the agency felt it would be too difficult to coordinate the 

inspections within its self-imposed time frame.[Footnote 38] OPS’s 

apparent lack of communication with states leaves some states unsure if 

they will have the resources and expertise to meet the demands of the 

integrity management initiative. State officials told us that they are 

unsure how many of their inspectors will be trained by OPS over the 

next few years, and that they do not know enough about OPS’s integrity 

management approach to determine whether they need to change some of 

their own in-house training, hire more inspectors, or both. One state’s 

officials said that, because OPS has not provided any information to 

their state, they could only speculate about states’ roles under the 

published final rule and could not justify requests for additional 

resources in preparation for the new integrity management approach. 

Another state official said that, given the availability of training in 

the past, it could take about 10 years to train just that state’s 

inspectors. When we raised this concern to OPS officials, they 

responded that the agency has changed its training schedule and will be 

capable of training more people.



Although OPS has described its relationship with its state partners as 

an important component of the integrity management program, OPS 

officials acknowledge that in their initial phase of implementing 

integrity management, they have not focused on communicating with 

states regarding their plans for implementing the new approach. The 

officials explained that they have delayed communicating this 

information to states because states were not involved in the first 

phase of implementation, which included quick hit inspections of 

hazardous liquid operators. OPS officials further noted that since 

September 11, 2001, their communications with states have focused on 

security-related issues. (However, as previously described, some state 

pipeline safety officials told us that they have not received clear 

guidance from OPS on their role in security oversight.) According to 

agency officials, they are starting to contact states that will be 

involved in their first comprehensive inspections of hazardous liquid 

operators, scheduled to begin in August 2002, and will communicate 

further with states about their role in integrity management as these 

inspections continue. In addition, OPS officials explained that the 

agency plans to hold an annual meeting with states in September 2002 

and a planning exercise with states in January 2003; both of these 

events will provide opportunities for OPS to communicate with states 

about their role in the integrity management initiative. However, these 

annual meetings do not address the need for OPS to formally communicate 

with states throughout the implementation process in order to 

effectively coordinate the use of both federal and state inspectors.



OPS Is Taking Action to Improve Data Quality:



Obtaining complete and accurate data on reportable pipeline incidents 

is important to OPS for monitoring operators’ safety performance, 

identifying safety trends, and planning future initiatives. Under the 

integrity management approach, useful and reliable data are also 

important, because OPS is using its data to, among other things, 

measure the effectiveness of this approach in improving pipeline 

safety. According to a joint government and industry task force report 

on hazardous liquids,[Footnote 39] complete and accurate information on 

pipeline incidents is essential for the successful implementation of a 

risk management system.



In the past, we, the Safety Board, DOT’s Office of the Inspector 

General, and others have identified problems with the completeness and 

accuracy of OPS’s data. For example, as we testified earlier this year, 

OPS’s former incident report forms included so few cause categories 

(seven or fewer, depending on the form) that about one-fourth of all 

pipeline incidents were attributed to “other” causes--a category too 

broad for useful analysis. In addition, OPS’s incident forms did not 

provide for collecting data on hazardous liquid spills of less than 50 

barrels or for measuring the total impact of an incident, particularly 

its damage costs. In addition, OPS did not require liquid pipeline 

operators to submit data on the characteristics of their pipeline 

infrastructure (e.g., age or size), which it needed to analyze trends 

and compare the operators’ safety performance, nor did it collect 

complete data from natural gas pipeline operators. Finally, OPS did not 

have a procedure for following up with operators to ensure that their 

incident reports included any necessary revisions.



To improve the completeness and accuracy of its data, OPS is 

undertaking several initiatives, most of which it plans to have 

implemented for the collection of 2002 data. To more accurately 

determine the causes of incidents, OPS revised its incident report 

forms in 2001 and early 2002 for natural gas transmission and hazardous 

liquid incidents, respectively, to include 25 categories of causes. The 

agency plans to revise the form for natural gas distribution incidents 

by the end of 2002. The revised forms for hazardous liquid operators 

also require these operators to report spills of 5 gallons or more 

(instead of 50 barrels or more) and to provide more complete 

information on the total costs of an incident. To enable it to better 

analyze trends and compare operators’ performance, OPS revised its 

annual report forms for natural gas transmission pipeline operators for 

2001 data and intends to revise these forms for natural gas 

distribution pipeline operators for 2002 data. In July 2002, the agency 

proposed instituting annual reports for liquid pipeline operators for 

2002 data. To ensure that operators complete incident reports in an 

accurate and timely manner, OPS has assigned an inspector in each 

region to review incident report forms for completeness and accuracy. 

It has also instituted new electronic notification procedures to ensure 

that operators submit revised incident reports, if necessary. These and 

other major data improvement initiatives are summarized in table 2.



Table 2: OPS’s Data Quality Initiatives:



Data problem: Data provided on incident reports were not complete or 

accurate.; Initiative: Revise incident report forms to include more 

cause categories, a wider range of hazardous liquid spills, and more 

information on total costs of an incident; revised forms also use 

electronic notification procedures to ensure completeness.; ; Inspector 

in each region will be responsible for regularly reviewing incident 

reports for relevance, completeness, and accuracy.; Status of 
initiative: 

Gas transmission and hazardous liquid forms revised in 2001 and early 
2002 

for 2002 data.; ; Revision of gas distribution form expected to be 
completed 

by the end of 2002 and usable to collect 2003 data.; ; Existing staff 
will 

be used in 2002 to review incident reports while new inspectors are 
being 

hired and trained.



Data problem: Data to analyze trends and compare operators’ performance 

were not sufficient.; Initiative: Revise existing annual report forms 

for natural gas pipeline operators to require more information (e.g., 

pipeline mileage, age, and type).; ; Institute annual reports for 

hazardous liquid pipeline operators.; Status of initiative: Form for 

natural gas transmission annual report revised in 2001 for 2001 

report.; ; Form for natural gas distribution annual report expected to 

be revised by the end of 2002, in time to collect data for 2002 

report.; ; New form for hazardous liquid annual report expected to be 

finalized in 2002, in time to collect data for 2002 report.



Data problem: OPS staff made errors entering data from operators’ 

reports into OPS’s database.; Initiative: Have operators file reports 

electronically to eliminate errors and expedite filing.; Status of 

initiative: Direct electronic filing by operators began in January 

2002.



Data problem: States collect data in different formats, limiting OPS’s 

ability to compare and consolidate data from different states.; 

Initiative: Establish a team to develop uniform data elements and 

reporting procedures.; Status of initiative: Completion expected by the 

end of 2003.



Data problem: OPS lacks complete understanding of the causes of 

incidents, which is needed to focus oversight efforts on the greatest 

risks.; Initiative: Hire contractors to analyze incident causes--focus 

in 2002 is on the consequences of incidents on gathering lines and the 

benefits of increasing the regulation of gathering lines.; Status of 

initiative: Contractors to provide reports by the end of 2002 and on a 

regular basis thereafter.



Source: GAO analysis of information provided by OPS.



[End of table]



According to OPS officials, OPS plans to use the data that it collects 

to, among other things, help measure the effectiveness of its integrity 

management approach, focus its oversight efforts on the greatest risks 

to pipeline safety, and prioritize research and development projects. 

One performance measure that OPS plans to develop using the new 

incident report forms is the number of high consequence areas affected 

by pipeline incidents. This number should decrease over time as 

operators focus their efforts on these areas through their integrity 

management programs. To focus its oversight efforts on the greatest 

risks, OPS plans to analyze the improved data on incident causes to 

better understand the greatest safety risks and deploy staff 

accordingly to address these risks. OPS also plans to use the data on 

incident causes to identify the research and development projects that 

are most critical to improving pipeline safety.



Although OPS’s initiatives appear to address past criticisms, 

government and industry officials believe it is too early to say 

whether further improvements are needed. According to the Safety Board, 

state pipeline safety officials, industry groups, and pipeline 

operators, OPS’s initiatives address the agency’s underlying data 

problems and will enable OPS to better understand the causes of 

incidents so it can focus its efforts to improve safety. However, 

officials from the Safety Board noted that these initiatives are merely 

a first step, and they emphasized that OPS should periodically reassess 

its forms and procedures and take steps to revise them as necessary. In 

addition, a state pipeline safety official noted that although there 

are now 25 cause categories on the incident forms, there will still be 

some uncertainty, since operators have the option of choosing “other.” 

Finally, officials from industry groups told us that it will be several 

years before OPS has sufficient data for analyzing trends in incidents.



Conclusions:



OPS is aggressively pursuing its integrity management approach and 

taking action to improve the quality of its data. If properly 

implemented, these initiatives should improve pipeline safety. However, 

OPS still has significant challenges to overcome in implementing its 

new regulatory approach. Although OPS is carrying out a variety of 

activities aimed at overcoming these challenges, the agency lacks a 

workforce plan containing current and future resource estimates for 

these initiatives. The absence of such a plan could hamper OPS’s 

ability to meet its ambitious time frames and successfully implement 

its new regulatory approach. Furthermore, OPS does not have an 

effective strategy for communicating with its state partners and, as a 

result, these states may not be fully aware of the role OPS expects 

them to play in implementing integrity management and may not be 

adequately prepared for this role. If states are not adequately 

prepared, OPS will probably not be able to meet its ambitious time 

frame for inspecting pipeline operators’ integrity management programs. 

Finally, the lack of a workforce plan and strategy for communicating 

with states may hamper OPS’s ability to ensure that it has the 

resources and expertise it needs to oversee pipeline security and that 

it is effectively involving states in this effort.



Recommendations for Executive Action:



We recommend that the Secretary of Transportation direct OPS to:



* develop a workforce plan that contains an updated assessment of OPS’s 

current and future staffing and training needs and an examination of 

the workforce’s deployment across the organization and:



* develop a strategy for communicating to the states what role they 

will play in conducting integrity management inspections and other 

oversight activities.



Agency Comments and Our Evaluation:



We provided a draft of this report to DOT for its review and met with 

DOT officials, including OPS’s Associate Administrator, to obtain their 

comments. In addition, DOT’s Assistant Secretary for Administration 

provided written comments, which are reprinted in appendix I. The DOT 

officials generally agreed with the draft report’s recommendations. 

Regarding workforce planning, they noted that OPS intends to formulate 

detailed plans for the longer term after it has completed the final 

integrity management rule for gas transmission pipelines. While we are 

encouraged that OPS intends to develop a workforce plan, we believe 

that the agency needs to ensure that its planning efforts encompass 

both its short-term and long-term staffing and training needs. In 

particular, the agency should develop a strategic workforce plan now in 

order to establish a solid foundation for implementing integrity 

management and accomplishing its mission and programmatic goals. Such a 

plan should identify the resources and expertise OPS needs to carry out 

its initiatives, including how it will leverage its resources with 

those of its state partners. A workforce plan will help the agency meet 

its ambitious time frame for implementing the integrity management 

approach and address challenges it faces in doing so. OPS should 

monitor and periodically update the plan to address changing needs.



Regarding communicating with the states, the DOT officials explained 

that OPS is trying to define what role the states will play in 

integrity management inspections and is currently engaged in 

discussions with states regarding their involvement in this initiative. 

Although we believe that this is a step in the right direction, the 

agency needs to formulate and adopt a strategy for communicating with 

its state partners that will help ensure that the agency effectively 

involves states in integrity management and other oversight efforts 

over the longer term.



OPS officials also provided some technical clarifications, which we 

have incorporated in this report as appropriate.



Scope and Methodology:



To examine OPS’s steps to implement the integrity management approach, 

identify the challenges OPS faces in implementing this approach, and 

assess OPS’s plans for obtaining the resources and expertise needed to 

oversee pipeline safety under this approach, we reviewed OPS documents, 

analyzed OPS’s resource estimates, visited states, and interviewed OPS 

and pipeline industry officials as well as others with pipeline safety 

expertise. OPS documents that we reviewed included the proposed and 

final rules that establish the integrity management requirements, 

comments on the proposed rule, OPS’s documentation on its plans for 

implementing the integrity management approach, and OPS’s resource 

estimates and training schedule. We analyzed OPS’s resource estimates 

to determine their accuracy and consistency. We also visited state 

pipeline agencies in Texas, Washington, New York, and Virginia. We 

chose to visit these states because their pipeline oversight agencies 

are among the most active of OPS’s state partners in implementing the 

integrity management approach. For example, officials in these states 

provided comments on OPS’s proposed integrity management rules and/or 

have been involved in efforts to develop integrity management program 

requirements. In addition, Texas has its own integrity management rule 

for natural gas and hazardous liquid pipeline operators. We also 

conducted in-person and telephone interviews with the following: 

representatives from state and national pipeline industry associations; 

officials at several pipeline companies; pipeline safety officials in 

those states we visited; representatives from environmental advocacy 

organizations; officials from the Environmental Protection Agency and 

the National Transportation Safety Board; representatives from Cycla 

Corporation, a contractor that is working for OPS on some components of 

implementing integrity management; a representative from the 

Transportation Safety Institute, which provides the training for state 

and federal pipeline safety inspectors; and officials from OPS’s 

headquarters and five regions.



To determine OPS’s major initiatives to improve the quality of its data 

on pipeline incidents, we reviewed and compared the agency’s new data-

collection forms with its previous forms. We also interviewed officials 

working for pipeline companies that fill out these forms. We 

interviewed officials from the Safety Board and the DOT Office of the 

Inspector General, OPS officials who implement the data-collection 

activities, representatives from pipeline industry associations, and 

state pipeline agency officials.



We conducted our work from November 2001 to July 2002 in accordance 

with generally accepted government auditing standards.



As arranged with your office, unless you publicly announce its contents 

earlier, we plan no further distribution of this report until 30 days 

after its date. At that time, we will send copies of this report to 

congressional committees and subcommittees with responsibilities for 

transportation safety issues, the Secretary of Transportation, the 

Administrator of the Research and Special Programs Administration, and 

the Director of the Office of Management and Budget. We will make 

copies available to others upon request. In addition, this report will 

be available at no charge on the GAO Web site at http://www.gao.gov.



If you or your staff have any questions about this report, please 

contact me at (202) 512-2834 or guerrerop@gao.gov. Key contributors to 

this report were Susan Fleming, Judy Guilliams-Tapia, Michael Horton, 

Wyatt Hundrup, and Sara Vermillion.



Sincerely yours,



Peter F. Guerrero

Director, Physical Infrastructure Issues:



Signed by Peter F. Guerrero:



[End of section]



Appendix I: Comments from the U.S. Department of Transportation:





U.S. Department of Transportation:



Assistant Secretary

for Administration:



400 Seventh St SW

Washington D C 20590:



August 7, 2002:



Mr. Peter Guerrero 

Director:



Physical Infrastructure Issues 

U.S. General Accounting Office 

441 G Street N.W. Washington, D.C. 20548:



Dear Mr. Guerrero:



We appreciate the opportunity to provide comments on the U.S. General 

Accounting Office (GAO) draft report regarding the status of efforts by 

the Research and Special Program Administration’s (RSPA) Office of 

Pipeline Safety (OPS) to implement its Integrity Management Program and 

improve the quality of data on pipeline incidents. OPS has achieved 

significant progress in both its integrity and data initiatives.



Setting and enforcing higher pipeline safety standards through the 

Integrity Management Program is already producing results for hazardous 

liquid pipelines. RSPA demonstrated that it is prepared to enforce 

these standards with its recently completed “quick hit” inspections. 

These inspections:



*Included all large hazardous liquid pipeline operators,



*Covered over 70,000 miles of pipelines, and:



*Resulted in enforcement actions on 85 percent of those operators.



At a recent public meeting in July, OPS unveiled its new complete 

inspection protocols for the comprehensive hazardous liquid pipeline 

inspections and answered many implementation questions. We wish to 

emphasize:



*OPS received overwhelmingly positive feedback from inspectors and 

industry representatives alike regarding the effectiveness of the 

protocols in achieving consistent enforcement of the hazardous liquid 

Integrity Management Program. *OPS is staffed, organized, and prepared 

to fully and effectively implement its final rules.



*The Integrity Management Program incorporates key attributes 

recommended by the National Transportation Safety Board and mandated by 

Congress, to ensure that pipelines continue to operate as safely as 

possible.



OPS is dedicated to completing the remaining tasks according to plan. 

The proposed rule for natural gas transmission pipelines is nearly 

completed. OPS is working with state agencies and the industry to fine 

tune performance measures.



To ensure that state partners are aware of their roles, OPS is 

finalizing policy documents to clarify expectations. Our comprehensive 

discussions with state pipeline safety partner agencies are:



*Clarifying a vision for state inspectors’ participation in integrity 

management inspections,



*Identifying state needs,



*Addressing training needs for state personnel,



*Improving overall communications, and:



*Making the Integrity Management Program plan review more efficient.



OPS has also been pursuing a logical, building block approach to 

formulating detailed workforce plans.Detailed inspection protocols are 

the basis for understanding the scope of tasks ahead, along with the 

inspection time and resources required.While OPS is finalizing the 

notice of proposed rulemaking on natural gas transmission pipelines, it 

is premature to detail inspection protocols. Similarly the training 

program, which is underway for hazardous liquids, can only be developed 

for natural gas once the final rule is completed. Once all of the 

critical building blocks come together, OPS will use these elements to 

complete analytically based workforce planning to ensure that long-term 

needs are met. While OPS has the resources it needs for the current 

workload, it is clear that additional inspection resources are needed 

to conduct inspections for both the Integrity Management Program and 

other traditional inspection and oversight activities. The President 

requested significant additional inspection resources for this purpose 

for FY 2003.



While the GAO draft report recognized OPS’ data improvement efforts, it 

should be noted that RSPA has several initiatives to improve the 

completeness and accuracy of its data to improve its oversight of 

pipeline safety. Specifically, OPS has:



*Issued the first rulemaking requiring an annual report for hazardous 

liquid pipelines - an essential step in improving the completeness and 

value of pipeline data, and *Modified incident and accident report 

forms to better reflect incident causes.



Overall, OPS is dedicated to effectively implementing the Integrity 

Management Program and the data improvements. Work is complete in many 

key areas and is underway to address remaining issues. While its 

schedule is ambitious and the challenges formidable, OPS has already 

demonstrated it is up to the challenge.



Once again, we appreciate the opportunity to offer these comments. 

Please contact Martin Gertel on 202-366-5145 with any questions.



Sincerely,



Melissa Allen:



Signed by Melissa Allen:



FOOTNOTES



[1] U.S. General Accounting Office, Human Capital: A Self-Assessment 

Checklist for Agency Leaders, GAO/OCG-00-14G (Washington, D.C.: 

September 2000).



[2] See 49 U.S.C. 60105. 



[3] See 49 C.F.R. pts. 190-199 (2002). 



[4] P.L. No. 104-304, 110 Stat. 3793 (1996). 



[5] U.S. General Accounting Office, Pipeline Safety: The Office of 

Pipeline Safety Is Changing How It Oversees the Pipeline Industry, GAO/

RCED-00-128 (Washington, D.C.: May 15, 2000).



[6] For hazardous liquid pipelines, a “high consequence area” is 

defined as a populated area, an area unusually sensitive to 

environmental damage, or a commercially navigable waterway. See 49 

C.F.R. 195.450 (2002). For natural gas transmission pipelines, OPS has 

developed a definition that focuses on populated or frequented areas. 

See 67 Fed. Reg. 1108, 1114 (Jan. 9, 2002).



[7] See 67 Fed. Reg. 2136, 2137 (Jan. 16, 2002).



[8] OPS is considering issuing requirements for integrity management 

programs for operators of natural gas distribution pipelines after the 

agency completes the rulemaking process for natural gas transmission 

pipelines.



[9] The final rule for OPS’s integrity management program for large 

hazardous liquid pipeline operators was published in December 2000. See 

65 Fed. Reg. 75378 (Dec. 1, 2000) (to be codified at 49 C.F.R. pt. 

195). The final rule for small hazardous liquid pipeline operators was 

published in January 2002. See 67 Fed. Reg. 2136 (Jan. 16, 2002).



[10] OPS plans to review all notifications received from operators and 

to respond in a timely manner to those in which it finds the proposed 

approach unacceptable.



[11] OPS requires operators to prioritize repairs in three categories: 

repair immediately, repair within 60 days, or repair within 6 months. 

See 49 C.F.R. 195.452(h)(4)(2002).



[12] However, the agency may combine the inspections in phases 1 and 2 

for these pipelines if the agency determines that it would be more 

efficient and equally effective to have one inspection. 



[13] OPS’s standard inspections verify whether pipeline operators are 

in compliance with minimum safety standards. They include “unit 

inspections” of an individual operating unit of a company’s pipeline 

system as well as “systemwide inspections” of all of a company’s 

related operating units. 



[14] For example, OPS is issuing its integrity management rules 

partially in response to a 1987 Safety Board recommendation that the 

agency require pipeline operators to periodically inspect pipelines. 

See U.S. General Accounting Office, Pipeline Safety: Progress Made, but 

Significant Requirements and Recommendations Not Yet Complete, 

GAO-01-1075 (Washington, D.C.: Sept. 28, 2001). 



[15] In response to concerns that we and others raised, OPS began an 

effort in 2000 to strengthen the enforcement of all its rules, 

including increasing the use of fines. See U.S. General Accounting 

Office, GAO/RCED-00-128 and Pipeline Safety: Status of Improving 

Oversight of the Pipeline Industry, GAO-02-517T (Washington, D.C.: Mar. 

19, 2002).



[16] For assessments using smart pigs, the flow of gas generally has to 

be reduced by about 30 percent for 1 day.



[17] See 49 C.F.R. 195.452(j)(5)(2002).



[18] External corrosion is the only threat for which industry standards 

for the application of direct assessment have been developed.



[19] Texas has implemented an integrity management program for 

intrastate pipeline operators. It is the only state with an intrastate 

integrity management program.



[20] Variance from the 5-year interval is allowed in two limited 

situations, provided the operator provides notification and 

justification to OPS. These situations are when there is an engineering 

basis for a longer period and when the best technology needed to assess 

the segment is temporarily unavailable. See 49 C.F.R. 195.452(j)(4) 

(2002).



[21] In a notice of proposed rulemaking, OPS proposed a definition of 

high consequence areas for natural gas transmission pipelines that is 

based on populated and frequented areas. See 67 Fed. Reg. 1108, 1114 

(Jan. 9, 2002).



[22] These standards, which provide guidance to natural gas operators 

on how to implement integrity management programs, were developed by a 

task force that included representatives from the natural gas pipeline 

industry, OPS, and the Safety Board.



[23] According to OPS officials, these measures will be included in 

DOT’s budget proposal and performance plan for fiscal year 2004. 



[24] These incident data are accessible to the public through OPS’s Web 

site.



[25] These measures would be made available to OPS electronically, 

either through a company Web site or a computer (modem) connection.



[26] In spring 2002, the American Petroleum Institute began to collect 

similar data from hazardous liquid operators on a voluntary basis. 

However, the institute intends to use these data for industrywide 

analyses and does not intend to report information on individual 

operators’ programs.



[27] The responsibility for oversight of pipeline security may change 

in the future. DOT’s Transportation Security Administration was created 

in November 2001 and has statutory responsibility for the security of 

all modes of transportation, although it has focused its initial 

efforts on aviation security. In June 2002, the President proposed 

legislation to create a new Department of Homeland Security. Under this 

proposal, federal responsibilities for securing transportation systems 

would be transferred to this department. 



[28] OPS gathered some preliminary information on operators’ security 

practices immediately after September 11, 2001, through a survey of 

major pipeline operators. 



[29] A critical facility is one whose failure would have a high 

consequence. 



[30] OPS has undertaken a number of other security-related initiatives 

since September 11, 2001. For example, the agency has worked with the 

Department of Energy, the Federal Energy Regulatory Commission, state 

pipeline agencies, and industry to address issues related to rapid 

response and recovery of pipeline service in the event of an attack and 

has solicited research and development proposals to protect pipeline 

infrastructure. 



[31] Pipeline Infrastructure Protection to Enhance Security and Safety 

Act, H.R. 3609, 107th Cong. (2001).



[32] We have previously reported that the identification of critical 

facilities is important for prioritizing protection efforts. See U.S. 

General Accounting Office, Homeland Security: A Risk Management 

Approach Can Guide Preparedness Efforts, GAO-02-208T (Washington, D.C.: 

Oct. 31, 2001). 



[33] In March 2002, the Office of Homeland Security announced the 

creation of a Homeland Security Advisory System in order to disseminate 

information on the risk of terrorist attacks. The system includes five 

levels of threat to characterize this risk and associated suggested 

protective measures. The office has requested comments on the system 

and plans to finalize it by September 2002. 67 Fed. Reg. 12047 (Mar. 

18, 2002). 



[34] Some legislation has been proposed that would protect such 

information. For example, H.R. 4 and H.R. 3609 would allow the 

Secretary of Transportation to withhold information on pipeline 

vulnerabilities from public disclosure. Energy Policy Act of 2002, H.R. 

4, Secs. 741-783, 107th Cong. (2002) and Pipeline Infrastructure 

Protection to Enhance Security and Safety Act, H.R. 3609, 107th Cong. 

(2001). 



[35] GAO/OCG-00-14G. 



[36] OPS’s proposed rule was published in April 2000, 65 Fed. Reg. 

21695 (Apr. 24, 2000), and the final rule was published in December 

2000, 65 Fed. Reg. 75378 (Dec. 1, 2000).



[37] OPS’s original resource estimates are also miscalculated. By 

incorrectly multiplying numbers, for example, OPS estimated that 1,640 

work weeks were required in the regions for implementing the small 

liquid integrity management rule, but the corrected figure is 2,495. 



[38] OPS made an exception in the case of Texas by allowing Texas 

inspectors to accompany OPS on the quick hit inspections, mostly 

because Texas has its own integrity management rule.



[39] The Joint Government/Industry Risk Assessment Quality Team, Risk 

Management within the Liquid Pipeline Industry, sponsored by OPS and 

the American Petroleum Institute, June 20, 1995.



GAO’s Mission:



The General Accounting Office, the investigative arm of Congress, 

exists to support Congress in meeting its constitutional 

responsibilities and to help improve the performance and accountability 

of the federal government for the American people. GAO examines the use 

of public funds; evaluates federal programs and policies; and provides 

analyses, recommendations, and other assistance to help Congress make 

informed oversight, policy, and funding decisions. GAO’s commitment to 

good government is reflected in its core values of accountability, 

integrity, and reliability.



Obtaining Copies of GAO Reports and Testimony:



The fastest and easiest way to obtain copies of GAO documents at no 

cost is through the Internet. GAO’s Web site ( www.gao.gov ) contains 

abstracts and full-text files of current reports and testimony and an 

expanding archive of older products. The Web site features a search 

engine to help you locate documents using key words and phrases. You 

can print these documents in their entirety, including charts and other 

graphics.



Each day, GAO issues a list of newly released reports, testimony, and 

correspondence. GAO posts this list, known as “Today’s Reports,” on its 

Web site daily. The list contains links to the full-text document 

files. To have GAO e-mail this list to you every afternoon, go to 

www.gao.gov and select “Subscribe to daily E-mail alert for newly 

released products” under the GAO Reports heading.



Order by Mail or Phone:



The first copy of each printed report is free. Additional copies are $2 

each. A check or money order should be made out to the Superintendent 

of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 

more copies mailed to a single address are discounted 25 percent. 

Orders should be sent to:



U.S. General Accounting Office



441 G Street NW,



Room LM Washington,



D.C. 20548:



To order by Phone: 	



	Voice: (202) 512-6000:



	TDD: (202) 512-2537:



	Fax: (202) 512-6061:



To Report Fraud, Waste, and Abuse in Federal Programs:



Contact:



Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov



Automated answering system: (800) 424-5454 or (202) 512-7470:



Public Affairs:



Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.



General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.



20548: