This is the accessible text file for GAO report number GAO-06-322T 
entitled 'Hurricane Protection: Statutory and Regulatory Framework for 
Levee Maintenance and Emergency Response for the Lake Pontchartrain 
Project' which was released on December 15, 2005. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Committee on Homeland Security and Governmental Affairs, 
U.S. Senate: 

United States Government Accountability Office: 

GAO: 

Not to Be Released Before 10:00 a.m. EST: 

Thursday, December 15, 2005: 

Hurricane Protection: 

Statutory and Regulatory Framework for Levee Maintenance and Emergency 
Response for the Lake Pontchartrain Project: 

Statement for the Record by Anu K. Mittal, Director, Natural Resources 
and Environment: 

GAO-06-322T: 

GAO Highlights: 

Highlights of GAO-06-322T, a statement for the record to the Committee 
on Homeland Security and Governmental Affairs, U.S. Senate: 

Why GAO Did This Study: 

The greatest natural threat posed to the New Orleans area is from 
hurricane-induced storm surges, waves, and rainfalls. To protect the 
area from this threat, the U.S. Army Corps of Engineers (Corps) was 
authorized by Congress in 1965 to design and construct a system of 
levees as part of the Lake Pontchartrain and Vicinity, Louisiana 
Hurricane Protection Project. Although federally authorized, the 
project was a joint federal, state, and local effort. For the levees in 
the project, the Corps was responsible for design and construction, 
with the federal government paying 70 percent of the costs and state 
and local interests paying 30 percent. 

As requested, GAO is providing information on the (1) level of 
protection authorized by Congress for the Lake Pontchartrain project; 
(2) authorities, roles, and responsibilities of the Corps and local 
sponsors with respect to the operation, maintenance, repair, 
replacement, and rehabilitation of the levees; (3) procedures in place 
to ensure that responsible parties maintain the levees in accordance 
with the authorized protection level; (4) authorities, roles, and 
responsibilities of the Corps and local parties when levees fail or are 
damaged; and (5) plans, capabilities, and activities that have been 
developed by the Corps to ensure an adequate emergency response when 
levees fail. 

GAO is not making any recommendations at this time. 

What GAO Found: 

Congress authorized the Lake Pontchartrain project to protect the New 
Orleans area from flooding caused by storm surge or rainfall associated 
with a hurricane that had the chance of occurring once in 200 years. 
This was termed as the “standard project hurricane” and represented the 
most severe combination of meteorological conditions considered 
reasonable for the region. As hurricanes are currently characterized, 
the Corps’ standard project hurricane approximately equals a fast-
moving category 3 hurricane, according to the Corps. 

Agreements between the Corps and four New Orleans levee districts—the 
local sponsors for the Lake Pontchartrain project—specify that the 
local sponsors are responsible for operation, maintenance, repair, 
replacement, and rehabilitation of the levees after construction of the 
project, or a project unit, is complete. Pre-Katrina, according to the 
Corps, most of the levees included in the Lake Pontchartrain project 
had been completed and turned over to the local sponsors for operations 
and maintenance. The Corps has authority to repair or rehabilitate 
completed flood control projects if (1) deficiencies are related to the 
original construction or (2) damage is caused by a flood and the 
project is active in the Corps’ Rehabilitation Inspection Program. 
According to internal Corps regulations, federal funds cannot be used 
for regular operations and maintenance activities. 

Both local sponsors and the Corps are required to conduct regular 
inspections to ensure that levees are properly maintained. If the Corps 
finds that local sponsors are not properly maintaining the levees, 
internal Corps regulations outline a series of steps, such as notifying 
the governor or taking legal action, that the Corps can take to bring 
the local sponsor in to compliance. Corps inspection reports for 2001-
2004 indicate that the completed portions of the Lake Pontchartrain 
project were maintained at an acceptable level. 

When levees fail or are damaged, the Corps has authority to provide a 
variety of emergency response actions. Specifically, the Corps is 
authorized to undertake emergency operations and rehabilitation 
activities and, if tasked by the Federal Emergency Management Agency, 
to provide disaster response, recovery, and mitigation assistance to 
state and local governments, as needed. In addition, a Department of 
Defense manual assigns responsibilities, prescribes procedures, and 
provides guidance for responding to hazards. State and local roles and 
responsibilities when levees fail are similar to the Corps’ 
responsibilities and are described in federal regulations. 

The Corps is authorized to prepare for emergency response when levees 
fail by undertaking disaster preparedness, advance measures, and hazard 
mitigation activities. The Corps’ New Orleans district has developed an 
all hazards emergency response plan for the New Orleans area. 

www.gao.gov/cgi-bin/getrpt?GAO-06-322T. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Anu K. Mittal at (202) 
512-3841 or mittala@gao.gov. 

[End of section] 

Madam Chairman and Members of the Committee: 

As you requested, this statement discusses the legislative and 
statutory framework governing levee maintenance and emergency response 
activities for the Lake Pontchartrain and Vicinity, Louisiana Hurricane 
Protection Project. This project, first authorized in 1965, is a joint 
federal, state, and local effort designed to protect the lowlands in 
the Lake Pontchartrain tidal basin within the greater New Orleans area 
from flooding by hurricane-induced sea surges and rainfall. As you 
know, the effects of Hurricane Katrina breached some of the 
approximately 125 miles of levees that are part of this project and 
flooded a large part of New Orleans. The breaches raised numerous 
questions about the design, construction, operation, and maintenance of 
the project levees and flood walls. In addition, the human suffering 
and loss of life resulting from Hurricane Katrina raised questions 
about the emergency response activities taken before, during, and after 
the flooding. 

For this statement, we did not assess the extent to which the U.S. Army 
Corps of Engineers (Corps) and local sponsors have complied with the 
legislative and regulatory requirements. Some aspects of these 
assessments will be part of our larger ongoing review of the federal 
response to the Hurricane Katrina disaster, including the levees, which 
we plan to report on in 2006. Specifically, this statement discusses 
the (1) level of protection authorized by Congress for the Lake 
Pontchartrain project; (2) authorities, roles, and responsibilities of 
the Corps and local sponsors with respect to the operation, 
maintenance, repair, replacement, and rehabilitation (OMRR&R) of the 
levees; (3) procedures required to ensure that responsible parties 
maintain the levees in accordance with the protection level authorized 
by Congress; (4) authorities, roles, and responsibilities of the Corps 
and local parties when levees fail or are damaged; and (5) plans, 
capabilities, and activities that have been developed by the Corps to 
ensure an adequate emergency response when levees fail. To conduct this 
work, we obtained and reviewed applicable laws, regulations, guidance, 
intergovernmental agreements, and other documents. We interviewed Corps 
personnel from headquarters, the Mississippi Valley Division, and the 
New Orleans District to obtain their perspectives on these issues. We 
performed the work reflected in this statement between October and 
December 2005 in accordance with generally accepted government auditing 
standards. 

In summary: 

* The Lake Pontchartrain project was authorized in 1965 to protect New 
Orleans and the surrounding area from flooding associated with a 
"standard project hurricane." A standard project hurricane was expected 
to occur once in 200 years and represented the most severe combination 
of meteorological conditions considered characteristic for the region. 
When Congress authorized the Lake Pontchartrain project, the current 
Saffir-Simpson Scale used by the National Weather Service to categorize 
hurricanes by intensity did not exist. According to the Corps, a 
standard project hurricane is roughly equivalent to a fast-moving 
category 3 hurricane on the Saffir-Simpson Scale. 

* Agreements between the Corps and local sponsors of the Lake 
Pontchartrain project specify that, when a project unit is complete, it 
will be turned over to the local sponsors for operation, maintenance, 
repair, replacement, and rehabilitation. According to the Corps, prior 
to Katrina, all but three sections of the project that make up the Lake 
Pontchartrain project had been completed and turned over to the local 
sponsors for operation and maintenance. 

* The Corps has the authority to repair or rehabilitate a flood control 
project if (1) deficiencies are identified that are the result of the 
original construction or (2) damage occurred from a flood and the 
project is active in the Corps' Rehabilitation Inspection Program. The 
Lake Pontchartrain project was active in the Rehabilitation Inspection 
Program prior to Hurricane Katrina. 

* Corps district and division employees are to oversee the OMRR&R 
activities of the local sponsors through annual inspections. If, in the 
course of these oversight activities, the Corps finds that a local 
sponsor is not properly maintaining the levees, Corps regulations 
outline a series of steps that the Corps can take to bring the local 
sponsor back into compliance. These steps include notifying the local 
sponsor or state governor, or initiating legal action against the local 
sponsor if other steps do not result in compliance. Based on Corps 
inspection reports from 2001 through 2004, all completed project units 
of the Lake Pontchartrain project were inspected annually and 
considered in acceptable condition. 

* In the event that levees fail or are damaged, the Corps has authority 
to provide a variety of emergency response actions. These actions 
include emergency operations, such as providing personnel and materials 
needed for flood fighting, and rehabilitation of damaged levees. 

* The Corps is also authorized to take actions in advance of disasters 
to ensure an adequate emergency response if levees fail. These actions 
are (1) disaster preparedness, including developing emergency response 
plans and training personnel to respond to emergencies; (2) advance 
measures, including providing supplies, equipment, and contracting for 
the construction of temporary and permanent flood control projects; and 
(3) hazard mitigation activities, which are intended to help prevent or 
reduce the possibility of a disaster, or reduce its damaging effects by 
identifying lessons learned after the event. Although we have not 
evaluated the Corps' efforts, Corps officials told us that they 
employed these authorities in preparing for the potential flooding that 
was predicted from Hurricane Katrina. In addition, after the levees 
were breached, the Corps used its response and rehabilitation 
authorities to provide flood-fighting assistance and to begin the 
repair and restoration of the levees. 

Background: 

Since its founding in 1718, the city of New Orleans and its surrounding 
areas have been subject to numerous floods from the Mississippi River 
and hurricanes. The greater New Orleans area, composed of Orleans, 
Jefferson, St. Charles, St. Bernard, and St. Tammany Parishes, sits in 
the tidal lowlands of Lake Pontchartrain and is bordered generally on 
its southern side by the Mississippi River. Lake Pontchartrain, a tidal 
basin of some 640 square miles, is connected with the Gulf of Mexico 
through Lake Borgne and the Mississippi Sound. 

The greatest natural threat posed to the New Orleans area is from 
hurricane-induced storm surges, waves, and rainfalls. Because of this 
threat, a series of control structures, concrete flood walls, and 
levees was proposed for the area along Lake Pontchartrain in the 1960s. 
Congress first authorized the construction of the Lake Pontchartrain 
and Vicinity, Louisiana Hurricane Protection Project in the Flood 
Control Act of 1965[Footnote 1] to provide hurricane protection to 
areas around the lake in Orleans, Jefferson, St. Bernard, and St. 
Charles Parishes. Although federally authorized, the project was a 
joint federal, state, and local effort. The Corps was responsible for 
project design and construction of the approximately 125 miles of 
levees, with the federal government paying 70 percent of the costs, and 
state and local interests paying 30 percent. Each of the four parishes 
protected by the project is associated with a local levee district that 
is generally composed of state-appointed officials and is considered a 
state entity. Specifically, Orleans Parish is associated with the 
Orleans Levee District, Jefferson Parish is associated with the East 
Jefferson Levee District, St. Bernard Parish is associated with the 
Lake Borgne Levee District, and St. Charles Parish is associated with 
the Pontchartrain Levee District. These levee districts are the local 
sponsors of the project, and their responsibilities include ensuring 
the integrity of the levee system in their districts throughout the 
year. 

Level of Protection Authorized by Congress: 

Congress authorized the Lake Pontchartrain project in 1965, 
substantially in accordance with a Chief of Engineers report, to 
protect the areas around the lake from flooding caused by storm surge 
or rainfall associated with a standard project hurricane. For the 
coastal region of Louisiana, a standard project hurricane was expected 
to have a frequency of occurrence of once in about 200 years, and 
represented the most severe combination of meteorological conditions 
considered reasonably characteristic for the region. According to the 
Chief of Engineers report, a standard project hurricane was selected as 
the design hurricane because of the urban nature of the area.[Footnote 
2] 

When Congress authorized the Lake Pontchartrain project, the 1 through 
5 scale--known as the Saffir-Simpson Scale--that is currently used by 
the National Weather Service to categorize hurricanes from lowest to 
highest intensity did not yet exist. According to the Corps, the 
standard project hurricane used for the Lake Pontchartrain project 
would roughly equal a fast-moving category 3 hurricane on the Saffir- 
Simpson Scale. In fact, the standard project hurricane for coastal 
Louisiana approximates the storm surge of a category 3 hurricane, the 
wind speed of a category 2 hurricane, and the barometric pressure at 
the center of a category 4 hurricane.[Footnote 3] Table 1 compares the 
coastal Louisiana standard project hurricane parameters to which the 
Lake Pontchartrain project was designed with the parameters for 
category 2, 3, and 4 hurricanes on the Saffir-Simpson Scale. 

Table 1: Comparison of Standard Project Hurricane Parameters for 
Coastal Louisiana with Category 2, 3, and 4 Hurricane Parameters: 

Central pressure[A]; 
Standard project hurricane for coastal Louisiana: 27.6 Hg; 
Saffir-Simpson category 2 hurricane: 28.50-28.91 Hg; 
Saffir- Simpson category 3 hurricane: 27.91-8.47 Hg; 
Saffir-Simpson category 4 hurricane: 27.17-27.88 Hg. 

Wind speed[B]; 
Standard project hurricane for coastal Louisiana: 100 mph; 
Saffir-Simpson category 2 hurricane: 96-110 mph; 
Saffir-Simpson category 3 hurricane: 111-130 mph; 
Saffir-Simpson category 4 hurricane: 131-155 mph. 

Radius of maximum winds[C]; 
Standard project hurricane for coastal Louisiana: 30 miles; 
Saffir-Simpson category 2 hurricane: N/A; 
Saffir- Simpson category 3 hurricane: N/A; 
Saffir-Simpson category 4 hurricane: N/A. 

Average forward speed[C]; 
Standard project hurricane for coastal Louisiana: 6 knots; 
Saffir-Simpson category 2 hurricane: N/A; 
Saffir- Simpson category 3 hurricane: N/A; 
Saffir-Simpson category 4 hurricane: N/A. 

Storm surge; 
Standard project hurricane for coastal Louisiana: 11.2-13 feet[D]; 
Saffir-Simpson category 2 hurricane: 6-8 feet; 
Saffir-Simpson category 3 hurricane: 9-12 feet; 
Saffir-Simpson category 4 hurricane: 13-18 feet. 

Source: GAO analysis of Corps and National Oceanic and Atmospheric 
Administration data. 

Notes: The shaded areas indicate those parameters on the Saffir-Simpson 
Scale that are most closely aligned with those for the standard project 
hurricane. 

[A] Central pressure is measured in inches of mercury (Hg) or 
millibars. 

[B] Wind speed for the standard project hurricane was measured as the 
maximum 5-minute average wind speed. The Saffir-Simpson Scale uses the 
maximum 1-minute average wind speed, a lower threshold. 

[C] The Corps estimated the radius of maximum winds and the average 
forward speed for a standard project hurricane, and the Saffir-Simpson 
Scale does not take either of these parameters into account. 

[D] The standard project hurricane calculated maximum surge heights for 
different geographic areas within the Lake Pontchartrain area. The 
maximum surge height for the South Shore of Lake Pontchartrain--where 
the 17th Street, London, and Industrial Canals are located--was 
estimated at 11.2 feet. 

[End of table] 

At landfall, which was approximately 60 miles southeast of New Orleans, 
Hurricane Katrina had a central pressure of 27.17 Hg and a wind speed 
of 140 mph. Wind speeds in New Orleans, which was west of the eye of 
Hurricane Katrina, reached just over 100 mph. According to the National 
Oceanic and Atmospheric Administration's National Climatic Data Center, 
data on other Hurricane Katrina parameters are not readily available 
for several reasons, including the destruction of certain buildings and 
monitoring equipment and would have been used to measure storm surge. 

Authorities, Roles, and Responsibilities for Operating and Maintaining 
the Levees: 

Consistent with federal law, agreements between the Corps and local 
sponsors of the Lake Pontchartrain project specify that local sponsors 
are responsible for operation, maintenance, repair, replacement, and 
rehabilitation of the levees when the construction of the project, or a 
project unit, is complete.[Footnote 4] However, the Corps has authority 
to (1) repair the project if deficiencies are the result of the 
original construction[Footnote 5] and (2) rehabilitate the project, if 
damage resulted from a flood and the project is active in the Corps' 
Rehabilitation Inspection Program.[Footnote 6] Corps district and 
division employees are to oversee OMRR&R activities performed by the 
local sponsors on an annual basis. 

Once construction of Lake Pontchartrain project units were completed, 
the Corps was to transfer these project units to the local sponsors for 
OMRR&R. These sponsors include the Orleans, East Jefferson, Lake 
Borgne, and Pontchartrain levee districts. Although the Corps has not 
yet provided us with dates on when the project units for the Lake 
Pontchartrain project were completed, after Hurricane Katrina, the 
Corps' New Orleans District and the Department of Defense's Task Force 
Guardian determined, based on three criteria, that almost the entire 
Lake Pontchartrain hurricane project had been turned over to local 
sponsors for ongoing OMRR&R responsibilities. The criteria used to make 
this determination were (1) if the project unit was completed in 
accordance with the designed level of protection specified in the 
project decision document, (2) if the project unit was being operated 
and maintained by the local sponsor, and (3) if the project unit had 
passed the annual Inspection of Completed Works in accordance with 
Corps regulations. Based on this evaluation, the task force determined 
that only three project units--a bridge over the 17th Street canal, a 
project unit in Jefferson Parish, and a project unit in St. Charles 
Parish--had not yet been completed and turned over to the local 
sponsors. Figure 1 shows the three project units that have not been 
completed and turned over to the local sponsors. 

Figure 1: Status of Completion and Turnover for Project Units in the 
Lake Pontchartrain and Vicinity Project: 

[See PDF for image] 

[End of figure] 

While the assurances signed by local sponsors do not define project 
completion, internal Corps regulations provide that completed projects 
or completed project units will normally be turned over when all 
construction, cleanup work, and testing of mechanical, electrical, and 
other equipment are complete and the project is in proper condition for 
the assumption of operation and maintenance by the local 
sponsors.[Footnote 7] Transfer is to be accomplished through a formal 
notice from the Corps to the local sponsor that includes a transfer 
date determined by the Corps' district engineers. According to Corps 
officials, the formal notice generally is in the form of a letter to 
the local sponsor. 

According to internal Corps regulations, upon transfer of a completed 
project to the local sponsors, the Corps may no longer expend federal 
funds on construction or project improvements.[Footnote 8] If the Corps 
determines that unsatisfactory conditions have developed as a result of 
the original levee construction, the Corps may undertake corrective 
action.[Footnote 9] For example, a Corps district official responsible 
for operations and maintenance oversight told us that if settlement of 
a completed levee occurs, this is not considered a design or 
construction flaw. Instead, this is considered a condition that should 
be addressed by the local sponsors as part of their normal operations 
and maintenance responsibilities. 

Local sponsors' responsibilities for OMRR&R of the completed portions 
of the Lake Pontchartrain project were established through local 
assurances signed by the levee districts and the Corps. For the Lake 
Pontchartrain hurricane project as constructed, these assurances were 
signed, and subsequently accepted by the federal government for the 
Orleans Levee District on June 21, 1985; the Pontchartrain Levee 
District on August 7, 1987; the East Jefferson Levee District on 
December 21, 1987; and the Lake Borgne Basin Levee District on December 
7, 1977. The formal assurances commit the local sponsors to, among 
other things, operate and maintain all features of the project in 
accordance with Corps regulations. Also, in accordance with internal 
Corps regulations, the Corps is required to provide local sponsors with 
an operations and maintenance manual at the time of, or at the earliest 
practicable date after, the transfer of OMRR&R responsibilities from 
the Corps to local sponsors for a completed project or project unit. 
The manual is intended to assist the responsible local authorities in 
carrying out their operation and maintenance obligations. According to 
Corps officials, the OMRR&R responsibilities for levees are 
straightforward, and the manual that the Corps provides local sponsors 
is a one-page document that outlines the requirements as described by 
federal regulations.[Footnote 10] Specifically, federal regulations 
require local sponsors to ensure that the structure is operating as 
intended and to continuously patrol the structure during flood periods 
to ensure that no conditions exist that might endanger the structure 
and to take immediate steps to control any condition that might 
endanger it. For maintenance, the regulations require local sponsors to 
ensure at all times that the structure is serviceable in times of 
flood. The regulations also require periodic inspections and 
maintenance measures, including the following: 

* promoting the growth of sod, including routine mowing of the grass 
and weeds; 

* exterminating burrowing animals; 

* removing drift material or wild growth from the levee (such as brush 
and trees); and: 

* repairing any damage to the levee caused by erosion. 

Repair, replacement, and rehabilitation are also considered part of the 
local sponsors' maintenance responsibilities, as outlined in internal 
Corps regulations. Repair refers to routine activities that maintain 
the project in well-kept condition; replacement refers to replacing 
worn-out elements; and rehabilitation refers to activities necessary to 
bring a deteriorated project back to its original condition. According 
to internal Corps' regulations, local sponsors' maintenance is 
considered to be deficient when these requirements have not 
fulfilled.[Footnote 11] 

Corps employees are to oversee local sponsors' OMRR&R activities to 
ensure compliance and project integrity. Corps employees are required 
to work directly with local sponsors to conduct annual compliance 
inspections; review local sponsors' semiannual compliance reports; and 
respond to engineering concerns, maintenance questions, and reports of 
problems. A Corps district official responsible for operations and 
maintenance oversight told us that generally the Lake Pontchartrain 
project's local sponsors have performed their operations and 
maintenance responsibilities as required and have been responsive to 
the Corps' concerns. Because the New Orleans district is part of the 
Mississippi Valley Division of the Corps, the division also has 
responsibility for managing and overseeing the periodic inspections 
conducted by district engineers; reviewing and approving district 
engineers' inspection reports; maintaining a database of information on 
inspections and remedial measures taken; and receiving annual OMRR&R 
summary reports from the districts under its command, aggregating these 
reports, and sending them to Corps headquarters. 

Federally authorized flood control projects, such as the Lake 
Pontchartrain project, are eligible for 100 percent federal 
rehabilitation if damaged by a flood as long as these projects are 
active in the Corps' Rehabilitation Inspection Program (rehabilitation 
program).[Footnote 12] To maintain active status in this program, the 
Lake Pontchartrain project's levees are required to pass an annual 
OMRR&R inspection conducted jointly by the Corps, the local sponsor, 
the state Department of Transportation and Development, and other 
stakeholders, as appropriate.[Footnote 13] According to the Corps' 
inspection reports from 2001 through 2004, all completed project units 
of the Lake Pontchartrain project were inspected each year and had 
received an acceptable rating. 

Procedures to Ensure That Levees Are Properly Maintained: 

Both local sponsors and the Corps are required to conduct oversight 
activities to ensure that levees are properly maintained. If, in the 
course of these oversight activities, the Corps finds that the local 
sponsors are not properly maintaining the levees, internal Corps 
regulations outline a series of steps that the Corps can take until the 
local sponsor comes into compliance. 

Local Sponsors' Oversight Activities: 

Federal regulations require that local levee districts are to appoint a 
permanent committee, headed by a superintendent, that will be 
responsible for all levee operation and maintenance activities and 
inspections of federally constructed flood control projects.[Footnote 
14] The superintendent of the levee district is responsible for 
performing periodic inspections of the levee to ensure that routine 
maintenance responsibilities have been effectively completed and that 
no hazards to the levee exist. Typically, these inspections take place 
prior to the flood or hurricane season, immediately following a high- 
water period, and at other intermediate periods throughout the year. 
During an inspection, the superintendent is required to examine and be 
certain, among other things, that: 

* drainage systems are in good working condition and not becoming 
clogged; 

* no unusual settlement or material loss of grade or levee cross 
section has taken place; 

* cattle guards and gates are in good condition; 

* the protective walls surrounding the levee have not been washed out 
or removed; 

* the levee crown is shaped to drain readily; 

* no unauthorized vehicular traffic or cattle grazing has occurred; 

* no water seepage or saturated areas are occurring; and: 

* levee access roads are being properly maintained. 

If, during these inspections, the superintendent discovers any levee 
portion to be in substandard condition, it is the levee district's 
responsibility to take immediate actions to correct the inadequacy. The 
superintendent is required to submit a report twice a year to the Corps 
District Engineer covering inspection, maintenance, and operation 
activities of the levee district. At this time, we have not examined 
the extent to which these steps were taken by the local sponsors, and 
the Corps has not provided us any documentation of such activities. 

The Corps' Oversight Activities: 

The Corps is responsible for overseeing the OMRR&R activities of the 
Lake Pontchartrain project's local sponsors through an annual 
compliance inspection program--known as the Inspection of Completed 
Works program--and reviewing the local sponsors' semiannual reports on 
OMRR&R activities submitted to the district office. According to 
internal Corps regulations, the primary purposes of the Inspection of 
Completed Works program are to prevent loss of life and catastrophic 
damages, preserve the value of the federal investment, and encourage 
local sponsors to bear responsibility for their own protection. 
According to Corps officials, for the Lake Pontchartrain project, the 
New Orleans District typically completes this annual compliance 
inspection prior to the hurricane season, in mid-May to early-June of 
each year. Our review of Corps inspection reports for 2001 through 2004 
indicate that while inspections of the Lake Pontchartrain hurricane 
protection levees in the Orleans and St. Bernard Parishes were 
generally conducted in May of each year, the inspections of the levees 
in Jefferson and St. Charles Parishes were generally conducted in the 
September to November timeframe.[Footnote 15] According to the Corps, 
these inspections are to cover the following items: 

* level of protection, 

* erosion control, 

* slope stability, 

* animal control, 

* unwanted vegetative growth, 

* concrete surfaces, and: 

* structural foundations. 

Based on the results of these inspections, the district and division 
are to characterize the inspected units on a scale from 1 to 3, where 1 
means that the project units have been maintained in accordance with 
the agreement between the Corps and the local sponsors and are expected 
to perform as designed, and 3 means that the project units have 
maintenance deficiencies such that the project would probably fail 
during floods of project design or lesser magnitudes. Within 120 days 
of an inspection, the district is expected to prepare an inspection 
report and provide it to its commanding unit. For example, the New 
Orleans District should prepare an inspection report for the Lake 
Pontchartrain project and forward it to the Mississippi Valley Division 
for review and approval. Reports that indicate maintenance deficiencies 
are also to be submitted annually to headquarters. All of the completed 
units of the Lake Pontchartrain hurricane levees passed with an 
acceptable rating for the period 2001 through 2004. 

If a project receives a rating of 3 as a result of an inspection, 
internal Corps regulations[Footnote 16] outline a progression of steps 
that the Corps can take to ensure that local sponsors fulfill their 
OMRR&R responsibilities and bring the levees back up to the designed 
level of protection. The steps are as follows: 

* Notify the sponsor orally of the deficiencies. 

* Notify the sponsor in writing. 

* Write a letter to the governor and the appropriate state agencies-- 
which, in the case of the Lake Pontchartrain project, is the Department 
of Transportation and Development in Louisiana--to enlist state 
participation to resolve the problem. 

* Notify the Federal Emergency Management Agency (FEMA) of the 
condition of the project. 

* If acceptable actions are not taken by the nonfederal sponsor, take 
actions to remove the project from eligibility for federal emergency 
rehabilitation. 

* Initiate legal action against the local sponsor to enforce OMRR&R 
obligations as outlined in local assurances. 

* Transmit a report to the Congress recommending authorization of a new 
sponsor or reauthorization of the project along with measures to 
eliminate hazards. 

Although not documented in the annual inspection reports, according to 
Corps officials, almost all past Lake Pontchartrain project 
deficiencies have been resolved upon oral notification of the local 
levee district. The official responsible for the Inspection of 
Completed Works program in New Orleans only could recall one or two 
instances when the Corps wrote a letter to a local sponsor requesting 
that the sponsor commit resources to repair a deficiency, which 
resulted in full compliance by the local sponsor. Internal Corps 
regulations specifically prohibit the use of federal funds to correct 
problems caused by a lack of adequate local maintenance. 

Authorities, Roles, and Responsibilities When Levees Fail: 

The Corps has authority to provide a variety of emergency response 
actions when levees fail or are damaged. Section 5 of the Flood Control 
Act of 1941, as amended, commonly referred to as Public Law 84-99, 
authorizes the Corps to conduct emergency operations and rehabilitation 
activities when levees fail or are damaged.[Footnote 17] In addition, 
under the Robert T. Stafford Disaster Relief and Emergency Assistance 
Act (Stafford Act), as amended, the Corps and other federal agencies 
may be tasked by FEMA to provide disaster response, recovery, and 
mitigation assistance to state and local governments.[Footnote 18] 
Furthermore, a Department of Defense Manual for Civil Emergencies 
assigns responsibilities, prescribes procedures, and provides guidance 
by which the Department of Defense responds to all hazards in 
accordance with the Stafford Act.[Footnote 19] Although we have not 
evaluated the Corps' efforts, Corps officials told us that after the 
levees were breached the Corps used its response and rehabilitation 
authorities to provide flood-fighting assistance and to begin the 
repair and restoration of the levees. State and local roles and 
responsibilities when levees fail are similar to the Corps' 
responsibilities and are also described in federal 
regulations.[Footnote 20] 

Public Law 84-99: 

Public Law 84-99 authorizes the Corps to conduct emergency operations 
and rehabilitation activities when levees fail or are damaged during 
storms or other events. Federal regulations specify that assistance is 
limited to providing emergency assistance to save lives and protect 
property, such as public facilities/services and residential, 
commercial, or industrial developments.[Footnote 21] This emergency 
assistance may be provided during and following a flood or coastal 
storm. However, under federal regulations, nonfederal interests must 
fully utilize their own resources, including manpower, supplies, 
equipment, and funds before Corps assistance may be provided.[Footnote 
22] The National Guard, as part of the state's resources when it is 
under state control, must be fully utilized as part of the nonfederal 
response. According to federal regulations, the Corps is not to use 
funds to reimburse local authorities for the costs of these emergency 
activities.[Footnote 23] 

To implement flood response operation authorities under Public Law 84- 
99, internal Corps regulations specify that Corps district commanders 
must issue a Declaration of Emergency. The Declaration of Emergency may 
initially be verbal, but must be made in writing and reported in the 
district's situation report within 24 hours. Authority to issue a 
Declaration of Emergency has been delegated to deputy district 
engineers and includes all supervisors in the chain of command, from 
the district commander to the chief of emergency management. 

Emergency operations include flood response and postflood response 
activities. 

* Flood response includes activities such as flood fighting and rescue 
operations. These activities include providing technical assistance, 
such as review and recommendations in support of state and local 
efforts and help determining feasible solutions to uncommon situations, 
and direct assistance by: 

* issuing supplies; 

* conducting rescue operations; 

* directing flood-fighting operations; and: 

* contingency contracting for emergency operations. 

Corps assistance during flood-fighting operations is to be temporary to 
meet the immediate threat and to supplement state and local efforts. 
This assistance is not intended to provide permanent solutions to flood 
problems and should be terminated when the emergency is over--for 
example, when flood waters have receded sufficiently. 

* Postflood response includes emergency debris removal, temporary 
restoration of critical transportation routes and public services and 
utilities, and after action review and reporting. 

Rehabilitation activities include the repair and restoration of 
eligible flood control projects and federally constructed hurricane or 
shore protection projects. Rehabilitation assistance is limited to 
federal and nonfederal flood control works that are in active status-- 
those found to be properly maintained during inspections--in the Corps' 
Rehabilitation Inspection Program at the time of the hurricane, storm, 
or flood event.[Footnote 24] Rehabilitation assistance is limited to 
repair or restoration of a flood control work to its predisaster 
condition and level of protection (e.g., the actual elevation of the 
levee, allowing for normal settlement).[Footnote 25] Any damage to 
federally constructed levees are repaired with 100 percent of the cost 
borne by the federal government; and damage to nonfederally constructed 
levees are repaired with 80 percent of the cost borne by the federal 
government and 20 percent by the local sponsor.[Footnote 26] Because 
the Lake Pontchartrain project is federally constructed and was active 
in the Corps' Rehabilitation Inspection Program, the Corps is 
authorized to rehabilitate any levees that failed or were damaged as a 
result of Hurricane Katrina, using this authority. Additionally, in the 
aftermath of Hurricane Katrina, the Assistant Secretary of the Army for 
Civil Works agreed to rehabilitate all of the damaged Lake 
Pontchartrain and other hurricane and flood control structures in the 
New Orleans area without any local cost share, under emergency 
authority provided in statute.[Footnote 27] Further, the federal 
government will fund the acquisition of lands, easements, rights-of- 
way, and disposal or borrow areas not owned or under control of the 
nonfederal sponsor, as well as the performance of relocations, that are 
needed for the rehabilitation and that are normally local 
responsibilities. The Corps estimates that funding these activities for 
the Lake Pontchartrain project will cost the federal government an 
additional $10 million and over $248 million in total for all damaged 
levee systems in the New Orleans area. 

Stafford Act: 

The Stafford Act, as amended, authorizes federal agencies, including 
the Corps, to take emergency response actions when the President has 
issued a major disaster declaration. Under the act, a presidential 
declaration may be made after receiving a request from the governor of 
the affected state.[Footnote 28] FEMA, within the Department of 
Homeland Security, is responsible for administering the major 
provisions of the Stafford Act. Actions taken under this authority 
include disaster response, recovery, and mitigation assistance to 
supplement state and local efforts. 

To meet its obligations for emergency response, the Department of 
Homeland Security developed a National Response Plan, which describes 
the roles and responsibilities of various federal agencies.[Footnote 
29] Within the National Response Plan, the Department of Defense has 
responsibility for Emergency Support Function #3--Public Works and 
Engineering. The plan designates the Corps as the operating agent for 
this function, to include planning, preparedness, and response, with 
assistance to be provided by other branches of the Department of 
Defense, as needed. 

The National Response Plan lists the following activities for the 
Corps: 

* coordination and support of infrastructure risk and vulnerability 
assessments; 

* participation in preincident activities, such as prepositioning 
assessment teams and contractors; 

* participation in postincident assessments of public works and 
infrastructure to help determine critical needs and potential work 
loads; 

* implementation of structural and nonstructural mitigation measures to 
minimize adverse effects or fully protect resources prior to an 
incident; 

* execution of emergency contracting support for life-saving and life- 
sustaining services, to include providing potable water, ice, emergency 
power, and other emergency commodities and services; 

* providing assistance in monitoring and stabilizing damaged 
structures, and demolishing structures designated as immediate hazards 
to public health and safety, and providing structural specialist 
expertise to support inspection of mass care facilities and urban 
search and rescue operations; 

* providing emergency repair of damaged infrastructure and critical 
public facilities, and supporting the restoration of critical 
navigation, flood control, and other water infrastructure systems; 

* managing, monitoring, and providing technical advice in the 
clearance, removal, and disposal of debris from public property and the 
re-establishment of ground and water routes into impacted areas; and: 

* implementing and managing FEMA's Public Assistance Program and other 
recovery programs involving federal, state, and tribal officials, 
including efforts to permanently repair, replace, or relocate damaged 
or destroyed public facilities and infrastructure. 

Department of Defense Manual for Civil Emergencies: 

A Department of Defense Manual For Civil Emergencies assigns 
responsibilities, prescribes procedures, and provides guidance by which 
the Department of Defense responds to all hazards in accordance with 
the Stafford Act. The policy states that commanders may conduct 
disaster relief operations when a serious emergency or disaster is so 
imminent that waiting for instructions from higher authority would 
preclude effective response. According to the policy, commanders may do 
what is required and justified to save human life, prevent immediate 
human suffering, or lessen major property damage or destruction. Action 
taken in accordance with the policy is limited to 10 days. A Corps 
commander providing assistance to civil authorities under this guidance 
is not required to obtain an agreement for reimbursement from the 
requesting agency before providing assistance. 

Planned Emergency Response Activities: 

The Corps is authorized by Public Law 84-99 to prepare for emergency 
response when levees fail by undertaking disaster preparedness, advance 
measures, and hazard mitigation activities. Although we have not 
evaluated the Corps' efforts, Corps officials told us that they took 
action in advance of Hurricane Katrina to prepare for the potential 
flooding that was predicted. As part of this effort, according to Corps 
officials, the Corps' New Orleans district used a draft hurricane 
preparedness plan for the New Orleans area. 

Disaster Preparedness: 

Corps division and district commanders are responsible for providing 
immediate and effective response and assistance prior to, during, and 
after emergencies and disasters. Although we have not reviewed the 
extent to which the Corps undertook these initiatives during the 
Katrina disaster, the Corps is responsible for the following: 

1. Creating an emergency management organization. Division and district 
commanders are expected to provide adequate staffing for a 
readiness/emergency management organization to accomplish the 
preparedness mission. In addition, divisions and districts should have 
teams readily available to provide assistance under the Corps' 
authorities for flood emergencies and other natural disasters; execute 
responsibilities and missions under the Stafford Act and the National 
Response Plan; staff a Crisis Management Team, consisting of an 
Emergency Manager and senior representatives from technical and 
functional areas to provide guidance and direction during emergency 
situations; and staff a Crisis Action Team, consisting of the personnel 
necessary to operate an emergency operations center. 

2. Establishing and maintaining plans and procedures. Corps 
headquarters, divisions, and districts are expected to prepare and 
maintain plans for emergencies and disasters, establishing an alternate 
emergency operations center, and reconstituting the district. These 
operation plans should cover emergency/disaster assistance procedures 
under all applicable authorities and potential mission assignments. 
Each division and district should have, at a minimum, an operation plan 
that provides procedures for generic disasters within the division and 
district. The plan should include general topics, such as activating, 
staffing, and operating the emergency operations center; reporting 
requirements; notification and alert rosters; and organizing for 
response to disasters. The plan should also have one or more appendixes 
that specifically address the disasters most likely to impact the 
division and district. Operation plans are reviewed and updated 
annually to reflect administrative changes. The division/district's 
generic or principal disaster operation plan is supposed to be 
reviewed, revised, and republished biennially. 

3. Training personnel for response. Divisions and districts are 
expected to ensure that personnel who are assigned emergency assistance 
responsibilities have been properly trained. 

4. Conducting exercises. Exercises are to be conducted at least once 
every two years, consistent with available funding. This requirement 
may be waived if an actual emergency response was conducted during the 
two-year period that was of sufficient magnitude to have adequately 
trained emergency team members and other personnel. 

5. Establishing adequate command and control facilities. Divisions, 
districts, and other Corps groups should provide a dedicated facility 
for an emergency operations center that will be able to provide command 
and control for emergency/disaster response and recovery activities. 

6. Maintaining supplies, tools, and equipment. Divisions and districts 
are expected to maintain equipment and supplies that can be readily 
available for use by the emergency operations center, disaster field 
offices, disaster field teams, planning response teams, and similar 
entities. Equipment should be stockpiled for use during emergency 
operations and exercises. 

7. Managing inspections of flood control projects. The Corps is 
responsible for ensuring that the levees are properly maintained to 
perform as designed during flood events. 

Advance Measures: 

The Corps may take advance measures prior to a flooding event to 
protect against loss of life and significant damages to urban areas and 
public facilities.[Footnote 30] In the case of imminent danger of levee 
failure or overtopping, the Corps can also take corrective actions to 
ensure the stability, integrity, and safety of the levee.[Footnote 31] 
Advance measures include the following: 

1. Technical assistance: providing technical review, advice, and 
recommendations to state and local agencies before an anticipated flood 
event. For example, the Corps may provide personnel to inspect existing 
flood control works to identify potential problems and solutions, 
evaluate conditions to determine the requirements for additional flood 
control protection, and recommend the most expedient construction 
methods; provide hydraulic, hydrologic, and geotechnical analysis; and 
provide information readily available at Corps districts to local 
entities for use in the preparation of local evacuation and contingency 
flood plans. 

2. Direct assistance: providing supplies, equipment, and contracting 
for the construction of temporary and permanent flood control projects. 
Examples of emergency contracting work include the construction of 
temporary levees; the repair, strengthening, or temporary raising of 
levees or other flood control works; shore protection projects; and 
removal of stream obstructions, including channel dredging of federal 
projects to restore the design flow. 

Advance measures taken by the Corps are intended to supplement ongoing 
or planned state and local efforts, and are designed to deal with a 
specific threat. To implement advanced measures, the governor should 
make a written request to the Corps. The local sponsor for the advance 
measure assistance must agree to execute a cooperative agreement and, 
at no cost to the Corps, when the operation is over, remove all 
temporary work constructed by the Corps or agree to upgrade the work to 
standards acceptable to the Corps. In addition, the local sponsor is 
responsible for providing traditional items of local cooperation, such 
as lands, easements, rights-of-way, and disposal areas necessary for 
the work. Advance measures assistance is temporary and must be 
terminated no later than when the flood threat ends. 

Hazard Mitigation: 

Hazard mitigation activities are intended to help prevent or reduce the 
possibility of a disaster or reduce its damaging effects. The Corps is 
required to participate on a FEMA-led hazard mitigation team to 
identify postdisaster mitigation opportunities and establish a 
framework for recovery. According to the Corps' hazard mitigation 
policy, division commanders are to appoint primary and alternate 
representatives to serve on the hazard mitigation team; establish 
procedures for quick and effective response to the requirements of the 
team; ensure essential information and data necessary to assess 
mitigation opportunities are available or capable of being obtained 
quickly; ensure division hazard mitigation team representatives are 
trained in flood hazard mitigation concepts and techniques; and provide 
reports to FEMA and Corps headquarters. Recommendations of the hazard 
mitigation team are intended to reduce or avoid federal expenditures 
resulting from flood situations.[Footnote 32] 

New Orleans District's Hurricane Preparedness Plan: 

The Corps' New Orleans District has a draft hurricane preparedness plan 
that defines the district's role and responsibilities in the event of 
an emergency due to a hurricane.[Footnote 33] The plan outlines the 
essential functions of the district before, during, and after a 
hurricane. These functions include pre-event planning, organization, 
response, and recovery in order to minimize the potential hazards to 
life and property. As part of this plan, the district defines emergency 
organizational staffing to support emergency operations. Selected 
personnel are assigned to specific teams or offices that, in the event 
of a disaster, are to provide the necessary liaison with federal, 
state, or local emergency management agencies; make decisions relative 
to Corps' capabilities and assignments; perform preliminary damage 
assessments; or accomplish specific missions. According to the plan, a 
New Orleans District Emergency Operations Center should be staffed to 
respond to an emergency, and the center is to become the focal point 
for collecting data, analyzing situations, allocating resources, 
furnishing reports to higher headquarters, and providing overall 
management and control of all district activities. With the activation 
of the emergency operations center, a crisis management team becomes 
responsible for coordinating and directing district activities in the 
crisis situation. A crisis action team is responsible for executing the 
activities as directed by the crisis management team. According to the 
plan, if a slow-moving category 3 or higher hurricane is approaching 
the area, the team should be activated and deployed at the direction of 
the commander. The plan does not contain any specific guidance on how 
the district would respond to a levee failure. 

In closing, Madam Chairman, the legislative and regulatory framework 
guiding the operations and maintenance of the levees divides this 
responsibility among a number of partners, depending upon specific 
circumstances. Similarly, the responsibilities for emergency 
preparedness and response are dependent on a variety of laws and 
regulations. As a result, the regulatory framework for these activities 
is complex and oftentimes unclear. Whether these responsibilities were 
appropriately fulfilled or played a role in the flooding of New Orleans 
in the wake of Hurricane Katrina in August 2005 is still to be 
determined. 

GAO Contact and Staff Acknowledgments: 

For further information on this testimony, please contact Anu Mittal at 
(202) 512-3841 or mittala@gao.gov. Individuals making contributions to 
this testimony included Ed Zadjura, Assistant Director; Allison Bawden; 
Kevin Bray; Kisha Clark; John Delicath; Doreen Feldman; Jessica 
Marfurt; Barbara Patterson; and Barbara Timmerman. 

FOOTNOTES 

[1] Pub. L. No. 89-298, § 204, 79 Stat. 1073, 1077 (1965). 

[2] H.R. Doc. No. 231, 89th Cong., 1st Sess. (1965). 

[3] Barometric pressure is a key indicator of a hurricane's intensity. 
The lower a hurricane's barometric pressure, the greater the wind speed 
and, therefore, the storm surge. 

[4] 33 U.S.C. § 2213(j). 

[5] Corps Regulation No. ER 1165-2-119. 

[6] Corps Regulation No. ER 500-1-1. 

[7] Corps Regulation No. ER 1150-2-301. 

[8] Corps Regulation No. ER 1150-2-301. 

[9] Corps Regulation No. ER 1165-2-119. 

[10] 33 C.F.R. § 208.10. According to Corps officials, the Corps has 
provided local sponsors with specific operations and maintenance 
manuals for the Bienvenue and Dupre floodgate structures in the Lake 
Pontchartrain project. 

[11] Corps Regulation No. ER 1130-2-530. 

[12] Locally authorized flood control projects can also participate in 
the rehabilitation program. If active, locally authorized projects are 
damaged in a flood emergency, the cost of rehabilitation is shared 
between the local authority and the federal government--20 percent and 
80 percent, respectively. 33 C.F.R. § 203.82(f). 

[13] For projects other than levees that have mechanical or electrical 
parts, such as locks, floodgates, drainage structures, and pumping 
stations, periodic engineering inspections are also performed. 

[14] 33 C.F.R. § 208.10(a)(2). 

[15] According to Corps officials, the majority of the protection in 
the Jefferson and St. Charles Parishes is flood protection along the 
Mississippi River as opposed to hurricane protection. Therefore, 
inspections are done prior to the high-water period on the Mississippi 
River. 

[16] Corps Regulation No. ER 1130-2-530. 

[17] 33 U.S.C. § 701n. The Corps' administrative policies, guidance, 
and operating procedures for natural disaster preparedness, response, 
and recovery activities are set out in 33 C.F.R. part 203. 

[18] 42 U.S.C. § 5121 et seq. 

[19] DOD 3025.1-M (June 1994). 

[20] 33 C.F.R. § 203.14. 

[21] 33 C.F.R. § 203.32. The regulations also specify that the Corps is 
not authorized to provide assistance to individual homeowners and 
businesses. 

[22] 33 C.F.R. § 203.14. 

[23] 33 C.F.R. § 203.32. 

[24] 33 C.F.R. § 203.41. 

[25] Corps Regulation No. ER 500-1-1. 

[26] Corps Regulation No. ER 500-1-1. 

[27] 33 U.S.C. § 701n. According to the Corps, local sponsors requested 
that the Corps undertake this work at full federal expense due to the 
unprecedented damage and impacts to local governments and the inability 
of the local sponsors to finance their share of the costs. According to 
the Corps, the Assistant Secretary of the Army for Civil Works approved 
the request with the concurrence of the Office of Management and Budget 
and notified the House and Senate Appropriations Subcommittees on 
Energy and Water Development. 

[28] 42 U.S.C. § 5170. 

[29] The Department of Homeland Security developed the National 
Response Plan in response to a presidential directive, HSPD-5. 

[30] Corps Regulation Nos. ER 500-1-1 and EP 500-1-1. 

[31] Corps Regulation Nos. ER 500-1-1 and EP 500-1-1. 

[32] Corps Regulation No. ER 500-1-1. 

[33] The district's hurricane preparedness plan is in draft form. 
According Corps officials, however, the draft plan was used to prepare 
and respond to Hurricane Katrina. Corps District Regulation No. DR 500- 
1-3.