This is the accessible text file for GAO report number GAO-09-673T 
entitled 'Architect Of The Capitol: Plans for Renovating the Cannon 
House Office Building and Garages' which was released on May 6, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony before the Committee on House Administration, House of 
Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 11:00 a.m. EDT:
May 6, 2009: 

Architect Of The Capitol: 

Plans for Renovating the Cannon House Office Building and Garages: 

Statement of Terrell G. Dorn, Director: 
Physical Infrastructure Issues: 

GAO-09-673T: 

[End of section] 

Mr. Chairman and Members of the Committee: 

We appreciate the opportunity to participate in this hearing to discuss 
renovations of the Cannon House Office Building and Garages. The Cannon 
House Office Building (Cannon Building)--completed in 1908--and the 
East and West House Underground Garages (East and West Garages)--built 
in 1968--have deteriorated over time and will need to be repaired, 
according to assessments conducted for the Architect of the Capitol 
(AOC). AOC plans to renovate these three facilities over approximately 
the next 8 years as part of a long-term effort to reduce maintenance 
backlogs and execute major renewal projects to sustain all Capitol 
Complex facilities. My statement today is based on work we conducted 
over the past several months to assess AOC's plans for renovating the 
Cannon Building and East and West Garages. To conduct this work, we 
toured the facilities, analyzed AOC documents--including facility 
condition assessments (FCA),[Footnote 1] planning studies, and project 
development documents--and interviewed AOC officials. We relied on the 
information in AOC's project documents and cost estimates, which was 
largely based on the work of professional consultants, and did not 
independently evaluate the condition of the facilities, determine 
repair needs, or estimate costs. 

Summary: 

Renovations of the Cannon Building and East and West Garages are needed 
to maintain the integrity and safety of these facilities and reduce the 
likelihood of unplanned outages and associated costs. According to 
comprehensive FCAs completed for AOC by an expert consultant, most of 
the deficiencies identified in the Cannon Building--such as 70-year-old 
hot water heating and building ventilation systems and damaged, often 
nonfunctional windows--should be corrected within the next 5 to 7 
years. The deficiencies identified in the garages are more urgent 
structural problems--including cracking concrete and corroding 
reinforcing steel--and, according to the FCAs, should be addressed 
within the next 2 to 4 years. In addition to correcting these and other 
identified deficiencies, the renovation projects will address other 
considerations, such as energy conservation, historic preservation, 
hazardous materials abatement, and fire safety. AOC anticipates that 
each of the garage renovation projects will last approximately 2 years 
while the Cannon Building renovation will be completed in phases over 5 
years. In order for these renovations to occur within the time frames 
specified in the FCAs, AOC has requested or plans to request $38 
million for construction of the East Garage renovation in fiscal year 
2010, $30 million for construction of the West Garage renovation in 
fiscal year 2012, and $753 million for the planning, design, and 
construction of the Cannon Building renovation beginning in fiscal year 
2010. (See figure 1.) Limiting the scope of the renovations by 
deferring some work could reduce near-term costs; however, such action 
may result in the need to make more expensive emergency repairs in the 
future that could disrupt operations. 

Figure 1: AOC's Planned Funding Requests for Cannon Building and East 
and West Garage Renovation Projects: 

[Refer to PDF for image: vertical bar graph] 

Fiscal year: 2010; 
Funding request: Cannon Building planning: $5 million; 
Funding request: East Garage construction: $38 million. 

Fiscal year: 2011; 
Funding request: Cannon Building design: $37 million. 

Fiscal year: 2012; 
Funding request: West Garage construction: $30 million. 

Fiscal year: 2013; 
Funding request: None. 

Fiscal year: 2014; 
Funding request: Cannon Building construction: $722 million. 

Total; 
Funding request: Cannon Building planning: $5 million; 
Funding request: Cannon Building design: $37[A] million; 
Funding request: Cannon Building construction: $711[A] million; 
Funding request: East Garage construction: $38 million; 
Funding request: West Garage construction: $30 million; 
Total Cannon Building requests: $753 million; 
Overall total: $821 million. 

[A] The table indicates that AOC will request full funding for the 
Cannon Building's design and construction for fiscal years 2011 ($37 
million) and 2014 ($711 million), respectively. However, AOC will 
likely request this funding over multiple years, beginning in 2011 for 
design work and 2014 for construction. 

Source: GAO analysis of AOC data. 

[End of figure] 

To date, AOC has followed a reasonable process to plan the renovations 
of the Cannon Building and East and West Garages, and the agency's 
current and planned requests for funding are timed to move the 
renovations forward within the time frames recommended in the FCAs. 
However, because the Cannon Building renovation is at an early stage of 
development--meaning that the plans lack definition and the cost 
estimate is preliminary--AOC's current estimate of $711 million for the 
renovation work should not be considered sufficiently accurate for 
funding purposes. To renovate the Cannon Building within the time frame 
recommended in the FCA and to provide Congress with better cost 
information for making future renovation decisions, it is important 
that AOC continue, as planned, to refine the project's scope and cost 
estimate over the next 2 years. AOC's request for $5 million in 2010 
and planned request for $37 million beginning in 2011 should allow the 
agency to proceed with planning and design and position it to award a 
contract for and complete the Cannon Building renovations within the 
recommended 5-to 7-year time frame. For the East and West Garages, cost 
estimates are more reliable because the projects are at a later stage 
of development and are based on more complete information than the 
Cannon Building and--with updates planned by AOC--are at an appropriate 
level of development to justify funding to enter into a contract for 
construction. 

Background: 

To develop and execute capital projects, AOC assesses the condition of 
its facilities; plans the work necessary to correct identified 
deficiencies and address other requirements; completes detailed design 
documents, including engineering plans and specifications; and awards 
contracts for construction services[Footnote 2]. As a project 
progresses through these stages--which generally take about 5 years to 
complete--its scope matures and its estimated cost is refined until, at 
the detailed design stage, the estimated cost should be fairly close to 
the actual cost of the awarded construction contract. AOC controls the 
timing of these project development activities through its project 
prioritization process--a standard approach for scoring projects that 
considers the project's urgency, type, and importance--and then 
prioritizes funding requests for planning studies, design, or 
construction work in its annual budget submission. In the past, we have 
recommended improvements to AOC's processes for developing projects and 
prioritizing their execution; AOC has implemented these 
recommendations. For example, in response to recommendations we made in 
January 2003 and December 2004, AOC has completed FCAs of most of the 
facilities under its jurisdiction and developed a process for 
prioritizing projects. More detailed information on AOC's process for 
developing and prioritizing projects appears in appendix I. 

Cannon Building Renovation Is in the Planning Stage, and Its Estimated 
Cost Is Expected to Change: 

According to AOC's FCA of the Cannon Building, most of the identified 
deficiencies should be corrected within 5 to 7 years.[Footnote 3] For 
example, hot water heating and air-handling systems, which are not 
publicly visible, have components dating back to the 1930s that are 
deficient and in need of replacement. Other deficiencies identified in 
the FCA include an outdated fire alarm system for which repair parts 
are difficult to obtain, worn and stained marble tile in corridors, and 
original windows that are damaged and often nonfunctional. 

AOC plans to correct most of the identified deficiencies through a 
comprehensive renovation project that will also consider requirements 
such as energy conservation, physical security, hazardous materials 
abatement, and historic preservation. The project is expected to 
include replacement windows, a new copper roof, and work to preserve 
and repair the building's stone exterior. On the interior, the project 
is expected to provide new wall and floor finishes in some areas; 
refurbish restrooms and make them more accessible to disabled people; 
and allow for complete replacement of all plumbing, heating and 
cooling, fire protection, electrical, and alarm systems. Included in 
the project is work to remove asbestos that may be contained in 
insulation used on hot water pipes in the building's heating system. In 
addition, the renovation will address fire safety issues related to 
work that AOC plans to complete through a separate project.[Footnote 4] 

To enable continued use of a part of the building during construction, 
AOC plans to complete the project in phases--a preconstruction phase 
and four construction phases (with each phase of construction roughly 
including one side of the four-sided building)--over 5 years. 
Accordingly, the project's cost will include an allowance for the 
construction (or renovation) of a temporary facility for displaced 
occupants in the preconstruction phase. AOC's preliminary planning 
studies suggest that this four-phase construction approach would allow 
for the most efficient operation, the fewest moves, and the shortest 
schedule of all phasing options considered.[Footnote 5] We have found 
in previous work that this method of phasing construction--renovating a 
portion of the building while keeping the remaining sections of the 
building operational--can be successful when the facility under 
construction must remain operational. For example, in renovating 
Bancroft Hall--the only residence facility at the United States Naval 
Academy--Navy officials executed a $251 million nine-phase renovation 
project over 9 years by making one section available for construction 
while the other eight sections were in use. 

Because the Cannon Building project is still in the planning stage, its 
scope and cost estimate are expected to change. For a project in the 
planning stage, the expected accuracy of its cost estimate is generally 
plus or minus 40 percent.[Footnote 6] As more is learned about a 
project during the planning process, the accuracy of its cost estimate 
is expected to improve. For example, we found some recommended work 
elements listed in AOC's draft planning study for Cannon Building 
renovations that were not addressed in the conceptual cost estimate 
included with the same study.[Footnote 7] AOC officials indicated that 
these work elements will be addressed in the updated cost estimate that 
will be provided in the final study. If conducted properly, AOC's 
planning actions should enable criteria to be developed such that 
users' needs are identified and satisfied within the overall 
constraints affecting the project.[Footnote 8] AOC currently estimates 
that the total cost to complete the planning work, develop the 
project's design, and construct the project will be $753 million. 
Specifically, AOC has requested $5 million for fiscal year 2010 to fund 
the development of a program of requirements to further refine the 
project's scope and intends to request $37 million beginning in fiscal 
year 2011 for design, and subject to scope determinations, $711 million 
beginning in fiscal year 2014 for construction. See figure 2 for more 
detailed information on the planned project's estimated costs. 

Figure 2: Estimated Costs for Cannon Building Renovation: 

[Refer to PDF for image: horizontal bar graph and photographs of 
existing conditions] 

Work Element: Planning: Program of requirements; 
Estimated costs: $5 million. 

Work Element: Design: Construction documents; 
Estimated costs: $37 million. 

Work Element: Construction[A]: Equipment and furnishings: $4 million. 
Estimated costs: 

Work Element: Construction[A]: Fire protection; 
Estimated costs: $9 million. 

Work Element: Construction[A]: Plumbing; 
Estimated costs: $10 million. 

Work Element: Construction[A]: Demolition; 
Estimated costs: $11 million. 

Work Element: Construction[A]: Swing space; 
Estimated costs: $15 million. 

Work Element: Construction[A]: Interiors[B]; 
Estimated costs: $55 million. 

Work Element: Construction[A]: Hazardous materials abatement; 
Estimated costs: $56 million. 

Work Element: Construction[A]: Electrical; 
Estimated costs: $60 million. 

Work Element: Construction[A]: Security; 
Estimated costs: $71 million. 

Work Element: Construction[A]: Construction contingency costs; 
Estimated costs: $81 million. 

Work Element: Construction[A]: Implementation costs[C]; 
Estimated costs: $86 million. 

Work Element: Construction[A]: Exteriors[D]; 
Estimated costs: $97 million. 

Work Element: Construction[A]: Heating and cooling; 
Estimated costs: $157 million. 

Work Element: Construction[A]: Total (rounded); 
Estimated costs: $753 million. 

[A] Construction costs are based on a March 2009 draft report of a 
planning study conducted by AOC's consultant, URS Corporation. The cost 
estimate assumes a 2014 construction contract award and includes a 3.5 
percent annual escalation factor from 2009 (the year the estimate was 
prepared) to the estimated midpoint of each phase of construction). 

[B] Interiors includes costs for floor and wall repair work related to 
window replacement and restroom refurbishment. 

[C] Implementation includes costs for construction contract 
administration, testing, inspection, and quality control. 

[D] Exteriors includes costs for window replacement, copper roof 
replacement, and stone preservation. 

[End of figure] 

East and West Garage Renovations Are Awaiting Construction, and 
Estimated Costs Are Firmer: 

AOC's FCAs of the East and West Garages identify structural 
deficiencies, including cracking and delaminating[Footnote 9] concrete 
and corroding reinforcing steel, that have weakened the structures. 
According to the FCAs, repairs should be completed within the next 2 to 
4 years. AOC plans to make the needed structural repairs to the garages 
as part of comprehensive renovation projects that will also provide new 
drainage systems, energy-efficient lighting, ventilation and heating 
equipment, and fire protection systems. AOC expects a 2-year duration 
for each of the garage renovation projects.[Footnote 10] 

AOC initially completed the designs of both garage projects in 2005 and 
updated the cost estimates for the projects in November 2008. Based on 
its current cost estimates, AOC has requested $38 million for fiscal 
year 2010 to fund construction of the East Garage renovation and plans 
to request $30 million for fiscal year 2012 to fund construction of the 
West Garage renovation. AOC has included a premium for extended shifts 
(overtime) or double shifts (back-to-back 8-hour shifts) in its project 
cost estimates so that each project can be completed in 2 years. In 
addition, AOC has included a $400,000 allowance in its fiscal year 2010 
funding request for updates to the projects' 5-year-old designs to 
account for further deterioration that may have occurred to the 
facilities and to incorporate work needed to address any code changes. 
As a result of the design updates, specifications for new equipment-- 
such as that planned to be part of the lighting and ventilation 
systems--can then reflect current technologies. AOC's funding requests 
also include or will include an allowance to provide temporary parking 
while the garages are being renovated, which will likely involve 
leasing space in nearby lots and busing people to the Capitol Complex. 
See figure 3 for additional information on the scope of the projects 
and their estimated construction costs. 

Figure 3: Estimated Costs for East and West Garage Renovations: 

[Refer to PDF for image: horizontal bar graph and photographs of 
existing conditions] 

East Garage: 

Work Element: Design allowance; 
Estimated costs: $0.4 million. 

Work Element: Premium for extended or double shifts; 
Estimated costs: $2.7 million. 

Work Element: Parking; 
Estimated costs: $6.1 million. 

Work Element: Interior rehabilitation[A]; 
Estimated costs: $28.4 million. 

Work Element: Total East Garage; 
Estimated costs: $37.6 million. 

West Garage: 

Work Element: Design allowance; 
Estimated costs: Included above. 

Work Element: Premium for extended or double shifts; 
Estimated costs: $2.3 million. 

Work Element: Parking; 
Estimated costs: $5.3 million. 

Work Element: Interior rehabilitation[A]; 
Estimated costs: $22.6 million. 

Work Element: Total West Garage; 
Estimated costs: $30.2 million. 

[A] Interior rehabilitation includes structural repairs and the 
provision of new drainage systems, energy-efficient lighting, 
ventilation and heating equipment, and fire protection systems. The 
estimate (for both East and West Garages) is based on probable 
construction costs in 2010 and includes mark-ups for construction 
contingency and implementation costs for services such as construction 
management, inspection, and quality control. 

[End of figure] 

Mr. Chairman, this concludes my prepared statement. I would be pleased 
to respond to any questions that you or other Members of the Committee 
might have. 

We conducted our work from November 2008 to May 2009 in accordance with 
all sections of GAO's Quality Assurance Framework that are relevant to 
our objectives. The framework requires that we plan and perform the 
engagement to obtain sufficient and appropriate evidence to meet our 
stated objectives and to discuss any limitations in our work. We 
believe that the information and data obtained, and the analysis 
conducted, provide a reasonable basis for any findings and conclusions. 

For further information on this statement, please contact Terrell G. 
Dorn at (202) 512-6923 or dornt@gao.gov. Contact points for our 
Congressional Relations and Public Affairs offices may be found on the 
last page of this statement. Individuals making key contributions to 
this testimony were Sara Vermillion, Assistant Director; Michael Armes, 
John Bauckman, George Depaoli, Elizabeth Eisenstadt, and Joshua Ormond. 

[End of section] 

Appendix I: AOC's Capital Projects Development and Prioritization 
Process: 

The Architect of the Capitol's (AOC) capital projects development 
process is based on sequential stages that include assessing the 
condition of facilities and identifying deficiencies, conducting 
planning work to develop the scope of projects to correct identified 
deficiencies and address other requirements, completing detailed design 
work, and awarding contracts for construction services. The timing of a 
project's progression through these development stages is affected by 
AOC's project prioritization process--a standard approach for scoring 
projects that considers the project's urgency, type, and importance. 
This process enables the agency to prioritize funding requests for 
planning studies, design, or construction work in its annual budget 
submission. 

Project Development Process: 

Facility Condition Assessments (FCA). As we recommended in 2003, AOC 
periodically assesses the condition of each of its facilities using a 
consultant that specializes in such work.[Footnote 11] Information on 
each deficiency identified at a facility through an FCA is stored in a 
database, along with an assessment of the urgency of the problem and 
the estimated cost to correct it. The urgency rating--immediate, high, 
medium, or low--assigned to each deficiency indicates the recommended 
time frame for corrective action: immediate (within 2 years), high 
(between 2 and 4 years), medium (between 5 and 7 years), or low 
(between 8 and 10 years). 

Planning. Approximately 3 to 5 years prior to construction, AOC 
contracts for planning studies that consider facility repair needs 
identified through the FCA and other factors in establishing conceptual 
plans and cost and schedule estimates for the project. In some cases, 
planning studies may include the development of a program of 
requirements--that is, a detailed framework of requirements to guide 
the project's designer and ensure a smooth transition from the planning 
to the design stage. The program of requirements sets functional 
requirements for space layouts and may outline requirements for other 
areas, such as telecommunications, physical security, energy 
conservation, historic preservation, fire safety, hazardous materials 
abatement, and accessibility. 

Design. At least 2 years prior to construction, AOC procures 
architectural and engineering services for the development of 
construction documents, including final plans, specifications, and a 
detailed cost estimate for the project. AOC uses these documents to 
solicit and evaluate construction contract bids. AOC's professional 
staff review the design periodically during its development to ensure 
that it fully meets project requirements. 

Construction. AOC procures construction services by following a 
solicitation process during which it requests proposals from 
contractors interested in performing the work detailed in the 
construction documents, evaluates the contractors' proposals, and 
awards the contract to the winning contractor in accordance with its 
acquisition regulations. 

Project Prioritization Process: 

As we recommended in 2003, AOC prioritizes projects through a 
standardized process that assesses each project's urgency, type, and 
importance.[Footnote 12] AOC scores each project's importance in six 
areas--preservation of historic resources, regulatory compliance, 
mission accommodation, economics, physical security, and energy 
efficiency and environmental quality--and uses these scores to 
determine the project's overall urgency--immediate, high, medium, or 
low--for prioritization. AOC also considers the type of project-- 
deferred maintenance, capital renewal, capital improvement, or capital 
construction--to further differentiate projects in the prioritization 
process. AOC annually evaluates funding requirements for developing its 
portfolio of projects and submits a budget request that identifies 
project-specific needs for each stage of the development process. 

[End of section] 

Footnotes: 

[1] Condition assessments provide information on a facility's state of 
repair and are developed from inspections of structural, electrical, 
mechanical, plumbing, and other building systems. FCA reports typically 
catalog all of the deficiencies identified during the inspections along 
with the estimated cost to correct the problems. 

[2] Construction could include any demolition, maintenance, repair, or 
restorative work completed at a facility. In some cases, construction 
work could also include building an addition to or expanding a 
facility. 

[3] AOC's consultant, ENTECH Engineering, Inc., is currently updating 
the FCA prepared as part of a planning study of the Cannon Building 
completed by another consultant, URS Corporation, in December 2004. We 
referenced a draft copy of the final ENTECH Engineering study in 
conducting our work. 

[4] AOC intends to execute a House Alternative Life Safety Approach 
(HALSA) project in fiscal year 2011 to address egress issues that are 
the subject of an Office of Compliance citation. According to the 
citation, exit stairwells in the building are unprotected against fire 
and smoke--thereby posing a safety risk to occupants--because they are 
either completely open or not equipped with fire-rated doors. To 
correct this problem while preserving the historic character of the 
building, AOC plans as part of the HALSA project to install cross- 
corridor fire-rated doors at each of the corner stairs and stairs 
adjacent to the rotunda to create compartments designed to protect 
occupants in the event of a fire. AOC will incorporate the HALSA design 
solution into its planning of the Cannon Building's renovation to 
determine whether there are any additional egress requirements that 
need to be addressed during the renovation. 

[5] Other options considered were a vertical phasing plan that would 
include more phases than the preferred four-phase approach and a 
horizontal phasing plan under which one-half of a floor would be 
renovated at a time. Because implementing either of these alternative 
phasing plans would require utility system bypasses that are not 
required under the preferred four-phase approach, AOC estimates that 
project costs would increase between $50 million and $125 million 
depending on which alternative approach was used. 

[6] Office of Management and Budget, Planning, Budgeting, Acquisition, 
and Management of Capital Assets, OMB Circular A-11, Part 7, Section 
300,"Planning Budgeting, Acquisition , and Management of Capital 
Assets," Supplement to Part 7, "Capital Programming Guide" (Washington, 
D.C.: June 2006) refers to the Department of Energy's "Cost Estimating 
Guide," DOE G 4301.1-1 (Washington, D.C.: Mar. 28, 1997). 

[7] AOC's consultant, URS Corporation, completed a planning study and 
cost estimate for the renovation of the Cannon Building in December 
2004 and is currently updating the study to reflect changes to project 
requirements and applicable codes and standards, as well as updating 
the cost estimate. We based our analysis on a draft copy of the final 
study. 

[8] For additional information on the planning stage of the project 
development process, see GAO, Guide to the Building Development 
Process, the First Phase: Conceptual Planning, [hyperlink, 
http://www.gao.gov/products/GAO-04-859G] (Washington, D.C.: July 2004). 

[9] Delamination is a splitting, cracking, or separation of a 
cementitious material (concrete) on the surface of a concrete 
structure. 

[10] AOC intends to award a contract for construction to renovate the 
East Garage. This contract will include an option to renovate the West 
Garage. 

[11] GAO, Architect of the Capitol: Management and Accountability 
Framework Needed for Organizational Transformation, [hyperlink, 
http://www.gao.gov/products/GAO-03-231] (Washington, D.C.: Jan. 17, 
2003). 

[12] [hyperlink, http://www.gao.gov/products/GAO-03-231]. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: