This is the accessible text file for GAO report number GAO-07-910T 
entitled 'Polar-Orbiting Operational Environmental Satellites: 
Restructuring Is Under Way, but Challenges and Risks Remain' which was 
released on June 7, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 

GAO: 

Testimony: 

Before the Subcommittee on Energy and Environment, House Committee on 
Science and Technology: 

For Release on Delivery: 

Expected at 1 p.m. EDT Thursday, June 7, 2007: 

Polar-orbiting Operational Environmental Satellites: 

Restructuring Is Under Way, but Challenges and Risks Remain: 

Statement of David A. Powner, Director: 
Information Technology Management Issues: 

GAO-07-910T: 

GAO Highlights: 

Highlights of GAO-07-910T, a testimony before the Subcommittee on 
Energy and Environment, House Committee on Science and Technology 

Why GAO Did This Study: 

The National Polar-orbiting Operational Environmental Satellite System 
(NPOESS) is a tri-agency acquisition—managed by the Departments of 
Commerce and Defense and the National Aeronautics and Space 
Administration—which experienced escalating costs, schedule delays, and 
technical difficulties. These factors led to a June 2006 decision to 
restructure the program thereby decreasing its complexity, increasing 
its estimated cost to $12.5 billion, and delaying the first two 
satellites by 3 to 5 years. 

GAO was asked to summarize a report being released today that (1) 
assesses progress in restructuring the acquisition, (2) evaluates 
progress in establishing an effective management structure, and (3) 
identifies the status and key risks on the program’s major segments. 

What GAO Found: 

The NPOESS program office has made progress in restructuring the 
acquisition by establishing and implementing interim program plans 
guiding contractors’ work activities in 2006 and 2007; however, 
important tasks remain to be done. Executive approvals of key 
acquisition documents are about 9 months late—due in part to the 
complexity of navigating three agencies’ approval processes. Delays in 
finalizing these documents could hinder plans to complete contract 
negotiations by July 2007 and could keep the program from moving 
forward in fiscal year 2008 with a new program baseline. 

The program office has also made progress in establishing an effective 
management structure by adopting a new organizational framework with 
increased oversight from program executives and by instituting more 
frequent and rigorous program reviews; however, plans to reassign the 
recently appointed Program Executive Officer will likely increase the 
program’s risks. Additionally, the program lacks a process and plan for 
identifying and filling staffing shortages, which has led to delays in 
key activities such as cost estimating and contract revisions. As of 
June 2007, key positions remain to be filled. 

Development and testing of major NPOESS segments—including key sensors 
and ground systems—are under way, but significant risks remain. For 
example, while work continues on key sensors, two of them—the 
visible/infrared imager radiometer suite and the cross-track infrared 
sounder—experienced significant problems and are considered high risk 
(see table). Continued sensor problems could cause further cost 
increases and schedule delays. Additionally, while progress has been 
made in reducing delays in the data processing system, work remains in 
refining the algorithms needed to translate sensor observations into 
usable weather products. Given the tight time frames for completing 
this work, it will be important for program officials and executives to 
continue to provide close oversight of milestones and risks. 

Table: Key NPOESS Components and Corresponding Risk Levels: 

NPOESS component: Visible/infrared imager radiometer suite; 
Risk level: High. 

NPOESS component: Cross-track infrared sounder; 
Risk level: High. 

NPOESS component: Ozone mapper/profiler suite; 
Risk level: Moderate. 

NPOESS component: Advanced technology microwave sounder; 
Risk level: Low. 

NPOESS component: Command, control, and communications system; 
Risk level: Low. 

NPOESS component: Interface data processing system; 
Risk level: Moderate. 

Source: GAO analysis of NPOESS Integrated program Office data. 

[End of section] 

What GAO Recommends: 

In its report, GAO recommends that the appropriate executives approve 
key acquisition documents, the Secretary of Defense delay reassigning 
the Program Executive, and the Secretary of Commerce ensure that 
program authorities identify and address staffing needs. Agency 
officials agreed with all of the recommendations except delaying the 
Program Executive’s reassignment. GAO believes that proceeding with 
this reassignment would increase program risks. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-910T]. 

To view the full product, click on the link above. For more 
information, contact David A. Powner, (202) 512-9286 and 
pownerd@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

We appreciate the opportunity to participate in today's hearing to 
discuss our work on the $12.5 billion dollar National Polar-orbiting 
Operational Environmental Satellite System (NPOESS) program. NPOESS is 
expected to be a state-of-the-art, environment-monitoring satellite 
system that will replace two existing polar-orbiting environmental 
satellite systems. Polar-orbiting satellites provide data and imagery 
that are used by weather forecasters, climatologists, and the military 
to map and monitor changes in weather, climate, the oceans, and the 
environment. The NPOESS program is considered critical to the United 
States' ability to maintain the continuity of data required for weather 
forecasting (including severe weather events such as hurricanes) and 
global climate monitoring through the year 2026. 

Three agencies share responsibility for the NPOESS program: the 
Department of Commerce's National Oceanic and Atmospheric 
Administration (NOAA), the Department of Defense (DOD)/United States 
Air Force, and the National Aeronautics and Space Administration 
(NASA). To manage the NPOESS program, these agencies established a tri- 
agency integrated program office. In recent years, the program has 
experienced escalating costs, schedule delays, and technical 
difficulties, which led to a June 2006 decision to restructure it. This 
decision decreased the complexity of the program by reducing the number 
of satellites and sensors, increased the estimated cost of the program 
to $12.5 billion, and delayed the launches of the first two satellites 
by 3 and 5 years, respectively. 

As requested, this statement summarizes a report being released today 
that (1) assesses the NPOESS program office's progress in restructuring 
the acquisition, (2) evaluates the program office's progress in 
establishing an effective management structure, and (3) identifies the 
status and key risks facing the program's major segments.[Footnote 1] 
The report includes recommendations to NOAA, NASA, and DOD to 
facilitate the restructuring of the program and to reduce program 
risks. In preparing this testimony, we relied on our work supporting 
the accompanying report. That report contains a detailed overview of 
our scope and methodology. All the work on which this testimony is 
based was performed in accordance with generally accepted government 
auditing standards. 

Results in Brief: 

The NPOESS program office has made progress in restructuring the 
acquisition by establishing and implementing interim program plans 
guiding contractors' work activities in 2006 and 2007; however, 
important tasks remain to be done. Although the program office 
developed key acquisition documents (including a memorandum of 
agreement on the roles and responsibilities of the three agencies, a 
revised acquisition strategy, and a system engineering plan) the 
responsible executives in the three agencies have not yet approved 
these documents--even though they were due by September 1, 2006. Delays 
in finalizing these documents could hinder plans to complete contract 
negotiations by July 2007 and could keep the program from moving 
forward in fiscal year 2008 with a new program baseline. 

The program office has also made progress in establishing an effective 
management structure by adopting a new organizational framework with 
increased oversight from program executives and by instituting more 
frequent and rigorous program management reviews; however, planned 
changes in executive management will likely increase program risk. 
Additionally, the program lacks a process and plan for identifying and 
filling staffing shortages, which has led to delays in key activities 
such as cost estimating and contract revisions. As of June 2007, key 
positions remain to be filled. 

Development and testing of major program segments--including key 
sensors and the ground systems--are under way, but significant risks 
remain. For example, work continues on key sensors, but two sensors-- 
the visible/infrared imager radiometer suite and the cross-track 
infrared sounder--have continued to experience significant 
difficulties. Additionally, while significant progress has been made in 
reducing delays in the NPOESS data processing system, much work remains 
in refining the algorithms needed to translate sensor observations into 
usable weather products. Continued sensor problems could cause further 
cost increases or schedule delays. Given the tight time frames for 
completing key sensors, integrating them with the demonstration 
spacecraft (called the NPOESS Preparatory Project or NPP), and 
developing, testing, and deploying the ground-based data processing 
systems, it will be important for the Integrated Program Office, the 
Program Executive Office, and the Executive Committee to continue to 
provide close oversight of milestones and risks. 

In our report, we made recommendations to the Secretaries of Commerce 
and Defense and to the Administrator of NASA to ensure that the 
appropriate executives finalize key acquisition documents in order to 
allow the restructuring of the program to proceed. We made 
recommendations to the Secretary of Defense to direct the Air Force to 
delay reassigning the recently appointed Program Executive Officer 
until key program risks are resolved. We also made recommendations to 
the Secretary of Commerce to ensure that NPOESS program authorities 
develop and implement a written process for identifying and addressing 
human capital needs and that they establish a plan to immediately fill 
needed positions. In written comments, all three agencies agreed that 
it was important to finalize key acquisition documents in a timely 
manner, and DOD proposed extending the due dates for the documents to 
July 2, 2007. In addition, the Department of Commerce concurred with 
our recommendation to identify and address human capital needs and 
immediately fill open positions in the NPOESS program office. Commerce 
noted that NOAA was taking actions in both areas. 

However, DOD did not concur with our recommendation to delay 
reassigning the Program Executive Officer, noting that the Program 
Director responsible for the acquisition program would remain in place 
for 4 years. While it is important that the System Program Director 
remain in place to ensure continuity in executing the acquisition, this 
position does not ensure continuity in the important oversight and 
coordination functions provided by the current Program Executive 
Officer. We remain concerned that reassigning the Program Executive at 
a time when NPOESS is still facing critical cost, schedule, and 
technical challenges will place the program at further risk. 

Background: 

Since the 1960s, the United States has operated two separate 
operational polar-orbiting meteorological satellite systems: the Polar-
orbiting Operational Environmental Satellite (POES) series-- managed by 
NOAA--and the Defense Meteorological Satellite Program (DMSP)--managed 
by the Air Force. These satellites obtain environmental data that are 
processed to provide graphical weather images and specialized weather 
products. These satellite data are also the predominant input to 
numerical weather prediction models, which are a primary tool for 
forecasting weather 3 or more days in advance-- including forecasting 
the path and intensity of hurricanes. The weather products and models 
are used to predict the potential impact of severe weather so that 
communities and emergency managers can help prevent and mitigate their 
effects. Polar satellites also provide data used to monitor 
environmental phenomena, such as ozone depletion and drought 
conditions, as well as data sets that are used by researchers for a 
variety of studies such as climate monitoring. 

NPOESS Overview: 

With the expectation that combining the POES and DMSP programs would 
reduce duplication and result in sizable cost savings, a May 1994 
Presidential Decision Directive required NOAA and DOD to converge the 
two satellite programs into a single satellite program capable of 
satisfying both civilian and military requirements.[Footnote 2] The 
converged program, NPOESS, is considered critical to the United States' 
ability to maintain the continuity of data required for weather 
forecasting and global climate monitoring through the year 2026. To 
manage this program, DOD, NOAA, and NASA formed a tri-agency Integrated 
Program Office, located within NOAA. 

Within the program office, each agency has the lead on certain 
activities: NOAA has overall program management responsibility for the 
converged system and for satellite operations; DOD has the lead on the 
acquisition; and NASA has primary responsibility for facilitating the 
development and incorporation of new technologies into the converged 
system. NOAA and DOD share the costs of funding NPOESS, while NASA 
funds specific technology projects and studies. The NPOESS program 
office is overseen by an Executive Committee, which is made up of the 
Administrators of NOAA and NASA and the Under Secretary of the Air 
Force. 

NPOESS is a major system acquisition that was originally estimated to 
cost about $6.5 billion over the 24-year life of the program from its 
inception in 1995 through 2018. The program is to provide satellite 
development, satellite launch and operation, and ground-based satellite 
data processing. These deliverables are grouped into four main 
categories: (1) the space segment, which includes the satellites and 
sensors; (2) the integrated data processing segment, which is the 
system for transforming raw data into environmental data records (EDR) 
and is to be located at four data processing centers; (3) the command, 
control, and communications segment, which includes the equipment and 
services needed to support satellite operations; and (4) the launch 
segment, which includes launch vehicle services. 

When the NPOESS engineering, manufacturing, and development contract 
was awarded in August 2002, the cost estimate was adjusted to $7 
billion. Acquisition plans called for the procurement and launch of six 
satellites over the life of the program, as well as the integration of 
13 instruments--consisting of 10 environmental sensors and 3 
subsystems. Together, the sensors were to receive and transmit data on 
atmospheric, cloud cover, environmental, climatic, oceanographic, and 
solar-geophysical observations. The subsystems were to support 
nonenvironmental search and rescue efforts, sensor survivability, and 
environmental data collection activities. The program office considered 
4 of the sensors to be critical because they provide data for key 
weather products; these sensors are in bold in table 1, which describes 
each of the expected NPOESS instruments. 

Table 1: Expected NPOESS Instruments as of August 31, 2004 (critical 
sensors are in bold): 

Instrument: Advanced technology microwave sounder (ATMS); 
Description: Measures microwave energy released and scattered by the 
atmosphere and is to be used with infrared sounding data from NPOESS's 
cross-track infrared sounder to produce daily global atmospheric 
temperature, humidity, and pressure profiles. 

Instrument: Aerosol polarimetry sensor; 
Description: Retrieves specific measurements of clouds and aerosols 
(liquid droplets or solid particles suspended in the atmosphere, such 
as sea spray, smog, and smoke). 

Instrument: Conical-scanned microwave imager/sounder (CMIS); 
Description: Collects microwave images and data needed to measure rain 
rate, ocean surface wind speed and direction, amount of water in the 
clouds, and soil moisture, as well as temperature and humidity at 
different atmospheric levels. 

Instrument: Cross-track infrared sounder (CrIS); 
Description: Collects measurements of the Earth's radiation to 
determine the vertical distribution of temperature, moisture, and 
pressure in the atmosphere. 

Instrument: Data collection system; 
Description: Collects environmental data from platforms around the 
world and delivers them to users worldwide. 

Instrument: Earth radiation budget sensor; 
Description: Measures solar short-wave radiation and long-wave 
radiation released by the Earth back into space on a worldwide scale to 
enhance long-term climate studies. 

Instrument: Ozone mapper/profiler suite (OMPS); 
Description: Collects data needed to measure the amount and 
distribution of ozone in the Earth's atmosphere. 

Instrument: Radar altimeter; 
Description: Measures variances in sea surface height/topography and 
ocean surface roughness, which are used to determine sea surface 
height, significant wave height, and ocean surface wind speed and to 
provide critical inputs to ocean forecasting and climate prediction 
models. 

Instrument: Search and rescue satellite aided tracking system; 
Description: Detects and locates aviators, mariners, and land-based 
users in distress. 

Instrument: Space environmental sensor suite; Description: Collects 
data to identify, reduce, and predict the effects of space weather on 
technological systems, including satellites and radio links. 

Instrument: Survivability sensor; 
Description: Monitors for attacks on the satellite and notifies other 
instruments in case of an attack. 

Instrument: Total solar irradiance sensor; 
Description: Monitors and captures total and spectral solar irradiance 
data. 

Instrument: Visible/infrared imager radiometer suite (VIIRS); 
Description: Collects images and radiometric data used to provide 
information on the Earth's clouds, atmosphere, ocean, and land 
surfaces. 

Source: GAO, based on NPOESS program office data. 

[End of table] 

In addition, a demonstration satellite (called the NPOESS Preparatory 
Project or NPP) was planned to be launched several years before the 
first NPOESS satellite in order to reduce the risk associated with 
launching new sensor technologies and to ensure continuity of climate 
data with NASA's Earth Observing System satellites. NPP is to host 
three of the four critical NPOESS sensors (VIIRS, CrIS, and ATMS), as 
well as one other noncritical sensor (OMPS). NPP is to provide the 
program office and the processing centers an early opportunity to work 
with the sensors, ground control, and data processing systems. 

When the NPOESS development contract was awarded, the schedule for 
launching the satellites was driven by a requirement that the 
satellites be available to back up the final POES and DMSP satellites 
should anything go wrong during the planned launches of these 
satellites. Early program milestones included (1) launching NPP by May 
2006, (2) having the first NPOESS satellite available to back up the 
final POES satellite launch in March 2008, and (3) having the second 
NPOESS satellite available to back up the final DMSP satellite launch 
in October 2009. If the NPOESS satellites were not needed to back up 
the final predecessor satellites, their anticipated launch dates would 
have been April 2009 and June 2011, respectively. 

NPOESS Experienced Cost Increases, Schedule Delays, and Technical 
Problems over Several Years: 

Over the last few years, NPOESS has experienced continued cost 
increases and schedule delays, requiring difficult decisions to be made 
about the program's direction and capabilities. In 2003, we reported 
that changes in the NPOESS funding stream led the program to develop a 
new program cost and schedule baseline.[Footnote 3] After this new 
baseline was completed in 2004, we reported that the program office 
increased the NPOESS cost estimate from about $7 billion to $8.1 
billion; delayed key milestones, including the planned launch of the 
first NPOESS satellite--which was delayed by 7 months; and extended the 
life of the program from 2018 to 2020.[Footnote 4] At that time, we 
also noted that other factors could further affect the revised cost and 
schedule estimates. Specifically, the contractor was not meeting 
expected cost and schedule targets on the new baseline because of 
technical issues in the development of key sensors, including the 
critical VIIRS sensor. Based on its performance through May 2004, we 
estimated that the contractor would most likely overrun its contract at 
completion in September 2011 by $500 million--thereby increasing the 
projected life cycle cost to $8.6 billion. The program office's 
baseline cost estimate was subsequently adjusted to $8.4 billion. 

In mid-November 2005, we reported that NPOESS continued to experience 
problems in the development of a key sensor, resulting in schedule 
delays and anticipated cost increases.[Footnote 5] At that time, we 
projected that the program's cost estimate had grown to about $10 
billion based on contractor cost and schedule data. We reported that 
the program's issues were due, in part, to problems at multiple levels 
of management--including subcontractor, contractor, program office, and 
executive leadership. Recognizing that the budget for the program was 
no longer executable, the NPOESS Executive Committee planned to make a 
decision in December 2005 on the future direction of the program--what 
would be delivered, at what cost, and by when. This involved deciding 
among options involving increased costs, delayed schedules, and reduced 
functionality. We noted that continued oversight, strong leadership, 
and timely decision making were more critical than ever, and we urged 
the committee to make a decision quickly so that the program could 
proceed. 

However, we subsequently reported that, in late November 2005, NPOESS 
cost growth exceeded a legislatively mandated threshold that requires 
DOD to certify the program to Congress.[Footnote 6] This placed any 
decision about the future direction of the program on hold until the 
certification took place in June 2006. In the meantime, the program 
office implemented an interim program plan for fiscal year 2006 to 
continue work on key sensors and other program elements using fiscal 
year 2006 funding. 

Nunn-McCurdy Process Led to a Decision to Restructure the NPOESS 
Program: 

The Nunn-McCurdy law requires DOD to take specific actions when a major 
defense acquisition program exceeds certain cost increase 
thresholds.[Footnote 7] The law requires the Secretary of Defense to 
notify Congress when a major defense acquisition is expected to overrun 
its project baseline by 15 percent or more and to certify the program 
to Congress when it is expected to overrun its baseline by 25 percent 
or more.[Footnote 8] In late November 2005, NPOESS exceeded the 25 
percent threshold, and DOD was required to certify the program. 
Certifying a program entailed providing a determination that (1) the 
program is essential to national security, (2) there are no 
alternatives to the program that will provide equal or greater military 
capability at less cost, (3) the new estimates of the program's cost 
are reasonable, and (4) the management structure for the program is 
adequate to manage and control costs. DOD established tri-agency teams-
-made up of DOD, NOAA, and NASA experts--to work on each of the four 
elements of the certification process. 

In June 2006, DOD (with the agreement of both of its partner agencies) 
certified a restructured NPOESS program, estimated to cost $12.5 
billion through 2026.[Footnote 9] This decision approved a cost 
increase of $4 billion over the prior approved baseline cost and 
delayed the launch of NPP and the first two satellites by roughly 3 to 
5 years. The new program also entailed establishing a stronger program 
management structure, reducing the number of satellites to be produced 
and launched from 6 to 4, and reducing the number of instruments on the 
satellites from 13 to 9--consisting of 7 environmental sensors and 2 
subsystems. It also entailed using NPOESS satellites in the early 
morning and afternoon orbits and relying on European satellites for 
midmorning orbit data.[Footnote 10] Table 2 summarizes the major 
program changes made under the Nunn-McCurdy certification decision. 

Table 2: Summary of Changes to the NPOESS Program: 

Key area: Life cycle range; 
Program before the Nunn-McCurdy decision: 1995-2020; 
Program after the Nunn-McCurdy decision: 1995-2026. 

Key area: Estimated life cycle cost; 
Program before the Nunn-McCurdy decision: $8.4 billion; 
Program after the Nunn-McCurdy decision: $12.5 billion. 

Key area: Launch schedule; 
Program before the Nunn-McCurdy decision: NPP by October 2006; First 
NPOESS by November 2009; Second NPOESS by June 2011; 
Program after the Nunn-McCurdy decision: NPP by January 2010; First 
NPOESS by January 2013; Second NPOESS by January 2016. 

Key area: Management structure; 
Program before the Nunn-McCurdy decision: System Program Director 
reports to a tri-agency steering committee and the tri-agency Executive 
Committee; Independent program reviews noted insufficient system 
engineering and cost analysis staff; 
Program after the Nunn-McCurdy decision: System Program Director is 
responsible for day-to-day program management and reports to the 
Program Executive Officer; Program Executive Officer oversees program 
and reports to the tri-agency Executive Committee. 

Key area: Number of satellites; 
Program before the Nunn-McCurdy decision: 6 (in addition to NPP); 
Program after the Nunn-McCurdy decision: 4 (in addition to NPP). 

Key area: Number of orbits; 
Program before the Nunn-McCurdy decision: 3 (early morning, midmorning, 
and afternoon); 
Program after the Nunn- McCurdy decision: 2 (early morning and 
afternoon; will rely on European satellites for midmorning orbit data). 

Key area: Number and complement of instruments; 
Program before the Nunn-McCurdy decision: 13 instruments (10 sensors 
and 3 subsystems); 
Program after the Nunn-McCurdy decision: 9 instruments (7 sensors and 2 
subsystems); 4 of the sensors are to provide fewer capabilities. 

Key area: Number of EDRs; 
Program before the Nunn-McCurdy decision: 55; 
Program after the Nunn-McCurdy decision: 39 (6 are to be degraded 
products). 

Source: GAO analysis of NPOESS Integrated Program Office data. 

[End of table] 

The Nunn-McCurdy certification decision established new milestones for 
the delivery of key program elements, including launching NPP by 
January 2010,[Footnote 11] launching the first NPOESS satellite (called 
C1) by January 2013, and launching the second NPOESS satellite (called 
C2) by January 2016. These revised milestones deviated from prior plans 
to have the first NPOESS satellite available to back up the final POES 
satellite should anything go wrong during that launch. 

Delaying the launch of the first NPOESS satellite means that if the 
final POES satellite fails on launch, satellite data users would need 
to rely on the existing constellation of environmental satellites until 
NPP data become available--almost 2 years later. Although NPP was not 
intended to be an operational asset, NASA agreed to move NPP to a 
different orbit so that its data would be available in the event of a 
premature failure of the final POES satellite. However, NPP will not 
provide all of the operational capability planned for the NPOESS 
spacecraft. If the health of the existing constellation of satellites 
diminishes--or if NPP data are not available, timely, and reliable-- 
then there could be a gap in environmental satellite data. Table 3 
summarizes changes in key program milestones over time. 

Table 3: Key Program Milestones: 

Milestones: Final POES launch[A]; 
As of the August 2002 contract award: March 2008; 
As of the February 2004 rebaselined program: March 2008; 
As of the June 2006 certification decision: February 2009; 
Change from 2004 rebaselined program: Not applicable. 

Milestones: NPP launch; 
As of the August 2002 contract award: May 2006; 
As of the February 2004 rebaselined program: October 2006; 
As of the June 2006 certification decision: January 2010[B]; 
Change from 2004 rebaselined program: 44-month delay. 

Milestones: First NPOESS satellite planned for launch (C1); 
As of the August 2002 contract award: April 2009; 
As of the February 2004 rebaselined program: November 2009; 
As of the June 2006 certification decision: January 2013; 
Change from 2004 rebaselined program: 38-month delay. 

Milestones: Final DMSP launch[A]; 
As of the August 2002 contract award: October 2009; 
As of the February 2004 rebaselined program: May 2010; 
As of the June 2006 certification decision: April 2012; 
Change from 2004 rebaselined program: Not applicable. 

Milestones: Second NPOESS satellite planned for launch (C2); 
As of the August 2002 contract award: June 2011; 
As of the February 2004 rebaselined program: June 2011; 
As of the June 2006 certification decision: January 2016; 
Change from 2004 rebaselined program: 55-month delay. 

Source: GAO analysis, based on NPOESS Integrated Program Office data. 

[A] POES and DMSP are not part of the NPOESS program. Their launch 
dates are provided to indicate the increased risk of satellite data 
gaps between when these systems launch and when the NPOESS satellites 
launch. 

[B] Although the certification decision specified that NPP is to launch 
by January 2010, NASA plans to launch it by September 2009 to reduce 
the possibility of a gap in climate data continuity. 

[End of table] 

In order to reduce program complexity, the Nunn-McCurdy certification 
decision decreased the number of NPOESS sensors from 13 to 9 and 
reduced the functionality of 4 sensors. Specifically, of the 13 
original sensors, 5 sensors remain unchanged, 3 were replaced with less 
capable sensors, 1 was modified to provide less functionality, and 4 
were cancelled. Table 4 shows the changes to NPOESS sensors, including 
the 4 identified in bold as critical sensors. 

Table 4: Changes to NPOESS Instruments (critical sensors are in bold): 

Instrument: ATMS; 
Status of instrument after the Nunn-McCurdy decision: Unchanged; 
Change description: Sensor is to be included on NPP and on the first 
and third NPOESS satellites. 

Instrument: Aerosol polarimetry sensor; 
Status of instrument after the Nunn-McCurdy decision: Cancelled; 
Change description: Sensor was cancelled, but could be reintegrated on 
future NPOESS satellites should another party choose to fund it.[A]. 

Instrument: CMIS; 
Status of instrument after the Nunn-McCurdy decision: Replaced; 
Change description: CMIS sensor was cancelled, and the program office 
is to procure a less complex Microwave imager/sounder for inclusion on 
the second, third, and fourth NPOESS satellites. 

Instrument: CrIS; 
Status of instrument after the Nunn-McCurdy decision: Unchanged; 
Change description: Sensor is to be included on NPP and on the first 
and third NPOESS satellites. 

Instrument: Data collection system; 
Status of instrument after the Nunn-McCurdy decision: Unchanged; 
Change description: Subsystem is to be included on all four NPOESS 
satellites. 

Instrument: Earth radiation budget sensor; 
Status of instrument after the Nunn-McCurdy decision: Replaced; 
Change description: Sensor was cancelled, and is to be replaced on the 
first NPOESS satellite (and no others) by an existing sensor with fewer 
capabilities called the Clouds and the Earth's Radiant Energy System. 

Instrument: OMPS; 
Status of instrument after the Nunn-McCurdy decision: Modified; 
Change description: One part of the sensor, called OMPS (nadir), is to 
be included on NPP and on the first and third NPOESS satellites; the 
remaining part, called OMPS (limb), was cancelled on the NPOESS 
satellites, but will be included on NPP.[A]. 

Instrument: Radar altimeter; 
Status of instrument after the Nunn- McCurdy decision: Cancelled; 
Change description: Sensor was cancelled, but could be reintegrated on 
future NPOESS satellites should another party choose to fund it. 

Instrument: Search and rescue satellite aided tracking system; 
Status of instrument after the Nunn-McCurdy decision: Unchanged; 
Change description: Subsystem is to be included on all four NPOESS 
satellites. 

Instrument: Space environmental sensor suite; 
Status of instrument after the Nunn-McCurdy decision: Replaced; 
Change description: Sensor is to be replaced by a less capable, less 
expensive, legacy sensor called the Space Environment Monitor on the 
first and third NPOESS satellites. 

Instrument: Survivability sensor; 
Status of instrument after the Nunn- McCurdy decision: Cancelled; 
Change description: Subsystem contract was cancelled, but could be 
reintegrated on future NPOESS satellites should another party choose to 
fund it. 

Instrument: Total solar irradiance sensor; 
Status of instrument after the Nunn-McCurdy decision: Cancelled; 
Change description: Sensor contract was cancelled, but could be 
reintegrated on future NPOESS satellites should another party choose to 
fund it. 

Instrument: VIIRS; 
Status of instrument after the Nunn-McCurdy decision: Unchanged; 
Change description: Sensor is to be included on NPP and on all four 
NPOESS satellites. 

Source: GAO analysis of NPOESS Integrated Program Office data. 

[A] Although direct program funding for these instruments was 
eliminated, the instruments could be reintegrated on NPOESS satellites 
should other parties choose to fund them. The Nunn-McCurdy decision 
requires the program office to allow sufficient space on the spacecraft 
for these instruments and to provide the funding needed to integrate 
them. 

[End of table] 

The changes in NPOESS sensors affected the number and quality of the 
resulting weather and environmental products, called environmental data 
records or EDRs. In selecting sensors for the restructured program, the 
agencies placed the highest priority on continuing current operational 
weather capabilities and a lower priority on obtaining selected 
environmental and climate measuring capabilities. As a result, the 
revised NPOESS system has significantly less capability for providing 
global climate measures than was originally planned. Specifically, the 
number of EDRs was decreased from 55 to 39, of which 6 are of a reduced 
quality. The 39 EDRs that remain include cloud base height, land 
surface temperature, precipitation type and rate, and sea surface 
winds. The 16 EDRs that were removed include cloud particle size and 
distribution, sea surface height, net solar radiation at the top of the 
atmosphere, and products to depict the electric fields in the space 
environment. The 6 EDRs that are of a reduced quality include ozone 
profile, soil moisture, and multiple products depicting energy in the 
space environment. 

NPOESS Acquisition Restructuring Is Well Under Way, but Key Steps 
Remain to Be Completed: 

Since the June 2006 decision to revise the scope, cost, and schedule of 
the NPOESS program, the program office has made progress in 
restructuring the satellite acquisition; however, important tasks 
remain to be done. Restructuring a major acquisition program like 
NPOESS is a process that involves identifying time-critical and high- 
priority work and keeping this work moving forward, while reassessing 
development priorities, interdependencies, deliverables, risks, and 
costs. It also involves revising important acquisition documents 
including the memorandum of agreement on the roles and responsibilities 
of the three agencies, the acquisition strategy, the system engineering 
plan, the test and evaluation master plan, the integrated master 
schedule defining what needs to happen by when, and the acquisition 
program baseline. Specifically, the Nunn-McCurdy certification decision 
required the Secretaries of Defense and Commerce and the Administrator 
of NASA to sign a revised memorandum of agreement by August 6, 2006. It 
also required that the program office, Program Executive Officer, and 
the Executive Committee revise and approve key acquisition documents 
including the acquisition strategy and system engineering plan by 
September 1, 2006, in order to proceed with the restructuring. Once 
these are completed, the program office can proceed to negotiate with 
its prime contractor on a new program baseline defining what will be 
delivered, by when, and at what cost. 

The NPOESS program office has made progress in restructuring the 
acquisition. Specifically, the program office has established interim 
program plans guiding the contractor's work activities in 2006 and 2007 
and has made progress in implementing these plans. The program office 
and contractor also developed an integrated master schedule for the 
remainder of the program--beyond fiscal year 2007. This integrated 
master schedule details the steps leading up to launching NPP by 
September 2009, launching the first NPOESS satellite in January 2013, 
and launching the second NPOESS satellite in January 2016. Near-term 
steps include completing and testing the VIIRS, CrIS, and OMPS sensors; 
integrating these sensors with the NPP spacecraft and completing 
integration testing; completing the data processing system and 
integrating it with the command, control, and communications segment; 
and performing advanced acceptance testing of the overall system of 
systems for NPP. 

However, key steps remain for the acquisition restructuring to be 
completed. Although the program office made progress in revising key 
acquisition documents, including the system engineering plan, the test 
and evaluation master plan, and the acquisition strategy plan, it has 
not yet obtained the approval of the Secretaries of Commerce and 
Defense and the Administrator of NASA on the memorandum of agreement 
among the three agencies, nor has it obtained the approval of the 
NPOESS Executive Committee on the other key acquisition documents. As 
of June 2007, these approvals are over 9 months past due. Agency 
officials noted that the September 1, 2006, due date for the key 
acquisition documents was not realistic given the complexity of 
coordinating documents among three different agencies. 

Finalizing these documents is critical to ensuring interagency 
agreement and will allow the program office to move forward in 
completing other activities related to restructuring the program. These 
other activities include completing an integrated baseline review with 
the contractor to reach agreement on the schedule and work activities, 
and finalizing changes to the NPOESS development and production 
contract. Program costs are also likely to be adjusted during upcoming 
negotiations on contract changes--an event that the Program Director 
expects to occur by July 2007. Completion of these activities will 
allow the program office to lock down a new acquisition baseline cost 
and schedule. Until key acquisition documents are finalized and 
approved, the program faces increased risk that it will not be able to 
complete important restructuring activities in time to move forward in 
fiscal year 2008 with a new program baseline in place. This places the 
NPOESS program at risk of continued delays and future cost increases. 

Progress Has Been Made in Establishing an Effective NPOESS Management 
Structure, but Executive Turnover Increases Risks and Staffing Problems 
Remain: 

The NPOESS program has made progress in establishing an effective 
management structure, but--almost a year after this structure was 
endorsed during the Nunn-McCurdy certification process--the Integrated 
Program Office still faces staffing problems. Over the past few years, 
we and others have raised concerns about management problems at all 
levels of the NPOESS program, including subcontractor and contractor 
management, program office management, and executive-level 
management.[Footnote 12] Two independent review teams also noted a 
shortage of skilled program staff, including budget analysts and system 
engineers. Since that time, the NPOESS program has made progress in 
establishing an effective management structure--including establishing 
a new organizational framework with increased oversight by program 
executives, instituting more frequent subcontractor, contractor, and 
program reviews, and effectively managing risks and performance. 
However, DOD's plans for reassigning the Program Executive Officer in 
the summer of 2007 increase the program's risks. Additionally, the 
program lacks a staffing process that clearly identifies staffing 
needs, gaps, and plans for filling those gaps. As a result, the program 
office has experienced delays in getting core management activities 
under way and lacks the staff it needs to execute day-to-day management 
activities. 

NPOESS Program Has Made Progress in Establishing an Effective 
Management Structure and Increasing Oversight Activities, but Executive 
Turnover Will Increase Program Risks: 

The NPOESS program has made progress in establishing an effective 
management structure and increasing the frequency and intensity of its 
oversight activities. Over the past few years, we and others have 
raised concerns about management problems at all levels of management 
on the NPOESS program, including subcontractor and contractor 
management, program office management, and executive-level management. 
In response to recommendations made by two different independent review 
teams, the program office began exploring options in late 2005 and 
early 2006 for revising its management structure. 

In November 2005, the Executive Committee established and filled a 
Program Executive Officer position, senior to the NPOESS Program 
Director, to streamline decision making and to provide oversight to the 
program. This Program Executive Officer reports directly to the 
Executive Committee. Subsequently, the Program Executive Officer and 
the Program Director proposed a revised organizational framework that 
realigned division managers within the Integrated Program Office 
responsible for overseeing key elements of the acquisition and 
increased staffing in key areas. In June 2006, the Nunn-McCurdy 
certification decision approved this new management structure and the 
Integrated Program Office implemented it. Figure 1 provides an overview 
of the relationships among the Integrated Program Office, the Program 
Executive Office, and the Executive Committee, as well as key divisions 
within the program office. 

Figure 1: Overview of New NPOESS Management Structure: 

[See PDF for image] 

Source: NOAA. 

[End of figure] 

Operating under this new management structure, the program office 
implemented more rigorous and frequent subcontractor, contractor, and 
program reviews, improved visibility into risk management and 
mitigation activities, and institutionalized the use of earned value 
management techniques to monitor contractor performance. In addition to 
these program office activities, the Program Executive Officer 
implemented monthly program reviews and increased the frequency of 
contacts with the Executive Committee. The Program Executive Officer 
briefs the Executive Committee in monthly letters, apprising committee 
members of the program's status, progress, risks, and earned value, and 
the Executive Committee now meets on a quarterly basis--whereas in the 
recent past, we reported that the Executive Committee had met only five 
times in 2 years.[Footnote 13] 

Although the NPOESS program has made progress in establishing an 
effective management structure, this progress is currently at risk. We 
recently reported that DOD space acquisitions are at increased risk due 
in part to frequent turnover in leadership positions, and we suggested 
that addressing this will require DOD to consider matching officials' 
tenure with the development or delivery of a product.[Footnote 14] In 
March 2007, NPOESS program officials stated that DOD is planning to 
reassign the recently appointed Program Executive Officer in the summer 
2007 as part of this executive's natural career progression. As of June 
2007, the Program Executive Officer has held this position for 19 
months. Given that the program is currently still being restructured, 
and that there are significant challenges in being able to meet 
critical deadlines to ensure satellite data continuity, such a move 
adds unnecessary risk to an already risky program. 

NPOESS Program Has Filled Key Vacancies but Lacks a Programwide 
Staffing Process: 

The NPOESS program office has filled key vacancies but lacks a staffing 
process that identifies programwide staffing requirements and plans for 
filling those needed positions. Sound human capital management calls 
for establishing a process or plan for determining staffing 
requirements, identifying any gaps in staffing, and planning to fill 
critical staffing gaps. Program office staffing is especially important 
for NPOESS, given the acknowledgment by multiple independent review 
teams that staffing shortfalls contributed to past problems. 
Specifically, these review teams noted shortages in the number of 
system engineers needed to provide adequate oversight of subcontractor 
and contractor engineering activities and in the number of budget and 
cost analysts needed to assess contractor cost and earned value 
reports. To rectify this situation, the June 2006 certification 
decision directed the Program Director to take immediate actions to 
fill vacant positions at the program office with the approval of the 
Program Executive Officer. 

Since the June 2006 decision to revise NPOESS management structure, the 
program office has filled multiple critical positions, including a 
budget officer, a chief system engineer, an algorithm division chief, 
and a contracts director. In addition, on an ad hoc basis, individual 
division managers have assessed their needs and initiated plans to hire 
staff for key positions. However, the program office lacks a 
programwide process for identifying and filling all needed positions. 
As a result, division managers often wait months for critical positions 
to be filled. For example, in February 2006, the NPOESS program 
estimated that it needed to hire up to 10 new budget analysts. As of 
September 2006, none of these positions had been filled. As of April 
2007, program officials estimated that they still needed to fill 5 
budget analyst positions, 5 systems engineering positions, and 10 
technical manager positions. The majority of the vacancies--4 of the 5 
budget positions, 4 of the 5 systems engineering positions, and 8 of 
the 10 technical manager positions--are to be provided by NOAA. NOAA 
officials noted that each of these positions is in some stage of being 
filled--that is, recruitment packages are being developed or reviewed, 
vacancies are being advertised, or candidates are being interviewed, 
selected, and approved. 

The program office attributes its staffing delays to not having the 
right personnel in place to facilitate this process, and it did not 
even begin to develop a staffing process until November 2006. Program 
officials noted that the tri-agency nature of the program adds unusual 
layers of complexity to the hiring and administrative functions because 
each agency has its own hiring and performance management rules. In 
November 2006, the program office brought in an administrative officer 
who took the lead in pulling together the division managers' individual 
assessments of needed staff and has been working with the division 
managers to refine this list. This new administrative officer plans to 
train division managers in how to assess their needs and to hire needed 
staff, and to develop a process by which evolving needs are identified 
and positions are filled. However, there is as yet no date set for 
establishing this basic programwide staffing process. As a result of 
the lack of a programwide staffing process, there has been an extended 
delay in determining what staff is needed and in bringing those staff 
on board; this has resulted in delays in performing core activities, 
such as establishing the program office's cost estimate and bringing in 
needed contracting expertise. Additionally, until a programwide 
staffing process is in place, the program office risks not having the 
staff it needs to execute day-to-day management activities. 

In commenting on a draft of our report, Commerce stated that NOAA 
implemented an accelerated hiring model. More recently, the NPOESS 
program office reported that several critical positions were filled in 
April and May 2007. However, we have not yet evaluated NOAA's 
accelerated hiring model and, as of June 2007, over 10 key positions 
remain to be filled. 

Major Program Segments Are Under Development, but Significant Risks 
Remain: 

Major segments of the NPOESS program--the space segment and ground 
systems segment--are under development; however, significant problems 
have occurred and risks remain. The program office is aware of these 
risks and is working to mitigate them, but continued problems could 
affect the program's overall cost and schedule. Given the tight time 
frames for completing key sensors, integrating them on the NPP 
spacecraft, and developing, testing, and deploying the ground-based 
data processing systems, it will be important for the NPOESS Integrated 
Program Office, the Program Executive Office, and the Executive 
Committee to continue to provide close oversight of milestones and 
risks. 

Space Segment--Progress Made, but Key Sensors Continue to Face Major 
Risks: 

The space segment includes the sensors and the spacecraft. Four sensors 
are of critical importance--VIIRS, CrIS, OMPS, and ATMS--because they 
are to be launched on the NPP satellite in September 2009. Initiating 
work on another sensor, the Microwave imager/sounder, is also important 
because this new sensor--replacing the cancelled CMIS sensor--will need 
to be developed in time for the second NPOESS satellite launch. Over 
the past year, the program made progress on each of the sensors and the 
spacecraft. However, two sensors, VIIRS and CrIS, have experienced 
major problems. The status of each of the components of the space 
segment is described in table 5. 

Table 5: Status of Selected Components of the Space Segment, as of 
April 2007: 

Space segment component: VIIRS; 
Risk level: High; 
Status: VIIRS development has continued in 2006 and in early 2007. In 
December 2006, the contractor completed environmental tests of VIIRS's 
engineering design unit (a prototype) and identified three problems.[A] 
While these problems were being studied, the program office approved 
the delivery of the engineering unit to the subcontractor responsible 
for integration and testing on NPP. In late February 2007, program 
officials determined that the contractor was able to mitigate all but 
one of the problems, and they approved the flight unit to proceed to 
system level integration with a goal of resolving the final problem 
before a technical readiness review milestone. VIIRS flight unit is 
scheduled to be delivered to NPP by July 2008. 

Space segment component: CrIS; 
Risk level: High; 
Status: Development of CrIS was put on hold in October 2006 when the 
flight unit designated to go on NPP experienced a major structural 
failure during its vibration testing. As of March 2007, a failure 
review board established by the contractors and the NPOESS program 
office identified causes for failure and has planned an approach to 
completing flight unit development and delivery for NPP. The review 
board has also initiated inspections of all sensor modules and 
subsystems for damage. The program office expects to restart acceptance 
testing in July 2007, and the CrIS flight unit is expected to be 
delivered to NPP by February 2008. 

Space segment component: OMPS; 
Risk level: Moderate; 
Status: As part of the Nunn-McCurdy certification in June 2006, one 
element of the OMPS sensor, called OMPS (limb), was removed from the 
program. In February 2007, program officials agreed to reintegrate OMPS 
(limb) on NPP if NOAA and NASA would fund it. This funding was approved 
in early April 2007. OMPS is currently on schedule for delivery to NPP 
by May 2008; however, there are concerns that the OMPS flight unit 
delivery will be so late in the integration testing process that there 
could be an insufficient schedule margin should a problem arise. 

Space segment component: ATMS; 
Risk level: Low; 
Status: The ATMS flight unit for NPP was developed by a NASA contractor 
and delivered to the program in October 2005. NASA integrated the 
flight unit on the spacecraft and is awaiting delivery of the other 
sensors in order to complete integration testing. 

Space segment component: Microwave imager/ sounder; 
Risk level: Not yet rated; 
Status: A new microwave imager/sounder sensor is being planned to 
replace the cancelled CMIS sensor. It is planned to be ready for the 
launch on the second NPOESS satellite. In October 2006, the program 
office issued a request for information seeking industry ideas for the 
design of the new sensor. The program office anticipates awarding a 
contract to develop the sensor by October 2008. 

Space segment component: Spacecraft; 
Risk level: Low; 
Status: The development of the spacecrafts for NPP and NPOESS are on 
track. The NPP spacecraft was completed in June 2005. Integration 
testing will be conducted once the NPP sensors are delivered; Early 
issues with the NPOESS spacecraft (including issues with antennas and a 
data storage unit) have been resolved; however, risks remain that could 
delay the completion of the spacecraft. A key risk involves delays in 
the delivery of the solar array, which may arrive too late to be 
included in some key testing. Other risks associated with the 
electrical power subsystem are taking longer than anticipated to 
resolve. 

Source: GAO analysis of NPOESS Integrated Program Office data. 

[A] The three problems are (1) band-to-band co-registration, an issue 
in which band registration shifts with different temperatures; (2) 
cross-talk, which involves information from sensor cells leaking into 
other cells; and (3) line-spread function issues, in which the 
instrument's focus changes with changes in temperature. 

[End of table] 

Program officials regularly track risks associated with various NPOESS 
components and work to mitigate them. Having identified both VIIRS and 
CrIS as high risk, OMPS as moderate risk, and the other components as 
low risk, the program office is working closely with the contractors 
and subcontractors to resolve sensor problems. Program officials have 
identified work-arounds that will allow them to move forward in testing 
the VIIRS engineering unit and have approved the flight unit to proceed 
to a technical readiness review milestone. Regarding CrIS, as of March 
2007, a failure review board identified root causes of its structural 
failure, identified plans for resolving them, and initiated inspections 
of sensor modules and subsystems for damage. An agency official 
reported that there is sufficient funding in the fiscal year 2007 
program office's and contractor's management reserve funds to allow for 
troubleshooting both VIIRS and CrIS problems. However, until the CrIS 
failure review board fully determines the amount of rework that is 
necessary to fix the problems, it is unknown if additional funds will 
be needed or if the time frame for CrIS's delivery will be delayed. 
According to agency officials, CrIS is not on the program schedule's 
critical path, and there is sufficient schedule margin to absorb the 
time it will take to conduct a thorough failure review process. 

Managing the risks associated with the development of VIIRS and CrIS is 
of particular importance because these components are to be 
demonstrated on the NPP satellite, currently scheduled for launch in 
September 2009. Any delay in the NPP launch date could affect the 
overall NPOESS program, because the success of the program depends on 
the lessons learned in data processing and system integration from the 
NPP satellite. Additionally, continued sensor problems could lead to 
higher final program costs. 

Ground Segment--Progress Has Been Made, but Work Remains: 

Development of the ground segment--which includes the interface data 
processing system, the ground stations that are to receive satellite 
data, and the ground-based command, control, and communications system-
-is under way and on track. However, important work pertaining to 
developing the algorithms that translate satellite data into weather 
products within the integrated data processing segment remains to be 
completed. Table 6 describes each of the components of the ground 
segment and identifies the status of each. 

Table 6: Status of Ground Segment Components: 

Ground segment component/description: Interface Data Processing System 
(IDPS): A ground-based system that is to process the sensors' data so 
that they are usable by the data processing centers and the broader 
community of environmental data users. IDPS will be deployed at the 
four weather data processing centers; 
Risk level: Moderate; 
Status: IDPS is being developed in a series of builds. Currently, IDPS 
build 1.4 has been delivered for testing and recently passed two key 
data transfer tests. Contractors are currently working to develop IDPS 
build 1.5, which is expected to be the build that will be used with 
NPP. However, work remains in three areas: system latency, algorithm 
performance, and calibration and validation planning; Latency--IDPS 
must process volumes of data within 65 minutes to meet NPP 
requirements. The contractor has made progress in reducing the latency 
of the system's data handling from 93 minutes to 73 minutes and is 
working to reduce it by 8 minutes more by resolving data management 
issues, increasing the number of processors, and increasing algorithm 
efficiency; Algorithm performance--IDPS algorithms are the mathematical 
functions coded into the system software that transform raw data into 
data products, including sensor data records and environmental data 
records. IDPS build 1.4 contains provisional algorithms, which are 
being refined as the sensors complete various stages of testing. 
Because some sensors are delayed, full characterization of those 
sensors in order to refine the algorithms has also been delayed and may 
not be completed in time for the delivery of IDPS build 1.5 in early 
2009. If this occurs, agency officials plan to improve the algorithms 
in build 1.5 during a planned maintenance upgrade prior to NPP launch; 
Calibration/validation--Calibration/ validation is the process for 
tweaking algorithms to provide more accurate observations. The 
contractor has documented a detailed schedule for calibration and 
validation during IDPS development and is developing a postlaunch task 
list to drive prelaunch preparation efforts. However, much work and 
uncertainty continue to exist in the calibration and validation area. A 
program official noted that, while teams can do a lot of preparation 
work, including building the infrastructure to allow sensor testing and 
having a good understanding of the satellite, sensors, and available 
data for calibration, many issues need to take place after launch. 

Ground segment component/description: Ground stations for receiving 
satellite data: 15 unmanned ground stations around the world (called 
SafetyNet™) are to receive satellite data and send these to the four 
data processing centers; 
Risk level: Low; 
Status: NOAA is working with domestic and foreign authorities to gain 
approval to operate ground stations to receive satellite data. 
According to agency officials, the full complement of ground stations 
will not be in place in time for the C1 launch: however, the ground 
stations will be phased in by the launch of C2. To date, the program 
office has reached agreement with 4 of 15 ground station sites. 

Source: GAO analysis of NPOESS Integrated Program Office data. 

[End of table] 

The NPOESS program office plans to continue to address risks facing 
IDPS development. Specifically, the IDPS team is working to reduce data 
processing delays by seeking to limit the number of data calls, improve 
the efficiency of the data management system, increase the efficiency 
of the algorithms, and increase the number of processors. The program 
office also developed a resource center consisting of a logical 
technical library, a data archive, and a set of analytical tools to 
coordinate, communicate, and facilitate the work of algorithm subject 
matter experts on algorithm development and calibration/validation 
preparations. Managing the risks associated with the development of the 
IDPS system is of particular importance because this system will be 
needed to process NPP data. 

Implementation of GAO Recommendations Should Reduce Program Risks: 

Because of the importance of effectively managing the NPOESS program to 
ensure that there are no gaps in the continuity of critical weather and 
environmental observations, in our accompanying report[Footnote 15] we 
made recommendations to the Secretaries of Defense and Commerce and to 
the Administrator of NASA to ensure that the responsible executives 
within their respective organizations approve key acquisition 
documents, including the memorandum of agreement among the three 
agencies, the system engineering plan, the test and evaluation master 
plan, and the acquisition strategy, as quickly as possible but no later 
than April 30, 2007. We also recommended that the Secretary of Defense 
direct the Air Force to delay reassigning the recently appointed 
Program Executive Officer until all sensors have been delivered to the 
NPOESS Preparatory Program; these deliveries are currently scheduled to 
occur by July 2008. We also made two additional recommendations to the 
Secretary of Commerce to (1) develop and implement a written process 
for identifying and addressing human capital needs and for streamlining 
how the program handles the three different agencies' administrative 
procedures and (2) establish a plan for immediately filling needed 
positions. 

In written comments, all three agencies agreed that it was important to 
finalize key acquisition documents in a timely manner, and DOD proposed 
extending the due dates for the documents to July 2, 2007. Because the 
NPOESS program office intends to complete contract negotiations by July 
4, 2007, we remain concerned that any further delays in approving the 
documents could delay contract negotiations and thus increase the risk 
to the program. 

In addition, the Department of Commerce agreed with our recommendation 
to develop and implement a written process for identifying and 
addressing human capital needs and to streamline how the program 
handles the three different agencies' administrative procedures. The 
department also agreed with our recommendation to plan to immediately 
fill open positions at the NPOESS program office. Commerce noted that 
NOAA identified the skill sets needed for the program and has 
implemented an accelerated hiring model and schedule to fill all NOAA 
positions in the NPOESS program. Commerce also noted that NOAA has made 
NPOESS hiring a high priority and has documented a strategy--including 
milestones--to ensure that all NOAA positions are filled by June 2007. 

DOD did not concur with our recommendation to delay reassigning the 
Program Executive Officer, noting that the NPOESS System Program 
Director responsible for executing the acquisition program would remain 
in place for 4 years. The Department of Commerce also noted that the 
Program Executive Officer position is planned to rotate between the Air 
Force and NOAA. Commerce also stated that a selection would be made 
before the departure of the current Program Executive Officer to 
provide an overlap period to allow for knowledge transfer and ensure 
continuity. However, over the last few years, we and others (including 
an independent review team and the Commerce Inspector General) have 
reported that ineffective executive-level oversight helped foster the 
NPOESS program's cost and schedule overruns. We remain concerned that 
reassigning the Program Executive at a time when NPOESS is still facing 
critical cost, schedule, and technical challenges will place the 
program at further risk. 

In addition, while it is important that the System Program Director 
remain in place to ensure continuity in executing the acquisition, this 
position does not ensure continuity in the functions of the Program 
Executive Officer. The current Program Executive Officer is experienced 
in providing oversight of the progress, issues, and challenges facing 
NPOESS and coordinating with Executive Committee members as well as the 
Defense acquisition authorities. Additionally, while the Program 
Executive Officer position is planned to rotate between agencies, the 
memorandum of agreement documenting this arrangement is still in draft 
and should be flexible enough to allow the current Program Executive 
Officer to remain until critical risks have been addressed. 

Further, while Commerce plans to allow a period of overlap between the 
selection of a new Program Executive Officer and the departure of the 
current one, time is running out. The current Program Executive Officer 
is expected to depart in early July 2007, and as of early June 2007, a 
successor has not yet been named. NPOESS is an extremely complex 
acquisition, involving three agencies, multiple contractors, and 
advanced technologies. There is not sufficient time to transfer 
knowledge and develop the sound professional working relationships that 
the new Program Executive Officer will need to succeed in that role. 
Thus, we remain convinced that given NPOESS current challenges, 
reassigning the current Program Executive Officer at this time would 
not be appropriate. 

In summary, NPOESS restructuring is well under way, and the program has 
made progress in establishing an effective management structure. 
However, key steps remain in restructuring the acquisition, including 
completing important acquisition documents such as the system 
engineering plan, the acquisition program baseline, and the memorandum 
of agreement documenting the three agencies' roles and 
responsibilities. Until these key documents are finalized, the program 
is unable to finalize plans for restructuring the program. 
Additionally, the program office continues to have difficulty filling 
key positions and lacks a programwide staffing process. Until the 
program establishes an effective and repeatable staffing process, it 
will have difficulties in identifying and filling its staffing needs in 
a timely manner. Having insufficient staff in key positions impedes the 
program office's ability to conduct important management and oversight 
activities, including revising cost and schedule estimates, monitoring 
progress, and managing technical risks. The program faces even further 
challenges if DOD proceeds with plans to reassign the Program Executive 
Officer this summer. Such a move would add unnecessary risk to an 
already risky program. 

In addition, the likelihood exists that there will be further cost 
increases and schedule delays because of technical problems on key 
sensors and pending contract negotiations. Major program segments-- 
including the space and ground segments--are making progress in their 
development and testing. However, two critical sensors have experienced 
problems and are considered high risk, and risks remain in developing 
and implementing the ground-based data processing system. Given the 
tight time frames for completing key sensors, integrating them, and 
getting the ground-based data processing systems developed, tested, and 
deployed, continued close oversight of milestones and risks is 
essential to minimize potential cost increases and schedule delays. 

Mr. Chairmen, this concludes my statement. I would be happy to answer 
any questions that you or members of the committee may have at this 
time. 

If you have any questions on matters discussed in this testimony, 
please contact me at (202) 512-9286 or by e-mail at pownerd@gao.gov. 
Other key contributors to this testimony include Colleen Phillips 
(Assistant Director), Carol Cha, and Teresa Smith. 

FOOTNOTES 

[1] GAO, Polar-Orbiting Operational Environmental Satellites: 
Restructuring Is Under Way, but Technical Challenges and Risks Remain, 
GAO-07-498 (Washington, D.C.: Apr. 27, 2007). 

[2] Presidential Decision Directive NSTC-2 (May 5, 1994). 

[3] GAO, Polar-orbiting Environmental Satellites: Project Risks Could 
Affect Weather Data Needed by Civilian and Military Users, GAO-03-987T 
(Washington, D.C.: July 15, 2003). 

[4] GAO, Polar-orbiting Environmental Satellites: Information on 
Program Cost and Schedule Changes, GAO-04-1054 (Washington, D.C.: Sept. 
30, 2004). 

[5] GAO, Polar-orbiting Operational Environmental Satellites: Technical 
Problems, Cost Increases, and Schedule Delays Trigger Need for 
Difficult Trade-off Decisions, GAO-06-249T (Washington, D.C.: Nov. 16, 
2005). 

[6] GAO, Polar-orbiting Operational Environmental Satellites: Cost 
Increases Trigger Review and Place Program's Direction on Hold, GAO-06- 
573T (Washington, D.C.: Mar. 30, 2006). 

[7] 10 U.S.C. § 2433 is commonly referred to as Nunn-McCurdy. 

[8] 10 U.S.C. § 2433 (e)(2) has recently been amended by Pub. L. No. 
109-163, § 802 (Jan. 6, 2006) and Pub. L. No. 109-364, § 213 (a) (Oct. 
17, 2006). 

[9] DOD estimated that the acquisition portion of the certified program 
would cost $11.5 billion. The acquisition portion includes satellite 
development, production, and launch, but not operations and support 
costs after launch. When combined with an estimated $1 billion for 
operations and support after launch, this brings the program life cycle 
cost to $12.5 billion. 

[10] The European Organization for the Exploitation of Meteorological 
Satellite's MetOp program is a series of three polar-orbiting 
satellites dedicated to operational meteorology. MetOp satellites are 
planned to be launched sequentially over 14 years. 

[11] According to program officials, although the Nunn-McCurdy 
certification decision specifies that NPP is to launch by January 2010, 
NASA plans to launch it by September 2009 to reduce the possibility of 
a climate data continuity gap. 

[12] GAO-06-249T; U.S. Department of Commerce, Office of the Inspector 
General, Poor Management Oversight and Ineffective Incentives Leave 
NPOESS Program Well Over Budget and Behind Schedule, OIG-17794-6-0001/ 
2006 (Washington, D.C.: May 2006). In addition, two independent teams 
reviewed the NPOESS program in 2005: A NASA-led Independent Review Team 
investigated problems with the VIIRS sensor and the impact on NPP, and 
a DOD-led Independent Program Assessment Team assessed the broader 
NPOESS program. The teams briefed the NPOESS Executive Committee on 
their findings in August 2005 and November 2005, respectively. 

[13] GAO-06-249T. 

[14] GAO, Space Acquisitions: Improvements Needed in Space Acquisitions 
and Keys to Achieving Them, GAO-06-626T (Washington, D.C.: Apr. 6, 
2006). 

[15] GAO-07-498.

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: