This is the accessible text file for GAO report number GAO-06-622T 
entitled 'Hurricane Katrina: Planning for and Management of Federal 
Disaster Recovery Contracts' which was released on April 10, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony before the Subcommittee on Federal Financial Management, 
Government Information, and International Security, Committee on 
Homeland Security and Governmental Affairs, U.S. Senate: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 11:30 a.m. CDT: 

Monday, April 10, 2006: 

Hurricane Katrina: 

Planning for and Management of Federal Disaster Recovery Contracts: 

Statement of William T. Woods, Director: 
Acquisition and Sourcing Management: 

GAO-06-622T: 

GAO Highlights: 

Highlights of GAO-06-622T, a testimony before the Subcommittee on 
Federal Financial Management, Government Information, and International 
Security, Committee on Homeland Security and Governmental Affairs, U.S. 
Senate. 

Why GAO Did This Study: 

The devastation experienced throughout the Gulf Coast region in the 
wake of Hurricanes Katrina and Rita has called into question the 
government’s ability to effectively respond to such disasters. The 
government needs to understand what went right and what went wrong, and 
to apply these lessons to strengthen its disaster response and recovery 
operations. 

The federal government relies on partnerships across the public and 
private sectors to achieve critical results in preparing for and 
responding to natural disasters, with an increasing reliance on 
contractors to carry out specific aspects of its missions. At the same 
time, the acquisition functions at several agencies are on GAO’s high-
risk list, indicating a vulnerability to fraud, waste, and abuse. 

This testimony discusses how three agencies—the General Services 
Administration, the Federal Emergency Management Agency (FEMA), and the 
U.S. Army Corps of Engineers (the Corps)—conducted oversight of key 
contracts used in response to the hurricanes. Efforts are ongoing by 
these agencies to address issues GAO and others have identified. 

What GAO Found: 

Agency acquisition and contractor personnel have been recognized for 
their hard work in providing the goods and services required to be 
responsive. The response efforts nonetheless suffered from three 
primary deficiencies: 

First, there was inadequate planning and preparation in anticipating 
requirements for needed goods and services. Some key agencies did not 
always have adequate plans for contracting in a major contingency 
situation. For example, while contracts for some items were in place 
prior to the storm, the Federal Emergency Management Agency did not 
adequately anticipate needs for such services as providing temporary 
housing and public buildings. There were also competing tensions 
between the selection of national contractors and the Stafford Act 
requirement that there be a preference for contractors from the 
affected area. Better planning could have alleviated those tensions. 

Second, there was a lack of clearly communicated responsibilities 
across agencies and jurisdictions to ensure effective outcomes. In a 
disaster situation, sometimes local or state officials determine the 
requirements and communicate them to FEMA, which then may write and 
award the contract or communicate the requirements to another agency 
that writes and awards the contract; and then FEMA or another agency 
will oversee contract performance. To ensure effective execution of the 
contract, this approach puts a premium on clear alignment of 
responsibilities and good communications, but our fieldwork identified 
examples where unclear responsibilities and poor communications 
resulted in poor acquisition outcomes. For example, the process for 
ordering and delivering ice heavily depends on effective communications 
between FEMA and the Corps. However, according to Corps officials, FEMA 
did not fully understand the contracting approach used by the Corps and 
ordered at least double the amount of ice required, resulting in an 
oversupply of ice and a lack of distribution sites to handle the volume 
ordered. 

And third, there were insufficient numbers and inadequate deployment of 
personnel to provide for effective contractor oversight. The purpose of 
monitoring is to ensure that contracted goods and services are 
delivered in accordance with the agreed upon schedule, cost, quality, 
and quantity provisions stated in the contract. Without sufficient 
numbers of trained people properly deployed, however, monitoring will 
not be effective, agencies may not be able to quickly identify and 
correct poor contractor performance, and agencies will be at risk of 
overpaying contractors. Our work indicated that while monitoring was 
occurring on the contracts we reviewed, the number of staff available 
was not always sufficient and staff were not effectively deployed. For 
example: FEMA’s contracts for installing temporary housing in four 
states had only 17 of the 27 technical monitors that had been 
determined necessary to oversee contractor performance. 

What GAO Recommends: 

GAO is not making any recommendations 

www.gao.gov/cgi-bin/getrpt?GAO-06-622T. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact William T. Woods at (202) 
512-4841 or woodsw@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

Thank you for inviting me here today to discuss the management and 
oversight of federal disaster recovery contracts related to Hurricanes 
Katrina and Rita. The size and strength of Hurricane Katrina resulted 
in one of the largest natural disasters in our nation's history, and in 
its aftermath major questions have been raised about our nation's 
readiness and ability to respond to catastrophic disasters. Hurricane 
Rita increased demands on an already stressed response and recovery 
effort by all levels of government. 

GAO has a large body of ongoing work on a range of issues relating to 
all phases of the preparation, response, recovery, and rebuilding 
efforts related to Hurricanes Katrina and Rita. GAO's work has been 
coordinated with the rest of the accountability community at the 
federal, state, and local levels to ensure that all significant issues 
associated with relief and recovery, including contracting, are 
addressed while avoiding unnecessary duplication of efforts. 

Comptroller General Walker recently testified on GAO's preliminary 
observations on the challenges encountered in the response to Hurricane 
Katrina, and he identified four themes that are similar to lessons 
learned from past catastrophic disasters.[Footnote 1] These include the 
central importance of (1) clearly defining and communicating leadership 
roles, responsibilities, and lines of authority for response in advance 
of a catastrophic disaster; (2) clarifying the procedures for 
activating the National Response Plan and applying them to emerging 
catastrophic disasters; (3) conducting strong advance planning and 
robust training and exercise programs; and (4) strengthening response 
and recovery capabilities for a catastrophic disaster. 

These themes directly relate to what I will discuss today, namely how 
three agencies planned for and conducted oversight of several key 
contracts in support of Katrina and Rita response and recovery efforts: 
the General Services Administration (GSA), the Federal Emergency 
Management Agency (FEMA), and the U.S. Army Corps of Engineers (the 
Corps). In doing our review we selected 13 mission-critical contracts 
each with a dollar value in excess of $5 million that were awarded to 
12 contractors performing work for the three agencies. We analyzed in 
detail how monitoring policies and processes were put into practice. We 
conducted our work from October 2005 through February 2006 in 
accordance with generally accepted government auditing standards. 

Summary: 

Given the environment in which they were operating, agency acquisition 
and contractor personnel have been recognized for their hard work in 
providing the goods and services required to be responsive. The 
response efforts nonetheless suffered from three primary deficiencies: 

* inadequate planning and preparation in anticipating requirements for 
needed goods and services, 

* lack of clearly communicated responsibilities across agencies and 
jurisdictions to ensure effective acquisition outcomes, and: 

* insufficient numbers and inadequate deployment of personnel to 
provide for effective contractor oversight. 

A number of efforts are under way by these agencies to address the 
issues we and others have identified. 

Contractors Role in Responding to Emergencies is Increasing: 

The private sector is an important partner with the government in 
responding to and recovering from natural disasters such as Hurricanes 
Katrina and Rita. As we recently noted,[Footnote 2] such partnerships 
increasingly underlie critical government operations. With hundreds of 
billions of tax dollars spent each year on goods and services, it is 
essential that all federal agency acquisitions be handled in an 
efficient, effective, and accountable manner. 

Over $87 billion of federal funding has been appropriated in response 
to the recent hurricanes. In responding to Hurricanes Katrina and Rita, 
the government depended heavily on contractors to deliver ice, water, 
and food supplies; patch rooftops; and provide housing to displaced 
residents and temporary facilities to local government agencies. 
Overall, the circumstances caused by the hurricanes created a difficult 
environment in which agencies had to balance the need to deliver goods 
and services quickly with the need for appropriate controls. Although 
achieving that balance is sometimes hard to accomplish, that fact must 
not be allowed to serve as an excuse for poor contracting practices. 

There Was Inadequate Planning and Preparation in Anticipating 
Requirements for Needed Goods and Services: 

The need for strong planning is one of the themes identified by the 
Comptroller General in regard to the government's overall response to 
the hurricanes. Planning also must explicitly address the need for and 
management of the contractor community. In this regard, we found that 
some key agencies did not always have adequate plans for contracting in 
a major contingency situation. We also noted the competing tensions 
between the selection of national contractors and the requirement under 
the Stafford Act for a preference for contractors from the affected 
area. Better planning could have alleviated those tensions. 

For example: 

* While contracts for some items were in place prior to the storm, the 
Federal Emergency Management Agency did not adequately anticipate needs 
for such services as providing temporary housing and public buildings. 

* The practice of the U.S. Army Corps of Engineers is to establish 
Planning and Response Teams for various missions assigned to it by FEMA 
prior to an event, with specific responsibilities assigned to team 
members. However, the Corps indicated it did not know prior to the 
hurricane that it would be tasked by FEMA with some of the mission 
assignments it received. In one case, faced with a compressed time 
frame for acquiring portable classrooms and with no prior knowledge 
about the classroom mission they were assigned, Corps contracting 
officials placed an order, under an existing agreement, with a 
subsidiary of an Alaska Native Corporation under the Small Business 
Administration's section 8(a) Business Development Program. The Corps 
accepted the contractor's proposed price of $39.5 million even though 
the Corps had information that the cost for the classrooms was 
significantly less than that. Based on our analysis of a quote obtained 
by the contractor from a local Mississippi business, the price the 
contractor actually paid for the classrooms, and prices for similar 
units from General Services Administration (GSA) schedule contracts, 
our preliminary conclusion is that the Corps could have, but failed to, 
negotiate a lower price. 

* Similarly, better management of requirements development could have 
avoided costs to house workers and victims. Based on information 
provided by local officials, FEMA spent $3 million for 4,000 base camp 
beds that were never used. 

* Preparation was also lacking in implementation of the Stafford Act 
preference for contractors residing or doing business in the affected 
area.[Footnote 3] The Corps staff expressed uncertainty regarding how 
to apply preferences or determine if a company was in an affected 
area.[Footnote 4] Several GSA and FEMA officials indicated they were 
aware of the Stafford Act, but stated it is difficult to immediately 
factor in local businesses in such a catastrophic event. GSA officials 
stated they plan to review the Federal Acquisition Regulation (FAR) to 
see if additional Stafford Act guidance is necessary.[Footnote 5] 

In discussing our findings and observations with FEMA officials, they 
indicated that in order to better respond to future disasters, they 
were taking steps to improve in areas such as staffing and 
premobilization capabilities. However, they also stated that such pre- 
planning and preparedness has a cost. The Corps commented that 
contracting staff need to have defined requirements in order to get the 
right type of contracts put in place, and the contracting staff did not 
always get defined requirements in a timely manner. Additionally, a 
Corps official commented that until funding for a particular mission is 
secured, preparation for it cannot go forward and this also delayed 
contracting efforts. Finally, both GSA and the Corps noted that they 
tried to reach out to local and small businesses through forums and 
other means to make them aware of opportunities to contract with the 
federal government. 

There Was a Lack of Clearly Communicated Responsibilities Across 
Agencies and Jurisdictions: 

We also found that processes for executing contracts were hindered by 
poor communication. As envisioned under the National Response Plan 
(NRP), federal agencies responding to a disaster carry out their 
acquisition functions through a network of federal, state, and local 
agencies. In some instances, the local or state officials determine the 
requirements and communicate them to FEMA; FEMA may write and award the 
contract or communicate the requirements to another agency that writes 
and awards the contract; and then FEMA or another agency oversees 
contract performance. This approach puts a premium on aligning roles 
and responsibilities clearly and maintaining good communications to 
ensure effective execution of the contract. 

Our fieldwork identified examples where unclear responsibilities and 
poor communications resulted in poor acquisition outcomes. For example: 

* FEMA officials stated that a contractor spent approximately $10 
million to renovate 160 rooms and furnish another 80 rooms in military 
barracks in Alabama that a FEMA survey team identified for use as 
temporary housing. To renovate the facility, FEMA headquarters awarded 
a contract without consulting local FEMA officials in Alabama. 
According to FEMA officials in Alabama, however, the facility was not 
needed and they tried to stop the renovation. These same FEMA officials 
stated that few evacuees agreed to live at the facility, and when 
officials decided to close the facility, it had only six occupants. 

* The process for ordering and delivering ice heavily depends on 
effective communications between FEMA and the Corps. However, according 
to Corps officials, FEMA did not fully understand the contracting 
approach used by the Corps and ordered at least double the amount of 
ice required, resulting in an oversupply of ice and a lack of 
distribution sites available to handle the volume ordered. 
Additionally, the local Corps personnel were not always aware of where 
ice might be delivered and did not have the authority to redirect ice 
as shipments arrived, resulting in inefficient distribution and receipt 
at the state level. 

* FEMA tasked GSA to write three contracts in Louisiana for base camps, 
hotel rooms, and ambulances, with a total value of over $120 million. 
GSA contracting officers awarded the contracts, but could not tell us 
which FEMA officials would be responsible for overseeing contractor 
performance. The FEMA official identified as the main point of contact 
by GSA did not have any knowledge of these contracts or who was 
responsible for oversight. Only after contacting multiple FEMA 
officials over a 3-week period were we able to determine the agency 
officials responsible for contract oversight. 

In commenting on our findings, GSA officials stated that their role is 
to provide resource support in the response phase of a disaster, 
meaning they are responsible for executing contracts under the NRP, and 
FEMA is responsible for monitoring the contracts. FEMA officials 
commented that there needs to be more clarity regarding procurement 
roles and indicated one of their goals is to work with GSA to clarify 
procurement responsibilities for the future. GSA officials indicated 
that the current memorandum of understanding between GSA and FEMA is 
being updated to reflect the standards of the new NRP as well. 

There Were Insufficient Numbers and Inadequate Deployment of Personnel 
to Provide for Effective Contractor Oversight: 

The purpose of agencies' monitoring processes is to ensure that 
contracted goods and services are delivered in accordance with the 
agreed-upon schedule, cost, quality, and quantity provisions stated in 
the contract. Without sufficient numbers of trained people properly 
deployed, however, effective monitoring is hampered and agencies may 
not be able to identify and correct poor contractor performance in a 
timely manner. Furthermore, agencies can be at risk of paying 
contractors more than the value of the services performed. 

Our work indicated that while monitoring was occurring on the contracts 
we reviewed, the number of monitoring staff available was not always 
sufficient, and staff were not always effectively deployed. For 
example: 

* FEMA's contracts for installing temporary housing in four states had 
only 17 of the 27 technical monitors that had been determined necessary 
to oversee contractor performance.[Footnote 6] 

* Corps officials responsible for overseeing the "blue roof" program's 
field operations told us it was slowed down due to the lack of 
sufficient monitors.[Footnote 7] 

Deployment practices did not always provide for appropriate 
notification of responsibilities or overlap of rotating contracting 
officers and oversight personnel, thus making knowledge transfer and 
continuity of contract management operations difficult. For example: 

* For four of the contracts we reviewed, officials were either unaware 
or not notified by FEMA of their oversight responsibilities. 

* The lack of overlap between oversight personnel for a large temporary 
housing contract left the most recent contract administrator with no 
knowledge or documentation of who had authorized the contractor to 
perform certain activities or why the activities were being performed. 

While discussing our findings and observations with FEMA officials, 
they emphasized that they lacked adequate staffing, but said they have 
made efforts to fill staffing gaps. Additionally, FEMA officials stated 
they recognize the need for continuity in contract oversight and 
indicated they are implementing a process to ensure workload and 
knowledge sharing among rotating personnel. However, they also believe 
that fewer transition difficulties exist now as a result of hiring more 
people and having more oversight officials staying in the affected 
areas. GSA officials indicated there may also be other alternatives for 
ensuring adequate contract oversight, such as designating GSA employees 
to conduct oversight on some contracts. Corps officials stated their 
policy is to rotate certain personnel every 29 days to keep personnel 
costs to a minimum because of regulations under the Fair Labor 
Standards Act.[Footnote 8] 

Previous Lessons Can Guide Agency Contracting Actions in Emergencies: 

In reviewing contracts awarded for Iraq--another contingency situation-
-GAO found that without effective acquisition planning, management 
processes, and sufficient numbers of capable people, poor acquisition 
outcomes resulted. GAO made recommendations regarding the need for 
ensuring that requirements for placing orders are within the scope of 
contracts; timely definition of contract terms and conditions, and 
sufficient numbers of trained staff who have clear responsibilities and 
guidance for overseeing contractor performance. Having these 
capabilities requires preparation, such as having prearranged contracts 
in place in advance of the disaster or other contingency. 

Among the issues that we have identified in previous reports that 
warrant consideration by agencies when contracting in an emergency are: 

* the strategies and flexibilities they will use to plan their 
procurements to avoid the risks associated with undefined contracts; 

* the knowledge they need to have to identify, select, and manage 
contractors to achieve successful outcomes; and: 

* the need to have competitively awarded contracts in place prior to 
the event against which orders can be placed as needed. 

In executing these contracts, agencies should consider such issues as 
how to effectively: 

* communicate and coordinate with other agencies and with contractors; 

* define contract terms and conditions to avoid excessive costs and 
ensure desired performance; and: 

* monitor contractors. 

Finally, agencies should consider crosscutting issues that affect their 
overall ability to manage contractors, such as the: 

* capability of their information systems to provide visibility into 
financial and contracting operations; 

* skills and training of the acquisition workforce; 

* alignment of responsibilities among the key officials in managing the 
award and oversight of contracts; and: 

* the policies, procedures, and guidance for managing contracts. 

In closing, in any acquisition, agencies must have in place sound 
acquisition plans, processes to make and communicate good business 
decisions, and a capable acquisition workforce to monitor contractor 
performance so that the government receives good value for the money 
spent. These components are critical to successfully managing contracts 
in any environment--even in a contingency situation such as that 
presented by Hurricanes Katrina and Rita. 

Mr. Chairman this concludes my statement. I would be happy to respond 
to any questions you or other members of the Subcommittee may have at 
this time. 

For further information regarding this testimony, please contact 
William T. Woods at (202) 512-4841 or woodsw@gao.gov. Individuals 
making key contributions to this testimony included Penny Augustine, 
James Kim, John Needham, and Shannon Simpson. 

[End of section] 

Appendix I: Recent GAO Products on Hurricanes Katrina and Rita: 

Hurricane Katrina: Comprehensive Policies and Procedures Are Needed to 
Ensure Appropriate Use of and Accountability for International 
Assistance. GAO-06-460, Washington, D.C.: April 6, 2006: 

Hurricane Katrina: Policies and Procedures Are Needed to Ensure 
Appropriate Use of and Accountability for International Assistance. GAO-
06-600T, Washington, D.C.: April 6, 2006: 

Hurricane Katrina: Status of the Health Care System in New Orleans and 
Difficult Decisions Related to Efforts to Rebuild It Approximately 6 
Months After Hurricane Katrina. GAO-06-576R, Washington, D.C.: March 
28, 2006: 

Agency Management of Contractors Responding to Hurricanes Katrina and 
Rita. GAO-06-461R, Washington, D.C.: March 16, 2006: 

Hurricane Katrina: GAO's Preliminary Observations Regarding 
Preparedness, Response, and Recovery. GAO-06-442T, Washington D.C.: 
March 8, 2006: 

Emergency Preparedness and Response: Some Issues and Challenges 
Associated with Major Emergency Incidents. GAO-06-467T. Washington: 
D.C.: February 23, 2006. 

Disaster Preparedness: Preliminary Observations on the Evacuation of 
Hospitals and Nursing Homes Due to Hurricanes. GAO-06-443R. Washington: 
D.C.: February 16, 2006. 

Investigation: Military Meals, Ready-To-Eat Sold on eBay. GAO-06-410R. 
Washington: D.C.: February 13, 2006. 

Expedited Assistance for Victims of Hurricanes Katrina and Rita: FEMA's 
Control Weaknesses Exposed the Government to Significant Fraud and 
Abuse. GAO-06-403T. Washington: D.C.: February 13, 2006. 

Statement by Comptroller General David M. Walker on GAO's Preliminary 
Observations Regarding Preparedness and Response to Hurricanes Katrina 
and Rita. GAO-06-365R. Washington, D.C.: February 1, 2006. 

Federal Emergency Management Agency: Challenges for the National Flood 
Insurance Program. GAO-06-335T. Washington, D.C.: January 25, 2006. 

Hurricane Protection: Statutory and Regulatory Framework for Levee 
Maintenance and Emergency Response for the Lake Pontchartrain Project. 
GAO-06-322T. Washington, D.C.: December 15, 2005. 

Hurricanes Katrina and Rita: Provision of Charitable Assistance. GAO- 
06-297T. Washington, D.C.: December 13, 2005. 

Army Corps of Engineers: History of the Lake Pontchartrain and Vicinity 
Hurricane Protection Project. GAO-06-244T. Washington, D.C.: November 
9, 2005. 

Hurricanes Katrina and Rita: Preliminary Observations on Contracting 
for Response and Recovery Efforts. GAO-06-246T. Washington, D.C.: 
November 8, 2005. 

Hurricanes Katrina and Rita: Contracting for Response and Recovery 
Efforts. GAO-06-235T. Washington, D.C.: November 2, 2005. 

Federal Emergency Management Agency: Oversight and Management of the 
National Flood Insurance Program. GAO-06-183T. Washington, D.C.: 
October 20, 2005. 

Federal Emergency Management Agency: Challenges Facing the National: 

Flood Insurance Program. GAO-06-174T. Washington, D.C.: October 18, 
2005. 

Federal Emergency Management Agency: Improvements Needed to Enhance 
Oversight and Management of the National Flood Insurance Program. GAO- 
06-119. Washington, D.C.: October 18, 2005. 

Army Corps of Engineers: Lake Pontchartrain and Vicinity Hurricane 
Projection Project. GAO-05-1050T. Washington, D.C.: September 28, 2005. 

Hurricane Katrina: Providing Oversight of the Nation's Preparedness, 
Response, and Recovery Activities. GAO-05-1053T. Washington, D.C.: 
September 28, 2005. 

FOOTNOTES 

[1] Hurricane Katrina: GAO's Preliminary Observations Regarding 
Preparedness, Response, and Recovery. GAO-06-442T, Washington D.C.: 
March 8, 2006. 

[2] GAO, 21st Century Challenges: Reexamining the Base of the Federal 
Government, GAO-05-325SP (Washington, D.C.: February 2005). 

[3] 42 U.S.C. § 5150. 

[4] GAO recently issued a decision on a protest of the terms of a 
solicitation issued by the Corps for demolition and debris removal in 
the State of Mississippi. The protester asserted, in part, that the 
Corps decision to limit the competition for this work to Mississippi 
firms improperly exceeded the authority granted under a provision of 
the Stafford Act to provide a preference to firms residing, or 
primarily doing business, in the area affected by a major disaster. 
GAO's decision did not view the Corps decision to implement the 
Stafford Act preference with a set-aside as an abuse of the agency's 
discretion, and the Corps did not act improperly by limiting this 
competition to Mississippi firms. AshBritt, Inc. B-297889, March 20, 
2006. 

[5] See FAR, Subpart 26.2-Disaster or Emergency Assistance Activities. 

[6] Data provided by FEMA official was dated November 18, 2005. 

[7] he Corps manages the Operation Blue Roof mission for FEMA. 
Operation Blue Roof provides assistance to storm victims in disaster 
areas through the installation of rolled plastic sheeting on damaged 
roofs, helping to protect property and allowing residents to remain in 
their homes. 

[8] 5 CFR § 551.208.