This is the accessible text file for GAO report number GAO-05-910T 
entitled 'Capitol Visitor Center: Update on Status of Project's 
Schedule and Costs' which was released on July 14, 2005.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Testimony:

Before the Subcommittee on the Legislative Branch, Committee on 
Appropriations, U.S. Senate:

United States Government Accountability Office:

GAO:

For Release on Delivery Expected at 10:30 a.m. EDT:

Thursday, July 14, 2005:

Capitol Visitor Center:

Update on Status of Project's Schedule and Costs:

Statement of Bernard L. Ungar, Director: 
Terrell Dorn, Assistant Director: 
Physical Infrastructure Issues:

GAO-05-910T:

Mr. Chairman and Members of the Subcommittee:

We are pleased to be here today to assist the Subcommittee in 
monitoring progress on the Capitol Visitor Center (CVC) project. As 
requested, we will focus our remarks today on the Architect of the 
Capitol's (AOC) progress in achieving selected project milestones and 
in managing the project's schedule since the Subcommittee's June 14 
hearing on the project.[Footnote 1] We will also discuss the project's 
costs and funding, including the potential cost impact of schedule- 
related issues. Our observations today are based on our review of 
schedules and financial reports for the CVC project and related records 
maintained by AOC and its construction management contractor, Gilbane 
Building Company; our observations on the progress of work at the CVC 
construction site; and our discussions with AOC's Chief Fire Marshal 
and CVC project staff, including AOC, its major CVC contractors, and 
representatives of an AOC schedule consultant, McDonough Bolyard Peck 
(MBP). We did not perform an audit; rather, we performed our work to 
assist Congress in conducting its oversight activities.

In summary, AOC and its major construction contractors have made 
progress on the project since the Subcommittee's June 14 hearing, but 
work on some of the selected milestones scheduled for completion by 
today's hearing is incomplete; some work has been postponed; and some 
new issues have arisen that could affect the project's progress. 
Specifically, as of July 12, AOC's sequence 2 contractor, Manhattan 
Construction Company, had completed work on 11 of the 17 selected 
milestones scheduled for completion before today's hearing; however, it 
completed only 3 of the 17 milestones on time. The sequence 2 
contractor missed the 14 remaining milestones for such reasons as 
unforeseen site conditions, design problems, and more time being taken 
to complete some other work than expected. In addition, the date 
scheduled for the initial operation of the utility tunnel is now about 
5 months later than AOC had anticipated, and unforeseen conditions 
could delay the installation of stone in the East Front. Although the 
June project schedule shows that the delay on the East Front stonework 
would move the scheduled opening date for the CVC project to October 
19, 2006, AOC does not expect the delays in completing the remaining 
milestones, including the utility tunnel and East Front stonework, to 
postpone the project's scheduled September 2006 completion date. In 
AOC's view, the contractor can recover the time lost in completing 
these milestones, as well as make up for delays in completing interior 
stonework, by such means as using temporary equipment, adding workers, 
or resequencing work, although using temporary equipment or adding 
workers will also increase the project's costs. Largely because of past 
problems, remaining risks and uncertainties, and the number of 
activities that are not being completed on time, we continue to believe 
that the project is more likely to be completed in the December 2006 to 
March 2007 time frame than in September 2006. AOC and its construction 
management contractor have continued their efforts to respond to two 
recommendations we made to improve the project's management--having a 
realistic, acceptable schedule and aggressively monitoring and managing 
adherence to that schedule. However, we still have some concerns about 
the amount of time scheduled for some activities, the extent to which 
resources can be applied to meet dates in the schedule, the linkage of 
related activities in the schedule, and the integration of planning for 
completing construction and starting operations. Since the 
Subcommittee's last CVC hearing, AOC has engaged contractors to help it 
respond to two other recommendations we made--developing risk 
mitigation plans and preparing a master schedule that integrates the 
major steps needed to complete construction with the steps needed to 
prepare for operations. AOC has also been taking a number of actions to 
improve coordination between the CVC project team and AOC's Fire 
Marshal Division. Insufficient coordination in this area has already 
affected the project's schedule and cost, and could do so again if 
further improvements are not made.

We continue to believe that the project's estimated cost at completion 
will be between $522 million and $559 million, and that, as we have 
previously indicated, AOC will likely need as much as $37 million more 
than it has requested to cover risks and uncertainties to complete the 
project. At this time, we believe that roughly $5 million to $15 
million of this $37 million is likely to be needed in fiscal year 2006, 
and the remainder in fiscal year 2007. In the next 2 to 3 months, AOC 
plans to update its estimate of the project's remaining costs. We will 
review this estimate and provide Congress with our estimate together 
with information on when any additional funding is likely to be needed. 
During the next several months, AOC is likely to face competing demands 
for funds that can be used for either CVC construction or operations, 
and it will be important for AOC to ensure that the available funds are 
optimally used. Finally, we are concerned that AOC may incur costs to 
open the facility to the public in September 2006 that it would not 
incur if it postponed the opening until after the remaining 
construction work is more or fully complete--that is, in March 2007, 
according to AOC's estimates.

We are recommending that AOC designate who will be responsible for 
integrating the planning and budgeting for CVC construction and 
operations and notify Congress in advance of any estimated costs it 
believes it will incur to open CVC to the public in September 2006 
rather than when the facility is more complete. AOC agreed with these 
recommendations.

Schedule Milestones and Management:

AOC and its major construction contractors have moved the CVC project 
forward since the Subcommittee's June 14 hearing, although the majority 
of the selected milestones scheduled for completion by today's hearing 
have not been completed on time. According to the construction 
management contractor, the base project's construction was about 70 
percent complete as of June 30, compared with about 65 percent as of 
May 31. The sequence 1 contractor, Centex Construction Company, which 
was responsible for the project's excavation and structural work, has 
continued to address punch-list items, such as stopping water leaks. 
Although AOC had expected the sequence 1 contractor to complete the 
punch-list work and be off-site by June 30, some of this work remains 
to be done. The sequence 1 contractor has closed its on-site project 
office and plans to send workers back to the site to complete the 
remaining work. AOC has retained funds from the sequence 1 contractor 
that it believes will be sufficient to cover the cost of the remaining 
work. Furthermore, the sequence 2 contractor, which is responsible for 
the mechanical, electrical, plumbing, and finishing work, has continued 
to make progress in these areas, including erecting masonry block, 
placing concrete, and installing finish stone, drywall framing, 
plaster, and granite pavers. Many of the granite pavers that were 
installed on the plaza deck for the inauguration have to be replaced 
because of problems with quality or damage after installation. The 
sequence 2 contractor plans to replace these pavers when the plaza deck 
will no longer be needed for deliveries of construction materials. The 
sequence 2 contractor has also continued work on the utility tunnel, 
and in June, AOC executed a sequence 2 contract modification to 
construct the House connector tunnel. AOC expects this work to begin 
soon.

As the Subcommittee requested, we worked with AOC to select sequence 2 
milestones that the Subcommittee can use to help track the project's 
progress from the Subcommittee's May 17 hearing to July 31. We and AOC 
selected 22 milestones, of which 11 were scheduled for completion 
before June 14, 6 others before July 14, and 5 others before July 31. 
These milestones are shown in appendix 1 and include activities on the 
project's critical path, as well as other activities that we and AOC 
believe are important for the project's timely completion.[Footnote 2] 
As we reported during the Subcommittee's June 14 hearing, AOC's 
sequence 2 contractor completed 6 of the 11 selected activities 
scheduled for completion before that date--3 were completed on time and 
3 were late. The remaining 5 activities had not been completed as of 
June 14. Of these 5, 4 have now been completed and as of July 12, 1 
remained incomplete. In addition, as of July 12, the contractor was 
late in completing 1 of the 6 selected activities scheduled for 
completion between June 14 and July 14 and had not yet completed the 
remaining 5. AOC does not expect these delays to extend the project's 
scheduled September 2006 completion date because it believes that the 
sequence 2 contractor can recover the lost time.

A few months ago, AOC expected the utility tunnel to be operational in 
October 2005, but it extended that date to March 20, 2006, before the 
June hearing. The June schedule shows the tunnel being operational on 
March 7. The sequence 2 contractor has indicated that the impact of the 
October-to-March delay on CVC construction could be mitigated by using 
temporary dehumidification equipment, adding more workers to certain 
utility tunnel activities, or both. However, this mitigation approach 
would increase the government's costs. We previously identified the 
utility tunnel as a project schedule and cost risk because of possible 
unforeseen conditions associated with underground work, and AOC and the 
sequence 2 contractor believe that such risk still exists with respect 
to the remaining tunnel work. Given this risk and the importance to the 
rest of the project of having the utility tunnel operational as soon as 
possible, AOC has asked the project team to explore options for 
accelerating the completion of the work necessary to begin the tunnel's 
operations. We agree with AOC that delays in making this tunnel 
operational could have significant adverse effects on other project 
elements and that priority attention should be given to this area. 
Accelerating work may be cost-beneficial in this case.

Since the June 14 hearing, the sequence 2 contractor has also 
encountered unforeseen conditions that, according to AOC's construction 
management contractor, could delay the installation of stone on the 
Capitol's East Front. Unless mitigated, this delay, in turn, could 
delay AOC's estimated September 15, 2006, opening date. In fact, the 
June schedule shows a 24-day delay for this work, which is on the 
project's critical path, and therefore pushes AOC's scheduled date for 
opening CVC to the public to October 19, 2006. AOC and its construction 
management contractor are assessing the situation and expect to have 
more information on this problem within the next month. However, they 
believe that they will be able to recover the lost time by resequencing 
work, although they acknowledge that their mitigation approach would 
require sufficient stone to be available. The project has not been 
receiving stone in the quantities set forth in the delivery schedule-- 
a risk that we previously identified--and AOC and its contractors have 
been taking action to address this problem, but have not yet resolved 
it. Mitigating this potential delay in East Front stone installation 
could increase the government's costs if the mitigation involves, among 
other actions, expediting the installation to recover lost time.

Our May 17 and June 14 statements contained several observations on 
AOC's management of the project's schedules, including our view that 
problems in this area contributed to slippage in the project's 
scheduled completion date and additional project costs associated with 
delays. The statements also discussed recommendations we had already 
made to AOC to enhance its schedule management. AOC had agreed with 
these recommendations and had generally begun to implement them, but we 
believed that it still needed to give priority attention to them to 
keep the project on track and as close to budget as possible. An 
updated discussion follows of the issues that need AOC's priority 
attention, along with current information on the status of AOC's 
actions to address these issues.

* Having realistic time frames for completing work and obtaining fully 
acceptable schedules from contractors. Over the course of the project, 
AOC's schedules have shown dates for completing tasks that project 
personnel themselves considered optimistic or unlikely to be met. In 
addition, the master project schedule (prepared by AOC's construction 
management contractor) that AOC was using in May 2005 (the April 
schedule that AOC said it would use as a baseline for measuring 
progress on the project) did not tie all interrelated activities 
together and did not identify the resources to be applied for all the 
activities, as AOC's contract requires. During the Subcommittee's June 
14 hearing, AOC said that it would reassess the time scheduled for 
tasks by today's hearing. Since the Subcommittee's June 14 hearing, 
AOC's construction management and sequence 2 contractors reviewed the 
reasonableness of the time scheduled for 14 critical or near-critical 
activities and determined that, in general, the time shown in the May 
2005 schedule reasonably reflected the time required to perform 11 of 
these activities. In addition, the sequence 2 contractor agreed to 
provide more detail about the 3 remaining activities so that the 
reasonableness of the time scheduled for them could be reviewed later.

Although the contractors' review did not involve a detailed, data-based 
analysis of the time scheduled for activities using such information as 
crew size and worker productivity, AOC's construction management 
contractor said that it would do such analyses in the future, as 
appropriate. The construction management contractor said it has not yet 
done such an analysis for stonework because, to date, less stone has 
been delivered to the site than was expected and more stone workers 
have been available than could be used, given the shortage of stone. In 
AOC's view, this stone shortage has begun to delay important 
activities, and as we previously indicated, AOC is working with its 
contractors to resolve the problem.

According to AOC's construction management contractor, both the 
project's May and June 2005 master schedules (1) reflect significant 
improvement in the linkage of interrelated tasks, although the 
contractor recognizes that more work needs to be done in this area and 
(2) generally provide sufficient information to manage the project's 
resources. However, the contractor also recognizes the need for the 
sequence 2 and other contractors to continue adding more detail to the 
activities scheduled for some project elements, such as the exhibit and 
expansion spaces, so that more of the interrelated activities will be 
linked in the schedule. The contractor also said that it will be 
continuously reassessing the extent to which construction contractors 
identify the resources they plan to apply to meet scheduled completion 
dates, as contractually required. Both adding detail to activities and 
identifying the resources to be applied are helpful in assessing the 
reasonableness of the time scheduled and in managing contractors' 
performance. The sequence 2 contractor has provided a separate schedule 
showing its target dates for adding more detail to 30 project tasks. On 
July 8, AOC's construction management contractor accepted the April 
project schedule, subject to several conditions.

Because the May 2005 master schedule for the CVC project contains 
additional detail on activities and information on resources to be 
applied, we agree with AOC's construction management contractor that 
this schedule represents an improvement over earlier schedules. 
However, we still have concerns about the extent to which the schedule 
links related activities, which the construction management contractor 
has agreed to address, and about whether AOC's September 15, 2006, 
target date for opening the facility to the public is realistic. For 
the following reasons, we continue to believe that the project is more 
likely to be substantially completed in the December 2006 to March 2007 
time frame than by September 2006:

* Because of unforeseen site conditions and other problems, AOC's 
construction contractors have had difficulty meeting a number of 
milestones. The project still faces risks and uncertainties that could 
adversely affect its schedule. As we noted in our June 14 testimony, 
the number of critical and near-critical paths the construction 
management contractor has identified complicates schedule management 
and increases the risk of problems that could lead AOC to miss the 
scheduled completion date. Like the project's May 2005 schedule, the 
June schedule shows seven paths that are critical or near critical. 
Among the critical paths are East Front stonework and some interior 
stonework, which slipped by 24 days and 3 days in June, respectively. 
In addition, some other interior stonework that is not generally on a 
critical path, such as the installation of wall stone in the Great 
Hall, has slipped by about 4 months since April because of stone 
shortages according to AOC. Continued slippages in interior stonework 
could make it difficult for the sequence 2 contractor to meet the 
September 15, 2006, completion date. Although the CVC project team 
believes that it can recover this time, its ability to do so is not yet 
clear, given the stone supply problem facing the project. Furthermore, 
although work on the utility tunnel progressed during June, the tunnel 
work continues to face risks and uncertainties that could delay the 
project, and the May and June schedules show that the start and finish 
dates for a number of activities have continued to slip. Although it is 
possible for AOC to recover this time, continued slippage could push so 
many activities to later dates that the contractors may not be able to 
complete all the work in the remaining available time.

* In our opinion, AOC lacks reasonable assurance that its contractors 
have accurately estimated the time necessary to complete work for a 
number of activities in the schedule. Although the construction 
management contractor's recent review of how much time is needed to 
complete schedule activities was helpful, we are still concerned about 
the reasonableness of the time allowed for a number of the activities. 
For example, one of the activities reviewed in June whose scheduled 
duration was found to be generally reasonable was final occupancy 
inspections. Although AOC's Fire Marshal Division is to do critical 
work associated with this activity, the duration review that took place 
since the June 14 hearing occurred without any input from that 
division, which is to conduct fire safety and occupancy inspections for 
the project and approve its opening to the public. The Chief Fire 
Marshal told us that although coordination has improved between his 
office and the CVC project team, he has not always had an opportunity 
to review project documentation early in the process and has not yet 
received the project schedule. As a result, he was uncertain whether 
the schedule provided enough time for his office to do its work. For 
example, as of July 8, he had not yet received documentation for the 
fire protection systems, which his office needs to examine before it 
can observe tests of these systems as the CVC team has already 
requested. The Fire Marshal Division will also be involved in fire 
alarm testing; the construction management contractor plans to assess 
the duration of this activity later after more detail is added to the 
schedule. In addition, at the time the construction management 
contractor performed its duration reassessment of East Front stonework, 
the project was experiencing difficulty getting stone deliveries on 
time. It is unclear to us how the duration of the stonework could have 
been determined to be reasonable given this problem and the lack of a 
clear resolution at the time.

* The May 2005 schedule includes a number of base project activities 
that could be completed after September 15, 2006, even though their 
completion would seem to be important for CVC to be open to the public. 
Such activities include installing security systems, kitchen equipment, 
and theater seating. According to the schedule, the late finish dates 
for these activities are after September 15. The late finish date is 
the latest date that an activity can be completed without delaying the 
scheduled completion date for the entire project. According to the 
construction management contractor, a number of activities in the 
schedule that are important to CVC's opening were not linked to the 
September 15 opening date in the schedule. The contractor agreed to 
address this issue.

* Last week, we began to update our risk assessment of the project's 
schedule and plan to have this update completed in September. AOC has 
also engaged a consultant to perform a risk assessment of the project's 
schedule and expects the assessment to be done by mid-September. We 
believe that better information on the likelihood of AOC's meeting its 
September 15, 2006, opening date will be available after our update and 
AOC's schedule risk assessment are done.

* Aggressively monitoring and managing contractors' adherence to the 
schedule, including documenting and addressing the causes of delays, 
and reporting accurately to Congress on the status of the project's 
schedule. We noted in our May 17 testimony that neither AOC nor its 
construction management contractor had previously (1) adhered to 
contract provisions calling for monthly progress review meetings and 
schedule updates and revisions, (2) systematically tracked and 
documented delays and their causes as they occurred or apportioned 
their time and costs to the appropriate parties on an ongoing basis, 
and (3) always accurately reported on the status of the project's 
schedule. On June 7 and July 8, AOC, its construction management 
contractor, the sequence 2 contractor, and AOC's schedule consultant 
conducted the first and second monthly reviews of the schedule's status 
using a newly developed approach that we discussed during the 
Subcommittee's June 14 hearing. Additionally, on June 28, we met with 
AOC and its construction management contractor to discuss how delays 
are to be analyzed and documented in conjunction with the new approach 
to schedule management. During that meeting, AOC's construction 
management contractor agreed to have its field supervisors document 
delays and their causes on an ongoing basis and its project control 
engineer summarize this information for discussion at the monthly 
schedule reviews. After assessing the new approach and observing the 
first two review sessions, we believe that, if effectively implemented 
and sustained, this approach should generally resolve the schedule 
management concerns we previously raised, including how delays will 
regularly be handled and how better information on the status of the 
project will be provided to Congress. As we indicated on June 14, we 
are encouraged by the construction management contractor's addition of 
a full-time project control engineer to the project and have seen 
noteworthy improvements in schedule management since his arrival. 
Nevertheless, we plan to closely monitor the implementation of this new 
approach, including the resources devoted to it, the handling of 
delays, and the accuracy of the information provided to Congress.

* Developing and implementing risk mitigation plans. While monitoring 
the CVC project, we have identified a number of risks and uncertainties 
that could have significant adverse effects on the project's schedule 
and costs. Some of these risks, such as underground obstructions and 
unforeseen conditions, have already materialized and have had the 
anticipated adverse effects. We believe the project continues to face 
risks and uncertainties, such as unforeseen conditions associated with 
the project's remaining tunnels, the East Front, and other work; scope 
gaps or other problems associated with the segmentation of the project 
between two major contractors; and shortages in the supply of stone and 
skilled stone workers. As discussed during the Subcommittee's June 14 
hearing, AOC has not yet implemented our recommendations that it 
develop risk mitigation plans for these types of risks and 
uncertainties, but it has agreed to do so by mid-September. On July 1, 
AOC added assistance in risk mitigation to the scope of its contract 
with its schedule consultant.

* Preparing a master schedule that integrates the major steps needed to 
complete CVC construction and the steps necessary to prepare for 
operations. A number of activities, such as obtaining operators' input 
into the final layouts of retail and food service areas, hiring and 
training staff, procuring supplies and services, and developing 
policies and procedures, need to be planned and carried out on time for 
CVC to open to the public when construction is complete. Although AOC 
has started to plan and prepare for CVC operations, as we indicated in 
our May 17 and June 14 testimonies, it has not yet developed a schedule 
that integrates the construction activities with the activities that 
are necessary to prepare for operations. The Subcommittee requested 
such a schedule during its April 13, 2005, hearing on AOC's fiscal year 
2006 budget request. Because it lacked funds, AOC had not been able to 
extend the work of a contractor that had been helping it plan and 
prepare for operations. During the week of June 6, AOC received 
authority to spend the funds needed to re-engage this contractor, and 
on June 30, AOC awarded a contract for the continued planning and 
preparation for CVC operations. Now that AOC has re-engaged its 
operations planning contractor, we believe that close coordination 
between AOC staff working with this contractor and the CVC project's 
construction team will be especially important for at least two 
reasons. First, the operations planning contractor's scope of work 
includes both the design of certain space within the CVC project and 
the wayfinding signs that are to be used within the project, and the 
timing and content of this work needs to be coordinated with CVC 
construction work. Second, about $7.8 million[Footnote 3] is available 
for either CVC construction or operations, and it will be important for 
AOC to balance the need for both types of funding to ensure optimal use 
of the funds. Moreover, it is not clear to us who in AOC will be 
specifically responsible for integrating the construction and 
operations schedules and for overseeing the use of the funds that are 
available for either construction or operations.

Project Costs and Funding:

As we said during the Subcommittee's May 17 and June 14 hearings, we 
estimate that the cost to complete the construction of the CVC project, 
including proposed revisions to its scope, will range from about $522 
million without provision for risks and uncertainties to about $559 
million with provision for risks and uncertainties. As of July 11, 
2005, about $483.7 million had been provided for CVC 
construction.[Footnote 4] In its fiscal year 2006 budget request, AOC 
asked Congress for an additional $36.9 million for CVC construction. 
AOC believes this amount will be sufficient to complete construction 
and, if approved, will bring the total funding provided for the 
project's construction to $520.6 million. Adding $1.7 million to this 
amount for additional work related to the air filtration system that we 
believe will likely be necessary brings the total funding needed to 
slightly more than the previously cited $522 million. AOC believes that 
it could obtain this $1.7 million, if needed, from the Department of 
Defense, which provided the other funding for the air filtration 
system. AOC's $36.9 million budget request includes $4.2 million for 
potential additions to the project's scope (e.g., congressional seals, 
an orientation film, and storage space for backpacks) that Congress 
will have to consider when deciding on AOC's fiscal year 2006 CVC 
budget request.

AOC has not asked Congress for an additional $37 million (the 
difference between $559 million and $522 million) that we believe will 
likely be needed to address the risks and uncertainties that continue 
to face the project. These include, but are not limited to, shortages 
in the supply of stone, unforeseen conditions, scope gaps, further 
delays, possible additional requirements or time needed because of life 
safety or security changes or commissioning, unknown operator 
requirements, and contractor coordination issues. These types of 
problems have been occurring, and as of June 30, 2005, AOC had received 
proposed sequence 2 change orders whose costs AOC now estimates exceed 
the funding available in fiscal year 2005 for sequence 2 changes by 
about $1.3 million. AOC's estimate of these change order costs has 
grown by about $900,000 during the past 4 weeks.[Footnote 5] AOC plans 
to cover part of this potential shortfall by requesting approval from 
the House and Senate Committees on Appropriations to reprogram funds 
that AOC does not believe will be needed for other project elements. At 
this time, AOC does not believe that it will need additional funds in 
fiscal year 2005, assuming it receives reprogramming authority for 
sequence 2 changes, unless it reaches agreement with the sequence 2 
contractor on the costs associated with 10 months' worth of delays that 
have already occurred. If AOC needs funds for this purpose or for other 
reasons, it can request approval from the Appropriations Committees to 
use part of the $10.6 million that Congress approved for transfer to 
the CVC project from funds appropriated for Capitol Buildings 
operations and maintenance.[Footnote 6]

For several reasons, we believe that AOC may need additional funds for 
CVC construction in the next several months. These reasons include the 
pace at which AOC is receiving change order proposals for sequence 2 
work, the problems AOC has encountered and is likely to encounter in 
finishing the project, the uncertainties associated with how much AOC 
may have to pay for sequence 2 delays, and uncertainty as to when AOC 
will have fiscal year 2006 funds available to it. For example, AOC is 
likely to incur additional costs for dehumidification or for additional 
workers to mitigate the expected delay in the utility tunnel. AOC may 
also incur more costs than it expects for certain activities, such as 
those necessary to support security during the remainder of the 
project's construction. AOC may be able to meet these needs as well as 
the other already identified needs by obtaining approval to use some of 
the previously discussed $10.6 million and by additional reprogramming 
of funds.[Footnote 7] However, these funds may not be sufficient to 
address the risks and uncertainties that may materialize from later 
this fiscal year through fiscal year 2007. Thus, while AOC may not need 
all of the $37 million we have suggested be allowed for risks and 
uncertainties, we believe that, to complete the construction of CVC's 
currently approved scope, AOC is likely to need more funds in fiscal 
years 2006 and 2007 than it has already received and has requested. 
Although the exact amount and timing of AOC's needs are not clear, we 
believe that between $5 million and $15 million of this $37 million may 
be required in fiscal year 2006. Effective implementation of our 
recommendations, including risk mitigation, could reduce AOC's funding 
needs.

Since the Subcommittee's June 14 hearing, three issues related to the 
project's costs have emerged that we believe should be brought to your 
attention. Discussion of these issues follows.

* First, coordination within the CVC project team and between the team 
and AOC's Fire Marshal Division has been an issue, especially with 
respect to the project's fire protection systems. Although the CVC 
project team established biweekly meetings with Fire Marshal Division 
staff in March 2005 to enhance coordination, gaps in coordination have, 
as discussed, already led to uncertainty about whether enough time has 
been scheduled for fire alarm testing and for building occupancy 
inspections. Such gaps have also increased the costs associated with 
the fire protection system. For example, AOC recently took contractual 
action costing over $90,000 to redesign the mechanical system for the 
Jefferson Building connection to the Library of Congress tunnel to meet 
the Fire Marshal Division's fire safety requirements. According to the 
Chief Fire Marshal, he was not given the opportunity to participate in 
the planning process before the design of the Jefferson Building 
connection was substantially completed. In addition, several fire- 
safety-related contract modifications and proposed change orders for 
additional work now total over $3.5 million. With better coordination 
between the CVC project team and the Fire Marshal Division, the need 
for some of this work might have been avoided or identified sooner, and 
had this work been identified during the original competition, the 
price would have been subject to competitive pressures that might have 
resulted in lower costs. Because of the fire protection system's 
increasing costs, disagreements within the CVC team and between the 
team and the Fire Marshal Division over fire safety requirements, 
problems in scheduling fire safety activities, and other related 
issues, we suggested that AOC take appropriate steps to address the 
coordination of fire protection activities related to the CVC project. 
AOC agreed and has taken action. For example, starting this week, AOC's 
Fire Marshal Division agreed to have a staff member work at the CVC 
site 2 days a week, and AOC CVC staff recently agreed to provide the 
necessary documentation to the Fire Marshal Division before its 
inspections or observations were needed.

* Second, as we indicated earlier in our testimony, we are concerned 
about the integration of planning, scheduling, and budgeting for CVC 
construction and operations. While the CVC project team has been 
overseeing CVC construction, other AOC staff have been assisting the 
operations planning contractor in planning and budgeting for CVC 
operations. Close coordination between the two groups will be 
especially important in the next few months, when decisions will likely 
have to be made on how to use the $7.8 million remaining from the $10.6 
million that Congress made available to the CVC project for either 
operations or construction. The Architect of the Capitol agreed to give 
this issue priority attention.

* Finally, we are concerned that AOC may incur additional costs for 
interim measures, such as temporary walls that it may have to construct 
to open CVC to the public in September 2006. Such interim measures may 
be needed to make the project safe for visitors if some other 
construction work has not been completed. For example, AOC may have to 
do additional work to ensure adequate fire protection for CVC, since 
the House and Senate expansion spaces are not scheduled to be done 
until March 2007. In addition, AOC may have to accelerate some work to 
have it completed by September 15, 2006. While it is not necessarily 
unusual to use a facility for its intended purpose before all 
construction work is complete, we believe that it will be important for 
Congress to know what additional costs AOC expects to incur to open CVC 
by September 15, 2006, so that Congress can weigh the costs and 
benefits of opening the facility then rather than at a later date, such 
as March 2007, when AOC plans to complete the House and Senate 
expansion spaces.

Recommendations for Executive Action:

To ensure that (1) Congress has sufficient information for deciding 
when to open CVC to the public and (2) planning and budgeting for CVC 
construction and operations are appropriately integrated, we recommend 
that the Architect of the Capitol take the following two actions:

* In consultation with other appropriate congressional organizations, 
provide Congress with an estimate of the additional costs that it 
expects will be incurred to open CVC to the public by September 15, 
2006, rather than later, such as after the completion of the House and 
Senate expansion spaces.

* Promptly designate who is responsible for integrating planning and 
budgeting for CVC construction and operations and give this activity 
priority attention.

Agency Comments:

AOC agreed to take the actions we are recommending. According to AOC, 
information on the estimated costs of the additional work necessary to 
open CVC to the public in September 2006 may not be available until 
this fall. In addition, AOC said that the recent re-engagement of the 
contractor assisting AOC in planning for CVC operations and the hiring 
of an executive director for CVC, which AOC plans to do in the next few 
months, are critical steps for integrating CVC construction and 
operations.

Mr. Chairman, this completes our prepared statement. We would be happy 
to answer any questions that you or other Subcommittee Members may have.

Contacts and Acknowledgments:

For further information about this testimony, please contact Bernard 
Ungar at (202) 512-4232 or Terrell Dorn at (202) 512-6923. Other key 
contributors to this testimony include Shirley Abel, Maria Edelstein, 
Elizabeth Eisenstadt, Brett Fallavollita, Jeanette Franzel, Jackie 
Hamilton, Bradley James, Scott Riback, and Kris Trueblood.

[End of section]

Appendix I: Capitol Visitor Center Critical Construction Milestones, 
May 2005-July 2005:

Activity: Wall Stone Area 1; 
Location: Great Hall[A,B]; 
Scheduled completion: 5/11/05; 
Actual completion: 6/06/05.

Scheduled for completion between 5/17/05 and 6/14/05: 

Activity: Wall Stone Area 3 Base Support; 
Location: Great Hall[A]; 
Scheduled completion: 5/20/05; 
Actual completion: 5/20/05.

Activity: Wall Stone Layout Area 4; 
Location: Great Hall; 
Scheduled completion: 5/20/05; 
Actual completion: 6/06/05.

Activity: Saw Cut Road at 1st Street; 
Location: Utility Tunnel[A]; 
Scheduled completion: 5/24/05; 
Actual completion: 6/27/05.

Activity: Wall Stone Area 4 Base Support; 
Location: Great Hall[A]; 
Scheduled completion: 5/27/05; 
Actual completion: 6/15/05.

Activity: Wall Stone Layout Area 5; 
Location: Great Hall; 
Scheduled completion: 5/27/05; 
Actual completion: 5/27/05.

Activity: Masonry Wall Lower Level East; 
Location: Cong. Auditorium; 
Scheduled completion: 6/03/05; 
Actual completion: 5/25/05.

Activity: Wall Stone Area 5 Base Support; 
Location: Great Hall[A]; 
Scheduled completion: 6/06/05; 
Actual completion: 6/09/05.

Activity: Wall Stone Layout Area 6; 
Location: Great Hall; 
Scheduled completion: 6/06/05; 
Actual completion: 6/15/05.

Activity: Drill/Set Soldier Piles at 1st Street; 
Location: Utility Tunnel[A]; 
Scheduled completion: 6/08/05.

Activity: Wall Stone Area 6 Base Support; 
Location: Great Hall[A]; 
Scheduled completion: 6/13/05; 
Actual completion: 6/17/05.

Scheduled for completion between 6/15/05 and 7/31/05: 

Activity: Wall Stone Layout Area 8; 
Location: Great Hall; 
Scheduled completion: 6/20/05.

Activity: Masonry Wall; 
Location: Orientation Theater; 
Scheduled completion: 6/24/05; 
Actual completion: 6/28/05.

Activity: Wall Stone Layout Area 9; 
Location: Great Hall; 
Scheduled completion: 6/24/05.

Activity: Wall Stone Area 9 Base Support; 
Location: Great Hall[A]; 
Scheduled completion: 7/05/05.

Activity: Wall Stone Installation Area 2; 
Location: Great Hall; 
Scheduled completion: 7/06/05.

Activity: Wall Stone Installation Area 3; 
Location: Great Hall; 
Scheduled completion: 7/06/05.

Activity: Wall Stone Installation Area 4; 
Location: Great Hall; 
Scheduled completion: 7/15/05.

Activity: Wall Stone Area 9 Base; 
Location: Great Hall[A]; 
Scheduled completion: 7/15/05.

Activity: Excavate/shore Station 0-1; 
Location: Utility Tunnel[A]; 
Scheduled completion: 7/21/05.

Activity: Concrete Working Slab 1st Street; 
Location: Utility Tunnel[A]; 
Scheduled completion: 7/26/05.

Activity: Waterproof Working Slab Station 0-1; 
Location: Utility Tunnel[A]; 
Scheduled completion: 7/29/05.

Source: AOC's April 2005 CVC sequence 2 construction schedule for the 
scheduled completion dates and AOC and its construction management 
contractor for the actual completion dates.

Note: Actual completion information was obtained on July 12.

[A] These activities are critical.

[B] This activity was scheduled for completion by the Subcommittee's 
May 17 hearing but was not done as of that date.

[End of table]

FOOTNOTES

[1] GAO, Capitol Visitor Center: Effective Schedule Management and 
Updated Cost Information Are Needed, GAO-05-811T (Washington, D.C.: 
June 14, 2005). See also GAO, Capitol Visitor Center: Priority 
Attention Needed to Manage Schedules and Contracts, GAO-05-714T 
(Washington, D.C.: May 17, 2005).

[2] A critical path is a sequence of activities in a schedule that has 
the longest duration. There is no scheduling flexibility or slack time 
associated with the activities. This means that a delay in a critical 
path activity will delay the entire project unless a way is found to 
reduce the time required for other activities along the critical path. 
A schedule may have multiple critical paths simultaneously, and the 
critical path through a project can change as the project is updated 
and as the time estimated to complete the tasks changes. Currently, 
AOC's schedule shows CVC's critical path running through some interior 
wall stone and East Front stonework. The schedule also shows other work 
elements, such as the utility tunnel and millwork, as near critical 
(i.e., having little slack time).

[3] See footnote 6.

[4] This amount does not include $700,000 made available by the Capitol 
Preservation Commission from the Capitol Preservation Fund for the 
design of the Library of Congress tunnel.

[5] In our May 17 testimony, we reported that AOC had about $700,000 
remaining in its fiscal year 2005 funding for sequence 2 changes after 
deducting the estimated costs for proposed changes it had received. As 
of June 1, the estimated costs for sequence 2 changes exceeded the 
amount available for such changes by about $400,000. Since then, 
another $900,000 in estimated costs for potential change orders has 
been identified. About two-thirds of the $900,000 increase in estimated 
costs for sequence 2 changes during June was for additional fire safety 
work.

[6] Public Law 108-447, enacted in December 2004, provided that up to 
$10.6 million could be so transferred upon the approval of the House 
and Senate Committees on Appropriations for the use of the CVC project. 
In March 2005, AOC requested that about $4 million of these funds be 
transferred to CVC, including some funds for such work as the design of 
the gift shop space and consultant services to transition the project 
from construction to operations. As of June 10, AOC had received 
approval to use about $2.8 million of this $10.6 million, leaving a 
balance of about $7.8 million that can be used in the future. None of 
the $10.6 million is included in the previously cited $483.7 million. 

[7] AOC has requested approval to reprogram about $1.6 million from 
sequence 1 construction and the East Front Interface to fund 
anticipated additional costs for the House connector tunnel, the 
Jefferson Building connection to the Library of Congress tunnel, and 
certain security-related work.