This is the accessible text file for GAO report number GAO-07-1250T 
entitled 'South Florida Ecosystem: Some Restoration Progress Has Been 
Made, but the Effort Faces Significant Delays, Implementation 
Challenges, and Rising Costs' which was released on September 20, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on International Operations and Organizations, 
Democracy and Human Rights, Committee on Foreign Relations, U.S. 
Senate: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 3:00 p.m. EDT: 

Wednesday, September 19, 2007: 

South Florida Ecosystem: 

Some Restoration Progress Has Been Made, but the Effort Faces 
Significant Delays, Implementation Challenges, and Rising Costs: 

Statement of Anu K. Mittal, Director: 

Natural Resources and Environment: 

South Florida Ecosystem Restoration: 

GAO-07-1250T: 

GAO Highlights: 

Highlights of GAO-07-1250T, a testimony before the Subcommittee on 
International Operations and Organizations, Democracy and Human Rights, 
Committee on Foreign Relations, U.S. Senate. 

Why GAO Did This Study: 

The South Florida ecosystem covers about 18,000 square miles, and is 
home to the Everglades, one of the world’s unique environmental 
resources. Historic efforts to redirect the flow of water through the 
ecosystem have jeopardized its health and reduced the Everglades to 
about half of its original size. In 1993, the United Nations 
Educational, Scientific, and Cultural Organization’s World Heritage 
Committee (WHC) added Everglades National Park (Park) to its List of 
World Heritage in Danger sites. In 2000, a strategy to restore the 
ecosystem was set; the effort was expected to take at least 40 years 
and cost $15.4 billion. It comprises 222 projects, including 60 key 
projects known as the Comprehensive Everglades Restoration Plan (CERP), 
to be undertaken by a multiagency partnership. 

This testimony is based on GAO’s May 2007 report, South Florida 
Ecosystem: Restoration Is Moving Forward, but Is Facing Significant 
Delays, Implementation Challenges, and Rising Costs, and a review of 
WHC decision documents relating to the Park’s listing. This statement 
addresses the (1) status of projects implemented (2) status of projects 
key to improving the health of the Park, (3) project sequencing 
factors, and (4) funding provided for the effort and extent to which 
costs have increased. 

What GAO Found: 

Of the restoration effort’s 222 projects, 43 have been completed, 107 
are being implemented, and 72 are in design, in planning, or are not 
yet started. The completed and ongoing projects will provide improved 
water quality and water flow within the ecosystem and additional 
habitat for wildlife. According to restoration officials, significant 
progress has been made in acquiring land, constructing water quality 
projects, and restoring a natural water flow to the Kissimmee River—the 
headwater of the ecosystem. Many of the policies, strategies, and 
agreements required to guide the restoration in the future are also now 
in place. However, the 60 CERP projects, which are the most critical to 
the restoration’s overall success, are among those that are currently 
being designed, planned, or have not yet started. Some of these 
projects are behind schedule by up to 6 years. Florida recently began 
expediting the design and construction of eight key projects, with the 
hope that they would immediately benefit the environment, enhance flood 
control, and increase water supply, thus providing further momentum to 
the restoration. 

In 2006, the WHC adopted several key benchmarks that if met would 
facilitate removal of the Everglades National Park from its List of 
World Heritage in Danger sites. As noted by WHC, achievement of these 
benchmarks was linked to the implementation of nine key restoration 
projects. However, only one of these projects has been completed, four 
are currently being implemented and four are currently being designed. 
Moreover, the benefits of these projects will not be available for many 
years because most of the projects are scheduled for completion between 
2011 and 2035. There are no overarching sequencing criteria that 
restoration officials use when making implementation decisions for all 
222 projects that make up the restoration effort. Instead, decisions 
for 162 projects are driven largely by the availability of funds. 

There are regulatory criteria to ensure that the goals and purposes of 
the 60 CERP projects are achieved in a cost effective manner. However, 
the 2005 sequencing plan developed for these projects is not consistent 
with the criteria because some of the data needed to fully apply these 
criteria were not available. Therefore, there is little assurance that 
the plan will be effective. GAO recommended that the agencies obtain 
the needed data and then comprehensively reassess the sequencing of the 
CERP projects. 

From fiscal years 1999 through 2006, the federal government contributed 
$2.3 billion and Florida contributed $4.8 billion, for a total of about 
$7.1 billion for the restoration. However, federal funding was about 
$1.4 billion short of the funds originally projected for this period. 
In addition, the total estimated costs for the restoration have 
increased by 28 percent—from $15.4 billion in 2000 to $19.7 billion in 
2006 because of project scope changes, increased construction costs, 
and higher land costs. More importantly, these cost estimates do not 
represent the true costs for the overall restoration effort because 
they do not include all cost components for a number of projects. 

What GAO Recommends: 

GAO is not making any new recommendations. 

[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-1250T]. 

To view the full product click on the link above. For more information, 
contact Anu K. Mittal at 202-512-3841 or mittala@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

We are pleased to be here today to participate in your hearing on 
protecting the Everglades. As you know, restoring the South Florida 
ecosystem is a complex, long-term effort. This vast region, which is 
home to a rapidly growing population of more than 6 million people and 
supports a large agriculture-, tourism-, and recreation-based economy, 
also encompasses one of the world's unique environmental resources--the 
Everglades. Recognizing the importance of the Everglades, in 1979, the 
World Heritage Committee (WHC) of the United Nations Educational, 
Scientific, and Cultural Organization (UNESCO) included Everglades 
National Park (Park) on its list of world cultural and natural heritage 
sites of importance. However, over the past 100 years, engineering 
projects designed to control floods and supply water to the residents 
of South Florida have diverted water from the Everglades. This 
alteration of water flow, coupled with agricultural and industrial 
activities and urbanization, has jeopardized the ecosystem's health and 
reduced the Everglades to about half of its original size. In light of 
the Everglades deteriorating condition, in 1993 the WHC added the Park 
to its List of World Heritage in Danger sites. These sites are 
determined to be facing serious and specific threats and require major 
conservation efforts. 

In 1996, through the Water Resources Development Act of 1996, the 
Congress formalized the South Florida Ecosystem Restoration Task Force, 
an effort established by federal agencies in 1993 to stem the 
deterioration of the ecosystem and restore the Everglades to a more 
natural state. The Task Force was expanded to include state, local, and 
tribal representatives and was charged with coordinating and 
facilitating efforts to restore the ecosystem. The restoration effort 
currently consists of 222 projects, which include 60 key projects that 
comprise the Comprehensive Everglades Restoration Plan (CERP), 28 
projects that lay the foundation for the CERP projects (that we refer 
to as CERP-related projects); and 134 projects that are not directly 
related to CERP (that we refer to as non-CERP projects). According to 
WHC and Park documents, nine of the 222 projects are key to achieving a 
set of benchmarks adopted by the WHC in 2006 that, when met, would lead 
to the removal of the Park from its list of sites in danger. 

Our testimony today focuses on the (1) status of restoration projects 
and their expected benefits, (2) status of projects that are key to 
restoring the health of Everglades National Park, (3) factors that 
influence the sequencing of project implementation, and (4) amount of 
funding provided to the restoration effort since 1999 and the extent to 
which costs have increased. Our testimony is based primarily on our May 
2007 report [Footnote 1]on the status of the South Florida Ecosystem 
Restoration Initiative. In addition, at the request of the 
subcommittee, we reviewed publicly available WHC decision documents 
regarding Everglades National Park's inclusion on the List of World 
Heritage in Danger. We conducted our work in accordance with generally 
accepted government auditing standards. 

In summary, we found the following: 

* Forty-three of the 222 projects that constitute the South Florida 
ecosystem restoration effort have been completed, while the remaining 
projects are currently being implemented or are in design, being 
planned, or have not yet started. Many of the completed projects are 
intended primarily to improve water quality in natural areas or to 
acquire or improve tracts of land in order to preserve wildlife 
habitat. The projects now being implemented also emphasize the 
restoration of wildlife habitat by acquiring or improving land, as well 
as the construction of key CERP-related projects that will improve 
water flow to natural areas. The projects not yet implemented are 
largely CERP projects that are crucial to realizing the restoration's 
overall goals, but these projects are progressing slowly. Despite the 
slow progress, agency officials report a number of achievements, such 
as finalizing key CERP agreements and restoring a more natural water 
flow to the Kissimmee River which is the headwater of the ecosystem. In 
addition, because of the continuing delays in implementing critical 
CERP projects, the state has begun expediting the design and 
construction of some of these projects with its own resources. The 
state hopes that its efforts will provide some immediate environmental, 
flood control and water supply benefits and will help provide some 
impetus to the larger CERP effort. 

* Most of the nine projects that were identified by the WHC as being 
critical to removing Everglades National Park from the list of world 
heritage sites in danger have not yet been completed. Specifically, 
only one project has been completed, four are currently being 
implemented, and four are currently in the planning and design phase. 
Moreover, the benefits from these projects may not be apparent for many 
more years. For example, five of the projects have scheduled completion 
dates from 2012 to 2035. 

* There are no overarching criteria to ensure that the 222 projects 
that make up the restoration effort are implemented in a sequence that 
would ensure the achievement of environmental benefits as early as 
possible and in the most cost effective manner. Instead, implementation 
decisions for the 162 CERP-related and non-CERP projects are largely 
driven by available funding. The 60 CERP projects--which are critical 
to successfully achieving the restoration--have sequencing criteria; 
however, when the agencies developed their sequencing plan for CERP 
projects in 2005, they did not have key data and other information to 
fully apply these criteria. Recently, the agencies began revising the 
CERP project schedules and sequencing plan, but they still do not have 
the key information needed to fully apply the established criteria. As 
a result, there is little assurance that the revised sequencing plan, 
when it is final, will lead to a CERP project implementation plan that 
will provide restoration benefits as early as possible and in the most 
cost-effective manner. We recommended that the agencies obtain the 
information needed to fully apply the required criteria and then 
comprehensively reassess its sequencing decisions to ensure that the 
CERP projects have been appropriately sequenced. 

* Participating federal and state agencies provided a total of $7.1 
billion for the restoration effort from fiscal years 1999 through 2006. 
During this period, the federal government contributed about $2.3 
billion to the restoration effort and Florida contributed about $4.8 
billion. However, the federal contribution to the effort has been about 
$1.4 billion less than agencies expected during this period. Because 
the state has contributed more than its share the overall shortfall for 
the restoration effort has been about $1.2 billion. At the same time, 
the total projected cost of the restoration effort has increased by 28 
percent--from $15.4 billion in 2000 to $19.7 billion in 2006. According 
to agency officials, the overall cost increases are due to project 
scope changes, increased construction costs, and higher land costs. 
Moreover, these cost estimates do not reflect the true cost of the 
restoration effort, which could be significantly higher because most 
CERP projects are still in the conceptual phase and their full cost is 
not yet known. 

Background: 

The South Florida ecosystem covers about 18,000 square miles in 16 
counties. It extends from the Kissimmee Chain of Lakes south of Orlando 
to Lake Okeechobee, and continues south past the Florida Bay to the 
reefs southwest of the Florida Keys. The ecosystem is in jeopardy today 
because of past efforts that diverted water from the Everglades to 
control flooding and to supply water for urban and agricultural 
development. The Central and Southern Florida project, a large-scale 
water control project begun in the late 1940s, constructed more than 
1,700 miles of canals and levees and over 200 water control structures 
that drain an average of 1.7 billion gallons of water per day into the 
Atlantic Ocean and the Gulf of Mexico. This construction resulted in 
insufficient water for the natural system and for the growing 
population, along with degraded water quality. Today, the Everglades 
has been reduced to half its original size and the ecosystem continues 
to deteriorate because of the alteration of the water flow, impacts of 
agricultural and industrial activities, and increasing urbanization. 

In response to growing signs of ecosystem deterioration, federal 
agencies established the South Florida Ecosystem Restoration Task Force 
in 1993 to coordinate ongoing federal restoration activities. The Water 
Resources Development Act of 1996 formalized the Task Force and 
expanded its membership to include state, local, and tribal 
representatives, and charged it with coordinating and facilitating 
efforts to restore the ecosystem. The Task Force, which is chaired by 
the Secretary of the Department of the Interior, consists of 14 members 
representing 7 federal agencies, 2 American Indian tribes, and 5 state 
or local governments.[Footnote 2] 

To accomplish the restoration, the Task Force established the following 
three goals: 

* Get the water right. The purpose of this goal is to deliver the right 
amount of water, of the right quality, to the right places, at the 
right times. However, restoring a more natural water flow to the 
ecosystem while providing adequate water supplies and controlling 
floods will require efforts to expand the ecosystem's freshwater supply 
and improve the delivery of water to natural areas. Natural areas of 
the ecosystem are made up of federal and state lands, and coastal 
waters, estuaries, bays, and islands. 

* Restore, preserve, and protect natural habitats and species. To 
restore lost and altered habitats and recover the endangered or 
threatened species native to these habitats, the federal and state 
governments will have to acquire lands and reconnect natural habitats 
that have become disconnected through growth and development, and halt 
the spread of invasive species. 

* Foster compatibility of the built and natural systems. To achieve the 
long-term sustainability of the ecosystem, the restoration effort has 
the goal of maintaining the quality of life in urban areas while 
ensuring that (1) development practices limit habitat fragmentation and 
support conservation and (2) traditional industries, such as 
agriculture, fishing, and manufacturing, continue to be supported and 
do not damage the ecosystem. 

The centerpiece for achieving the goal to get the water right is the 
Comprehensive Everglades Restoration Plan (CERP), approved by the 
Congress in the Water Resources Development Act of 2000 (WRDA 2000). 
CERP is one of the most ambitious restoration efforts the federal 
government has ever undertaken. It currently encompasses 60 individual 
projects that will be designed and implemented over approximately 40 
years.[Footnote 3] These projects are intended to increase the water 
available for the natural areas by capturing much of the water that is 
currently being diverted, storing the water in many different 
reservoirs and storage wells, and releasing it when it is needed. The 
cost of implementing CERP will be shared equally between the federal 
government and the state of Florida and will be carried out primarily 
by the U.S. Army Corps of Engineers (the Corps) and the South Florida 
Water Management District (SFWMD), which is the state authority that 
manages water resources for South Florida.[Footnote 4] After the Corps 
and SFWMD complete the initial planning and design for individual CERP 
projects, they must submit the proposed projects to the Congress to 
obtain authorization and funding for construction. 

In addition to the CERP projects, another 162 projects are also part of 
the overall restoration effort. Twenty-eight of these projects, when 
completed, will serve as the foundation for many of the CERP projects 
and are intended to restore a more natural water flow to Everglades 
National Park and improve water quality in the ecosystem. Nearly all of 
these "CERP-related" projects were already being designed or 
implemented by federal and state agencies, such as the Department of 
the Interior and SFWMD, in 2000 when the Congress approved CERP. The 
remaining 134 projects include a variety of efforts that will, among 
other things, expand wildlife refuges, eradicate invasive species, and 
restore wildlife habitat, and are being implemented by a number of 
federal, state, and tribal agencies, such as the U.S. Fish and Wildlife 
Service, the Florida Department of Environmental Protection (FDEP), and 
the Seminole Tribe of Florida. Because these projects were not 
authorized as part of CERP and do not serve as CERP's foundation, we 
refer to them as "non-CERP" projects. 

Success in completing the restoration effort and achieving the expected 
benefits for the ecosystem as quickly as possible and in the most cost- 
effective manner depends on the order, or sequencing, in which many of 
the 222 projects will be designed and completed. Appropriate sequencing 
is also important to ensure that interdependencies among restoration 
projects are not ignored. For example, projects that will construct 
water storage facilities and stormwater treatment areas need to be 
completed before undertaking projects that remove levees and restore a 
more natural water flow to the ecosystem. 

Recognizing the threats that Everglades National Park was facing, in 
1993, UNESCO's World Heritage Committee (WHC) included the Park on its 
List of World Heritage in Danger. This list includes cultural or 
natural properties that are facing serious and specific threats such as 
those caused by large-scale public or private projects or rapid 
urbanization; the outbreak or the threat of an armed conflict; 
calamities and cataclysms; and changes in water levels, floods, and 
tidal waves. The Park's inclusion on the list resulted from five 
specific threats: (1) urban encroachment; (2) agricultural fertilizer 
pollution; (3) mercury contamination of fish and wildlife; (4) lowered 
water levels due to flood control measures; and (5) damage from 
Hurricane Andrew, which struck the south Florida peninsula in 1992 with 
winds exceeding 164 miles per hour. In 2006, WHC adopted a set of 
benchmarks that, when met, would lead to the Park's removal from the 
list. According to Park and WHC documents, nine projects that are part 
of the overall restoration effort will contribute to the achievement of 
these benchmarks. 

Although Many Restoration Projects Have Been Completed or Are Ongoing, 
Key Restoration Benefits Are Expected to Come From Projects Not Yet 
Implemented: 

Forty-three of the 222 projects that constitute the South Florida 
ecosystem restoration effort have been completed, while the remaining 
projects are currently being implemented or are either in design, being 
planned, or have not yet started. Table 1 shows the status of the 222 
restoration projects. 

Table 1: Status of the 222 Restoration Projects by Project Group: 

CERP; 
Completed: 0; 
In implementation: 7; 
Not yet implemented: Planning/design: 21; 
Not yet implemented: Not yet started: 32; 
Total: 60. 

CERP-related; 
Completed: 15; 
In implementation: 10; 
Not yet implemented: Planning/design: 3; 
Not yet implemented: Not yet started: 0; 
Total: 28. 

Non-CERP; 
Completed: 28; 
In implementation: 90; 
Not yet implemented: Planning/design: 2; 
Not yet implemented: Not yet started: 14; 
Total: 134. 

Total; 
Completed: 43; 
In implementation: 107; 
Not yet implemented: Planning/design: 26; 
Not yet implemented: Not yet started: 46; 
Total: 222. 

Source: GAO analysis of documents provided by Task Force and 
participating agencies. 

[End of table] 

Completed Restoration Projects --Although 43 of the 222 projects have 
been completed since the beginning of the restoration effort, this 
total is far short of the 91 projects that the agencies reported would 
be completed by 2006.[Footnote 5] Nine projects were completed before 
2000 when the strategy to restore the ecosystem was set. These projects 
are expected to provide benefits primarily in the area of habitat 
acquisition and improvement. Thirty-four projects were completed 
between 2000 and 2006. The primary purposes of these projects range 
from the construction of stormwater treatment areas, to the acquisition 
or improvement of land for habitat, to the drafting of water supply 
plans. 

Ongoing Restoration Projects --Of the 107 projects currently being 
implemented,[Footnote 6] 7 are CERP projects, 10 are CERP-related 
projects, and 90 are non-CERP projects. Five of the seven CERP projects 
are being built by the state in advance of the Corps' completion of the 
necessary project implementation reports and submission of them to the 
Congress for authorization and appropriations. Nonetheless, some of the 
CERP projects currently in implementation are significantly behind 
schedule. For example, four of the seven CERP projects in 
implementation were originally scheduled for completion between 
November 2002 and September 2006, but instead will be completed up to 6 
years behind their original schedule because it has taken the Corps 
longer than originally anticipated to design and obtain approval for 
these projects. Overall, 19 of the 107 projects currently being 
implemented have expected completion dates by 2010. Most of the 
remaining 88 projects are non-CERP habitat acquisition and improvement 
projects that have no firm end date because the land will be acquired 
from willing sellers as it becomes available. 

Projects Not Yet Implemented --Of the 72 restoration projects not yet 
implemented--in design, in planning, or not yet started--53 are CERP 
projects that are expected to be completed over the next 30 years and 
will provide important benefits such as improved water flow, additional 
water for restoration as well as other water-related needs. In 
contrast, the other 19 projects include 3 CERP-related and 16 non-CERP 
projects, which are expected to be completed by or before 2013. 
Consequently, the full environmental benefits for the South Florida 
ecosystem restoration that the CERP projects were intended to provide 
will not be realized for several decades. Several of the CERP projects 
in design, in planning, or not yet begun, were originally planned for 
completion between December 2001 and December 2005, but instead will be 
completed from 2 to 6 years behind their original schedule. According 
to agency officials CERP project delays have occurred for the following 
reasons: 

* It took longer than expected to develop the appropriate policy, 
guidance, and regulations that WRDA 2000 requires for the CERP effort. 

* Some delays were caused by the need to modify the conceptual design 
of some projects to comply with the requirements of WRDA 2000's savings 
clause. According to this clause, CERP projects cannot transfer or 
eliminate existing sources of water unless an alternate source of 
comparable quantity and quality is provided, and they cannot reduce 
existing levels of flood protection.[Footnote 7] 

* Progress was limited by the availability of less federal funding than 
expected and a lack of congressional authorization for some of the 
projects. 

* The extensive modeling that accompanies the design and implementation 
of each project in addition to the "cumbersome" project review process 
may have also contributed to delays, as well as stakeholder comment, 
dispute resolution, and consensus-building that occurs at each stage of 
a project. 

* Delays have occurred in completing the CERP-related Modified Water 
Deliveries to Everglades National Park (Mod Waters) project, which is a 
major building block for CERP. These delays, in turn, have delayed CERP 
implementation. 

Given the continuing delays in implementing critical CERP projects, the 
state has begun expediting the design and construction of some of these 
projects with its own resources. The state's effort, known as Acceler8, 
includes most of the CERP projects that were among WRDA 2000's 10 
initially authorized projects, whose costs were to be shared by the 
federal government and the state. According to Florida officials, by 
advancing the design and construction of these projects with its own 
funds, the state hopes to more quickly realize restoration benefits for 
both the natural and human environments and to jump-start the overall 
CERP effort once the Congress begins to authorize individual projects. 
The Acceler8 projects include seven that are affiliated with CERP and 
an eighth that expands existing stormwater treatment areas. The state 
expects to spend more than $1.5 billion to design and construct these 
projects by 2011. 

Restoration Projects That Would Help Achieve the World Heritage 
Committee's Benchmarks Will Not Be Completed for Many Years: 

Most of the restoration projects that would help Everglades National 
Park achieve the WHC's benchmarks for removing the Park from its list 
of world heritage sites in danger have not been completed. According to 
Park and WHC documents, nine restoration projects were key to meeting 
these benchmarks. Table 2 lists the nine projects, the type of project, 
implementation status, and expected completion date. 

Table 2: Status of Nine Restoration Projects Key to Achieving the World 
Heritage Committee's Benchmarks: 

Project: Storm Water Treatment Areas 3/4; 
Type: CERP-related; 
Purpose: Water Quality; 
Stage: Completed; 
Completion Date: 2005. 

Project: East Everglades Addition to Everglades National Park; 
Type: Non-CERP; 
Purpose: Habitat Acquisition and Improvement; 
Stage: Ongoing; 
Completion Date: TBD. 

Project: Everglades Agriculture Area Storm Water Treatment Areas 
Expansion; 
Type: CERP-related; 
Purpose: Water Quality; 
Stage: Ongoing; 
Completion Date: 2010. 

Project: Modified Water Deliveries; 
Type: CERP-related; 
Purpose: Water Storage and Flow; 
Stage: Ongoing; 
Completion Date: 2011. 

Project: C-111 (South Dade); 
Type: CERP-related; 
Purpose: Water Storage and Flow; 
Stage: Ongoing; 
Completion Date: 2012. 

Project: C-111 Spreader Canal; 
Type: CERP; 
Purpose: Water Quality; 
Stage: Not Yet Implemented; 
Completion Date: 2015[A]. 

Project: Everglades National Park Seepage Management; 
Type: CERP; 
Purpose: Water Storage and Flow; 
Stage: Not Yet Implemented; 
Completion Date: 2015. 

Project: Water Conservation Area 3 --DECOMP; 
Type: CERP; 
Purpose: Water Storage and Flow; 
Stage: Not Yet Implemented; 
Completion Date: 2020. 

Project: Central Lake Belt Storage; 
Type: CERP; 
Purpose: Water Storage and Flow; 
Stage: Not Yet Implemented; 
Completion Date: 2035. 

Source: GAO analysis of agency provided data. 

[A] SFWMD is expediting the design and construction of this project 
with its own funds in advance of congressional authorization, which may 
result in earlier completion. 

[End of table] 

As table 2 shows, only one of the nine projects has been completed; 
four projects are ongoing and will not be completed until at least 
2012; and four projects are still in planning and design and are not 
expected to be completed until some time between 2015 and 2035. 

In February 2007, the United States prepared a status report for the 
WHC on the progress made in achieving the benchmarks that the committee 
had established for the Park in 2006. Based on its review of this 
progress report, at a benchmarks meeting on April 2-3, 2007, the WHC's 
draft decision was to retain Everglades National Park on the list of 
world heritage sites in danger; to recommend that the United States 
continue its commitment to the restoration and conservation of the Park 
and provide the required financial resources for the full 
implementation of the activities associated with CERP. WHC's draft 
decision also requested that the United States provide an updated 
report by February 1, 2008 on the progress made towards implementation 
of the corrective measures. However, at the WHC session held between 
June 23 and July 2, 2007, the WHC decided to remove the Park from the 
list of world heritage sites in danger and commended the United States 
for the progress made in implementing corrective measures. In its final 
decision, the WHC encouraged the United States to continue its 
commitment to the restoration and provide the required financial 
resources for the full implementation of the activities associated with 
CERP. It is unclear from the WHC final decision document whether any 
additional or new information was provided to the committee that led to 
its final decision. 

The Overall Restoration Effort Has No Sequencing Criteria and Criteria 
Established For CERP Projects Have Not Been Fully Applied: 

No overall sequencing criteria guide the implementation of the 222 
projects that comprise the South Florida ecosystem restoration effort. 
For the 60 CERP projects there are clearly defined criteria to be 
considered in determining the scheduling and sequencing of projects. 
However, the Corps has not fully applied these criteria when making 
CERP project sequencing decisions, because it lacked key data such as 
updated environmental benefits data and interim goals. As a result the 
Corps primarily relied on technical interdependencies and availability 
of funding as the criteria for making sequencing decisions.[Footnote 8] 
The Corps has recently started to revisit priorities for CERP projects' 
and alter project schedules that were established in 2005 (this process 
is referred to as CERP-reset). However, because the Corps continues to 
lack certain key data for making sequencing decisions, the revised 
plan, when completed, will also not fully adhere to the criteria. 

Although CERP-related projects provide the foundation for many CERP 
projects, there are no established criteria for determining their 
implementation schedule and their estimated start and completion dates 
largely depend upon when and if the implementing agency will have 
sufficient funding to implement the project. For example, the 
construction of the Mod Waters project has been delayed several times 
since 1997 because, among other things, Interior did not receive enough 
funding to complete the construction of this project. This project is 
expected to restore natural hydrologic conditions across 190,000 acres 
of habitat in Everglades National Park and assist in the recovery of 
threatened and endangered plants and wildlife. The completion date for 
the Mod Waters Project has slipped again and it is now not expected to 
be completed until 2011. Because completion of this project is critical 
to the implementation of other CERP projects such as the Water 
Conservation Area 3 Decompartmentalization and Sheetflow Enhancement 
(Decomp) project--a project that many agency officials consider key to 
restoring the natural system--these delays will have a ripple effect on 
the completion date of this project as well. 

Similarly, for non-CERP projects, agencies reported that they do not 
have any sequencing criteria; instead, they decide on the scheduling 
and timing of these projects primarily if and when funding becomes 
available. For example, Florida has a land acquisition program to 
acquire lands for conservation and habitat preservation throughout the 
state, including for some non-CERP projects that are part of the South 
Florida ecosystem restoration effort. State officials have identified 
lands and added them to a list of priority projects proposed for 
acquisition throughout the state. However, whether or not these lands 
will be acquired for non-CERP projects depends on whether there is 
available funding in the annual budget, there are willing sellers, and 
the land is affordable based on the available funding. 

Because of the correct sequencing of CERP projects is essential to the 
overall success of the restoration effort, we recommended that the 
Corps obtain the data that it needs to ensure that all required 
sequencing criteria are considered and then comprehensively reassess 
its sequencing decisions to ensure that CERP projects have been 
appropriately sequenced to maximize the achievement of restoration 
goals. The agency agreed with our recommendation. 

Federal Agencies and Florida Have Provided More Than $7 Billion for 
Restoration Activities Since 1999, But Estimated Costs Have Increased 
and Are Likely to Rise: 

From fiscal year 1999 through fiscal year 2006, federal and state 
agencies participating in the restoration of the South Florida 
ecosystem provided $7.1 billion for the effort. Of this total, federal 
agencies provided $2.3 billion and Florida provided $4.8 billion. Two 
agencies--the Corps and Interior--provided over 80 percent of the 
federal contribution. As figure 1 shows, federal and state agencies 
allocated the largest portion of the $7.1 billion to non-CERP projects 
for fiscal years 1999 through 2006. 

Figure 1: Federal and State Funding Provided for CERP, CERP-Related, 
and Non-CERP Projects and Activities, Fiscal Years 1999-2006: 

[See PDF for image] 

Source: GAO analysis of federal and state agencies restoration funding 
data. 

Note: Amounts do not total to $7.1 billion due to rounding. The amounts 
are $1.93 billion for CERP-related, $2.35 billion for CERP, and $2.80 
billion for non-CERP. 

[End of figure] 

While federal agencies and Florida provided about $2.3 billion during 
fiscal years 1999 through 2006 for CERP projects, this amount was about 
$1.2 billion less than they had estimated needing for these projects 
over this period. This was because the federal contribution was $1.4 
billion less than expected. This shortfall occurred primarily because 
CERP projects did not receive the congressional authorization and 
appropriations that the agencies had expected. In contrast, Florida 
provided a total of $2 billion over the period, exceeding its expected 
contribution to CERP by $250 million, and therefore making up some of 
the federal funding shortfall. 

Additionally, between July 31, 2000, and June 30, 2006, the total 
estimated cost for the South Florida ecosystem restoration grew from 
$15.4 billion to $19.7 billion, or by 28 percent. A significant part of 
this increase can be attributed to CERP projects; for these projects 
costs increased from $8.8 billion to $10.1 billion. This increase 
represents nearly 31 percent of the increase in the total estimated 
cost for the restoration. Agency officials reported that costs have 
increased for the restoration effort primarily because of inflation, 
increased land and construction costs, and changes in the scope of 
work. Furthermore, the costs of restoring the South Florida ecosystem 
are likely to continue to increase for the following reasons: 

* Estimated costs for some of the projects are not known or fully known 
because they are still in the design and planning stage. For example, 
the total costs for one project that we examined--the Site 1 
Impoundment project--grew by almost $36 million; from about $46 million 
to about $81 million after the design phase was completed. If other 
CERP projects, for which initial planning and design have not yet been 
completed, also experience similar increases in project costs, then the 
estimated total costs of not only CERP but the overall restoration 
effort will grow significantly. 

* The full cost of acquiring land for the restoration effort is not 
known. Land costs for 56 non-CERP land projects, expected to total 
862,796 acres, have not yet been reported. According to state 
officials, Florida land prices are escalating rapidly, owing primarily 
to development pressures. Consequently, future project costs are likely 
to rise with higher land costs. Similarly, while land acquisition costs 
for CERP projects are included as part of the total estimated project 
costs, thus far, the state has acquired only 54 percent of the land 
needed for CERP projects, at a cost of $1.4 billion. An additional 
178,000 acres have yet to be acquired; the cost of these purchases is 
not yet known and is therefore not fully reflected in the cost of CERP 
and overall restoration costs. 

* The cost of using new technologies for the restoration effort is 
unknown. The Congress authorized pilot projects in 1999 and 2000 to 
determine the feasibility of applying certain new technologies for 
storing water, managing seepage, and reusing treated wastewater. While 
the pilot projects have been authorized, the cost to construct or 
implement projects based on the results of the pilot projects is not 
yet known. 

In conclusion, Mr. Chairman, our review of the South Florida Ecosystem 
restoration effort shows that the some progress has been made in moving 
the restoration forward. However, the achievement of the overall goals 
of the restoration and ultimately improvements in the ecological 
condition of Everglades National Park depends on the effective 
implementation of key projects that have not progressed as quickly as 
was expected. Moreover, the shortfall in federal funding has 
contributed to some of these delays and at the same time the costs of 
the restoration continues to increase and we believe could rise 
significantly higher than the current estimate of almost $20 billion. 
In light of these concerns, we believe that restoring the South Florida 
Ecosystem and Everglades National Park, will continue to be a 
significant challenge for the foreseeable future. This concludes our 
prepared statement. We would be happy to respond to any questions you 
may have. 

GAO Contacts: 

If you have any questions about this statement, please contact Anu K. 
Mittal @ 202-512-3841 or mittala@gao.gov. Other contributors to this 
statement include Sherry McDonald (Assistant Director) and Kevin Bray. 

Footnotes: 

[1] South Florida Ecosystem Restoration: Restoration is Moving Forward, 
but Is Facing Significant Delays, Implementation Challenges, and Rising 
Costs, GAO-07-520 (Washington, D.C.: May 31, 2007 

[2] Representatives from the state's major industries, environmental 
groups, and other stakeholders provide comments to the Task Force 
through public meetings and forums. 

[3] The original number of individual projects in CERP was 68. In 
addition to these 68, CERP included 6 pilot projects and 3 proposed 
feasibility studies. Since CERP's approval in 2000, the Corps and the 
South Florida Water Management District have reorganized the projects 
to group those that are logically connected into broader projects. For 
example, several projects around Lake Okeechobee have been combined 
into one project. At the time of our report, CERP consisted of 60 
projects, but the total number of projects that make up CERP may 
continue to change as implementation progresses and projects are added, 
combined, divided into multiple parts or phases, or deleted. 

[4] Although SFWMD is CERP's primary nonfederal sponsor, the Florida 
Department of Environmental Protection as well as three county 
governments and two American Indian tribes also serve as nonfederal 
sponsors for portions of the plan. 

[5] South Florida Ecosystem Restoration Task Force, Coordinating 
Success: Strategy for Restoration of the South Florida Ecosystem, 
Volume 2 (Miami, Fla.: July 31, 2000). 

[6] Some projects have multiple components, and while the entire 
project cannot be counted as completed, important components of it may 
be finished. Unless all components of the project were complete, we 
counted these projects as being implemented. 

[7] The sources of water and levels of flood protection that must be 
protected are those that were in existence on the date of WRDA 2000's 
enactment--December 11, 2000. 

[8] An agreement establishing interim goals was signed by the 
Departments of the Army and the Interior and the state of Florida in 
late April/early May 2007. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548: 

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400: 

U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Susan Becker, Acting Director, Beckers@gao.gov (202) 512-4800: 

U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: