This is the accessible text file for GAO report number GAO-05-754T 
entitled 'Nuclear Regulatory Commission: Challenges Facing NRC in 
Effectively Carrying Out Its Mission' which was released on May 27, 
2005.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Testimony:

Before the Subcommittee on Clean Air, Climate Change, and Nuclear 
Safety, Committee on Environment and Public Works, U.S. Senate:

United States Government Accountability Office:

GAO:

For Release on Delivery Expected at 10:00 a.m. EDT:

Thursday, May 26, 2005:

Nuclear Regulatory Commission:

Challenges Facing NRC in Effectively Carrying Out Its Mission:

Statement of Jim Wells, Director, Natural Resources and Environment:

GAO-05-754T:

GAO Highlights:

Highlights of GAO-05-754T, a testimony before  the Subcommittee on 
Clean Air, Climate Change, and Nuclear Safety, Committee on Environment 
and Public Works, U.S. Senate: 

Why GAO Did This Study:

The Nuclear Regulatory Commission (NRC) has the regulatory 
responsibility to, among other things, ensure that the nation’s 103 
commercial nuclear power plants are operated in a safe and secure 
manner.  While the nuclear power industry’s overall safety record has 
been good, safety issues periodically arise that threaten the 
credibility of NRC’s regulation and oversight of the industry.  

Recent events make the importance of NRC’s regulatory and oversight 
responsibilities readily apparent.  The terrorist attacks on September 
11, 2001, focused attention on the security of facilities such as 
commercial nuclear power plants, while safety concerns were heightened 
by shutdown of the Davis-Besse nuclear power plant in Ohio in 2002, and 
the discovery of missing or unaccounted for spent nuclear fuel at three 
nuclear power plants.  

GAO has issued a total of 15 recent reports and testimonies on a wide 
range of NRC activities.  This testimony (1) summarizes GAO’s findings 
and associated recommendations for improving NRC mission-related 
activities and (2) presents several cross-cutting challenges NRC faces 
in being an effective and credible regulator of the nuclear power 
industry.  

What GAO Found:

GAO has documented many positive steps taken by NRC to advance the 
security and safety of the nation’s nuclear power plants.  It has also 
identified various actions that NRC needs to take to better carry out 
its mission.  First, with respect to its security mission, GAO found 
that NRC needs to improve security measures for sealed sources of 
radioactive materials --- radioactive material encapsulated in 
stainless steel or other metal used in medicine, industry, and 
research--which could be used to make a “dirty bomb.”  GAO also found 
that, although NRC was taking numerous actions to require nuclear power 
plants to enhance security, NRC needed to strengthen its oversight of 
security at the plants.  Second, with respect to its public health and 
safety, and environmental missions, GAO found that NRC needs to conduct 
more effective analyses of plant owners’ funding for decommissioning to 
ensure that the significant volume of radioactive waste remaining after 
the permanent closure of a plant are properly disposed.  Further, NRC 
needs to more aggressively and comprehensively resolve issues that led 
to the shutdown of the Davis-Besse nuclear power plant by improving its 
oversight of plant safety conditions.  Finally, NRC needs to do more to 
ensure that power plants are effectively controlling spent nuclear 
fuel, including developing and implementing appropriate inspection 
procedures.

GAO has identified several cross-cutting challenges affecting NRC’s 
ability to effectively and credibly regulate the nuclear power 
industry.  Recently, NRC has taken two overarching approaches to its 
regulatory and oversight responsibilities.  These approaches are to (1) 
develop and implement a risk-informed regulatory strategy that targets 
the most important safety-related activities and (2) strike a balance 
between verifying plants’ compliance with requirements through 
inspections and affording licensees the opportunity to demonstrate that 
they are operating their plants safety.  NRC must overcome significant 
obstacles to fully implement its risk-informed regulatory strategy 
across agency operations, especially with regards to developing the 
ability to identify emerging technical issues and adjust regulatory 
requirements before safety problems develop.  NRC also faces inherent 
challenges in achieving the appropriate balance between more direct 
oversight and industry self-compliance.  Incidents such as the 2002 
shutdown of the Davis-Besse plant and the unaccounted for spent nuclear 
fuel at several plants raise questions about whether NRC has the risk 
information that it needs and whether it is appropriately balancing 
agency involvement and licensee self-monitoring.  Finally, GAO believes 
that NRC will face challenges managing its resources while meeting 
increasing regulatory and oversight demands.  NRC’s resources have 
already been stretched by the extensive effort to enhance security at 
plants in the wake of the September 11, 2001, terrorist attacks.  
Pressure on NRC’s resources will continue as the nation’s fleet of 
plants age and the industry’s interest in expansion grows, both in 
licensing and constructing new plants, and re-licensing and increasing 
the power output of existing ones.  

www.gao.gov/cgi-bin/getrpt?GAO-05-754T.

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Jim Wells at (202) 512-
3841 or wellsj@gao.gov.

[End of section]

Mr. Chairman and Members of the Subcommittee:

I am pleased to be here today to participate in the Subcommittee's 
oversight hearing on the Nuclear Regulatory Commission (NRC). NRC has 
the regulatory responsibility to ensure that the nation's 103 operating 
commercial nuclear power plants are operated in a safe and secure 
manner. These plants provide about 20 percent of the country's 
electricity, but safety of their operations is paramount, given the 
potentially devastating effects of a nuclear accident. While the 
nuclear power industry's overall safety record has been good, safety 
issues periodically arise that raise questions about NRC's regulation 
and oversight of the industry and challenge its credibility for 
guaranteeing the safety of the nation's aging fleet of nuclear power 
plants. NRC plays an important role in protecting public health and the 
environment through its regulation of the nuclear power industry and 
other civilian use of nuclear material, and we commend the Subcommittee 
for holding this hearing.

NRC was formed in 1975, to regulate the various commercial and 
institutional uses of nuclear energy, including nuclear power plants. 
NRC's mission is to regulate the nation's civilian use of nuclear 
material to ensure adequate protection of public health and safety, to 
promote the common defense and security, and to protect the 
environment. NRC's activities include, among other things, licensing 
nuclear reactors (including license transfers and operating experience 
evaluation), reviewing plant safety procedures, imposing enforcement 
sanctions for violations of NRC requirements, and participating in 
homeland security efforts (including threat assessment, emergency 
response, mitigating strategies, security inspections, and force-on- 
force exercises). NRC also has regulatory oversight for the 
decommissioning of nuclear reactors, including accumulating sufficient 
funds to carry out decommissioning, and for the interim storage of 
spent nuclear fuel --the used fuel periodically removed from reactors 
in nuclear power plants.

The importance of NRC's regulatory and oversight responsibilities is 
made readily apparent by recent events. The terrorist attacks on 
September 11, 2001, and the subsequent discovery of nuclear power 
plants on a list of possible terrorist targets have focused attention 
on the security of the nation's commercial nuclear power plants. Safety 
concerns were heightened by the discovery of a pineapple-sized cavity 
in the carbon steel reactor vessel head, and subsequent 2-year 
shutdown, of the Davis-Besse nuclear power plant in Ohio in 2002. 
Additional safety concerns were raised by the discovery of missing or 
unaccounted for spent nuclear fuel at three nuclear power plants. 
Further, the decommissioning of some of the nations' aging nuclear 
power plants raises the issue of whether NRC is ensuring that plant 
owners are accumulating sufficient funds for decommissioning plants in 
a way that best protects public health, safety, and the environment.

Over the past 2 years, we have issued a total of 15 reports and 
testimonies on a wide range of NRC activities. (These reports are 
listed in Appendix I). While our work has primarily focused on 
identifying ways that NRC can strengthen its regulation and oversight 
of the nuclear power industry, we have documented a number of 
productive steps NRC has taken to improve its mission-related 
activities. One example is the substantial effort that NRC has made in 
working with the industry to enhance security at nuclear power plants 
since the September 11, 2001, terrorist attacks. Another example is 
NRC's considerable effort to analyze what went wrong at the Davis-Besse 
plant in 2002, and to incorporate the lessons learned into its 
processes. Today, my testimony will briefly summarize our recently 
completed NRC work. Specifically, this testimony (1) summarizes GAO's 
findings and associated recommendations for improving NRC mission- 
related activities and (2) provides some observations on cross-cutting 
challenges that NRC faces in being an effective and credible regulator 
of the nuclear power industry.

This testimony is based on seven of our recently issued reports. The 
other eight reports either address issues for which NRC is not the 
primary federal agency - such as radioactive waste disposal and nuclear 
nonproliferation --or concern internal NRC administrative matters -- 
such as fee recovery and information technology management. We did not 
perform additional audit work in preparing this testimony. The work for 
our previously issued reports was conducted in accordance with 
generally accepted government auditing standards.

Summary:

While NRC has improved its operations in a number of ways in recent 
years, GAO believes that the agency needs to take a number of 
additional actions to better fulfill its mission of ensuring that the 
nation's nuclear power plants and other civilian users of nuclear 
material operate in a safe and secure manner. First, operations related 
to NRC's security mission need to be improved. Specifically, we found 
that NRC has not developed adequate security measures for sealed 
sources of radioactive materials ---radioactive material encapsulated 
in stainless steel or other metal used in medicine, industry, and 
research ---which could be used to make a "dirty bomb." We also found 
that despite taking numerous actions to respond to the heightened risks 
of a terrorist attack, NRC's oversight of physical security at the 
nation's commercial nuclear power plants could be strengthened. Second, 
operations related to NRC's public health and safety, and environmental 
missions need to be improved. Specifically, we found that NRC's 
analyses of plant owners' contributions of funds for the 
decommissioning of nuclear power plants, and its processes for acting 
on reports that show insufficient funds, do not ensure that the 
significant radioactive waste hazards that exist following the 
permanent closure of a nuclear power plant will be properly addressed. 
Further, we found that the issues surrounding the shutdown of the Davis-
Besse power plant reveal important weaknesses in NRC's oversight of the 
safety of nuclear power plant operations. Finally, we found that NRC 
has not taken adequate steps to ensure that power plants are 
effectively controlling spent nuclear fuel, including developing and 
implementing appropriate inspection procedures to verify plants' 
compliance with NRC requirements.

NRC faces several cross-cutting challenges in being an effective and 
credible regulator of the nuclear power industry. In response to the 
agency's limited resources and its desire to reduce the regulatory 
burden and cost on plants, NRC is taking two overarching approaches to 
meeting its regulatory and oversight responsibilities: (1) developing 
and implementing a risk-informed regulatory strategy that targets 
industry's most important safety-related or safety-significant 
activities, and (2) striking a balance between verifying plants' 
compliance with requirements through inspections and affording 
licensees the opportunity to demonstrate that they are operating their 
plants safely. We believe that NRC must overcome significant obstacles 
in implementing its risk-informed regulatory strategy across the 
agency, especially with regards to developing the ability to identify 
emerging technical issues and adjust regulatory requirements before 
safety problems develop. We also believe that NRC faces inherent 
challenges in balancing oversight and industry self-compliance, 
especially with regards to positioning the agency so it is able to 
identify diminishing performance at individual plants before they 
become a problem. Incidents such as the 2002 shutdown of the Davis- 
Besse plant and the unaccounted for spent nuclear fuel at several 
plants raise questions about whether NRC has the risk information that 
it needs and whether it is appropriately balancing agency involvement 
and licensee self-monitoring. Finally, we believe that NRC will face 
challenges managing its resources while meeting increasing regulatory 
and oversight demands. NRC's resources have already been stretched by 
the extensive effort to enhance security at plants in the wake of the 
September 11, 2001, terrorist attacks. Pressure on NRC's resources will 
continue as the nation's fleet of plants age and the industry's 
interest in expansion grows, both in licensing and constructing new 
plants, and re-licensing and increasing the power output of existing 
ones.

Regulatory and Oversight Functions Vital to NRC's Mission Need to be 
Improved:

Our recent analyses of NRC programs identified several areas where NRC 
needs to take action to better fulfill its mission and made associated 
recommendations for improvement. With respect to NRC's security 
mission, we found that the security of sealed radioactive sources and 
the physical security at nuclear power plants need to be strengthened. 
With respect to its public health and safety, and environmental 
missions, we found several shortcomings that need to be addressed. 
NRC's analyses of plant owners' contributions could be improved to 
better ensure that adequate funds are accumulating for the 
decommissioning of nuclear power plants. By contrast, we found that NRC 
is ensuring that requirements for liability insurance for nuclear power 
plants owned by limited liability companies are being met. Further, to 
ensure the safety of nuclear power plants NRC must more aggressively 
and comprehensively resolve oversight issues related to the shutdown of 
the Davis-Besse plant. Finally, NRC's methods of ensuring that power 
plants are effectively controlling spent nuclear fuel need to be 
improved.

Operations Related to NRC's Security Mission Could Be Improved:

In August 2003, we reported on federal and state actions needed to 
improve security of sealed radioactive sources.[Footnote 1] Sealed 
radioactive sources, radioactive material encapsulated in stainless 
steel or other metal, are used worldwide in medicine, industry, and 
research. These sealed sources could be a threat to national security 
because terrorists could use them to make "dirty bombs." We were asked 
among other things to determine the number of sealed sources in the 
United States. We found that the number of sealed sources in use today 
in the United States is unknown primarily because no state or federal 
agency tracks individual sealed sources. Instead, NRC and the agreement 
states[Footnote 2] track numbers of specific licensees. NRC and the 
Department of Energy (DOE) have begun to examine options for developing 
a national tracking system, but to date, this effort has had limited 
involvement by the agreement states. NRC had difficulty locating owners 
of certain generally licensed devices it began tracking in April 2001, 
and has hired a private investigation firm to help locate them. Twenty- 
five of the 31 agreement states that responded to our survey indicated 
that they track some or all general licensees or generally licensed 
devices, and 17 were able to provide data on the number of generally 
licensed devices in their jurisdictions, totaling approximately 17,000 
devices. GAO recommended that NRC (1) collaborate with states to 
determine the availability of the highest risk sealed sources, (2) 
determine if owners of certain devices should apply for licenses, (3) 
modify NRC's licensing process so sealed sources cannot be purchased 
until NRC verifies their intended use, (4) ensure that NRC's evaluation 
of federal and state programs assesses the security of sealed sources, 
and (5) determine how states can participate in implementing additional 
security measures. NRC disagreed with some of our findings.

In September 2003, we reported that NRC's oversight of security at 
commercial nuclear power plants needed to be strengthened.[Footnote 3] 
The September 11, 2001, terrorist attacks intensified the nation's 
focus on national preparedness and homeland security. Among possible 
terrorist targets are the nation's nuclear power plants which contain 
radioactive fuel and waste. NRC oversees plant security through an 
inspection program designed to verify the plants' compliance with 
security requirements. As part of that program, NRC conducted annual 
security inspections of plants and force-on-force exercises to test 
plant security against a simulated terrorist attack. GAO was asked to 
review (1) the effectiveness of NRC's security inspection program and 
(2) legal challenges affecting power plant security. At the time of our 
review, NRC was reevaluating its inspection program. We did not assess 
the adequacy of security at the individual plants; rather, our focus 
was on NRC's oversight and regulation of plant security.

We found that NRC had taken numerous actions to respond to the 
heightened risk of terrorist attack, including interacting with the 
Department of Homeland Security and issuing orders designed to increase 
security and improve defensive barriers at plants. However, three 
aspects of NRC's security inspection program reduced the agency's 
effectiveness in overseeing security at commercial nuclear power 
plants. First, NRC inspectors often used a process that minimized the 
significance of security problems found in annual inspections by 
classifying them as "non-cited violations" if the problem had not been 
identified frequently in the past or if the problem had no direct, 
immediate, adverse consequences at the time it was identified. Non- 
cited violations do not require a written response from the licensee 
and do not require NRC inspectors to verify that the problem has been 
corrected. For example, guards at one plant failed to physically search 
several individuals for metal objects after a walk-through detector and 
a hand-held scanner detected metal objects in their clothing. These 
individuals were then allowed unescorted access throughout the plant's 
protected area. By extensively using non-cited violations for serious 
problems, NRC may overstate the level of security at a power plant and 
reduce the likelihood that needed improvements are made. Second, NRC 
did not have a routine, centralized process for collecting, analyzing, 
and disseminating security inspections data to identify problems that 
may be common to plants or to provide lessons learned in resolving 
security problems. Such a mechanism may help plants improve their 
security. Third, although NRC's force-on-force exercises can 
demonstrate how well a nuclear plant might defend against a real-life 
threat, several weaknesses in how NRC conducted these exercises limited 
their usefulness. Weaknesses included (1) using more personnel to 
defend the plant during these exercises than during normal operations, 
(2) using attacking forces that are not trained in terrorist tactics, 
and (3) using unrealistic weapons (rubber guns) that do not simulate 
actual gunfire. Furthermore, at the time, NRC has made only limited use 
of some available improvements that would make force-on-force exercises 
more realistic and provide a more useful learning experience.

Finally, we also found that even if NRC strengthens its inspection 
program, commercial nuclear power plants face legal challenges in 
ensuring plant security. First, federal law generally prohibits guards 
at these plants from using automatic weapons, although terrorists are 
likely to have them. As a result, guards at commercial nuclear power 
plants could be at a disadvantage in firepower, if attacked. Second, 
state laws regarding the permissible use of deadly force and the 
authority to arrest and detain intruders vary, and guards were unsure 
about the extent of their authorities and may hesitate or fail to act 
if the plant is attacked. GAO made recommendations to promptly restore 
annual security inspections and revise force-on-force exercises. NRC 
disagreed with many of GAO's findings, but did not comment on GAO's 
recommendations.

In September 2004, we testified on our preliminary observations 
regarding NRC's efforts to improve security at nuclear power 
plants.[Footnote 4] The events of September 11, 2001, and the 
subsequent discovery of commercial nuclear power plants on a list of 
possible terrorist targets have focused considerable attention on 
plants' capabilities to defend against a terrorist attack. NRC is 
responsible for regulating and overseeing security at commercial 
nuclear power plants. We were asked to review (1) NRC's efforts since 
September 11, 2001, to improve security at nuclear power plants, 
including actions NRC had taken to implement some of GAO's September 
2003 recommendations to improve security oversight, and (2) the extent 
to which NRC is in a position to assure itself and the public that the 
plants are protected against terrorist attacks. The testimony reflected 
the preliminary results of GAO's review. We are currently performing a 
more comprehensive review in which we are examining (1) NRC's 
development of its 2003 design basis threat (DBT), which establishes 
the maximum terrorist threat that commercial nuclear power plants must 
defend against, and (2) the security enhancements that plants have put 
in place in response to the design basis threat and related NRC 
requirements. We expect to issue a report on our findings later this 
year.

In the earlier work, we found that NRC responded quickly and decisively 
to the September 11, 2001, terrorist attacks with multiple steps to 
enhance security at commercial nuclear power plants. NRC immediately 
advised plants to go to the highest level of security using the system 
in place at the time, and issued advisories and orders for plants to 
make certain enhancements, such as installing more physical barriers 
and augmenting security forces, which could be quickly completed to 
shore up security. According to NRC officials, their inspections found 
that plants complied with these advisories and orders. Later, in April 
2003, NRC issued a new DBT and required the plants to develop and 
implement new security plans to address the new threat by October 2004. 
NRC is also improving its force-on-force exercises, as GAO recommended 
in its September 2003 report. While its efforts had enhanced security, 
NRC was not yet in a position to provide an independent determination 
that each plant has taken reasonable and appropriate steps to protect 
against the new DBT. According to NRC officials, the facilities' new 
security plans were on schedule to be implemented by October 2004. 
However, NRC's review of the plans, which are not available to the 
general public for security reasons, had primarily been a paper review 
and was not detailed enough for NRC to determine if the plans would 
protect the facility against the threat presented in the DBT. In 
addition, NRC officials generally were not visiting the facilities to 
obtain site-specific information and assess the plans in terms of each 
facility's design. NRC is largely relying on the force-on-force 
exercises it conducts to test the plans, but these exercises will not 
be conducted at all facilities for 3 years. We also found that NRC did 
not plan to make some improvements in its inspection program that GAO 
previously recommended. For example, NRC was not following up to verify 
that all violations of security requirements had been corrected, nor 
was the agency taking steps to make "lessons learned" from inspections 
available to other NRC regional offices and nuclear power plants.

Operations Related to NRC's Public Health and Safety and Environmental 
Missions Can Be Improved:

In October 2003, we reported that NRC needs to more effectively analyze 
whether nuclear power plant owners are adequately accumulating funds 
for decommissioning plants.[Footnote 5] Following the closure of a 
nuclear power plant, a significant radioactive waste hazard remains 
until the waste is removed and the plant site is decommissioned. In 
1988, NRC began requiring owners to (1) certify that sufficient 
financial resources would be available when needed to decommission 
their nuclear power plants and (2) require them to make specific 
financial provisions for decommissioning. In 1999, GAO reported that 
the combined value of the owners' decommissioning funds was 
insufficient to ensure enough funds would be available for 
decommissioning. GAO was asked to update its 1999 report, and to 
evaluate NRC's analysis of the owners' funds and the agency's process 
for acting on reports that show insufficient funds.

We found that although the collective status of the owners' 
decommissioning fund accounts has improved considerably since GAO's 
last report, some individual owners were not on track to accumulate 
sufficient funds for decommissioning. Based on our analysis and using 
the most likely economic assumptions, we concluded that the combined 
value of nuclear power plant owners' decommissioning fund accounts in 
2000--about $26.9 billion--was about 47 percent greater than needed at 
that point to ensure that sufficient funds would be available to cover 
the approximately $33 billion in estimated decommissioning costs when 
the plants are permanently closed. This value contrasts with GAO's 
prior finding that 1997 account balances were collectively 3 percent 
below what was needed. However, overall industry results can be 
misleading. Because funds are generally not transferable from funds 
that have more than sufficient reserves to those with insufficient 
reserves, each individual owner must ensure that enough funds are 
available for decommissioning their particular plants. We found that 33 
owners with ownership interests in a total of 42 plants had accumulated 
fewer funds than needed through 2000, to be on track to pay for 
eventual decommissioning. In addition, 20 owners with ownership 
interests in a total of 31 plants recently contributed less to their 
trust funds than we estimated they needed in order to put them on track 
to meet their decommissioning obligations.

NRC's analysis of the owners' 2001 biennial reports was not effective 
in identifying owners that might not be accumulating sufficient funds 
to cover their eventual decommissioning costs. In reviewing the 2001 
reports, NRC reported that all owners appeared to be on track to have 
sufficient funds for decommissioning. In reaching this conclusion, NRC 
relied on the owners' future plans for fully funding their 
decommissioning obligations. However, based on the owners' actual 
recent contributions, and using a different method, GAO found that 
several owners could be at risk of not meeting their financial 
obligations for decommissioning when these plants stop operating. In 
addition, for plants with more than one owner, NRC did not separately 
assess the status of each co-owner's trust funds against each co- 
owner's contractual obligation to fund decommissioning. Instead, NRC 
assessed whether the combined value of the trust funds for the plant as 
a whole were reasonable. Such an assessment for determining whether 
owners are accumulating sufficient funds can produce misleading results 
because owners with more than sufficient funds can appear to balance 
out owners with less than sufficient funds, even though funds are 
generally not transferable among owners. Furthermore, we found that NRC 
had not established criteria for taking action when it determines that 
an owner is not accumulating sufficient decommissioning funds.

We recommended that NRC (1) develop an effective method for determining 
whether owners are accumulating decommissioning funds at sufficient 
rates and (2) establish criteria for taking action when it is 
determined that an owner is not accumulating sufficient funds. NRC 
disagreed with these recommendations, suggesting that its method is 
effective and that it is better to deal with unacceptable levels of 
financial assurance on a case-by-case basis. GAO continues to believe 
that limitations in NRC's method reduce its effectiveness and that, 
without criteria, NRC might not be able to ensure owners are 
accumulating decommissioning funds at sufficient rates.

In May 2004, we issued a report on NRC's liability insurance 
requirements for nuclear power plants owned by limited liability 
companies.[Footnote 6] An accident at one the nation's commercial 
nuclear power plants could result in personal injury and property 
damage. To ensure that funds would be available to settle liability 
claims in such cases, the Price-Anderson Act requires licensees of 
these plants to have primary insurance--currently $300 million per 
site. The act also requires secondary coverage in the form of 
retrospective premiums to be contributed by all licensees of nuclear 
power plants to cover claims that exceed primary insurance. If these 
premiums are needed, each licensee's payments are limited to $10 
million per year and $95.8 million in total for each of its plants. In 
recent years, limited liability companies have increasingly become 
licensees of nuclear power plants, raising concerns about whether these 
companies--which shield their parent corporations' assets--will have 
the financial resources to pay their retrospective premiums. We were 
asked to determine (1) the extent to which limited liability companies 
are the licensees for U.S. commercial nuclear power plants, (2) NRC's 
requirements and procedures for ensuring that licensees of nuclear 
power plants comply with the Price-Anderson Act's liability 
requirements, and (3) whether and how these procedures differ for 
licensees that are limited liability companies.

We found that of the 103 operating nuclear power plants, 31 were owned 
by 11 limited liability companies. Three energy corporations--Exelon, 
Entergy, and the Constellation Energy Group--were the parent companies 
for eight of these limited liability companies. These 8 subsidiaries 
were the licensees or co-licensees for 27 of the 31 plants. We also 
found that NRC requires all licensees for nuclear power plants to show 
proof that they have the primary and secondary insurance coverage 
mandated by the Price-Anderson Act. Licensees sign an agreement with 
NRC that requires the licensee to keep the insurance in effect. 
American Nuclear Insurers also has a contractual agreement with each of 
the licensees that obligates the licensee to pay the retrospective 
premiums to American Nuclear Insurers if these payments become 
necessary. A certified copy of this agreement, which is called a bond 
for payment of retrospective premiums, is provided to NRC as proof of 
secondary insurance. Finally, we found that NRC does not treat limited 
liability companies differently than other licensees with respect to 
the Price-Anderson Act's insurance requirements. Like other licensees, 
limited liability companies must show proof of both primary and 
secondary insurance coverage. American Nuclear Insurers also requires 
limited liability companies to provide a letter of guarantee from their 
parent or other affiliated companies with sufficient assets to pay the 
retrospective premiums. These letters state that the parent or 
affiliated companies are responsible for paying the retrospective 
premiums if the limited liability company does not. American Nuclear 
Insurers informs NRC that it has received these letters.

In May 2004, we also issued a report documenting the need for NRC to 
more aggressively and comprehensively resolve issues related to the 
shutdown of the Davis-Besse nuclear power plant.[Footnote 7] The most 
serious safety issue confronting the nation's commercial nuclear power 
industry since Three Mile Island in 1979, was identified at the Davis- 
Besse plant in Ohio in March of 2002. After NRC allowed Davis-Besse to 
delay shutting down to inspect its reactor vessel for cracked tubing, 
the plant found that leakage from these tubes had caused extensive 
corrosion on the vessel head--a vital barrier in preventing a 
radioactive release. GAO determined (1) why NRC did not identify and 
prevent the corrosion, (2) whether the process NRC used in deciding to 
delay the shutdown was credible, and (3) whether NRC is taking 
sufficient action in the wake of the incident to prevent similar 
problems from developing at other plants.

We found that NRC should have, but did not identify or prevent the 
corrosion at Davis-Besse because agency oversight did not produce 
accurate information on plant conditions. NRC inspectors were aware of 
indications of leaking tubes and corrosion; however, the inspectors did 
not recognize the importance of the indications and did not fully 
communicate information about them to other NRC staff. NRC also 
considered FirstEnergy--Davis-Besse's owner--a good performer, which 
resulted in fewer NRC inspections and questions about plant conditions. 
NRC was aware of the potential for cracked tubes and corrosion at 
plants like Davis-Besse but did not view them as an immediate concern. 
Thus, despite being aware of the development of potential problems, NRC 
did not modify its inspection activities to identify such conditions. 
Additionally, NRC's process for deciding to allow Davis-Besse to delay 
its shutdown lacked credibility. Because NRC had no guidance for making 
the specific decision of whether a plant should shut down, it instead 
used guidance for deciding whether a plant should be allowed to modify 
its operating license. However, NRC did not always follow this guidance 
and generally did not document how it applied the guidance. 
Furthermore, the risk estimate NRC used to help decide whether the 
plant should shut down was also flawed and underestimated the risk that 
Davis-Besse posed. Finally, even though it underestimated the risk 
posed by Davis-Besse, the risk estimate applied to the plant still 
exceeded levels generally accepted by the agency. Nevertheless, Davis- 
Besse was allowed to delay the plant's shutdown.

After this incident, NRC took several significant actions to help 
prevent reactor vessel corrosion from recurring at nuclear power 
plants. For example, NRC has required more extensive vessel 
examinations and augmented inspector training. I would also like to 
note that, in April 2005, NRC proposed a $5.45 million fine against the 
licensee of the Davis-Besse plant. The principal violation was that the 
utility restarted and operated the plant in May 2000, without fully 
characterizing and eliminating leakage from the reactor vessel head. 
Additional violations included providing incomplete and inaccurate 
information to NRC on the extent of cleaning and inspecting the reactor 
vessel head in 2000.

While NRC has not yet completed all of its planned actions, we remain 
concerned that NRC has no plans to address three systemic weaknesses 
underscored by the incident at Davis-Besse. Specifically, NRC has 
proposed no actions to help it better (1) identify early indications of 
deteriorating safety conditions at plants, (2) decide whether to shut 
down a plant, or (3) monitor actions taken in response to incidents at 
plants. Both NRC and GAO had previously identified problems in NRC 
programs that contributed to the Davis-Besse incident, yet these 
problems continued to persist. Because the nation's nuclear power 
plants are aging, GAO recommended that NRC take more aggressive actions 
to mitigate the risk of serious safety problems occurring at Davis- 
Besse and other nuclear power plants.

In April 2005, we issued a report outlining the need for NRC to do more 
to ensure that power plants are effectively controlling spent nuclear 
fuel.[Footnote 8] Spent nuclear fuel--the used fuel periodically 
removed from reactors in nuclear power plants--is too inefficient to 
power a nuclear reaction, but is intensely radioactive and continues to 
generate heat for thousands of years. Potential health and safety 
implications make the control of spent nuclear fuel of great 
importance. The discovery, in 2004, that spent fuel rods were missing 
at the Vermont Yankee plant in Vermont generated public concern and 
questions about NRC's regulation and oversight of this material. GAO 
reviewed (1) plants' performance in controlling and accounting for 
their spent nuclear fuel, (2) the effectiveness of NRC's regulations 
and oversight of plants' performance, and (3) NRC's actions to respond 
to plants' problems controlling their spent fuel.

We found that nuclear power plants' performance in controlling and 
accounting for their spent fuel has been uneven. Most recently, three 
plants--Vermont Yankee and Humboldt Bay (California) in 2004, and 
Millstone (Connecticut) in 2000--have reported missing spent fuel. 
Earlier, several other plants also had missing or unaccounted for spent 
fuel rods or rod fragments. NRC regulations require plants to maintain 
accurate records of their spent nuclear fuel and to conduct a physical 
inventory of the material at least once a year. The regulations, 
however, do not specify how physical inventories are to be conducted. 
As a result, plants differ in the regulations' implementation. For 
example, physical inventories at plants varied from a comprehensive 
verification of the spent fuel to an office review of the records and 
paperwork for consistency. Additionally, NRC regulations do not specify 
how individual fuel rods or segments are to be tracked. As a result, 
plants employ various methods for storing and accounting for this 
material. Further, NRC stopped inspecting plants' material control and 
accounting programs in 1988. According to NRC officials, there was no 
indication that inspections of these programs were needed until the 
event at Millstone. At the time of our review, NRC was collecting 
information on plants' spent fuel programs to decide if it needs to 
revise its regulations and/or oversight. It had its inspectors collect 
basic information on all facilities' programs. It also contracted with 
the Department of Energy's Oak Ridge National Laboratory in Tennessee 
to review NRC's material control and accounting programs for nuclear 
material. NRC is planning to request information from plants and plans 
to visit over a dozen plants for more detailed inspection. The results 
of these efforts may not be completed until late 2005, over 5 years 
after the incident at Millstone that initiated NRC's efforts. However, 
we believed NRC has already collected considerable information 
indicating problems or weaknesses in plants' material control and 
accounting programs for spent fuel.

GAO recommended that NRC (1) establish specific requirements for the 
way plants control and account for loose rods and fragments as well as 
conduct their physical inventories, and (2) develop and implement 
appropriate inspection procedures to verify plants' compliance with the 
requirements.

NRC Faces Several Broad Challenges in Effectively Regulating and 
Overseeing Nuclear Power Plants:

Based on our recent work at NRC, we have identified several cross- 
cutting challenges that NRC faces as it works to effectively regulate 
and oversee the nuclear power industry. First, NRC must manage the 
implementation of its risk-informed regulatory strategy across the 
agency's operations. Second, and relatedly, NRC must strive to achieve 
the appropriate balance between more direct involvement in the 
operations of nuclear power plants and self-reliance and self-reporting 
on the part of plant operators to do the right things to ensure safety. 
Third, and finally, NRC must ensure that the agency effectively manages 
resources to implement its risk-informed strategy and achieve the 
appropriate regulatory balance in the current context of increasing 
regulatory and oversight demands as the industry's interest in 
expansion grows.

NRC Must Manage the Implementation of Its Risk-Informed Regulatory 
Strategy:

Nuclear power plants have many physical structures, systems, and 
components, and licensees have numerous activities under way, 24-hours 
a day, to ensure that plants operate safely. NRC relies on, among other 
things, the agency's on-site resident inspectors to assess plant 
conditions and oversee quality assurance programs, such as maintenance 
and operations, established by operators to ensure safety at the 
plants. Monitoring, maintenance, and inspection programs are used to 
ensure quality assurance and safe operations. To carry out these 
programs, licensees typically prepare numerous reports describing 
conditions at plants that need to be addressed to ensure continued safe 
operations. Because of the significant number of activities and 
physical structures, systems, and components, NRC adopted a risk- 
informed strategy to focus inspections on those activities and pieces 
of equipment that are considered to be the most significant for 
protecting public health and safety. Under the risk-informed approach, 
some systems and activities that NRC considers to have relatively less 
safety significance receive little agency oversight. With its current 
resources, NRC can inspect only a relatively small sample of the 
numerous activities going on during complex plant operations. NRC has 
adopted a risk-informed approach because it believes that it can focus 
its regulatory resources on those areas of the plant that the agency 
considers the most important to safety. NRC has stated the adoption of 
this approach was made possible by the fact that safety performance at 
plants has improved as a result of more than 25 years of operating 
experience.

Nevertheless, we believe that NRC faces a significant challenge in 
effectively implementing its risk-informed strategy, especially with 
regards to improving the quality of its risk information and 
identifying emerging technical issues and adjusting regulatory 
requirements before safety problems develop. The 2002 shutdown of the 
Davis-Besse plant illustrates this challenge, notably the shortcomings 
in NRC's risk estimate and failure to sufficiently address the boric 
acid corrosion and nozzle cracking issues. We also note that NRC's 
Inspector General considers the development and implementation of a 
risk-informed regulatory oversight strategy to be one of the most 
serious management challenges facing NRC.

NRC Must Balance Oversight and Industry Self-Compliance:

Under the Atomic Energy Act of 1954, as amended, and the Energy 
Reorganization Act of 1974, as amended, NRC and the operators of 
nuclear power plants share the responsibility for ensuring that nuclear 
reactors are operated safely. NRC is responsible for issuing 
regulations, licensing and inspecting plants, and requiring action, as 
necessary, to protect public health and safety. Plant operators have 
the primary responsibility for safely operating their plants in 
accordance with their licenses. NRC has the authority to take actions, 
up to and including shutting down a plant, if licensing conditions are 
not being met and the plant poses an undue risk to public health and 
safety.

NRC has sought to strike a balance between verifying plants' compliance 
with requirements through inspections and affording licensees the 
opportunity to demonstrate that they are operating their plants safely. 
While NRC oversees processes, such as the use of performance measures 
and indicators, and requirements that licensees maintain their own 
quality assurance programs, NRC, in effect, relies on licensees and 
trusts them to a large extent to make sure their plants are operated 
safely. While this approach has generally worked, we believe that NRC 
still has work to do to effectively position itself so that it can 
identify problems with diminishing performance at individual plants 
before they become serious. For example, incidents such as the 2002 
discovery of the extensive reactor vessel head corrosion at the Davis- 
Besse plant and the unaccounted for spent nuclear fuel at several 
plants across the country, raise questions about whether NRC is 
appropriately balancing agency involvement and self-monitoring by 
licensees. An important aspect of NRC's ability to rely on licensees to 
maintain their own quality assurance programs is a mechanism to 
identify deteriorating performance at a plant before the plant becomes 
a problem. At Davis-Besse, NRC inspectors viewed the licensee as a good 
performer based on its past performance and did not ask the questions 
that should have been asked about plant conditions. Consequently, the 
inspectors did not make sure that the licensee adequately investigated 
the indications of the problem and did not fully communicate the 
indications to the regional office and NRC headquarters.

NRC Must Manage Agency Resources to Meet Increasing Regulatory and 
Oversight Demands:

Finally, Mr. Chairman, I would also like to comment briefly on NRC's 
resources. While we have not assessed the adequacy of NRC's resources, 
we have noted instances, such the shutdown of the Davis-Besse plant, 
where resource constraints affected the agency's oversight or delayed 
certain activities. NRC's resources have been challenged by the need to 
enhance security at nuclear power plants after the September 11, 2001, 
terrorist attacks, and they will continue to be challenged as the 
nation's fleet of nuclear power plants age and the industry's interest 
grows in both licensing and constructing new plants, and re-licensing 
and increasing the output of existing plants. Resource demands will 
also increase when the Department of Energy submits for NRC review, an 
application to construct and operate a national depository for high- 
level radioactive waste currently planned for Yucca Mountain, Nevada. 
We believe that it is important for NRC and the Congress to monitor 
agency resources as these demands arise in order to ensure that NRC can 
meet all of its regulatory and oversight responsibilities and fulfill 
its mission to ensure adequate protection of public health, safety, and 
the environment.

Conclusion:

In closing, we recognize and appreciate the complexities of NRC's 
regulatory and oversight efforts required to ensure the safe and secure 
operation of the nation's commercial nuclear power plants. As GAO's 
recent work has demonstrated, NRC does a lot right but it still has 
important work to do. Whether NRC carries out its regulatory and 
oversight responsibilities in an effective and credible manner will 
have a significant impact on the future direction of our nation's use 
of nuclear power.

Finally, we note that NRC has generally been responsive to our report 
findings. Although the agency does not always agree with our specific 
recommendations, it has continued to work to improve in the areas we 
have identified. It has implemented many of our recommendations and is 
working on others. For example, with respect to nuclear power plant 
security, NRC has restored its security inspection program and resumed 
its force-on-force exercises with a much higher level of intensity. It 
is also strengthening these exercises by conducting them at individual 
plants every 3 years rather than every 8 years, and is using laser 
equipment to reduce the exercises' artificiality. Another example 
involves sealed radioactive sources. NRC is working with agreement 
states to develop a process for ensuring that high-risk radioactive 
sources cannot be obtained before verification that the materials will 
be used as intended. NRC anticipates that an NRC-agreement state 
working group will deliver a recommended approach to NRC senior 
management later this year. In addition, NRC continues to work on its 
broader challenges. For example, the agency intends to develop 
additional regulatory guidance to expand the application of risk- 
informed decision making, including addressing the need to establish 
quality requirements for risk information and specific instructions for 
documenting the decision making process and its conclusions.

We will continue to track NRC's progress in implementing our 
recommendations. In addition, as members of this subcommittee are 
aware, GAO has been asked to review the effectiveness of NRC's 
activities for overseeing nuclear power plants, that is, its reactor 
oversight process. An important part of that work would be to review 
the agency's risk-informed regulatory strategy and its effectiveness in 
identifying deteriorating plant performance as well as whether NRC is 
making progress toward effectively balancing agency inspections and 
self-monitoring by licensees.

Mr. Chairman, this completes my prepared statement. I would be pleased 
to respond to any questions that you or other Members of the 
subcommittee may have.

GAO Contacts and Staff Acknowledgements:

For further information about this testimony, please contact me at 
(202) 512-3841 (or at wellsj@gao.gov). John W. Delicath, Ilene Pollack, 
and Raymond H. Smith, Jr. made key contributions to this testimony.

[End of section]

Related GAO Products:

Nuclear Waste: Preliminary Observations on the Quality Assurance 
Program at the Yucca Mountain Repository. GAO-03-826T. Washington, 
D.C.: May 28, 2003.

Nuclear Regulatory Commission: Revision of Fee Schedules; Fee Recovery 
for FY 2003. GAO-03-934R. Washington, D.C.: June 30, 2003.

Spent Nuclear Fuel: Options Exist to Further Enhance Security. GAO-03- 
426. Washington, D.C.: July 15, 2003.

Nuclear Security: Federal and State Action Needed to Improve Security 
of Sealed Radioactive Sources. GAO-03-804. Washington, D.C.: August 6, 
2003.

Nuclear Regulatory Commission: Oversight of Security at Commercial 
Nuclear Power Plants Needs to Be Strengthened. GAO-03-752. Washington, 
D.C.: September 4, 2003.

Nuclear Regulation: NRC Needs More Effective Analysis to Ensure 
Accumulation of Funds to Decommission Nuclear Power Plants. GAO-04-32. 
Washington, D.C.: October 30, 2003.

Information Technology Management: Governmentwide Strategic Planning, 
Performance Measurement, and Investment Management Can Be Further 
Improved. GAO-04-49. Washington, D.C.: January 12, 2004.

Yucca Mountain: Persistent Quality Assurance Problems Could Delay 
Repository Licensing and Operation. GAO-04-460. Washington, D.C.: April 
30, 2004.

Nuclear Regulation: NRC Needs to More Aggressively and Comprehensively 
Resolve Issues Related to the Davis-Besse Nuclear Power Plant's 
Shutdown. GAO-04-415. Washington, D.C.: May 17, 2004.

Nuclear Regulation: NRC's Liability Insurance Requirements for Nuclear 
Power Plants Owned by Limited Liability Companies. GAO-04-654. 
Washington, D.C.: May 28, 2004.

Low-Level Radioactive Waste: Disposal Availability Adequate in the 
Short Term, but Oversight Needed to Identify Any Future Shortfalls. GAO-
04-604. Washington, D.C.: June 10, 2004.

Nuclear Nonproliferation: DOE Needs to Take Action to Further Reduce 
the Use of Weapons-Usable Uranium in Civilian Research Reactors. GAO- 
04-807. Washington, D.C.: July 30, 2004.

Nuclear Regulatory Commission: Preliminary Observations on Efforts to 
Improve Security at Nuclear Power Plants. GAO-04-1064T. Washington, 
D.C.: September 14, 2004.

Low-Level Radioactive Waste: Future Waste Volumes and Disposal Options 
Are Uncertain. GAO-04-1097T. Washington, D.C.: September 30, 2004.

Nuclear Regulatory Commission: NRC Needs to Do More to Ensure that 
Power Plants Are Effectively Controlling Spent Nuclear Fuel. GAO-05- 
339. Washington, D.C.: April 8, 2005.

FOOTNOTES

[1] GAO: Nuclear Security Federal and State Action Needed to Improve 
Security of Sealed Radioactive Sources, GAO-03-804 Washington, D.C.: 
Aug. 6, 2003.

[2] Agreement states are the 33 states that have entered into an 
agreement with the NRC under subsection 274(b) of the Atomic Energy Act 
(AEA) under which NRC relinquishes to the states portions of its 
regulatory authority to license and regulate source, byproduct, and 
certain quantities of special nuclear material. 

[3] GAO: Nuclear Regulatory Commission: Oversight of Security at 
Commercial Nuclear Power Plants Needs to Be Strengthened, GAO-03-752 
(Washington, D.C.: Sept. 4, 2003).

[4] GAO, Nuclear Regulatory Commission: Preliminary Observations on 
Efforts to Improve Security at Nuclear Power Plants, GAO-04-1064T 
(Washington, D.C.: Sept. 14, 2004).

[5] GAO: Nuclear Regulation: NRC Needs More Effective Analysis to 
Ensure Accumulation of Funds to Decommission Nuclear Power Plants, GAO-
04-32 (Washington, D.C.: Oct. 30, 2003).

[6] GAO, Nuclear Regulation: NRC's Liability Insurance Requirements for 
Nuclear Power Plants Owned by Limited Liability Companies, GAO-04-654 
(Washington, D.C.: May 28, 2004).

[7] GAO, Nuclear Regulation: NRC Needs to More Aggressively and 
Comprehensively Resolve Issues Related to the Davis-Besse Nuclear Power 
Plant's Shutdown, GAO-04-415 (Washington, D.C.: May 17,2004).

[8] GAO, Nuclear Regulatory Commission: NRC Needs to Do More to Ensure 
that Power Plants Are Effectively Controlling Spent Nuclear Fuel, GAO-
05-339 (Washington, D.C.: Apr. 8, 2005).