This is the accessible text file for GAO report number GAO-04-438T 
entitled 'Business Systems Modernization: Internal Revenue Service 
Needs to Further Strengthen Program Management' which was released on 
February 12, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Testimony:

Before the Subcommittee on Oversight, Committee on Ways and Means, 
House of Representatives:

United States General Accounting Office:

GAO:

For Release on Delivery Expected at 9:00 a.m. EST:

Thursday, February 12, 2004:

Business Systems Modernization:

Internal Revenue Service Needs to Further Strengthen Program 
Management:

Statement of Robert F. Dacey:

Director, Information Security Issues:

GAO-04-438T:

GAO Highlights:

Highlights of GAO-04-438T, testimony before the Subcommittee on 
Oversight, House Committee on Ways and Means 

Why GAO Did This Study:

The Internal Revenue Service (IRS) has been grappling with modernizing 
its computer systems for many years. IRS’s current program, commonly 
referred to as Business Systems Modernization (BSM), began in fiscal 
year 1999; about $1.4 billion has been reported spent on it to date. 
While progress has been made, the program continues to face 
significant challenges and risks. 

In recognition of these risks, IRS and a contractor recently completed 
several comprehensive assessments of BSM, including one of its 
Customer Account Data Engine (CADE) project, which is to modernize the 
agency’s outdated data management system. 

At the request of the Subcommittee on Oversight, House Committee on 
Ways and Means, GAO’s testimony will summarize (1) GAO’s prior 
findings and recommendations, along with those of the recent 
assessments; and (2) actions IRS has taken or plans to take to address 
these issues. 


What GAO Found:

Prior GAO reviews have disclosed numerous modernization management 
control deficiencies that have contributed to reported cost overruns 
and schedule delays. The table below illustrates the degree to which 
costs and completion dates for ongoing projects have grown from their 
initial estimates. Reasons for such delays include inadequate 
definition of systems requirements, increases in project scope, and 
underestimation of project complexity. These impair IRS’s ability to 
make future systems investment decisions and delay delivery of 
benefits to taxpayers. GAO has made a series of recommendations 
focusing on stronger program management—and limiting modernization 
activities until such management practices were in place. 

IRS BSM Project Cost/Schedule Variance Summary: 

[See PDF for table]

[End of table]

IRS has made important progress in implementing management controls, 
establishing infrastructure, delivering certain business applications, 
and balancing the pace of the program with the agency’s ability to 
manage it. Nevertheless, IRS needs to further strengthen BSM program 
management, including fully implementing modernization management 
controls in such areas as cost and schedule estimating. 

The recent BSM assessments identified many weaknesses, consistent with 
prior GAO findings, that contributed to the cost overruns and schedule 
delays, and offered recommendations to address them. IRS has responded 
by identifying 46 discrete issues to be resolved; according to the 
agency, 27 of these have been completed. Commitment of appropriate 
resources, top management attention, and continuing oversight by 
Congress and others are critical to the success of BSM. 

www.gao.gov/cgi-bin/getrpt?GAO-04-438T.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Robert F. Dacey at 
(202) 512-3317 or daceyr@gao.gov.

[End of section]

Mr. Chairman and Members of the Subcommittee:

I am pleased to be here today to discuss the Internal Revenue Service's 
(IRS) actions to modernize its computer systems. Although updated 
through the years, IRS's set of computer systems is based on an 
architecture that dates from the 1960s. This architecture has inhibited 
IRS's ability to effectively and efficiently perform its mission of 
providing service to taxpayers and enforcing the nation's tax laws. 
However, IRS's attempts to modernize its computer systems and 
underlying architecture now span three decades. Given the long history 
of continuing delays and design difficulties, we previously designated 
IRS's modernization program as a high-risk area in 1995.[Footnote 1] It 
remains so today.[Footnote 2]

IRS's current multibillion-dollar effort, known as the Business Systems 
Modernization (BSM) program, was initiated in fiscal year 1999. IRS 
contracted with Computer Sciences Corporation (CSC) as the prime 
contractor to assist with designing, developing, and integrating a new 
set of information systems that were intended to replace IRS's aging 
business and tax processing systems. To date, about $1.7 billion has 
been appropriated for the program, including about $388 million for 
fiscal year 2004.[Footnote 3]

To facilitate congressional oversight of this program, annual 
appropriations laws since fiscal year 1998 have mandated that 
modernization funds not be available until IRS submits to the 
congressional appropriations committees for approval a modernization 
expenditure plan that satisfies six legislative conditions, including 
that it be reviewed by us.[Footnote 4] We are currently reviewing the 
fiscal year 2004 BSM expenditure plan. During our past reviews of such 
plans, we have noted numerous modernization management control 
deficiencies and made recommendations to correct them. Although IRS has 
made progress in implementing our recommendations, BSM continues to 
face significant challenges and serious risks. Recognizing these risks, 
IRS and CSC recently completed several in-depth and more comprehensive 
assessments on the health of the BSM program, including an independent 
technical assessment of the Customer Account Data Engine (CADE) 
project, a project critical to the success of BSM. IRS has developed an 
action plan to address the assessments' recommendations, and has begun 
to act on it.

In my testimony today I will summarize our prior findings and 
recommendations and those of the recently completed program 
assessments. I will also discuss the actions IRS reports it has taken 
or plans to take to address issues raised by these assessments.

In preparing this testimony, we relied on our prior reports and 
testimony on IRS's systems modernization activities and BSM expenditure 
plans. We also reviewed and analyzed information contained in the BSM 
expenditure plan for fiscal year 2004; Carnegie Mellon University 
Software Engineering Institute's (SEI) independent technical 
assessment of CADE; reports on the BSM program by the Treasury 
Inspector General for Tax Administration and the IRS Oversight Board; 
and IRS briefing materials (1) analyzing the root causes of BSM project 
cost increases and schedule delays, (2) independent reviews of CSC's 
business processes and IRS's procurement practices, and (3) IRS's 
action plan to address issues identified by the reviews. We did not 
independently validate planned projects' cost estimates or confirm, 
through system and project management documentation, the validity of 
IRS-provided information on the projects' content and progress. Our 
work was performed during the past month, in accordance with generally 
accepted government auditing standards.

Background:

The tax administration system that collects about $2 trillion in 
revenues each year is critically dependent on a collection of obsolete 
computer systems developed by the IRS over the last 40 years. IRS 
envisions a future in which its tax processing environment will be 
virtually paper-free, and up-to-date taxpayer information will be 
readily available to IRS employees to respond to taxpayer inquiries. To 
accomplish this, IRS embarked on its ambitious BSM program. BSM 
involves the development and delivery of a number of modernized 
business, data, and core infrastructure projects that are intended to 
provide improved and expanded service to taxpayers as well as IRS 
internal business efficiencies. Recognizing the long-term commitment 
needed to solve the problem of obsolete computer systems, Congress set 
up a special BSM account in fiscal year 1998 to fund IRS's systems 
modernization efforts.

IRS initiated CADE as part of BSM, to modernize the agency's outdated 
and inefficient data management system.[Footnote 5] IRS also sees this 
project as the corporate data source enabling future customer service 
and financial management applications. CADE is therefore IRS's linchpin 
modernization project. In light of the projects that depend on CADE, as 
well as the many interrelationships that are to exist among CADE and 
IRS's modernized applications and among CADE and current IRS 
applications, the agency must manage this critical project effectively. 
Without CADE, the business systems modernization program cannot 
succeed.

IRS Has Made Improvements, But Systems Modernization Program Remains 
High-Risk:

IRS's attempts to modernize its aging computer systems span several 
decades. This long history of continuing delays and design difficulties 
led to our designating IRS's Tax Systems Modernization program, BSM's 
predecessor, as a high-risk area in 1995.[Footnote 6] During the mid-
1990s we reported on several technical and management weaknesses 
associated with Tax Systems Modernization, a program that began in the 
1980s. These weaknesses related to incomplete or inadequate strategic 
information management practices; immature software development 
capability; incomplete systems architecture, integration planning, 
system testing, and test planning practices; and the lack of an 
effective organizational structure to consistently manage and control 
systems modernization organizationwide. We made a series of 
recommendations for correcting these weaknesses and limiting 
modernization activities until they were corrected.[Footnote 7] IRS 
subsequently discontinued the program after the agency had spent about 
$4 billion without receiving expected benefits. In fiscal year 1999, 
IRS launched the BSM program. IRS contracted with CSC as its prime 
systems integration services contractor for systems modernization, 
helping it design new systems and identify other contractors to develop 
software and perform other tasks.

In our reviews of IRS's BSM expenditure plans, we have identified 
numerous deficiencies in the BSM program, including a continuation of 
the weaknesses noted above. Also, a consistent challenge for IRS has 
been to make sure that the pace of systems acquisition projects does 
not exceed the agency's ability to manage them. In May and November 
2000, we reported that projects were in fact getting ahead of the 
modernization management capacity that needed to be in place to manage 
them effectively.[Footnote 8] In February 2002 we reported that such an 
imbalance was due to IRS's first priority and emphasis being on getting 
the newer, more modern systems--with their anticipated benefits to 
taxpayers--up and running.[Footnote 9] In so doing, however, management 
controls had not been given equal attention and thus had not kept pace. 
This emphasis on new systems added significant cost, schedule, and 
performance risks that escalate as a program advances. Moreover, these 
risks increased as IRS moved forward because of interdependencies among 
projects, and the complexity of associated workload activities to be 
performed increased dramatically as more systems projects were built 
and deployed.

In addition, we identified other deficiencies in the BSM program, 
including the need to establish processes that meet the level 2 
requirements of the SEI's Software Acquisition Capability Maturity 
Model',[Footnote 10] and to improve modernization management controls 
and capabilities, such as those related to configuration management, 
risk management, enterprise architecture implementation, human capital 
strategic management, integrated program scheduling, and cost and 
schedule estimating.

In response to our recommendations, IRS has made important progress. 
First, significant progress has been made in establishing the 
modernization management controls needed to effectively acquire and 
implement information technology systems. For example, IRS has:

* invested incrementally in its modernization projects;

* defined a systems life cycle management methodology, which IRS refers 
to as the Enterprise Life Cycle;

* developed and is using a modernization blueprint, commonly called an 
enterprise architecture, to guide and constrain its modernization 
projects; and:

* established processes that meet the level 2 requirements of the SEI's 
Software Acquisition Capability Maturity Model'.

Second, IRS has made progress in establishing the infrastructure 
systems on which future business applications will run. For example, 
IRS has delivered elements of the Security and Technology 
Infrastructure Release to provide the hardware, software, and security 
solutions for modernization projects. IRS has also built an enterprise 
integration and test environment that provides the environment and 
tools for multiple vendors associated with a release to perform 
integration and testing activities.

Third, it has delivered certain business applications that are 
producing benefits today. These applications include:

* Customer Communications 2001, to improve telephone call management, 
call routing, and customer self-service applications;

* Customer Relationship Management Examination, to provide off-the-
shelf software to IRS revenue agents to allow them to accurately 
compute complex corporate transactions; and:

* Internet Refund/Fact of Filing, to improve customer self-service by 
providing to taxpayers via the Internet instant refund status 
information and instructions for resolving refund problems.

Fourth, IRS took steps to align the pace of the program with the 
maturity of IRS's controls and management capacity, including 
reassessing its portfolio of planned projects.

Nevertheless, IRS continued to face challenges to fully develop and 
implement its modernization management capacity. Last June we reported 
that IRS had not yet fully implemented a strategic approach to ensuring 
that it has sufficient human capital resources for implementing BSM, 
nor had it fully implemented management controls in such areas as 
configuration management, estimating costs and schedules, and employing 
performance-based contracting methods.[Footnote 11] We made several 
recommendations to address those issues. Our analysis has shown that 
weak management controls contributed directly to the cost, schedule, 
and/or performance shortfalls experienced by most projects. Given that 
the tasks associated with those projects that are moving beyond design 
and into development are by their nature more complex and risky and 
that IRS's fiscal year 2004 BSM expenditure plan supports progress 
toward the later phases of key projects and continued development of 
other projects, systems modernization projects likely will encounter 
additional cost and schedule shortfalls. IRS will need to continue to 
assess the balance between the pace of the program and the agency's 
ability to manage it.

Projects Continue to Incur Cost Increases and Schedule Delays:

Based on IRS's expenditure plans, BSM projects have consistently cost 
more and taken longer to complete than originally estimated. Table 1 
shows the life cycle variance in cost and schedule estimates for 
completed and ongoing BSM projects. These variances are based on a 
comparison of IRS's initial and revised cost and schedule estimates to 
complete initial operation[Footnote 12] or full deployment[Footnote 13] 
of the projects.

Table 1: IRS BSM Project Cost/Schedule Variance Summary:

Project: Completed Projects; 
Security and Technology Infrastructure Release 1; 
Cost variance (in thousands): +$7,553; 
Reported/revised: estimated cost: (in thousands): $41,287; 
Schedule variance (in months): +5; 
Reported/revised estimated completion date: 1/31/02; 
(initial operation).

Project: Completed Projects; 
Customer Communications 2001; 
Cost variance (in thousands): +5,310; 
Reported/revised: estimated cost: (in thousands): 46,420; 
Schedule variance (in months): +9; 
Reported/revised estimated completion date: 2/26/02; 
(full deployment).

Project: Completed Projects; 
Customer Relationship Management Exam; 
Cost variance (in thousands): -1,938; 
Reported/revised: estimated cost: (in thousands): 7,375; 
Schedule variance (in months): +3; 
Reported/revised estimated completion date: 9/30/02; 
(full deployment).

Project: Completed Projects; 
Human Resources Connect Release 1; 
Cost variance (in thousands): +200; 
Reported/revised: estimated cost: (in thousands): 10,200; 
Schedule variance (in months): 0; 
Reported/revised estimated completion date: 12/31/02; 
(initial operation).

Project: Completed Projects; 
Internet Refund/Fact of Filing; 
Cost variance (in thousands): +12,923; 
Reported/revised: estimated cost: (in thousands): 26,432; 
Schedule variance (in months): +14; 
Reported/revised estimated completion date: 9/26/03; 
(full deployment).

Project: Ongoing Projects[A]; 
Modernized e-File Release 1; 
Cost variance (in thousands): +17,057; 
Reported/revised: estimated cost: (in thousands): 46,303; 
Schedule variance (in months): +4.5; 
Reported/revised estimated completion date: 3/31/04; 
(initial operation).

Project: Ongoing Projects[A]; 
e-Services; 
Cost variance (in thousands): +86,236; 
Reported/ revised: estimated cost: (in thousands): 130,281; 
Schedule variance (in months): +18; 
Reported/revised estimated completion date: 4/ 30/05; 
(full deployment).

Project: Ongoing Projects[A]; 
CADE Release 1; 
Cost variance (in thousands): +36,760; 
Reported/revised: estimated cost: (in thousands): 97,905; 
Schedule variance (in months): +30b; 
Reported/revised estimated completion date: 6/30/05[B]; 
(full deployment).

Project: Ongoing Projects[A]; 
Integrated Financial System Release 1; 
Cost variance (in thousands): +53,916; 
Reported/revised: estimated cost: (in thousands): 153,786; 
Schedule variance (in months): TBD[B]; 
Reported/ revised estimated completion date: TBD[B]; 
(full deployment).

Project: Ongoing Projects[A]; 
Custodial Accounting Project Release 1; 
Cost variance (in thousands): +72,058; 
Reported/revised: estimated cost: (in thousands): 119,219; 
Schedule variance (in months): TBD[B]; 
Reported/ revised estimated completion date: TBD[B]; 
(full deployment).

Project: Ongoing Projects[A]; 
Customer Account Management Release 1; 
Cost variance (in thousands): TBD[C]; 
Reported/revised: estimated cost: (in thousands): TBD[C]; 
Schedule variance (in months): TBD[C]; 
Reported/ revised estimated completion date: TBD[C]. 

Source: GAO analysis of data contained in IRS's BSM expenditure plans.

[A] Projects ongoing as of 9/30/03.

[B] Project schedules for CADE, the Integrated Financial System, and 
the Custodial Accounting Project are currently under review.

[C] To be determined. Work on the Customer Account Management project 
was suspended following the completion of preliminary design 
activities. No further work is planned until at least fiscal year 2005.

[End of table]

As the table indicates, the cost and schedule estimates for full 
deployment of the e-Services project have increased by just over $86 
million and 18 months, respectively. In addition, the estimated cost 
for the full deployment of CADE release 1 has increased by almost $37 
million, and project completion has been delayed by 30 months. In 
addition to the modernization management control deficiencies discussed 
above, our work has shown that the increases and delays were caused, in 
part, by:

* inadequate definitions of systems requirements. As a result, 
additional requirements have been incorporated into ongoing projects.

* increases in project scope. For example, the e-Services project has 
changed significantly since the original design. The scope was 
broadened by IRS to provide additional benefits to internal and 
external customers.

* cost and schedule estimating deficiencies. IRS has lacked the 
capability to effectively develop reliable cost and schedule estimates.

* underestimating project complexity. This factor has contributed 
directly to the significant delays in the CADE release 1 schedule.

* competing demands of projects for test facilities. Testing 
infrastructure capacity is insufficient to accommodate multiple 
projects when testing schedules overlap.

* project interdependencies. Delays with one project have had a 
cascading effect and have caused delays in related projects.

These schedule delays and cost overruns impair IRS's ability to make 
appropriate decisions about investing in new projects, delay delivery 
of benefits to taxpayers, and postpone resolution of material 
weaknesses affecting other program areas.

Producing reliable estimates of expected costs and schedules is 
essential to determining a project's cost-effectiveness. In addition, 
it is critical for budgeting, management, and oversight. Without this 
information, the likelihood of poor investment decisions is increased.

Schedule slippages delay the provision of modernized systems' direct 
benefits to the public. For example, slippages in CADE will delay IRS's 
ability to provide faster refunds and respond to taxpayer inquiries on 
a timely basis.

Delays in the delivery of modernized systems also affect the 
remediation of material internal management weaknesses. For example, 
IRS has reported a material weakness associated with the design of the 
master files. CADE is to build the modernized database foundation that 
will replace the master files. Continuing schedule delays will place 
resolution of this material weakness further out into the future. In 
addition, the Custodial Accounting Project is intended to address a 
financial material weakness and permit the tracking from submission to 
disbursement of all revenues received from individual taxpayers. This 
release has yet to be implemented, and a revised schedule has not yet 
been determined. Finally, the Integrated Financial System is intended 
to address financial management weaknesses. When IRS submitted its 
fiscal year 2003 BSM expenditure plan, release 1 of the Integrated 
Financial System was scheduled for delivery on October 1, 2003. 
However, it has yet to be implemented, and additional cost increases 
are expected.

Internal and Independent Assessments of BSM Have Identified Significant 
Weaknesses and Risks:

Given the continued cost overruns and schedule delays experienced by 
these BSM projects, IRS and CSC launched internal and independent 
assessments during 2003 of the health of BSM as whole, as well as CADE. 
Table 2 describes these assessments.

Table 2: BSM Assessments Undertaken During 2003:

Subject: Root cause analysis; 
Organization conducting assessment: IRS; 
Purpose: To review data from historical documents and interviews to 
determine root causes for schedule delays and cost increases.

Subject: PRIME review; 
Organization conducting assessment: Bain and Company; 
Purpose: To identify root causes of breakdown in CSC's business 
processes and engagement model and provide recommended solutions.

Subject: IRS Office of Procurement Assessment; 
Organization conducting assessment: Acquisition Solutions, Inc.; 
Purpose: To assess the efficiency and effectiveness of the IRS 
procurement organization structure, employment of best practices, 
management and administration, staffing, and to briefly review BSM 
contracting.

Subject: CADE assessment; 
Organization conducting assessment: SEI; 
Purpose: To provide an independent technical assessment of CADE 
program history and the feasibility of future plans.

Source: IRS:

[End of table]

The IRS root cause analysis, PRIME review, and the Office of 
Procurement assessment revealed several significant weaknesses that 
have driven project cost overruns and schedule delays, and also 
provided a number of actionable recommendations for IRS and CSC to 
address the identified weaknesses and reduce the risk to BSM. 
Deficiencies identified are consistent with our prior findings and 
include:

* poorly defined requirements,

* low program productivity levels,

* project scope creep,

* IRS/PRIME role confusion,

* immature management processes,

* ineffective integration across IRS, and:

* insufficient applications and technology engineering.

As noted, CADE release 1 has experienced significant reported cost 
overruns and schedule delays throughout its life cycle, and has yet to 
be delivered. SEI's independent technical assessment of CADE pointed to 
four primary factors that have caused the project to get off track and 
resulted in such severe cost and schedule impairments: (1) the 
complexity of CADE release 1 was not fully understood; (2) the initial 
business rules engine effort stalled; (3) both IRS and PRIME technical 
and program management were ineffective in key areas, including 
significant breakdowns in developing and managing CADE requirements; 
and (4) the initially contentious relationship between IRS and PRIME 
hindered communications. SEI also warned that CADE runs the risk of 
further trouble with later releases due to unexplored/unknown 
requirements; security and privacy issues that have not been properly 
evaluated (e.g., online transactions are different from the way IRS 
does business today); dependence on an unproven business rules 
engine[Footnote 14] software product; and the critical, expensive, and 
lengthy business rules harvesting[Footnote 15] effort that has not yet 
been started. SEI offered several recommendations to address current 
CADE issues and reduce project risk in the future.

IRS Is Acting to Resolve Issues Identified in the BSM Assessments:

Based on these assessments, IRS identified a total of 46 specific 
issues for resolution in the following six areas, and developed a BSM 
action plan comprising individual action plans to address each issue:

* Organization and Roles. Immediate steps are needed to clarify IRS/
PRIME roles and responsibilities and clearly define decision-making 
authorities.

* Key Skills & Strengthening the Team. Strengthened skills and 
capabilities are needed in such key areas as project management and 
systems engineering.

* Technology-Architecture & Engineering. More focus is needed to 
improve current systems architecture integration.

* Technology-Software Development Productivity & Quality. Improvements 
in product quality and productivity are essential to strengthening 
software delivery performance.

* Acquisition. Contracting and procurement practices require major 
streamlining to improve overall contract management.

* CADE. Delivery of CADE release 1 will require aggressive focus and 
attention, and a business rules engine solution requires additional 
evaluation.

These 46 issue action plans were assigned completion dates and an IRS 
or PRIME owner was assigned to take the lead in implementing each plan. 
IRS and PRIME each also assigned a senior-level executive to drive the 
execution of the issue action plans, identify and help mitigate 
implementation hindrances or roadblocks, and ensure successful 
completion of all planned actions. To assess the efficacy of the BSM 
action plan, MITRE was tasked with conducting an independent analysis 
and provided feedback to IRS on the effectiveness of the specific issue 
action plans to address the associated findings/recommendations and 
correct any problems found.

IRS has reported making steady progress with implementing the BSM 
action plan. According to the IRS BSM program office, as of late 
January 2004, 27 of the 46 issue action plans have been completed. 
Examples of completed actions include (1) making business owners and 
program directors accountable for project success; (2) assigning teams 
to investigate and resolve problem areas on key projects such as CADE, 
the Integrated Financial System, and e-Services; (3) aligning critical 
engineering talent to the most critical projects; (4) increasing the 
frequency of CADE program reviews; and (5) issuing a firm fixed-price 
contracting policy.

Significant further work remains to complete implementation of the 
remaining 19 open issue action tasks. Bain & Company--which conducted 
the independent review of PRIME--has been hired to facilitate the 
implementation of various issue action plans within the Organization 
and Roles challenge area, while IRS has also contracted with SEI to 
conduct further periodic reviews of the CADE project.

Additionally, the IRS Oversight Board recently issued a report[Footnote 
16] on its own independent analysis of the BSM program, which made 
several observations and recommendations that are consistent with those 
discussed here. IRS has conducted an analysis of this report to 
reconcile the board's recommendations with those that are currently 
being addressed in the BSM action plan. As a result, IRS plans to open 
two additional issues and action plans to address (1) rationalizing and 
streamlining oversight of the BSM program, and (2) determining and 
maintaining a manageable portfolio of projects. IRS expects to complete 
the majority of the BSM action plan by end of April of this year, and 
fully implement any remaining open actions by the end of the calendar 
year.

Further, during 2003, the Treasury Inspector General for Tax 
Administration performed several reviews related to management of the 
BSM program and for specific BSM projects. These reviews identified 
several issues, including those related to compliance with the defined 
management and project development processes, full implementation of 
disciplined project testing processes and procedures, IRS's cost and 
schedule estimation process, and contract management. IRS management 
reaffirmed their commitment to fully implement key management and 
project development processes.

Concluding Observations:

IRS's multibillion-dollar BSM program is critical to agency's 
successful transformation of its manual, paper-intensive business 
operations and fulfilling its restructuring activities. The agency has 
made important progress in establishing long-overdue modernization 
management capabilities and in acquiring foundational system 
infrastructure and some applications that have benefited the agency and 
the public. However, our reviews, those of the Treasury inspector 
general, and the recently completed internal and independent 
assessments of the BSM program clearly demonstrate that significant 
challenges and serious risks remain. IRS acknowledges this and is 
acting to address them.

To successfully address these challenges and risks and to modernize its 
systems, IRS needs to continue to strengthen BSM program management by 
continuing efforts to:

* balance the scope and pace of the program with the agency's capacity 
to handle the workload, and:

* institutionalize the management processes and controls necessary to 
resolve the deficiencies identified by the reviews and assessments.

Commitment of appropriate resources and top management attention are 
critical to resolving the identified deficiencies. In addition, 
continuing oversight by the Congress, OMB, and others, as well as 
ongoing independent assessments of the program, can assist IRS in 
strengthening the BSM program.

Meeting these challenges and improving performance are essential if IRS 
and the PRIME contractor are to successfully deliver the BSM program 
and ensure that BSM does not suffer the same fate as previous IRS 
modernization efforts.

Mr. Chairman, this concludes my statement. I would be pleased to 
respond to any questions that you or other members of the subcommittee 
may have at this time.

Contacts and Acknowledgments:

For information about this testimony, please contact me at (202) 512-
3317 or by e-mail at daceyr@gao.gov. Individuals making key 
contributions to this testimony include Bernard R. Anderson, Michael P. 
Fruitman, Timothy D. Hopkins, and Gregory C. Wilshusen.

FOOTNOTES

[1] U.S. General Accounting Office, High-Risk Series: An Overview, GAO/
HR-95-1 (Washington, D.C.: February 1995).

[2] U.S. General Accounting Office, High-Risk Series: An Update, 
GAO-03-119 (Washington, D.C.: January 2003).

[3] P.L. 108-199, Div. F, Title II, Jan. 23, 2004. IRS uses the 
appropriated totals to cover contractor costs related to the BSM 
program. IRS funds internal costs for managing BSM with another 
appropriation. These costs are not tracked separately for BSM-related 
activities.

[4] The other five legislative conditions are that the expenditure plan 
(1) meets Office of Management and Budget's (OMB) capital planning and 
investment control review requirements; (2) complies with IRS's 
enterprise architecture; (3) conforms with IRS's enterprise life cycle 
methodology; (4) is approved by IRS, Treasury, and OMB; and (5) 
complies with federal acquisition rules, requirements, guidelines, and 
system acquisition management practices. 

[5] The current system--referred to by IRS as the master files--
contains taxpayer account and return data. There are master files for 
individuals, businesses, and employer retirement plans. A nonmaster 
file for taxpayer data also exists that cannot be stored in the other 
master files due to data format and space limitations.

[6] GAO/HR-95-1.

[7] U.S. General Accounting Office, Tax Systems Modernization: 
Management and Technical Weaknesses Must Be Corrected If Modernization 
Is to Succeed, GAO/AIMD-95-156 (Washington, D.C.: July 26, 1995) and 
Tax Systems Modernization: Blueprint Is a Good Start, But Not Yet 
Sufficiently Complete to Build or Acquire Systems, GAO/AIMD/GGD-98-54 
(Washington, D.C.: Feb. 24, 1998).

[8] U.S. General Accounting Office, Tax Systems Modernization: Results 
of Review of IRS' March 7, 2000, Expenditure Plan, GAO/AIMD-00-175 
(Washington, D.C.: May 24, 2000) and Tax Systems Modernization: Results 
of Review of IRS' August 2000 Interim Spending Plan, GAO-01-91 
(Washington, D.C.: Nov. 8, 2000).

[9] U.S. General Accounting Office, Business Systems Modernization: IRS 
Needs to Better Balance Management Capacity with Systems Acquisition 
Workload, GAO-02-356 (Washington, D.C.: Feb. 28, 2002).

[10] Carnegie Mellon University's Software Engineering Institute has 
developed criteria, known as the Software Acquisition Capability 
Maturity Model,' for determining organizations' software acquisition 
management effectiveness or maturity. A Level 2 organization has 
established its basic project management processes in the following key 
process areas: acquisition planning, solicitation, requirements 
development and management, project management, contract tracking and 
oversight, evaluation, and transition to support.

[11] U.S. General Accounting Office, Business Systems Modernization: 
IRS Has Made Significant Progress in Improving Its Management Controls, 
but Risks Remain, GAO-03-768 (Washington, D.C.: June 27, 2003)

[12] Initial operation refers to the point at which a project is 
authorized to begin enterprisewide deployment.

[13] Full deployment refers to the point at which enterprisewide 
deployment has been completed and a project is transitioned to 
operations and support.

[14] A business rules engine translates business rules, or processing 
criteria (e.g., income tax refunds of $x or more are held for 
administrative review), into executable computer code which processes 
transactions related to a tax form, and selects and executes correct 
rules based on the tax year and tax form.

[15] Business rules harvesting refers to the process of extracting, 
defining, and documenting tax processing criteria from a variety of 
sources, including IRS subject matter experts, legacy system source 
code, the tax code, and various other paper documents.

[16] IRS Oversight Board Special Report, Independent Analysis of IRS 
Business Systems Modernization, December 2003.