This is the accessible text file for GAO report number GAO-09-620T 
entitled 'Coast Guard: Update on Deepwater Program Management, Cost, 
and Acquisition Workforce' which was released on April 22, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Homeland Security, Committee on 
Appropriations, House of Representatives: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 10:00 a.m. EDT:
Wednesday, April 22, 2009: 

Coast Guard: 

Update on Deepwater Program Management, Cost, and Acquisition 
Workforce: 

Statement of John P. Hutton, Director: 
Acquisition and Sourcing Management: 

GAO-09-620T: 

GAO Highlights: 

Highlights of GAO-09-620T, testimony before the Subcommittee on 
Homeland Security, Committee on Appropriations, House of 
Representatives. 

Why GAO Did This Study: 

The Deepwater Program is intended to recapitalize the Coast Guard’s 
fleet and includes efforts to build or modernize five classes each of 
ships and aircraft, and procure other key capabilities. In 2002, the 
Coast Guard contracted with Integrated Coast Guard Systems (ICGS) to 
manage the acquisition as systems integrator. After the program 
experienced a series of failures, the Coast Guard announced in April 
2007 that it would take over the lead role, with future work on 
individual assets to be potentially bid competitively outside of the 
existing contract. A program baseline of $24.2 billion was set as well. 
In June 2008, GAO reported on the new approach and concluded that while 
these steps were beneficial, continued oversight and improvement was 
necessary. The Coast Guard has taken actions to address the 
recommendations in that report. This testimony updates key issues from 
prior work: (1) Coast Guard program management at the overall Deepwater 
Program and asset levels; (2) how cost, schedules, and capabilities 
have changed from the 2007 baseline and how well costs are communicated 
to Congress; and (3) Coast Guard efforts to manage and build its 
acquisition workforce. 

GAO reviewed Coast Guard acquisition program baselines, human capital 
plans and other documents, and interviewed officials. For information 
not previously reported, GAO obtained Coast Guard views. The Coast 
Guard generally concurred with the findings. 

What GAO Found: 

The Coast Guard has assumed the role of systems integrator for the 
overall Deepwater Program by reducing the scope of work on contract 
with ICGS and assigning these functions to Coast Guard stakeholders. As 
part of its systems integration responsibilities, the Coast Guard has 
undertaken a fundamental reassessment of the capabilities, number, and 
mix of assets it needs; according to an official, it expects to 
complete this analysis by the summer of 2009. At the individual 
Deepwater asset level, the Coast Guard has improved and begun to apply 
the disciplined management process found in its Major Systems 
Acquisition Manual, but did not meet its goal of complete adherence to 
this process for all Deepwater assets by the second quarter of fiscal 
year 2009. For example, key acquisition management activities—such as 
operational requirements documents and test plans—are not in place for 
assets with contracts recently awarded or in production, placing the 
Coast Guard at risk of cost overruns or schedule slips. 

Due in part to the Coast Guard’s increased insight into what it is 
buying, the anticipated cost, schedules, and capabilities of many of 
the Deepwater assets have changed since the establishment of the $24.2 
billion baseline in 2007. Coast Guard officials have stated that this 
baseline reflected not a traditional cost estimate but rather the 
anticipated contract costs as determined by ICGS. As the Coast Guard 
has developed its own cost baselines for some assets, it has become 
apparent that some of the assets it is procuring will likely cost more 
than anticipated. Information to date shows that the total cost of the 
program may grow by $2.1 billion. As more cost baselines are developed 
and approved, further cost growth may become apparent. In addition, 
while the Coast Guard plans to update its annual budget requests with 
asset-based cost information, the current structure of its budget 
submission to Congress does not include certain details at the asset 
level, such as estimates of total costs and total numbers to be 
procured. The Coast Guard’s reevaluation of baselines has also changed 
its understanding of the delivery schedules and capabilities of 
Deepwater assets. 

One reason the Coast Guard sought a systems integrator from outside the 
Coast Guard was because it recognized that it lacked the experience and 
depth in workforce to manage the acquisition internally. The Coast 
Guard acknowledges that it still faces challenges in hiring and 
retaining qualified acquisition personnel and that this situation poses 
a risk to the successful execution of its acquisition programs. 
According to human capital officials in the acquisition directorate, as 
of April 2009, the acquisition branch had 16 percent of positions 
unfilled, including key jobs such as contracting officers and systems 
engineers. Even as it attempts to fill its current vacancies, the Coast 
Guard plans to increase the size of its acquisition workforce 
significantly by the end of fiscal year 2011. While the Coast Guard may 
be hard-pressed to fill these positions, it has made progress in 
identifying the broader challenges it faces and is working to mitigate 
them. In the meantime, the Coast Guard has been increasing its use of 
support contractors. 

View [hyperlink, http://www.gao.gov/products/GAO-09-620T] or key 
components. For more information, contact John Hutton at (202) 512-4841 
or huttonj@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss the Coast Guard's management 
and oversight of its Deepwater Program. The Deepwater Program began in 
the late 1990s as an effort to recapitalize the Coast Guard's 
operational fleet and now includes projects to build or modernize five 
classes each of ships and aircraft, as well as to procure other 
capabilities such as improved command, control, communications, 
computers, intelligence, surveillance, and reconnaissance (C4ISR) and 
unmanned aircraft. Recognizing that it did not have in place the 
experience and depth in its workforce to manage the acquisition, the 
Coast Guard contracted with Integrated Coast Guard Systems (ICGS) as a 
systems integrator in June 2002. After experiencing a series of 
programmatic failures, the Commandant acknowledged in April 2007 that 
the Coast Guard had relied too heavily on contractors to do the work of 
government and that government and industry had failed to control 
costs. He announced several major changes to the acquisition approach 
for Deepwater, the key one being that the Coast Guard would take over 
the lead role in systems integration from ICGS, with future work on 
individual assets to be potentially bid competitively outside of the 
existing contract. In May 2007, soon after this announcement, the 
Department of Homeland Security (DHS) approved a revised acquisition 
program baseline of $24.2 billion for the Deepwater Program. 

In June 2008, we reported on our assessment of the preliminary steps 
the Coast Guard had taken to revise its acquisition approach and 
concluded that while these steps were beneficial, continued oversight 
and improvement was necessary to further mitigate risks.[Footnote 1] 
The Coast Guard has taken actions to address the recommendations we 
made in that report. My statement is based largely on ongoing work for 
this subcommittee.[Footnote 2] We plan to provide a more complete 
analysis of the Deepwater issues raised in this statement in a report 
this summer. 

My focus today will be on: 

* Coast Guard efforts to manage the Deepwater Program at both the 
overall system and asset levels; 

* how cost, schedules, and capabilities have changed from the 2007 
baseline, and how well costs are communicated to Congress; and: 

* Coast Guard efforts to manage and build its acquisition workforce. 

As part of our ongoing work, we reviewed key Coast Guard documentation 
such as the Coast Guard's Major Systems Acquisition Manual, approved 
acquisition program baselines, and human capital plans. We also 
interviewed Coast Guard officials in the acquisition directorate, 
including program managers and contracting officers, and in other 
directorates such as those responsible for human capital issues and for 
assessing and developing operational requirements for Deepwater assets. 
This work was conducted between September 2008 and April 2009. We also 
relied on our past work regarding the Deepwater Program. Appendix I 
lists our selected reports on the Deepwater Program. All work for this 
statement was conducted in accordance with generally accepted 
government auditing standards. Those standards require that we plan and 
perform the audit to obtain sufficient, appropriate evidence to provide 
a reasonable basis for our findings and conclusions based on our audit 
objectives. We believe that the evidence obtained provides a reasonable 
basis for our findings and conclusions based on our audit objectives. 
For issues where our observations are based on work that has not been 
previously reported, we obtained Coast Guard views on our findings and 
incorporated technical comments where appropriate. The Coast Guard 
generally concurred with our findings. 

Background: 

The Coast Guard is a multimission, maritime military service within 
DHS. The Coast Guard's responsibilities fall into two general 
categories--those related to homeland security missions, such as port 
security and vessel escorts, and those related to non-homeland security 
missions, such as search and rescue and polar ice operations. To carry 
out these responsibilities, the Coast Guard operates a number of 
vessels and aircraft and, through its Deepwater Program, is currently 
modernizing or replacing those assets. 

At the start of the Deepwater Program in the late 1990s, the Coast 
Guard chose to use a system-of-systems acquisition strategy. A system- 
of-systems is defined as a set or arrangement of assets that results 
when independent assets are integrated into a larger system that 
delivers unique capabilities. As the systems integrator, ICGS was 
responsible for designing, constructing, deploying, supporting, and 
integrating the Deepwater assets into a system-of-systems. Under this 
approach, the Coast Guard provided the contractor with broad, overall 
performance specifications--such as the ability to interdict illegal 
immigrants--and ICGS determined the asset specifications. According to 
Coast Guard officials, the ICGS proposal was submitted and priced as a 
package; that is, the Coast Guard bought the entire solution and could 
not reject any individual component. In November 2006, the Coast Guard 
submitted a cost, schedule, and performance baseline to DHS that 
established the total acquisition cost of the ICGS solution at $24.2 
billion and projected that the acquisition would be completed in 2027. 
In May 2007, shortly after the Coast Guard had announced its intention 
to take over the role of systems integrator, DHS approved the baseline. 

Table 1 describes in more detail the assets the Coast Guard is planning 
to procure according to approved baselines. 

Table 1: Information on Deepwater Assets: 

Asset: National Security Cutter; 
Quantity: 8 ships; 
Description: The NSC is intended to be the flagship of the Coast 
Guard's fleet, with an extended on-scene presence, long transits, and 
forward deployment. The cutter and its aircraft and boat assets are to 
operate worldwide. 

Asset: Offshore Patrol Cutter; 
Quantity: 25 ships; 
Description: The OPC is intended to conduct patrols for homeland 
security functions, law enforcement, and search and rescue operations. 
It will be designed for long-distance transit, extended on-scene 
presence, and operations with multiple aircraft and boats. 

Asset: Fast Response Cutter; 
Quantity: 58 ships; 
Description: The FRC is conceived as a patrol boat with high readiness, 
speed, adaptability, and endurance to perform a wide range of missions. 

Asset: Medium Endurance Cutter Sustainment; 
Quantity: 27 ships; 
Description: The cutter sustainment project is intended to improve the 
cutters' operating and cost performance by replacing obsolete, 
unsupportable, or maintenance-intensive equipment. 

Asset: Patrol Boat Sustainment; 
Quantity: 20 ships; 
Description: The patrol boat sustainment project is intended to improve 
the boats' operating and cost performance by replacing obsolete, 
unsupportable, or maintenance-intensive equipment. 

Asset: Cutter Small Boats; 
Quantity: 124 boats; 
Description: Cutter small boats are an integral component of the 
planned capabilities for the larger cutters and patrol boats and are 
critical to achieving success in all operational missions. The Coast 
Guard is currently restructuring its cutter small boat programs. 

Asset: Maritime Patrol Aircraft; 
Quantity: 36 aircraft; 
Description: The MPA is intended to be a transport and surveillance, 
fixed-wing aircraft used to perform search and rescue missions, enforce 
laws and treaties, and transport cargo and personnel. 

Asset: HC-130J Long-Range Surveillance Aircraft; 
Quantity: 6 aircraft; 
Description: The HC-130J is a four-engine turbo-prop aircraft that the 
Coast Guard intends to deploy with improved interoperability, C4ISR, 
and sensors to enhance surveillance, detection, classification, 
identification, and prosecution. 

Asset: HC-130H Long-Range Surveillance Aircraft; 
Quantity: 16 aircraft; 
Description: The HC-130H is the legacy Coast Guard long-range 
surveillance aircraft, which the Coast Guard intends to update with 
structural sustainability, improved interoperability, C4ISR, and 
sensors to enhance surveillance, detection, classification, 
identification, and prosecution. 

Asset: HH-65 Multimission Cutter Helicopter; 
Quantity: 102 aircraft; 
Description: The HH-65 Dolphin is the Coast Guard's short-range 
recovery helicopter which is being upgraded in phases to improve its 
engines, communications equipment, avionics, and other capabilities. 

Asset: HH-60 Medium Range Recovery Helicopter; 
Quantity: 42 aircraft; 
Description: The HH-60J is a medium-range recovery helicopter designed 
to perform search and rescue missions offshore in all weather 
conditions. The Coast Guard intends to upgrade the helicopters' 
avionics, C4ISR, and other systems. 

Asset: Unmanned Aerial System; 
Quantity: To be determined; 
Description: The Coast Guard has deferred acquisition of this asset 
because of challenges in technology maturation of the ICGS proposed 
design. The Coast Guard continues its analysis of needs and 
alternatives, with an acquisition plan for this asset in development. 

Asset: C4ISR; 
Quantity: n.a.; 
Description: The Coast Guard's acquisition of C4ISR capabilities 
includes upgrades to existing cutters and shore installations, 
acquisitions of new assets, and development of a common operating 
picture to provide operationally-relevant information and knowledge 
across the full range of Coast Guard operations. 

Source: GAO analysis of Coast Guard data. 

[End of table] 

In deciding to take over the systems integrator role from ICGS, the 
Coast Guard has taken steps to increase government control and 
accountability by, among other things, applying the disciplined program 
management processes in its Major Systems Acquisition Manual (MSAM) to 
Deepwater assets. The MSAM requires documentation and approval of 
acquisition decisions at key points in a program's life-cycle by 
designated officials at high levels. The Coast Guard has established a 
number of goals and deadlines for completing these activities in its 
Blueprint for Acquisition Reform, which was initially released in July 
2007 and was last updated in July 2008. 

Coast Guard Has Assumed the Role of Systems Integrator But Lags In 
Applying Disciplined Asset-Level Processes as It Continues with 
Procurements: 

The Coast Guard has taken three major steps to become the systems 
integrator for the Deepwater Program. It has defined and assigned 
systems integrator functions to Coast Guard stakeholders, begun to 
reassess the capabilities and mix of assets it requires, and 
significantly reduced the contractual responsibilities of ICGS. While 
the Coast Guard has made progress in applying the disciplined MSAM 
acquisition process to its Deepwater assets, it did not meet its goal 
of being fully compliant by the second quarter of fiscal year 2009. In 
the meantime, the Coast Guard continues with production of certain 
assets and award of new contracts in light of what it views as pressing 
operational needs. 

Coast Guard Has Assumed Key Roles and Responsibilities from ICGS in 
Becoming the Systems Integrator: 

The role of systems integrator involves planning, organizing, and 
integrating a mix of assets into a system-of-systems capability greater 
than the sum of the capabilities of the individual parts. ICGS's role 
as systems integrator for the Deepwater Program included requirements 
management, systems engineering, and defining how assets would be 
employed by Coast Guard users in an operational setting. In addition, 
the contractor had technical authority over all asset design and 
configuration decisions. In 2008, the Coast Guard acknowledged that in 
order to assume the role of systems integrator, it needed to define 
systems integrator functions and assign them to Coast Guard 
stakeholders. Through codified changes to internal relationships, 
policies, and contractual arrangements, the Coast Guard has done so. 
For example, the Coast Guard formally designated certain directorates 
as technical authorities to establish, monitor, and approve technical 
standards for Deepwater assets related to design, construction, 
maintenance, logistics, C4ISR, and life-cycle staffing and training. 
The Coast Guard's capabilities directorate determines operational 
requirements and the asset mix to satisfy those requirements and 
establishes priorities. This directorate is expected to collaborate 
with the technical authorities to ensure that the Coast Guard's 
technical standards are incorporated during the requirements 
development process. Further, the acquisition directorate's program and 
project managers are to be held accountable for ensuring that the 
assets it procures fulfill operational requirements and the technical 
authority standards. The relationships between Coast Guard directorates 
in executing their systems integrator roles are represented graphically 
in figure 1. 

Figure 1: Directorate Relationships: 

[Refer to PDF for image: illustration] 

Technical Authorities: 

* Human Resources(CG-1); 
- Requirements: Assistant Commandant for Capability (CG-7). 

* Engineering and Logistics (CG-4); 

* Command, Control, Communications, Computers and IT (CG-6); 
- Acquisitions: Assistant Commandant for Acquisitions (CG-9). 

(direct relationship between CG-7 and CG-9) 

Source: GAO analysis based on Coast Guard documents. 

[End of figure] 

When it contracted with ICGS, the Coast Guard had limited insight into 
how the contractor's proposed solution would meet overall mission 
needs, limiting its ability to justify the proposed solution and make 
informed decisions about possible trade-offs. To improve its insight, 
the capabilities directorate has initiated a fundamental reassessment 
of the capabilities and mix of assets the Coast Guard needs to fulfill 
its Deepwater missions. The goals of this fleet mix analysis include 
validating mission performance requirements and revisiting the number 
and mix of all assets that are part of the Deepwater Program. A 
specific part of the study will be to analyze alternatives and 
quantities for the Offshore Patrol Cutter, an asset which accounts for 
a projected $8 billion of the total Deepwater costs. According to an 
official, the results of this analysis are expected in the summer of 
2009. Coast Guard leadership plans to assess the results and make 
future procurement decisions based on the analysis. 

In conjunction with its assuming the role of systems integrator, the 
Coast Guard has significantly reduced the scope of work on contract 
with ICGS. In March 2009, the Coast Guard issued a task order to ICGS 
limited to tasks such as data management and quality assurance for 
assets currently under contract with ICGS including C4ISR, the Maritime 
Patrol Aircraft (MPA), and the National Security Cutter (NSC). The 
Coast Guard is currently developing plans to transition these functions 
from ICGS to the Coast Guard or an independent third party by February 
2011 when this task order expires. For assets procured or planned to be 
procured outside of the ICGS contract such as the Offshore Patrol 
Cutter, systems engineering and program management functions are 
expected to be carried out by the Coast Guard with support from third 
parties and contractors. According to officials, the Coast Guard has no 
plans to award additional orders to ICGS for systems integrator 
functions within the current award term or for any work after the award 
term expires in January 2011.[Footnote 3] 

As Asset-level Management Gets Underway, Production and Award of New 
Contracts Are Proceeding Despite Some Gaps in Knowledge: 

Since our June 2008 report on the Deepwater Program, and taking into 
account our recommendation, the Coast Guard has improved its MSAM 
process.[Footnote 4] For example, the process now dictates that the 
acquisition project and program managers work collaboratively with the 
technical authorities as described above. The MSAM process was revised 
to require acquisition planning and an analysis of alternatives for 
procurement to start at an earlier stage, which is intended to help 
inform the budget and planning processes. Other improvements include 
the adoption of our recommendation for a formal design review, 
Milestone 2A, before authorizing low-rate initial production. The MSAM 
phases and milestones are shown in figure 2. 

Figure 2: Major Systems Acquisition Manual (MSAM) Phases and 
Milestones: 

[Refer to PDF for image: illustration] 

Project identification: 

Project initiation (milestone 0): 

Concept and technology development (milestone 1): 
* Begin acquisition. 

Capability development and demonstration (milestones 2 and 2A): 
* Approve low-rate initial production. 

Production & deployment (milestone 3): 
* Approve full-rate production. 

Operations & support: 

Source: Coast Guard. 

Note: Black diamonds denote milestones. 

[End of figure] 

Because the Coast Guard previously exempted Deepwater from the MSAM 
process, assets were procured without following a disciplined program 
management approach. Recognizing the importance of ensuring that each 
acquisition project is managed through sustainable and repeatable 
processes and wanting to adhere to proven acquisition procedures, in 
July 2008, the Coast Guard set a goal of completing the MSAM 
acquisition management activities for all Deepwater assets by the 
second quarter of fiscal year 2009. However, of the 12 Deepwater assets 
in the concept and technology development phase or later, 9 are behind 
plan in terms of MSAM compliance. In the meantime, the Coast Guard has 
proceeded with production and awarded new contracts without all of the 
knowledge it needs to ensure that the capabilities it is buying will 
meet Coast Guard needs within cost and schedule constraints. 

For assets already in production, such as the MPA and the NSC, the 
Coast Guard has made some progress in the past year in retroactively 
developing acquisition documentation with the intent of providing the 
traceability from mission needs to operational performance that was 
previously lacking. For example, the Coast Guard approved an 
operational requirements document for the MPA in October 2008 to 
establish a formal performance baseline and identify attributes for 
testing. Through this process, the Coast Guard discovered that ICGS's 
requirement for operational availability (the amount of time that an 
aircraft is available to perform missions) was excessive compared to 
the Coast Guard's own standards. According to a Coast Guard official, 
the ICGS requirement would have needlessly increased costs to maintain 
and operate the aircraft. 

Even as the Coast Guard gains this additional knowledge about MPA 
requirements, it is continuing with this procurement despite not having 
completed operational testing. According to the MSAM, testing in an 
operational environment should be completed with the initial production 
variants of an asset to demonstrate that capabilities meet requirements 
before committing to larger purchases. An approved test plan helps 
ensure that the tests conducted are clearly linked to requirements and 
mission needs. While the MPA began an operational assessment in July 
2008, the Coast Guard still lacked, as of March 2009, a test plan 
approved by DHS and endorsed by its independent test authority, the 
Navy's Commander Operational Testing and Evaluation Force. With 11 of 
36 MPAs already on contract, the Coast Guard has completed the 
operational assessment[Footnote 5] but does not plan to complete 
operational testing until the fiscal year 2011 time frame. Similarly, 
according to Coast Guard officials, operational testing of the NSC, 
also conducted by the Coast Guard's independent test authority, has 
begun in the absence of an approved test plan, which is now expected in 
July 2009. By the time testing is scheduled to be completed in 2011, 
the Coast Guard plans to have six of eight NSCs either built or on 
contract. 

According to the MSAM process, operational requirements must be 
approved before procuring an asset. However, since committing to the 
MSAM process, the Coast Guard has awarded new contracts for assets 
without having all required acquisition documentation in place, due to 
its determination that the need for these capabilities is pressing. 
This situation puts the Coast Guard at risk of cost overruns and 
schedule slips if it turns out that what it is buying does not meet 
requirements. 

* In September 2008, after conducting a full and open competition, the 
Coast Guard awarded an $88.2 million contract for the design and 
construction of a lead Fast Response Cutter. However, the Coast Guard 
does not have an approved operational requirements document or test 
plan for this asset. Recognizing the risks inherent in this approach, 
the Coast Guard developed a basic requirements document and an 
acquisition strategy based on procuring a proven design. These 
documents were reviewed and approved by the Coast Guard's capabilities 
directorate, the engineering and logistics directorate, and chief of 
staff before the procurement began. According to a Coast Guard 
official, the Coast Guard intends to have an approved operational 
requirements document before procuring additional ships. 

* In February 2009, the Coast Guard issued a $77.7 million task order 
to ICGS for a second segment of C4SIR design and development, before 
developing its requirements for performance. Design and development 
costs for the first segment increased from $55.5 million to $141.3 
million. According to Coast Guard officials, this increase was due in 
part to the structure of the ICGS contract under which the Coast Guard 
lacked visibility into the software development processes and 
requirements. Furthermore, ICGS's C4ISR solution for the Deepwater 
Program contains proprietary software. The Coast Guard has acquired 
data rights to the software and, according to Coast Guard officials, 
has determined that the capabilities it is buying meet Coast Guard 
technical standards for maintenance, logistics, and interoperability. 

Coast Guard Developing More Realistic Cost Estimates for Deepwater 
Assets, but Cost Reporting May Not Keep Congress Fully Informed: 

Since the establishment of the $24.2 billion baseline for the Deepwater 
program in 2007, the anticipated cost, schedules, and capabilities of 
many of the Deepwater assets have changed, in part due to the Coast 
Guard's increased insight into what it is buying. The purpose of the 
2007 baseline was to establish cost, schedule, and operational 
requirements for the Deepwater system as a whole; these were then 
allocated to the major assets. Coast Guard officials have stated that 
this baseline reflected not a traditional cost estimate but rather the 
anticipated contract costs as determined by ICGS. Furthermore, the 
Coast Guard lacked insight into how ICGS arrived at some of the costs 
for Deepwater assets. 

As the Coast Guard has assumed greater responsibility for management of 
the Deepwater Program, it has begun to improve its understanding of 
costs by establishing new baselines for individual assets based on its 
own cost estimates. These baselines begin at the asset level and are 
developed by Coast Guard project managers, validated by a separate 
office within the acquisition branch and, in most cases, are reviewed 
and approved by DHS. The estimates use common cost estimating 
procedures and assumptions, and may account for costs not previously 
captured. Beginning in September 2008 the Coast Guard began submitting 
new baselines to DHS. To date, 10 asset baselines have been submitted 
to DHS and 4 have been approved. These new baselines are formulated 
using various sources of information depending on the acquisition phase 
of the asset. For example, the baseline for the NSC was updated using 
the actual costs of material, labor, and other considerations already 
in effect at the shipyards. The baselines for other assets, like the 
MPA, were updated using independent cost estimates. As the Coast Guard 
approaches major milestones, such as the decision to enter low-rate 
initial production or begin system development, officials have stated 
that the cost estimates for all assets will be reassessed and 
revalidated. 

Better-informed Baselines Suggest Deepwater Costs Could Exceed $24.2 
Billion: 

As the Coast Guard has developed its own cost baselines for Deepwater 
assets, it has become apparent that some of the assets it is procuring 
will likely cost more than anticipated. While the Coast Guard is still 
in the process of communicating the effect and origin of these cost 
issues to DHS, information available to date for assets shows that the 
total cost of the program will likely exceed $24.2 billion, with 
potential cost growth of approximately $2.1 billion through the life of 
the Deepwater Program. As more baselines are approved by DHS, further 
cost growth may become apparent. Table 2 provides the estimates of 
asset costs available as of April 2009. It does not reflect the roughly 
$3.6 billion in other Deepwater costs, such as program management, that 
the Coast Guard states do not require a new baseline. 

Table 2: Changes from 2007 Deepwater Baseline (Then-year dollars in 
millions): 

Asset: National Security Cutter; 
2007 baseline: $3,450; 
Current estimate: (as of April 2009): $4,749; 
Change: $1,299. 

Asset: Offshore Patrol Cutter; 
2007 baseline: $8,098; 
Current estimate: (as of April 2009): baseline in development, due 
November 2009. 

Asset: Fast Response Cutter[A]; 
2007 baseline: $3,206; 
Current estimate: (as of April 2009): baseline with DHS. 

Asset: Medium Endurance Cutter Sustainment; 
2007 baseline: $317; 
Current estimate: (as of April 2009): $321[B]; 
Change: $4. 

Asset: Patrol Boat Sustainment; 
2007 baseline: $117; 
Current estimate: (as of April 2009): $194[B]; 
Change: $77. 

Asset: Maritime Patrol Aircraft; 
2007 baseline: $1,706; 
Current estimate: (as of April 2009): $2,223; 
Change: $517. 

Asset: HC-130J Long-Range Surveillance Aircraft; 
2007 baseline: $11; 
Current estimate: (as of April 2009): $167[C]; 
Change: $156. 

Asset: HC-130H Long-Range Surveillance Aircraft; 
2007 baseline: $610; 
Current estimate: (as of April 2009): baseline with DHS. 

Asset: HH-65 Multimission Cutter Helicopter; 
2007 baseline: $741; 
Current estimate: (as of April 2009): baseline with DHS. 

Asset: HH-60 Medium Range Recovery Helicopter; 
2007 baseline: $451; 
Current estimate: (as of April 2009): baseline with DHS. 

Asset: Cutter Small Boats; 
2007 baseline: $110; 
Current estimate: (as of April 2009): baseline in development, due June 
2009. 

Asset: Unmanned Aerial System; 
2007 baseline: $503; 
Current estimate: (as of April 2009): baseline in development. 

Asset: C4ISR; 
2007 baseline: $1,353; 
Current estimate: (as of April 2009): baseline with DHS. 

Source: GAO analysis of Coast Guard documentation. 

[A] In the 2007 baseline, costs for two variants of the Fast Response 
Cutter were presented. The new baseline will represent the total costs 
for the recently awarded design. 

[B] Reflects the threshold, or maximum allowable, cost. 

[C] Reflects estimate presented in the Coast Guard's Fiscal Year 2008 
Deepwater Expenditure Plan. The initial estimate of $11 million only 
included fleet introduction costs and did not include the acquisition 
cost of the aircraft or installation of the mission systems. 

[End of table] 

The effort by the Coast Guard to develop new baselines provides not 
only a better understanding of the costs of the Deepwater assets, but 
also insight into the drivers of any cost growth. For example, the new 
NSC baseline attributes a $1.3 billion rise in cost to a range of 
factors, from the additional costs to correct fatigue issues on the 
first three cutters to the rise in commodity and labor prices. The 
additional $517 million needed to procure all 36 MPA is attributed 
primarily to items that were not accounted for in the previous 
baseline, including a simulator to train aircrews, facility 
improvements, and adequate spare parts. By understanding the reasons 
for cost growth, the Coast Guard may be able to better anticipate and 
control costs in the future. 

The Coast Guard has structured some of the new baselines to show how 
cost growth could be controlled by making trade-offs in asset 
quantities and/or capabilities. For example, the new MPA baseline 
provides cost increments that show the acquisition may be able to 
remain within its initial allotment of the overall $24.2 billion if 8 
fewer aircraft are acquired. Coast Guard officials have stated that 
other baselines currently under review by DHS present similar cost 
increments. This information, if combined with data from the fleet mix 
study to show the effect of quantity or capability reductions on the 
system-of-systems as a whole, offers a unique opportunity to the Coast 
Guard for serious discussions of trade-offs. 

The Coast Guard's reevaluation of baselines has also changed its 
understanding of the delivery schedules and capabilities of Deepwater 
assets. According to the new baselines, a number of assets will be 
available for operational use later than originally anticipated. This 
includes a 12-month delay for the NSC to reach its initial operating 
capability and an 18-month delay for the MPA. Coast Guard officials 
stated that the restructuring of the unmanned aircraft and small boat 
projects has delayed the deployment of these assets with the NSC and 
affects the ship's anticipated capabilities in the near term. We plan 
to report later this summer on the operational effect of the delays in 
the NSC project. 

Current Budget Reporting Lacks Detail at Asset Level, and May Not 
Adequately Inform Congress: 

While the Coast Guard plans to update its annual budget requests with 
asset-based cost information, the current structure of its budget 
submission could limit Congress's understanding of details at the asset 
level. The budget submission presents total acquisition costs only at 
the overall Deepwater system level ($24.2 billion), and the description 
of funding for individual assets does not include key information such 
as costs beyond the current 5-year capital investment plan, i.e., life- 
cycle costs, or the total quantities of assets planned. For example, 
while the justification of the NSC request includes an account of the 
capabilities the asset is expected to provide, how these capabilities 
link to the Coast Guard's missions, and details on what activities past 
appropriations have funded, it does not include estimates of total 
program cost, future award or delivery dates of remaining assets, or 
even the total number of assets to be procured. 

Our past work has emphasized that one of the keys to a successful 
capital acquisition, such as the multibillion-dollar ships and aircraft 
the Coast Guard is procuring, is budget submissions that clearly 
communicate needs.[Footnote 6] A key part of this communication is to 
provide decision makers with information about cost estimates, risks, 
and the scope of a planned project before committing substantial 
resources to it. Good budgeting also requires that the full costs of a 
project be considered upfront when decisions are made. Other agencies 
within the federal government that acquire systems similar to those of 
the Coast Guard capture these elements in justifications of their 
requests. To illustrate, table 3 provides a comparison of the 
information found in the NSC budget justification with that used by the 
Navy for its shipbuilding programs. 

Table 3: Comparison of Budget Justifications: 

Coast Guard (NSC); 
Prior year allocation: [Check]; 
Current request: [Check]; 
5-year outlook: [Check]; 
Future contract awards: [Empty]; 
Total acquisition cost: [Empty]; 
Total asset quantities: [Empty]. 

Navy; 
Prior year allocation: [Check]; 
Current request: [Check]; 
5-year outlook: [Check]; 
Future contract awards: [Check]; 
Total acquisition cost: [Check]; 
Total asset quantities: [Check]. 

Source: GAO analysis. 

[End of table] 

While the Coast Guard does include some of this information in its 
asset-level Quarterly Acquisition Reports to Congress and the Deepwater 
Program Expenditure Report, these documents are provided only to the 
appropriations committees, and the information is restricted due to 
acquisition sensitive material. 

Coast Guard Having Difficulty Staffing Government Acquisition Positions 
but Working To Improve Processes: 

One reason the Coast Guard originally sought a systems integrator was 
because it recognized that it lacked the experience and depth in its 
workforce to manage the acquisition internally. Now that the Coast 
Guard has taken control of the Deepwater acquisition, it acknowledges 
that it faces challenges in hiring and retaining qualified acquisition 
personnel and that this situation poses a risk to the successful 
execution of its acquisition programs. According to human capital 
officials in the acquisition directorate, as of April 2009, the 
acquisition branch had funding for 855 military and civilian personnel 
and had filled 717 of these positions--leaving 16 percent unfilled. The 
Coast Guard has identified some of these unfilled positions as core to 
the acquisition workforce, such as contracting officers and 
specialists, program management support staff, and engineering and 
technical specialists. Even as it attempts to fill its current 
vacancies, the Coast Guard plans to increase the size of its 
acquisition workforce significantly by the end of fiscal year 2011. 

Coast Guard Has Expanded Collaboration with Independent Third Parties 
and Increased Use of Support Contractors to Assist with Acquisition: 

To supplement and enhance the use of its internal expertise, the Coast 
Guard has increased its use of third-party, independent experts outside 
of both the Coast Guard and existing Deepwater contractors. For 
example, a number of organizations within the Navy provided independent 
views and expertise on a wide range of issues, including testing and 
safety. In addition, the Coast Guard will use the American Bureau of 
Shipping, an independent organization that establishes and applies 
standards for the design and construction of ship and other marine 
equipment, as an advisor and independent reviewer on the design and 
construction of the Fast Response Cutter. The Coast Guard has also 
begun a relationship with a university-affiliated research center to 
augment its expertise as it executes its fleet mix analysis. 

In addition to third party experts, the Coast Guard has been increasing 
its use of support contractors. Currently, there are approximately 200 
contractor employees in support of the acquisition directorate-- 
representing 24 percent of its total acquisition workforce--a number 
that has steadily increased in recent years. These contractors are 
performing a variety of services--some of which support functions the 
Coast Guard has identified as core to the government acquisition 
workforce--including project management support, engineering, contract 
administration, and business analysis and management. While support 
contractors can provide a variety of essential services, their use must 
be carefully overseen to ensure that they do not perform inherently 
governmental roles. The Coast Guard acknowledges this risk and is 
monitoring its use of support contractors to properly identify the 
functions they perform, as well as developing a policy to define what 
is and what is not inherently governmental. 

Coast Guard Has Made Progress in Identifying and Mitigating Acquisition 
Workforce Challenges: 

While the Coast Guard may be hard-pressed to fill the government 
acquisition positions it has identified both now and in the future, it 
has made progress in identifying the broader challenges it faces and is 
working to mitigate them. The Coast Guard has updated two documents key 
to this effort, the Blueprint for Acquisition Reform, now in its third 
iteration, and the Acquisition Human Capital Strategic Plan, which is 
in its second iteration. Each document identifies challenges the Coast 
Guard faces in developing and managing its acquisition workforce and 
outlines initiatives and policies to meet these challenges. For 
example, the Acquisition Human Capital Strategic Plan lays out three 
overall challenges and outlines over a dozen strategies the Coast Guard 
is pursuing to address them in building and maintaining an acquisition 
workforce. The discussion of strategies includes status indicators and 
milestones to monitor progress, as well as supporting actions such as 
the formation of partnerships with the Defense Acquisition University 
and continually monitoring turnover in critical occupations. The 
Blueprint for Acquisition Reform supports many these initiatives and 
provides deadlines for their completion. In fact, the Coast Guard has 
already completed a number of initiatives including: 

* achieving and maintaining Level III program manager certifications, 

* adopting a model to assess future workforce needs, 

* incorporating requests for additional staff into the budget cycle, 

* initiating tracking of workforce trends and metrics, 

* expanding use of merit-based rewards and recognitions, and: 

* initiating training on interactions and relationships with 
contractors. 

Concluding Observations: 

In conclusion, I'd like to emphasize several key points as we continue 
to oversee the various Coast Guard initiatives discussed today. It is 
important to recognize that Coast Guard leadership has made significant 
progress in identifying and addressing the challenges in taking on the 
role of systems integrator for the Deepwater Program. The Coast Guard 
is continuing to build on this progress by starting to follow a 
disciplined program management approach that improves its knowledge of 
what is required to meet its goals. An important component of this 
approach is gaining realistic assessments of needed capabilities and 
associated costs to enable the Coast Guard and Congress to better 
execute decision making and oversight. The Coast Guard's ability to 
build an adequate acquisition workforce is critical, and over time the 
right balance must be struck between numbers of government and 
contractor personnel. Until the Coast Guard gains a thorough 
understanding of what it is buying and how much it will cost, and is 
able to put in place the necessary workforce to manage the Deepwater 
Program, it will continue to face risks in carrying out this 
multibillion dollar acquisition. 

Mr. Chairman, this concludes my statement and I would be happy to 
respond to any questions the committee may have. 

GAO Contact and Acknowledgements: 

For further information about this testimony, please contact John P. 
Hutton, Director, Acquisition and Sourcing Management, at (202) 512- 
4841, huttonj@gao.gov. Other individuals making key contributions to 
this testimony include Michele Mackin, Assistant Director; Greg 
Campbell; Carolynn Cavanaugh; J. Kristopher Keener; Angie Nichols- 
Friedman; and Sylvia Schatz. 

[End of section] 

Related GAO Products: 

Coast Guard: Change in Course Improves Deepwater Management and 
Oversight, but Outcome Still Uncertain. [hyperlink, 
http://www.gao.gov/products/GAO-08-745]. Washington, D.C.: June 24, 
2008. 

Coast Guard: Observations on Changes to Management and Oversight of the 
Deepwater Program. [hyperlink, 
http://www.gao.gov/products/GAO-09-462T]. Washington, D.C.: March 24, 
2009. 

Status of Selected Assets of the Coast Guard's Deepwater Program. 
[hyperlink, http://www.gao.gov/products/GAO-08-270R]. Washington, D.C.: 
March 11, 2008. 

Coast Guard: Deepwater Program Management Initiatives and Key Homeland 
Security Missions. [hyperlink, 
http://www.gao.gov/products/GAO-08-531T]. Washington, D.C.: March 5, 
2008. 

Coast Guard: Status of Efforts to Improve Deepwater Program Management 
and Address Operational Challenges. [hyperlink, 
http://www.gao.gov/products/GAO-07-575T]. Washington, D.C.: March 8, 
2007. 

Coast Guard: Status of Deepwater Fast Response Cutter Design Efforts. 
[hyperlink, http://www.gao.gov/products/GAO-06-764]. Washington, D.C.: 
June 23, 2006. 

Coast Guard: Changes to Deepwater Plan Appear Sound, and Program 
Management Has Improved, but Continued Monitoring Is Warranted. 
[hyperlink, http://www.gao.gov/products/GAO-06-546]. Washington, D.C.: 
April 28, 2006. 

Coast Guard: Progress Being Made on Addressing Deepwater Legacy Asset 
Condition Issues and Program Management, but Acquisition Challenges 
Remain. [hyperlink, http://www.gao.gov/products/GAO-05-757]. 
Washington, D.C.: July 22, 2005. 

Coast Guard: Preliminary Observations on the Condition of Deepwater 
Legacy Assets and Acquisition Management Challenges. [hyperlink, 
http://www.gao.gov/products/GAO-05-651T]. Washington, D.C.: June 21, 
2005. 

Coast Guard: Deepwater Program Acquisition Schedule Update Needed. 
[hyperlink, http://www.gao.gov/products/GAO-04-695]. Washington, D.C.: 
June 14, 2004. 

Contract Management: Coast Guard's Deepwater Program Needs Increased 
Attention to Management and Contractor Oversight. [hyperlink, 
http://www.gao.gov/products/GAO-04-380]. Washington, D.C.: March 9, 
2004. 

Coast Guard: Actions Needed to Mitigate Deepwater Project Risks. 
[hyperlink, http://www.gao.gov/products/GAO-01-659T]. Washington, D.C.: 
May 3, 2001. (120827): 

[End of section] 

Footnotes: 

[1] GAO, Coast Guard: Change in Course Improves Deepwater Management 
and Oversight, but Outcome Still Uncertain, [hyperlink, 
http://www.gao.gov/products/GAO-08-745] (Washington, D.C.: June 24, 
2008). 

[2] Our ongoing work is also being done for the Subcommittee on 
Homeland Security, Committee on Appropriations, U.S. Senate. 

[3] In June 2002, the Coast Guard awarded the Deepwater contract to 
ICGS. The award was an indefinite delivery, indefinite quantity 
contract with a 5-year base period and five potential extensions of the 
contract (award terms) of up to 5 years each. Based on the government's 
assessment of its performance, ICGS earned one award term of 43 months. 
According to Coast Guard officials, the Coast Guard and ICGS have 
executed a bilateral contract modification removing any future award 
terms from the ICGS contract. 

[4] [hyperlink, http://www.gao.gov/products/GAO-08-745]. 

[5] The focus of an operational assessment is on significant trends 
noted in development efforts, programmatic voids, risk areas, adequacy 
of requirements, and the ability of the program to support operational 
testing. An operational assessment may be conducted at any time using 
technology demonstrators, prototypes, mock-ups, engineering development 
models, or simulations, but is not to substitute for initial 
operational testing and evaluation. 

[6] GAO, Executive Guide: Leading Practices in Capital Decision-Making, 
[hyperlink, http://www.gao.gov/products/GAO/AIMD-99-32] (Washington, 
D.C.: December 1998). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: